B08_-_Atch_1_-_LAKE_312420_Project_Specifications.pdf
PDF 2 MB Posted
- Attached to
- LAKE - REPLACE HORSEPOWER COVE LIFT STATION
- Solicitation number
- 140P8126B0008
About this file
This is a Project Specifications document for the replacement of the Horsepower Cove lift station at Lake Mead National Recreation Area in Boulder City, Nevada (PMIS 312420). The project involves removing and disposing of existing main sewage lift station equipment and installing new equipment including a wet well, overflow tank with back drain, electrical panel/controls, meter vault, auto dialer panel, and a new lift station pumping unit with submerged pumps. The work is contracted as a single prime contract with payment on a lump sum basis for Contract Line Item 0001.
The specifications establish comprehensive requirements for construction operations, including work hours of 7:00 a.m. to 5:00 p.m. Monday through Friday, with major utility switchovers limited to Tuesdays through Thursdays. The contractor must obtain all necessary permits from the Nevada Division of Environmental Protection (NDEP) and Clark County Dust Control before beginning site construction, with Arthur Sammons designated as the owner/operator for NDEP applications. All equipment entering the park must be cleaned outside the facility to prevent non-native species introduction, with inspections required before proceeding past paved surfaces. The contractor is responsible for maintaining existing utilities as operational, protecting natural features, preserving trees and vegetation, and complying with park regulations including desert tortoise awareness training. Key administrative requirements include submission of an Accident Prevention Plan, Quality Control Plan, Construction Schedule, Schedule of Values, insurance certificates, and waste management plan within specified timeframes. Weekly progress meetings are mandatory, and the contractor must provide daily logs with photos documenting work performed. The project manager is Carl Bush (702-293-8735), and the National Park Service Denver Service Center administers the specifications under federal contract 140P8126B0008.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
LAKE MEAD NATIONAL RECREATION AREA
BOULDER BEACH & HORSEPOWER COVE
REPLACE HORSEPOWER COVE LIFT STATION
LAKE
PMIS 312420
PROJECT SPECIFICATIONS
NATIONAL PARK SERVICE (NPS)
DENVER SERVICE CENTER (DSC)
LAKE 312420 Professional Seals - 1
Professional seals by Design Professionals and others responsible for preparing Construction Documents:
Civil Engineer – Patricia J. Sullivan, Martin/Martin Consulting Engineers
Electrical Engineer – Jon Brooks, AE Design, Inc.
03/25/2026
12/31/202706/30/26
03/16/26
LAKE 312420 TOC - 1
Table of Contents
Division 01: General Requirements Number of Pages
01 11 00 Summary of Work 01 27 00 Definition of Contract Line Items 01 31 00 Project Management and Coordination 01 33 23 Submittal Procedures 01 35 23 Safety Requirements 01 40 00 Quality Requirements 01 50 00 Temporary Facilities and Controls 01 67 00 Product Requirements 01 73 29 Cutting and Patching 01 77 00 Closeout Procedures 01 78 23 Operation and Maintenance (O&M) Data
Division 26: Electrical
26 05 00 Common Work Results for Electrical 26 05 19 Low-Voltage Electrical Power Conductors and Cables 26 05 26 Grounding and Bonding for Electrical Systems 26 05 29 Hangers and Supports for Electrical Systems 26 05 33 Raceway and Boxes for Electrical Systems 26 05 44 Sleeves and Sleeve Seals for Electrical Raceways and Cabling 26 05 53 Identification for Electrical Systems 26 28 16 Enclosed Switches and Circuit Breakers
Division 31: Earthwork
31 10 00 Site Clearing 31 20 00 Earth Moving 31 23 33 Trenching and Backfilling
Division 33: Utilities
33 31 00 Sanitary Utility Sewage Piping 33 32 00.01 Wastewater Utility Pumping Stations – Boulder Beach 33 32 00.02 Wastewater Utility Pumping Stations – Horsepower Cove
LAKE 312420 01 11 00 - 1
081325 SUMMARY OF WORK
NPS DSC Division 1 Specifications National Park Service (NPS) - Denver Service Center (DSC) | 8-13-25
LAKE 312420
SECTION 01 11 00 - SUMMARY OF WORK
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes the following:
1. Work Covered by Contract Documents
2. Work Phases
3. Work Under Other Contracts
4. Government-Furnished Materials
5. Construction Contractor Use of Site
6. Public Use of Site
7. Occupancy Requirements for Buildings
8. Conduct of Operations
9. Work Restrictions
10. Special Construction Requirements
11. Soils Investigation Report
12. Additional Reports
1.2 WORK COVERED BY CONTRACT DOCUMENTS
A. Project Location: Lake Mead National Recreation Area, Horsepower Cove, Boulder City, NV. The Horsepower Cove lift station is located southeast of the intersection of Horsepower Cove and Hemenway Harbor Road.
B. The Work consists of:
1. Boulder Beach Lift Station - Horsepower Cove Lift Station – PMIS 312420:
Replace the existing main sewage lift station equipment, remove and dispose of the existing lift station pumping equipment, installing a new wet well, overflow tank with back drain, electrical panel/controls and meter vault. There will be an additional panel added to house a new auto dialer and installation of a new lift station pumping unit incorporating submerged pumps on top of the wet well.
C. Project will be constructed under a single prime contract.
LAKE 312420 01 11 00 - 2
1.3 CONSTRUCTION CONTRACTOR USE OF SITE
A. General: Construction Contractor shall have limited use of site for construction operations. Limit use of premises to areas within the Construction limits indicated on drawings. Do not disturb portions of Project site beyond areas in which the Work is indicated.
1. Public access in public areas shall always be maintained. NPS Employee access shall be maintained to all facilities during construction.
B. Storage of Materials: Confine storage of materials to:
1. Horsepower Cove: Anywhere in the parking area from the road to the buildings.
C. Parking: Confine parking to existing parking areas.
D. Stockpiling: Confine stockpiling to the same areas described in 1.4 B Storage of Materials.
E. Preservation of Natural Features:
1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
2. Provide temporary barriers to protect existing trees and plants and root zones.
3. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with
Contracting Officer/Contracting Officer’s Representative (CO/COR) and remove agreed-on roots and branches that interfere with construction.
4. Do not fasten ropes, cables, or guys to existing trees.
5. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.
F. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to Government employees, and emergency vehicles at all times. Do not use for parking or storage of materials.
1. Schedule deliveries to minimize use of driveways and entrances.
2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
G. Construction Camp: Establishment of a camp within park will not be permitted.
H. Hauling Restrictions: Comply with legal load restrictions in hauling of materials. Load restrictions on park roads are identical to state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Construction Contractor of liability for damage which may result from moving of equipment.
I. Bridge Restrictions: Identify jurisdictions, load restrictions, permit requirements, time and calendar restrictions as outlined.
LAKE 312420 01 11 00 - 3
1.4 PUBLIC USE OF SITE
A. Construction Contractor shall conduct their operations to ensure the least inconvenience to public.
1. Road closures may be permitted, when required, upon specific approval of CO for a maximum of 15 minutes.
2. Traffic control devices shall be used around the active job site.
3. Open trenches should be minimized when the Construction Contractor is not working. Tape or cone off trench areas when not working.
4. Trenches shall be brought back up to existing grade in active driving areas or the use of steel plates shall be used to cover the trench for vehicular traffic when not being actively worked on.
1.5 CONDUCT OF OPERATIONS
A. Construction Contractor shall conduct their operations in conformance with rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by Park Superintendent.
B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed unless stated in the Work Restrictions below or without prior consent from the CO. Submit requests 3 business/calendar days in advance of the work to the CO/COR for approval.
C. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the CO/COR.
1.6 WORK RESTRICTIONS
A. On-Site Work Hours: Work shall be generally performed during normal business working hours of 7:00 a.m. to 5:00 p.m., Monday through Friday, except when otherwise indicated.
1. Due to the location of the construction site and vicinity of the public, these hours should be adhered to including idling of equipment, starting of equipment, backup alarms of equipment and delivery of equipment.
B. Existing Utilities
1. Construction Contractor shall at all times protect and maintain as functional and operational the existing force main, lift station, and sewage collection system.
Coordination with the NPS to maintain these systems as operational is required.
2. Existing Utilities: Notify CO/COR and utility companies of proposed locations and times for excavation.
3. Construction Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.
4. If damage occurs to an unknown utility, repair utility repair utility at no additional expense to the Government..
5. Contractor shall verify the elevation of all existing water and sewer lines to verify vertical and horizontal alignment.
a. Locations and elevations shown on the drawings may be subject to minor field adjustment by COR before construction.
LAKE 312420 01 11 00 - 4
b. If changes in stakeout are required, Contractor shall cooperate with the COR in prompt establishment of the field control for altered or adjusted work.
C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:
1. Notify CO/COR not less than two business days in advance of proposed utility interruptions.
2. Do not proceed with utility interruptions without CO’s written permission.
3. Hours and length of Utility Shutdowns:
a. Major turnovers and switchovers shall be made during the week on Tuesdays, Wednesdays, or Thursdays.
b. Notify CO/COR and USB staff 3 business days before switchover.
c. Construction Contractor shall be responsible for maintaining any bypass pumping or removal of sewage for an extended shutdown.
D. Nonsmoking Building/Tobacco Use/Vaping: Smoking is not permitted within building or within 25 feet of entrances, operable windows, or outdoor air intakes.
1.7 SPECIAL CONSTRUCTION REQUIREMENTS
A. Project Management and Communication Software: Software administered by NPS shall be used to manage communication and document sharing during construction.
1. See Section 01 31 00 "Project Management and Coordination" for requirements on using NPS project management and communication software.
B. Park Entry: The Construction Contractor shall furnish a list of personnel with phone contact information. Vehicles associated with the Construction Contractor shall be waived entrance fee upon entering in a marked company vehicle or by providing the names of employees entering in personal vehicles. The entrance fee is waived only for the purpose of reporting directly to a specific work location. Any deviation for recreational purposes is subject to payment of required entrance fees.
C. Permitting and Fees:
1. The Construction Contractor is responsible for obtaining and paying for all fees and costs for necessary permits and approvals for all construction activities associated with this Project.
2. Permits from the Nevada Division of Environmental Protection (NDEP) are expected to be needed.
3. Permits for Clark County Dust Control are expected to be needed.
4. Arthur Sammons, Environmental Protection Specialist shall be listed as the owner/operator for all NDEP applications and permits.
5. Prior to beginning site construction, apply for and receive any needed permits and approvals from NDEP. No work shall commence prior to receiving permits and approvals. A copy of the permits and approvals shall be forwarded to the NPS for review.
6. Construction Contractor shall provide all needed Professional Engineering services for inspections, signatures and closures needed to approve or close out any permit.
LAKE 312420 01 11 00 - 5
D. Park Regulations: Ensure all personnel (contractors, subcontractors, and vendors) entering or working in the park are familiar with and obey all park regulations. Law enforcement rangers will intervene if they perceive any unsafe or unlawful activity.
E. Emergency and Medical Reporting
1. All accidents and incidents shall be reported to the CO/COR.
a. The Construction Contractor or subcontractor shall contact Park Dispatch for any medical emergency or traffic accident occurring within the Park.
b. Emergency number: Dial 911 as needed.
c. Park Dispatch: 702-293-8932 EMERGENCY. Park Dispatch shall be called so that the entrance station will be prepared should any emergency vehicles (e.g.
ambulance) need to enter the Park and so that any available Emergency Medical Services personnel in the Park might respond until such time as the ambulance arrives.
d. The Construction Contractor or subcontractor is required to report ANY personal injury and/or property damage incident occurring within the park. This report must be made to a Law Enforcement Ranger at the first available opportunity before leaving the park: Park Dispatch: 702-293-8998 NON-EMERGENCY
F. Environmental Compliance
1. The Construction Contractor and all employees working on the Project will be required to take “Desert Tortoise Awareness Training” which will be provided by the Government at no cost to the Construction Contractor. This training will take approximately 30 minutes or less.
2. The Construction Contractor’s employees shall never handle a desert tortoise.
3. The Construction Contractor and employees shall immediately report the presence of any desert tortoise to the CO/COR.
4. Herbicides shall not be used in or around the Project site.
5. Contact the CO/COR for coordination with the LAKE Resources Team.
G. Equipment Washing
1. Equipment washing is required to preclude the introduction and spread of non-native species into the Park. Therefore, all equipment shall be cleaned outside of the Park before entering the Park. Equipment leaving the park for any reason must be re-washed before returning to the job site. Equipment that is moved from the job site, but remains within the original developed area, need not be re-washed prior to returning to the job site. It is also known that there are areas inside the Park that have non-native plants and weed species infestation. Therefore, before equipment can be moved from one developed area to another, it must be washed at the location identified on the Site Plan (see attached site plan and mileage table) to ensure weeds are not spread from one developed area to another.
2. The Construction Contractor shall clean all equipment prior to the equipment entering Lake Mead National Recreation Area. It is recommended that cleaning be accomplished by hot water, pressure washing, using water only. All equipment surfaces shall be cleaned, with special emphasis given to the undercarriage. This includes, but is not limited to:
wheel wells, bumpers, radiator grills, springs, shock absorbers, wire harnesses, skid plates, oil pans, axles, frame ledges, buckets, tracks, belly pans, etc. Cleaning shall also include all dirt and debris inside the cab, or operator area. A Shop-Vac or commercial car wash vacuum system may be used for operator compartments, provided the method
LAKE 312420 01 11 00 - 6
used effectively removes all visible debris. Equipment cleaning is for the purpose of removing any seed and soil accumulations to prevent the potential spread of non-native plant and weed species from outside the park to locations inside the park. Cleaning shall be performed in a manner that will reasonably remove all visible soil, plant, and other foreign material. All equipment that requires washing shall be inspected by government personnel, or contractors/partners assigned to this duty, to ensure compliance.
3. Equipment that requires washing is generally defined as track or rubber-tired machinery intended for use primarily off-road. Examples include backhoes, loaders, earthmovers, graders, rollers, bulldozers, water trucks, etc; or four wheel drive or passenger vehicles that are driven in off road areas. Equipment may also be stationary, such as a material screening plant, conex storage containers, or a mobile office (mobile offices may be cleaned in the same manner as operator compartments as outlined in paragraph 2). The equipment is generally under the direct control of the contractor or sub-contractors, is likely to remain on the construction site for an extended period of time, and may contain adhered soil and seed from other project sites.
4. Equipment/Vehicles that do not require washing are defined as those normally used for highway driving only, and travel primarily on paved surfaces and well maintained service roads and parking areas (this includes approved staging areas). Examples include semi-tractor trailers, dump trucks, concrete trucks, pickup trucks, fuel trucks, service trucks, etc. These delivery and passenger vehicles are generally not under the direct control of the contractor, have no earth-moving function, and do not remain on the project site.
These vehicles have a low probability of carrying adhered soil and seed from other projects. However, every vehicle and piece of equipment is subject to rejection from entering the park if there are obvious signs (covered in mud, plant material adhered to it, etc.) that it could be transporting non-native species into the Park.
H. Post Equipment Washing Inspections:
1. All equipment subject to inspection will be inspected by government, or other authorized personnel prior to leaving the paved surface or designated washing area identified on the Site Plan. Equipment determined to be free of soil or mud based on visual examination by government personnel will be cleared to enter the project area, or proceed to other areas of the park as appropriate. The Contractor shall arrange for needed inspections by contacting the NPS inspection office no less than 5 working days prior to the inspection.
Such contact shall provide sufficient time to accommodate scheduling and travel to the site. Equipment not passing initial inspection must be rewashed outside the park at no additional expense to the government.
2. A list of government Inspectors for this project will be provided by: Kelly Wallace, Cell phone: 702-371-9673. Contact the CO/COR for coordination with the LAKE Resources Team.
1.8 DESIGNATED OFFICIALS
A. The NPS Project Manager (PM) and Contracting Officer’s Representative (COR) will be:
Carl Bush PE, Lake Mead NRA Telephone: 702-293-8735 (w) 702-859-0194 (cell) Email: carl_bush@nps.gov
B. The Contracting Officer (CO) will be:
mailto:carl_bush@nps.gov
LAKE 312420 01 11 00 - 7
TBD.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 11 00
LAKE 312420 01 27 00 - 1
012721 DEFINITION OF CONTRACT LINE ITEMS
NPS DSC Division 1 Specifications National Park Service (NPS) - Denver Service Center (DSC) | 1-27-21
LAKE 312420 SECTION
01 27 00 – DEFINITION OF CONTRACT LINE ITEMS PART 1 -
GENERAL
1.1 SUMMARY
A. Section explains in general, what is and is not included in a contract line item, and limits or cut-off points where one item ends and another begins.
B. If no contract line item exists for a portion of work, include costs in a related item.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 LIST OF CONTRACT LINE ITEMS
A. Deleted
B. Contract Line Item Number 0001: PMIS 312420 Replace Horsepower Cover Lift Station.
1. This item consists of Replace the existing main sewage lift station equipment, remove and dispose of the existing lift station pumping equipment, installing a new wet well, overflow tank with back drain, electrical panel/controls and meter vault. There will be an additional panel added to house a new auto dialer and installation of a new lift station pumping unit incorporating submerged pumps on top of the wet well.
2. Measurement for payment will be lump sum.
3. Payment will be made at the contract lump sum price.
LAKE 312420 01 27 00 - 2
012721 DEFINITION OF CONTRACT LINE ITEMS
END OF SECTION 01 27 00
LAKE 312420 01 31 00 - 1
091025 PROJECT MANAGEMENT AND COORDINATION
NPS DSC Division 1 Specifications National Park Service (NPS) - Denver Service Center (DSC) | 9-10-25
LAKE 312420
SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
1. Definitions
2. Construction Coordination
3. Submittals
4. Coordination Drawings
5. Requests for Information (RFIs)
6. NPS Project Management and Communication Software
7. Project Meetings
8. Environmental Coordination
9. Permits
B. Related Requirements:
1. Section 01 77 00 "Closeout Procedures" for coordinating closeout of the Contract.
1.2 DEFINITIONS
A. Agency with Jurisdiction B. Construction Permits – Contractor Provided C. Government Furnished Permits
1.3 CONSTRUCTION COORDINATION
A. Coordination: Coordinate construction operations included in different Sections of Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components with other Construction Contractors to ensure maximum accessibility for required maintenance, service, and repair.
3. Make provisions to accommodate items scheduled for later installation.
http://www.nps.gov/dscw/definitionsdc_a.htm#awj http://www.nps.gov/dscw/definitionsdc_c.htm#cpcp http://www.nps.gov/dscw/definitionsdc_g.htm#gfperm
LAKE 312420 01 31 00 - 2
4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of components, including mechanical and electrical.
5. Properly plan construction operations to include permit requirements. Allow enough time to execute permit provisions to maintain work schedule, site visits, inspections, and reporting deadlines.
B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other Construction Contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to:
1. Preparation of Construction Contractor Construction Schedule
2. Preparation of the Schedule of Values
3. Installation and removal of temporary facilities and controls
4. Delivery and processing of submittals
5. Progress meetings
6. Permit requirements
7. Pre-installation conferences
8. Project closeout activities
9. Commissioning activities
D. Daily Log: A daily log shall be prepared by the Contractor representing the work that was performed that day.
1. The log shall describe the tasks performed that day and the contractor staff working.
2. Two (2) or more representative photos of the tasks being performed that day shall be included in each daily log.
3. The submitted daily logs shall be in a pdf format. Emailing to the Contracting Officer /
Contracting Officer’s Representative (CO/COR) is acceptable.
4. The daily logs shall be sent to the CO/COR once a week. For every week worked in the field, the daily log shall be sent to the CO/COR.
E. Photo Requirements: Photos of all connections are to be taken and provided. Photos taken documenting the progress of the construction and the suitability of each connection. This is especially important for any connection, cable connector or piping that will be buried.
1. Photos shall be JPG format.
2. No labels or text shall be placed on the photographs.
3. High resolution photos are preferred.
4. Name or number the photos to represent the task shown in the photo.
5. Photo files shall be transmitted to the CO/COR at the end of the construction as part of the close-out procedures.
1.4 SUBMITTALS
A. Division 1 submittals required prior to mobilization:
LAKE 312420 01 31 00 - 3
1. Letter designating Project Superintendent
a. In addition to the project superintendent, the Construction Contractor shall provide other supervisory and administrative personnel as required for proper work performance. This may include special personnel required for coordination of operations with subcontractors and material suppliers.
b. Staff Roster: Within 14 days after the NTP, the Construction Contractor shall submit a list of staff assignments, including subcontractor personnel (if applicable), working at the job site. Identify each individual and their duties and responsibilities.
2. Construction Baseline Schedule
3. A Comprehensive Schedule of Values
4. Accident Prevention Plan
5. Written statements from Subcontractors certifying compliance with applicable labor standard clauses.
6. Certificates of Insurance and Standard Form SF1413 for Contactor and all Subcontractors
7. Waste Management Plan
8. Quality Control Plan
9. List of Required Construction Permits (when applicable). Include the following information for each permit:
a. Name of Permit
b. Agency(ies) with Jurisdiction issuing the permit
c. Information required from the Government to complete permit application
1.5 REQUESTS FOR INFORMATION (RFIs)
A. General: Immediately on discovery of the need for additional information or interpretation of Contract Documents, Construction Contractor shall prepare and submit an RFI.
1. CO/COR will not respond to RFIs submitted by other entities controlled by Construction Contractor.
2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.
B. Content of RFI: Include detailed, legible description of item needing information or interpretation and the following:
1. RFI number, numbered sequentially
2. Date
3. RFI subject
4. Specification Section number and title and related paragraphs, as appropriate.
5. Drawing number and detail references, as appropriate.
6. Field dimensions and conditions, as appropriate.
7. Construction Contractor's suggested resolution: If suggested resolution impacts Contract
Time or Contract Sum, Construction Contractor shall state impact in RFI.
8. Construction Contractor's signature
9. Requested date for response
10. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop
Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.
a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.
LAKE 312420 01 31 00 - 4
C. RFI Form: Complete and submit on NPS project management and communication software if used, otherwise, transmit to CO/COR.
D. CO/COR’s Action: CO/COR will review each RFI, determine action required, and respond. The CO/COR will determine the critical nature of each RFI and issue response accordingly.
1. The following are not considered to be RFIs and will receive no action:
a. Requests for approval of submittals.
b. Requests for approval of substitutions.
c. Requests for approval of Construction Contractor's means and methods.
d. Requests for coordination information already indicated in Contract Documents.
e. Requests for adjustments in Contract Time or Contract Sum.
f. Requests for interpretation of Architect's actions on submittals.
g. Incomplete RFIs or inaccurately prepared RFIs.
2. CO/COR's action may include a request for additional information; time for response will date from time of receipt of additional information.
3. CO/COR's action on RFIs may result in need for a change to Contract Time or Contract Sum. All contract changes will be processed according to the terms and conditions of the contract.
1.6 PROJECT MANAGEMENT AND COMMUNICATION SOFTWARE - OPTIONAL
A. Use to manage project communication and document sharing during contract period on:
1. Project directory
2. Project correspondence
3. Meeting agendas and minutes
4. Contract modifications forms and logs
5. RFI form and processing
6. Task and issue management
7. Photo documentation
8. Baseline schedule, schedule updates and calendar management
9. Submittal form and processing
10. Payment coordination documentation
11. Reminder and tracking functions
12. Archiving functions
13. Notification of submittal and RFI statuses and current responsible party
14. Permits and addendums
B. Some documents are not suitable to be shared using NPS project management and communication software. Documents containing Personal Identifying Information (PII) (i.e. certified payrolls) shall not be shared and shall be coordinated with the project team as appropriate.
1.7 PROJECT MEETINGS
A. Preconstruction Conference: Before the start of construction, the CO/COR will arrange an on-site meeting with Construction Contractor. Meeting agenda will include the following as a minimum:
LAKE 312420 01 31 00 - 5
1. Roles & Responsibilities / Lines of Authority
2. Park rules and regulations
3. Jobsite Safety
4. Resolution of comments on required Division 1 documents
5. Coordination of Subcontractors
6. Labor law application
7. Modifications
8. Payments to Construction Contractor
9. Payroll reports
10. Contract time
11. Liquidated damages
12. Construction Contractor Performance Evaluation
13. Display of Hotline posters
14. Notice to proceed
15. Correspondence procedures
16. NPS project management and communication software
17. Acceptance/rejection of work
18. Progress meetings
19. Submittal procedures
20. Environmental requirements
21. Permit requirements
22. As-constructed drawings/operation and maintenance (O&M) manuals.
23. Saturday, Sunday, holiday and night work.
24. Reference materials
25. Value engineering
26. Schedule of Values
B. Progress Meetings: CO/COR will schedule weekly meetings with Construction Contractor.
1. Attendees: In addition to Government Representatives, each Construction Contractor, Subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented.
Participants at meetings shall be familiar with the Project and authorized to conclude matters relating to the Work.
2. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. Meeting agenda will include:
a. Approval of minutes of previous meetings
b. Submittal status
c. Review of off-site fabrication and delivery schedules.
d. Requests for information (RFI) and other issues.
e. Modifications
f. Work in progress and projected.
1) Status of required inspections (Special Inspections, Accessibility, etc.)
g. Inspections of work in progress and projected (Special inspections, Accessibility, etc.)
h. Construction Schedule update (provide updated Critical Path Method (CPM)).
i. Status of Project Record Drawings and O&M manuals.
j. Other business relating to work.
k. Permit requirements
LAKE 312420 01 31 00 - 6
C. Preinstallation Conferences: Conduct at Project site before each construction activity that requires coordination with other construction.
1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by installation and its coordination or integration with other materials and installations that have preceded or will follow shall attend meetings. Advise the CO/COR of scheduled meeting dates.
2. Agenda: Review progress of other construction activities and preparations for particular activity under consideration, including requirements for:
a. Contract Documents
b. Options
c. Related RFIs
d. Related Change Orders
e. Purchases
f. Deliveries
g. Submittals
h. Review of mockups
i. Possible conflicts
j. Compatibility requirements
k. Time schedules
l. Weather limitations
m. Manufacturer's written instructions
n. Warranty requirements
o. Compatibility of materials
p. Acceptability of substrates
q. Temporary facilities and controls
r. Space and access limitations
s. Regulations of agency(ies) with jurisdiction
t. Testing and inspecting requirements
u. Installation procedures
v. Coordination with other work
w. Required performance results
x. Protection of adjacent work
y. Protection of construction and personnel
3. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.
4. Reporting: Distribute minutes of meetings to each party present and to other parties requiring information.
5. Do not proceed with installation if the conference cannot be successfully concluded.
Initiate whatever actions are necessary to resolve impediments to the performance of Work and reconvene the conference at the earliest feasible date.
1.8 ENVIRONMENTAL COORDINATION
A. Construction Contractor’s Environmental Manager: Designate on-site party responsible for overseeing Construction Contractor’s conformance to environmental goals for project and implementing procedures for environmental protection.
LAKE 312420 01 31 00 - 7
1. Qualifications: Minimum 3 years Construction experience on projects of similar size and scope; with environmental procedures similar to this project; familiar with environmental regulations applicable to construction operations.
2. Responsibilities: Responsibilities shall include:
a. Compliance with applicable Federal, State, and local environmental regulations, including maintaining required documentation.
b. Implementation of Waste Management Plan (WMP).
c. Present overview of environmental issues and summarize site specific procedures relating to management plans at Preconstruction conference.
d. Training for Construction Contractor personnel in accordance with position requirements.
e. Monitoring and documentation of environmental procedures.
B. Perform project quality control in accordance with requirements specified in Related Sections, including:
1. Quality Requirements
C. Construction Contractor’s Environmental Training Program: Construction Contractor shall provide environmental training for workers performing work on project site. Training shall include:
1. Overview of environmental issues related to Project.
2. Review of site-specific procedures and management plans:
a. Construction Waste Management
b. Noise and Acoustics Management
3. Pollution Prevention (P2) practices: Submit evidence of P2 training.
4. Compliance with environmental regulations: As specified in Regulatory Requirements.
Submit Construction Contractor 40 CFR (Code of Federal Regulations) employee training records upon request of the CO/COR.
D. Provide documentation for environmental procedures as specified herein and in accordance with the approved Waste Management Plan.
1.9 PERMITS
A. General:
1. Permits and Responsibilities: Construction Contractor shall, without additional expense to the Government, be responsible for obtaining necessary licenses and permits, and for complying with Federal, State and municipal laws, codes, and regulations applicable to the performance of the work. Construction Contractor shall also be responsible for damages to persons or property that occur as a result of Construction Contractor’s fault or negligence;
and for materials delivered and work performed until completion and acceptance of the work.
2. For the purpose of this contract, Construction Contractor will not be considered an agent of the Government. Construction Contractor shall comply with appropriate Federal, State and local laws.
LAKE 312420 01 31 00 - 8
B. Potential Permits: Permits listed below were identified during the design process as likely to be required based on typical means and methods of construction. The list is provided to assist Construction Contractor in determining which permits will be required for contract’s chosen means and methods. The list shall not be considered complete; it is the Construction Contractors’ responsibility to determine means and methods and obtain required permits. Construction Contractor shall obtain all permits required to legally conduct work.
1. Electrical Utility Hookup – Nevada Energy
2. Sewer Hookup – Nevada Division of Environmental Protection
3. Construction trailer, Utilities hookup permit - Lake Mead National Recreation Area
4. Dust Control Permit – Clark County Division of Air Quality
C. Coordination with Agency(ies) with Jurisdiction Issuing Permits
1. Coordination: Contact the Agency(ies) with Jurisdiction as needed and sufficiently in advance to avoid delaying work: Coordinate meetings, reporting requirements, inspections, and other requirements.
D. Administrative Procedures:
1. Coordinate scheduling and timing of required administrative provisions of project permits with Agency(ies) with Jurisdiction, Construction Manager, and Park to avoid conflicts.
2. Supply needed information to Agency(ies) with Jurisdiction issuing permits, pay fees required and provide material needed to comply with permit’s conditions and provisions.
3. Upload permits to NPS project management and communication software when permits are obtained. If project management software is not used, transmit to CO/COR.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 31 00
LAKE 312420 01 33 23 - 1
040225 SUBMITTAL PROCEDURE
NPS DSC Division 1 Specifications National Park Service (NPS) - Denver Service Center (DSC) | 4-2-25
LAKE 312420
SECTION 01 33 23 - SUBMITTAL PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other submittals.
1.2 DEFINITIONS
A. Action Submittals: Written, graphic information, and physical samples that require Government’s responsive action.
B. Informational Submittals: Written information that does not require Government’s responsive action. Submittals may be rejected for not complying with requirements.
C. File Transfer Protocol (FTP): Communications protocol that enables transfer of files to and from another computer over a network and that serves as the basis for standard Internet protocols. An FTP site is a portion of a network located outside of network firewalls within which internal and external users are able to access files.
D. Portable Document Format (PDF): An open standard file format licensed by Adobe Systems used for representing documents in a device-independent and display resolution-independent fixed-layout document format.
1.3 GENERAL SUBMITTAL PROCEDURES
A. General: Prepare and submit submittals required by individual Specification Sections and in some cases as requested in drawings. Types of submittals are indicated in individual specific sections.
1. Contracting Officer/Contracting Officer’s Representative (CO/COR) reserves right to require submittals in addition to those called for in individual sections.
B. Coordination: Coordinate preparation and processing of submittals with performance of construction activities. Review for legibility, accuracy, completeness, and compliance with Contract Documents.
1. Coordinate submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.
2. Coordinate transmittal of different types of submittals for related parts of Work so processing will not be delayed because of need for concurrent review coordination.
LAKE 312420 01 33 23 - 2
a. CO/COR reserves right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.
C. Submittal List: Submittal list is attached to the end of this Specification Section. The intent is to provide an overall summary of submittal requirements. The requirements of individual Specification Sections and terms and conditions of the Contract still apply regardless of what is shown on submittal list.
D. Processing Time: Allow enough time for submittal review and re-submittals. Contract time extensions will not be authorized if submittals are not transmitted with enough time to permit processing, including re-submittals.
1. Action Submittals
a. Initial Review: Allow 30 days for initial review of each submittal. Allow additional time if coordination with subsequent submittals is required.
b. Re-submittal Review: Allow 10 days for review of each re-submittal.
2. Informational submittals
a. Review: Allow 10 days for review of each submittal.
E. Approved Equal Submittal Requirements:
1. For each item proposed, submit supporting data, including:
a. Drawings and samples as appropriate.
b. Comparison of the salient characteristics of the proposed item with that specified.
c. Changes required in other elements of the work because of the substitution.
d. Name, address, and telephone number of vendor.
e. Manufacturer’s literature regarding installation, operation, and maintenance, including schematics for electrical and hydraulic systems, lubrication requirements, and parts lists. Describe availability of maintenance service, and state source of replacement materials.
2. A request for approval constitutes a representation that Construction Contractor:
a. Has investigated the proposed item and determined that it is equal or superior in all respects to that specified.
b. Will provide the same warranties for the proposed item as for the item specified.
c. Has determined that the proposed item is compatible with interfacing items.
d. Will coordinate installation of an approved item and make changes required in other elements of the work because of the substitution.
e. Waives claims for additional expenses that may be incurred as a result of the substitution.
F. Submittals: Identify and incorporate information in each submittal file as follows:
1. Transmittal Form (CM-16): Utilize NPS Transmittal Form for all submittals. No action will be taken on a submittal item unless accompanied by this Transmittal Form.
https://www.nps.gov/dscw/con_subreview21.htm
LAKE 312420 01 33 23 - 3
2. Physical samples: Complete Transmittal Form and deliver physical sample to the CO/COR (or designee) on site for processing. All comments and actions will be documented on the Transmittal Form.
G. Identification: Submittal number or other unique identifier, including revision identifier.
1. Submittal number shall use a sequential number (e.g. .001). Re-submittals shall include alphabetic suffix after another decimal point (e.g. .001.A).
H. Re-submittals: Make re-submittals using same process used with initial submittal.
1. Note date and content of previous submittal.
2. Note date and content of revision in the title block on the Transmittal Form (CM-16) and clearly indicate extent of revision.
3. Re-submit submittals until they are marked "Approved" or "Approved with notations".
I. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators, installers, and others as necessary for performance of construction activities.
J. Use for Construction: Use only final submittals with mark indicating "Approved" or "Approved with notations". Ensure notations have been incorporated and, at a minimum, keep one copy of final approved submittal on site for use during construction.
1.4 CONSTRUCTION CONTRACTOR’S USE OF CAD/BIM FILES
A. General: At Construction Contractor’s written request, copies of CAD/BIM (Computer Aided Design/Building Information Modeling) files will be provided to Construction Contractor for use in connection with Project, subject to:
1. Files provided as is; no format or other changes to files or changes to objects in the drawing will be done by the Government
PART 2 - PRODUCTS
2.1 ACTION SUBMITTALS
A. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.
1. If information must be specially prepared for submittal because standard printed data are not suitable for use, submit as Shop Drawings, not as Product Data.
2. Mark each submittal to show which products and options are applicable.
3. As applicable, include:
a. Manufacturer’s product specifications.
b. Manufacturer’s installation instructions: When Contract Documents require compliance with manufacturer’s printed instructions, provide one complete set of instructions to CO/COR and keep another complete set of instructions at the project site until substantial completion.
LAKE 312420 01 33 23 - 4
c. Manufacturer’s catalog cuts: Submit only pertinent pages; mark each page of standard printed data to identify specific products proposed for use.
d. Wiring diagrams showing factory-installed wiring.
e. Printed performance curves.
f. Operational range diagrams.
g. Compliance with specified referenced standards.
h. Testing by recognized testing agency.
4. Submit product data in PDF (portable document format) file format before or concurrent with samples.
B. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data.
1. Preparation: Fully illustrate requirements in Contract Documents. As applicable, include:
a. Dimensions
b. Identification of products
c. Fabrication and installation drawings
d. Roughing-in and setting diagrams
e. Wiring diagrams showing field-installed wiring, including power, signal, and control wiring
f. Shopwork manufacturing instructions
g. Templates and patterns
h. Schedules
i. Notation of coordination requirements
j. Notation of dimensions established by field measurement
k. Relationship to adjoining construction clearly indicated
l. Seal and signature of professional engineer if specified
m. Wiring Diagrams: Differentiate between manufacturer-installed and field-installed wiring
2. Submit shop drawings as PDF electronic file
C. Samples: Submit Samples for review of kind, color, pattern, and texture for a check of these characteristics with other elements and for a comparison of these characteristics between submittal and actual component as delivered and installed.
1. Transmit Samples that contain multiple, related components such as accessories together in one submittal package.
2. Complete and post the Transmittal Form (CM-16) on the NPS project management and communication software website for processing and documentation of action on submitted samples. If NPS project management and communication software website is not used, transmit to CO/COR.
3. Identification: Attach label on unexposed side of Samples that includes:
a. Generic description of Sample
b. Product name and name of manufacturer
c. Sample source
d. Submittal Number and title of appropriate Specification Section
LAKE 312420 01 33 23 - 5
4. Disposition: Maintain sets of approved Samples at Project site, available for quality-control comparisons throughout course of construction activity. Sample sets may be used to determine final acceptance of construction associated with each set.
5. Samples for Initial Selection: Submit manufacturer’s color charts consisting of units or sections of units showing full range of colors, textures, and patterns available.
a. Number of Samples: Submit two full set(s) of available choices where color, pattern, texture, or similar characteristics are required to be selected from manufacturer’s product line. CO/COR will return with options selected.
6. Samples for Verification: Submit full-size units or Samples of size indicated, prepared from same material to be used for the Work, cured and finished in manner specified, and physically identical with material or product proposed for use, and that show full range of color and texture variations expected. Samples include: partial sections of manufactured or fabricated components; small cuts or containers of materials; complete units of repetitively used materials; swatches showing color, texture, and pattern; color range sets; and components used for independent testing and inspection.
a. Number of Samples: Submit four sets of Samples. CO/COR will retain three Sample sets; remainder will be returned.
D. Construction Materials: Construction Contractor is encouraged to submit products made out of recycled or environmentally responsible material. Every effort will be made by NPS to approve these materials.
2.2 INFORMATIONAL SUBMITTALS
A. General: Prepare and submit Informational Submittals required by individual Specification Sections.
1. Post informational submittals as PDF electronic files directly to the NPS project management and communication software, if used, otherwise transmit to CO/COR.
2. Certificates and Certifications: Provide a notarized statement with signature of entity responsible for preparing certification. Certificates and certifications shall be signed by officer or other individual authorized to sign documents on behalf of that entity.
3. Informational submittals that do not comply with requirements specified in Contract Documents will be rejected and one copy will be returned.
B. Accident Prevention Plan: Comply with requirements specified in Section 01 35 23 "Safety Requirements."
C. Quality Control Plan: Comply with requirements specified in Section 01 40 00 "Quality Requirements."
D. Qualification Data: Prepare written information demonstrating capabilities and experience of firm or person. Include lists of completed projects with project names and addresses, names and addresses of architects and owners, and other information specified.
E. Welding Certificates: Prepare written certification that welding procedures and personnel comply with Contract Documents. Submit record of Welding Procedure Specification (WPS) and
LAKE 312420 01 33 23 - 6
Procedure Qualification Record (PQR) on American Welding Society (AWS) forms. Include names of firms and personnel certified.
F. Installer Certificates: Prepare written statements on manufacturer’s letterhead certifying Installer complies with Contract Documents and, where required, is authorized by manufacturer for this specific Project.
G. Manufacturer Certificates: Prepare written statements on manufacturer’s letterhead certifying manufacturer complies with Contract Documents. Include evidence of manufacturing experience where required.
H. Product Certificates: Prepare written statements on manufacturer’s letterhead certifying product complies with Contract Documents.
I. Material Certificates: Prepare written statements on manufacturer’s letterhead certifying material complies with Contract Documents.
J. Material Test Reports: Prepare reports written by a qualified testing agency, on testing agency’s standard form, indicating and interpreting test results of material for compliance with requirements in Contract Documents.
K. Product Test Reports: Prepare written reports indicating current product produced by manufacturer complies with…