Statement of Work Summary: Heat Pump System Replacement for USGS Fredericksburg Magnetic Observatory
This is a Statement of Work for the replacement of an existing heat pump system at the USGS Fredericksburg Magnetic Observatory's Office Building (Building 8) located at 4270 Tesla Road, Woodford, VA 22580. The project objective is to replace one nonfunctioning heat pump split system that serves the central/common area of the 1-story, 2,078 square-foot wood frame structure constructed in 1955 and rehabilitated in 2008. The building is primarily occupied by the Bureau of Indian Affairs with some USGS usage for office space and housing of computer servers and data communication equipment.
The required heat pump system must be 120-volt single phase with a minimum cooling and heating capacity of 22,000 BTU each, achieve a Seasonal Energy Efficiency Ratio 2 of 15 (15 SEER 2), maintain temperature at 71°F/22°C with ±4°F/±2°C tolerance, provide quiet operation from sunset to sunrise, include auto-off energy waste prevention, and include a 5-year minimum full parts and labor warranty. The contractor must deliver and install the outdoor unit on the ground and the indoor fan coil unit in the attic at existing locations, provide all necessary ductwork and refrigerant piping, reuse existing electrical wiring and line voltage circuits, provide new condensate piping, connect to the existing Ecobee Wi-Fi thermostat, and verify system operation per manufacturer guidelines. Work must be completed within 60 days of the Notice to Proceed during normal business hours (8 AM–5 PM, Monday–Friday) with minimum 72-hour advance notice for utility outages. The contractor must maintain a current Virginia contractor license, obtain all necessary permits and licenses, provide training to USGS personnel, and submit complete maintenance data, training manuals, and manufacturer warranties upon completion. Special site considerations include a 600-foot exclusion radius around two magnetic operations buildings and coordination with building tenants to minimize disruption.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140G0226Q0094_Amd_0003.pdf | ||
| Sol_140G0226Q0094_Amd_0002.pdf | ||
| Sol_140G0226Q0094_Amd_0001.pdf | ||
| B05_Atch_2_Wage_Determination.pdf | ||
| Sol_140G0226Q0094.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work
Heat Pump System Replacement for USGS Fredericksburg Magnetic Observatory
A. Background
The USGS Geomagnetism Program established its first observatory at Cheltenham, Maryland in 1900, when the Program was part of the Coast and Geodetic Survey. The USGS Fredericksburg Magnetic
Observatory was moved to Fredericksburg in 1956, a site that for many years served as the Program’s headquarters. Today, because it has produced high-quality data for so many years, Fredericksburg is one of the world’s most important observatories.
The USGS Fredericksburg Magnetic Observatory site consists of thirteen buildings on approximately 45 acres. The building of interest for this project is the Office Building (Building 8) (Fig. 1).
Building 8 is 1-story wood frame structure containing approximately 2,078 square feet of space. It is used as office space and to house computer servers and data communication equipment. Although USGS uses some space in this building, the main tenant is the Bureau of Indian Affairs. The building was constructed in 1955 and rehabilitated for its current purpose circa 2008.
One of the existing heat pump split systems that serve Building 8 needs to be replaced. The unit to be replaced serves the central/common area of Building 8.
B. Objective
The objective of this project is to replace the existing incorrectly functioning heat pump unit at the observatory Office Building (Bldg. 8) with a new heat pump system.
C. Project Location
USGS Fredericksburg Magnetic Observatory
4270 Tesla Road
Woodford, VA 22580
D. USGS Points of Contact (POC)
Contracting Officer: TBD
Facility Manager (acting): Krissy Lewis
USGS Geomagnetism Program Facility Manager, Acting
303-273-8471 klewis@usgs.gov
Site Representative: TBD
E. Requirements
Minimum Requirements for the Building 8 heat pump split system:
• 120-volt, single phase
• High efficiency o Maintain 71°F/22°C with ±4°F/±2°C o Seasonal Energy Efficiency Ratio 2: 15 (15 SEER 2) o Peak Hours Energy efficiency o Quiet or reduced noise operation from sunset to sunrise o Auto-Off energy waste prevention.
• Cooling capacity: 22,000 BTU
• Heating capacity: 22,000 BTU
• 5-year minimum full parts and labor warranty.
Any necessary accessories for installation and operation shall also be included.
F. Tasks
The contractor shall complete the following:
1. Tasks – Building 8
a. Deliver, uncrate, and assemble new units.
b. Remove and dispose of old units.
c. Install new outdoor heat pump unit on the ground within the same location as the existing heat pump unit.
d. Install new indoor fan coil unit in the building attic area within the same location as the existing fan coil unit.
e. Provide and install all necessary ductwork required to connect the new indoor fan coil unit to the existing duct system.
f. Reutilize the existing line voltage wiring for both the indoor fan coil unit and the outdoor heat pump unit.
mailto:klewis@usgs.gov
g. Provide and install new outdoor electrical disconnect and reconnect the existing line voltage circuit to the new outdoor electrical disconnect.
h. Provide and install a new liquid-tight electrical circuit from the outdoor disconnect to the new heat pump unit.
i. Reconnect the existing line voltage electrical circuits to the new fan coil unit. Reutilize both of the electrical disconnects located in the attic.
j. Provide and install all necessary refrigerant piping to connect the new heat pump equipment to the existing refrigerant piping.
k. Provide and install new condensate piping as required to connect the new fan coil unit to the existing condensate piping located in the attic.
l. Connect new unit to Ecobee Wi-Fi programmable thermostat currently located in
Building 8.
m. Check system to ensure it operates within manufacturer’s guidelines.
G. General Performance and Requirements
The contractor shall:
1. Furnish all labor, equipment, and supervision.
2. Confine operations to prevent or minimize damage to the natural surroundings, and plant material.
3. Protect existing structures and finishes, both interior and exterior, from damage during construction.
4. Coordinate with USGS regarding any required utility outages a minimum of 72 hours in advance.
5. Provide temporary weather protection to prevent damage to any interior areas.
6. Keep dust and dirt pollution to a minimum and ensure safety of persons in the work area.
7. Be responsible for the repair or replacement of damaged building material or components resulting from the demolition or installation of items under this contract. Materials and methods shall match existing structures.
8. Take all necessary precautions to prevent fires or injury to the public, building occupant(s), or damage to property of others during the performance of this contract.
9. The Contractor shall at all times keep the work area, including storage areas, free from accumulations of waste materials. Before completing the work, the Contractor shall remove from the work and premises any rubbish, tools, equipment, and materials that are not the property of the Government. Upon completing the work, the Contractor shall leave the work area in a clean, neat, and orderly condition satisfactory to the Facility Manager or Site
Representative. Train designated USGS personnel in adjustment, operation, maintenance, and safety requirements of the installed systems and other pertinent equipment.
10. All construction debris and rubbish shall be removed from the site daily and disposed of properly according to local, State, and federal guidelines.
11. The contractor shall be responsible for making all arrangements for the receipt of materials and supplies at the job site. Government personnel are not permitted to receive or sign for items delivered to the site.
H. Hours of Operation
Normal working hours shall be between 8 AM and 5 PM, Monday-Friday. The contractor shall not work
Saturdays, Sundays, legal holidays, or other non-normal working hours, unless otherwise authorized by the Contracting Officer. Requests to work times other than normal hours shall be made in writing.
I. Special Site Considerations
The contractor shall not work or store equipment or materials within a 600’ radius of the two magnetic operations buildings on site. The two magnetic buildings are the Variations building and Absolutes building; see Fig 1.
Building 8 will be occupied by tenants during this project. The contractor shall coordinate their work schedule with the tenants and take special consideration in minimizing any affects this work may have on the tenants. The contractor shall immediately notify the CO or Facility Manager if the work will affect the habitability of the office.
Contractor shall provide on-site toilet facilities for workers if determined necessary; contractor will not have access to USGS lavatory facilities. Facilities (porta-johns) will be located in coordination with the
Site Representative.
Contractor will have access to water from the hose bibs and power from the building’s outlets, both of which will be provided at no charge. The contractor is responsible for installing and removing their own temporary connections (hoses, extension cords, etc.) and for carefully conserving Government utilities.
See FAR 52.236-14, Availability and Use of Utility Services.
J. Deliverables
The contractor shall submit the following to the USGS Facility Manager:
1. Information Documents
a. A complete set of maintenance data and information for the newly installed HAC system.
i. Training manuals
ii. Manufacturer warranties
K. Schedule
The contractor shall (a) commence work under this contract once given the Notice to Proceed by the
Contracting Officer, (b) prosecute the work diligently, and (c) complete the work no later than 60 days from the Notice to Proceed. The time for completion shall include final cleanup of premises.
L. Quality Assurance
1. The contractor shall be responsible for visiting and inspecting the site to verify measurements, ascertain the nature and quality of the work to be performed, inform themselves of the general and local conditions (which can affect the work or the cost thereof), and compare the specifications with the work to be performed. Failure to do so will not relieve the successful contractor of their responsibility for estimating properly the difficulty or cost of furnishing materials and successfully performing the work in accordance with the true meaning of the specifications without additional costs to the government. Drawings furnished may not be to scale.
2. In any case of discrepancy in the specifications, the matter shall be immediately submitted to the Contracting Officer, without whose decision said discrepancy shall not be adjusted by the contractor, save only at their own risk and expense.
3. Any changes affecting the scope of work shall originate from or be approved by the
Contracting Officer in writing.
4. All materials and workmanship shall be subject to the inspection and approval of the USGS
Facility Manager or Site Representative. All work unsatisfactorily performed shall be promptly corrected and made acceptable to the Government at no extra cost.
5. The Contractor shall confine all work on the Government premises to areas authorized or approved by the USGS Facility Manager or Site Representative.
6. The USGS Facility Manager or Site Representative shall perform final inspection and acceptance with the contractor on-site upon completion of job performance.
M. Conditions Affecting the Work
It will be the responsibility of the contractor to inspect the site, determine the quantity of work involved, compare the specifications with the work to be done, and inform themselves as to all conditions, including other work, if any, being performed. Failure to do so will in no way relieve the successful contractor from the necessity of furnishing any materials or performing any work that may be required to carry out the contract in accordance with the true intent and meaning of the specifications without additional cost to the
Government. Contractor is required to have a CURRENT contractor license issued by the state of
Virginia.
N. Licenses-Permits
The contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses or permits, and for complying with any Federal, State, and Municipal laws, codes, and regulations in connection with the execution of the work.
O. Indemnity
The contractor shall confine all work on Government premises to areas authorized or approved by the
Contracting Officer or Facility Manager. The contractor shall save and keep harmless and indemnify the
Government against any and all liability claims, and costs of whatsoever kind and nature of injury to or death of any person or persons and for loss or damage to any property (Government or otherwise) occurring in connection with or in any way incident to or arising out of the occupancy, use, service, operations, or performance of work in connection with this contract, resulting in whole or part from the negligent acts or omissions of the contractor.
Figure 1: Site Layout at USGS Fredericksburg Magnetic Observatory. Red box indicates the Office
Building (Building 8). The Variations Building (Building 1) is the location of the scientific sensors.
Figure 2: Building 8 South View
Figure 3: Building 8 West View