This is a Statement of Work (SOW) for rehabilitating the Stovepipe Wells Reverse Osmosis (RO) Treatment Building located in Death Valley National Park, California. The project involves comprehensive upgrades to an existing water treatment facility originally constructed in the early 1970s, with work elements including installing metal decking under concrete ceilings, reconfiguring the building's entryway, replacing stairs, installing new air-exchange and air handler units, relocating tanks, installing LED lighting, and regrading the ground surface around the building.

The contract (PMIS #249755) includes a base scope of work and an optional additive bid item for installing a free-standing workstation overhead bridge crane inside the building. The crane specifications detail a 2,000-pound capacity system with 30-foot runway length, 7-foot bridge span, and motorized tractor drive operating at 480 volts, three-phase. The project will require adherence to multiple safety and technical standards, including OSHA regulations, ANSI standards, and specific environmental considerations unique to Death Valley National Park. The contractor must submit detailed documentation, including a site-specific safety plan, quality control reports, and comply with strict environmental and safety protocols during construction.

View the file

Other files for this federal contract opportunity

Other files attached to DEVA - REHAB STOVEPIPE WELLS RO BLDG, newest first.
File Type Posted
Sol_140P8125B0009_Amd_0002.pdf PDF
Sol_140P8125B0009_Amd_0001.pdf PDF
Sol_140P8125B0009.pdf PDF
B08_-_Atch_4_-_Limitation_on_Subcontracting_Report_Template.xlsx XLSX spreadsheet
B08_-_Atch_3_-_Wage_Determination_CA20250020.pdf PDF
B08_-_Atch_5_-_Construction_Contraction_Administration.pdf PDF
B08_-_Atch_2_-_DEVA_ConstructionDrawing.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Death Valley National Park, California

STATEMENT OF WORK:

Rehabilitate Stovepipe Wells Reverse Osmosis Treatment Building

PMIS #249755

By: Steven Bosiljevac, DEVA Civil Engineer Volunteer

February 2024

CONTRACT PRICE SCHEDULE

Death Valley National Park

PMIS NO. 249755

Rehabilitate Stovepipe Wells Reverse Osmosis Treatment Building

Offerors are required to submit an offer that conforms to the Solicitation with pricing for Contract Price Schedule’s Base Line Items and Additive Bid Item #1 Line Item - failure to do so may render the offer non-responsive. On lump-sum price items, provide total cost only; on unit price items, provide the unit price and the extended amount of total price for the item. If no price item exists for a portion of the work, include the costs in a related price item. In case of error in extension of prices, unit price governs. In case of error in summation, the total of the corrected price item amount governs. Round totals and extend prices to whole dollars. Pricing will be evaluated based on what is determined to be the best value to the Government.

Price award will be made based upon the following either:

Base Price:

Base Price: Price Line Items 1 through 9.

Base Price + Additive Bid Item #1 Price:

Base Price + Additive Bid Item #1 Price: Price Line Items 1 through 10.

ITEM TITLE

NUMBER

QUANTITY AND

UNIT OF

MEASURE

UNIT PRICE TOTAL PRICE

1.

Install metal decking under existing concrete ceilings

1 LS @$________ =$_________

2.

Reconfigure entryway into building

3.

Replace stairs from upper-level to lower-level

4.

Install new air-exchange unit 1 LS @$________ =$_________

5.

Relocate (E) backwash tank and

(E) calcite tank

6.

Install aluminum plates over wall openings

7.

Install new ceiling LED lighting 1 LS @$________ =$_________

8.

Install new air handler unit with heat pump

9.

Regrade ground surface around building exterior

1 LS @$________ =$_________

10. Additive Bid Item #1: Free-standing-workstation-overhead-bridge crane

TOTAL BASE PRICE (Items 1 to 9) -------------------------------------------------------- =$_________

TOTAL BASE PRICE + Additive Bid Item #1 (Items 1 to 10) -------------------------- =$_________

END OF SECTION

DEVA 249755 – Rehabilitate Stovepipe Wells Reverse Osmosis Treatment Building

STATEMENT OF WORK (SOW)

1. PROJECT LOCATION

The Stovepipe Wells areas within Death Valley National Park is located in Inyo County, California and is an approximately 2.5-hour drive (approximately 150 miles) west from Las Vegas, Nevada. The work site is located 0.22 south on Mosaic Canyon road coming off of Highway 190 at the west end of Stovepipe Wells Village. Generally, the speed limit on Highway 190 within Death Valley National Park is 65 MPH; however, there are numerous reduced speed zones within the Park.

2. OBJECTIVES:

The objective of this rehabilitation project is to make limited changes and improvements to the building to improve near-to-mid-term functionality of the facility.

3. PLACE OF PERFORMANCE:

The reverse osmosis treatment building located to the south southwest of the Stovepipe Wells Village in Death Valley National Park on Mosaic Canyon road.

Google Earth Image of the Stovepipe Wells area of Death Valley National Park.

4. PERIOD OF PERFORMANCE:

The Contracting Officer will specify the Period of Performance in the Construction Contract.

5. SUMMARY OF WORK:

This project’s scope of the Base is comprised of work elements that will provide for limited changes to the reverse osmosis treatment building (and equipment located within it) that was originally constructed in the early 1970s and to which multiple changes have since been made.

Roof decking will be installed on the underside of the existing concrete ceilings to prevent spalling concrete from falling from the ceilings. Most of the existing fluorescent lighting will be replaced with LED lighting – with existing plywood and pole shores to be removed. The building entrance will be reconfigured to increase the size of the entrance way from a single door to a double door. The air-exchange unit will be replaced, as will the HVAC air handler unit. The existing metal stairway will be replaced. Two tanks, calcite tank and backwash tank, used in the RO treatment system will be relocated and their associated plumbing will be replaced. The ground surface along the north, south, and east sides of the RO treatment plant building will be graded to allow for gravity flow of surface water away from the building and into the nearby natural drainage features.

The scope of Additive Bid Item #1 is to install a free-standing-workstation-overhead-bridge crane inside of the RO treatment plant building.

6. DESCRIPTIONS OF WORK ITEMS:

Under this contract, the contractor shall complete the following work items in accordance with the requirements given in these specifications:

A. General:

1. The intent of this section is to explain, in general, what is and what is not included in a Contract Price Schedule Line Items, and the limits where one Contract Price schedule Line Item ends and another begins.

2. The total contract price must cover all work required by the Contract Documents.

All costs in connection with the proper and successful completion of the work, including furnishing all materials, equipment, supplies, and appurtenances;

providing all construction equipment and tools; and performing all necessary labor and supervision to fully complete the work, must be included in the unit and lump sum prices of the Contract Price Schedule Line Items. All work not specifically set forth as a pay item in the Contract Price Schedule Line Items must be considered subsidiary obligations of the Contractor and all costs in connection therewith must be included in the prices submitted for the Contract Price Schedule Line Items.

3. If no Contract Price Schedule Line Item exists for a portion of the work, include the costs in a related Contract Price Schedule Line Item.

4. The description of the work of this section constitutes a summary of the work for the purpose of defining the contract work and is not intended to provide a detailed and exhaustive description of all aspects of the entirety of the work. For the complete and comprehensive description of the work all documents pertaining to the Contract Documents must be collectively considered.

B. Estimated Quantities:

1. All estimated quantities stipulated in the Contract Price Schedule or other Contact Documents are approximate and are to be used only:

a. As a basis for estimating the probable cost of the work.

b. For the purpose of comparing the Contract Price Schedules submitted for the work.

2. The basis of payment for unit price work and materials will be the actual amount of work done and materials furnished up to the not-to-exceed quantity.

3. Except where otherwise specified the unit or lump sum price for each Price Line Item and Option #1 Line Item of work must include all costs for such work.

C. Item Number 1 – Install metal decking under existing concrete ceiling - This line item consists of all labor, equipment, and materials required to install the metal decking (and associated appurtenances) in accordance with the Construction Documents. This item will be paid on a lump sum item basis.

D. Item Number 2 – Reconfigure entryway into building: This line item consists of all labor, equipment, and materials required to reconfigure the entryway into the building in accordance with the Construction Documents. This item will be paid on a lump sum item basis.

E. Item Number 3 – Replace stairs from upper level to lower level: This line item consists of all labor, equipment, and materials required to replace the stairway in the building that provides access from the upper level to the lower level of the building in accordance with the Construction Documents. This item will be paid on a lump sum item basis.

E. Item Number 4 – Install new air-exchange unit: This line item consists of all labor, equipment, and materials required to replace the existing air-exchange unit (aka confined space exhaust fan) in the building with a new air-exchange unit in accordance with the Construction Documents. This item will be paid on a lump sum item basis.

F. Item Number 5 – Relocate (E) backwash tank and (E) calcite tank: This line item consists of all labor, equipment, and materials required to relocate the (E) backwash tank and (E) calcite tank in the building in accordance with the Construction Documents.

This item will be paid on a lump sum item basis.

F. Item Number 6 – Install aluminum plates over wall opening: This line item consists of all labor, equipment, and materials required to install aluminum plate over designated openings in the walls in the building in accordance with the Construction Documents. This item will be paid on a lump sum item basis.

G. Item Number 7 – Install new ceiling LED lighting: This line item consists of all labor, equipment, and materials required to install new LED lighting on the ceilings in the building in accordance with the Construction Documents. This item will be paid on a lump sum item basis.

H. Item Number 8 – Install new air handler unit with heat pump: This line item consists of all labor, equipment, and materials required to replace the existing air handler unit and compressor unit in the building with a new air handler unit and a new heat pump unit in accordance with the Construction Documents. This item will be paid on a lump sum item basis.

I. Item Number 9 – Regrade ground surface around building’s exterior: This line item consists of all labor, equipment, and materials required to grade the ground surface on the north, south, and east sides of the building’s exterior in accordance with the Construction Documents. This item will be paid on a lump sum item basis.

J. Additive Bid Item #1: Free-standing-workstation-overhead-bridge crane: This line item consists of all labor, equipment, and materials required to install a free-standing-workstation-overhead-bridge crane in the building in accordance with the Construction Documents. This item will be paid on a lump sum item basis.

7. MATERIAL REQUIREMENTS:

A. Metal decking to be installed on the ceiling bays of the upper level and lower level: The metal decking shall be ASTM A653 SS Grade A50 steel, 22 gage having a cross-sectional geometry providing an effective moment of inertia of at least 0.178 inches to the fourth power per foot, an effective section modulus (at 50 ksi) of 0.176 inches cubed per foot, and vertical web shear of at least 2688 pounds per foot. The surface of the decking facing the existing concrete ceiling shall have a gray primer coat applied to it, and the visible surface of the decking shall have a white primer coat applied to it.

B. Angle steel for supporting the metal decking: The metal decking shall be supported continuously on both ends on ASTM A36 (minimum) steel angle – 3” X 3” x 3/16”.

C. Concrete anchors for mounting angle steel supporting the metal decking: The steel angle shall be fastened to the existing concrete beams supporting the concrete ceilings using high-performance ½” diameter anchor rod for use with injectable hybrid/epoxy anchors (carbon steel, ASTM F1554 grade 36, hot-dip galvanized) at three feet on center. Mechanical wedge anchors are not permitted

D. LED lighting: The components of the LED lighting fixtures system must comply with the

National Electric Code (NEC.) The LED lighting fixtures shall be for tube lighting four feet in length and must be rated for industrial water treatment buildings where chlorine is present.

Each LED lighting fixture shall hold two four-feet-long LED tubes. For each LED lighting fixture (have two four-feet long LED tubes) the color rendering index must be a minimum of 80 and it must have a minimum brightness output of 5,200 lumens. The LED lighting fixtures must be mountable to the steel decking. Wiring for the LED lighting fixtures can be either PVC or metal and must be NEC compliant, as well as all associated electrical components.

The existing fluorescent lighting system components (including ballasts) cannot be converted for installation of the new LED lighting fixtures. The LED tubes must be rated for a minimum functional life of 50,000 hours.

E. Electrical conductors and electrical conduit for LED lighting system: The electrical conductors and electrical conduit must comply with the NEC. The electrical conductors shall be insulated copper and the electrical conduit shall be either PVC or metal.

F. Aluminum plate: The sheets of aluminum plate for covering the wall/door openings into the elevator shaft shall be a minimum 3/16 inch thick. The aluminum plate shall be fastened to the reinforced concrete walls using high-performance 3/8” diameter anchor rod for use with injectable hybrid/epoxy anchors (carbon steel, ASTM F1554 grade 36, hot-dip galvanized) at eighteen inches on center both vertically and horizontally. For openings smaller than eighteen inches (horizontally or vertically or both) shall have a minimum of four anchors with one anchor installed at each corner. Provide two inches of distance from the center of the anchor to the edge of the aluminum plate.

G. Entry door: The entry door shall be an exterior-rated metal double door (each door 36” wide by 80” high) 18 gauge with polystyrene core with integral door frame flush mounted with weather stripping across the top and the full length on each side. The doors do not need to be fire rated. The configuration shall be a left hand reverse active (left side door opens to the outside lefthand side) and an inactive right hand side door opens outside to the right with 180 degree rotation – the inactive right hand door shall have stainless steel surface bolts installed at both the top and bottom of the door on the inside (with fasteners installed in the door frame above the upper surface bolt and in the threshold below the lower surface bolt.)

The lock shall be a rim cylinder & C keyway. Both doors shall have 12” by 34” kick plates on the outside face. A full-length security astragal shall be installed on the outside of the lefthand side door. Both doors shall have kick stops mounted on the inside of the door along with a bottom sweep with EPDM insert. Below the doors a metal threshold shall be installed. The west side of the new door frame shall be secured to a new 8-inch steel channel section – the steel channel section shall be installed vertically up against the remaining windows’ frame with the top and bottom of the channel section welded to new steel plate (ASTM A36) fastened to the existing concrete using high-performance 3/8” diameter anchor rod for use with injectable hybrid/epoxy anchors (carbon steel, ASTM F1554 grade 36, hot-dip galvanized.) The opening left from the removal of the single door shall be closed off using steel plate fastened to the concrete surface on the north side of this opening and then 4-inch channel sections shall be installed in an “X” configuration with then aluminum sheets (3/16th inch thick) are to be fastened to the flanges of the channel sections on both the inside and outside of the building.

H. Steel plate and steel angle for steel collar around concrete column on the lefthand side (when entering the building) of the entryway: ASTM A36 steel plate 3/16” thick and 2” by 2” by 3/16” steel angle.

I. Channel section structural steel and steel decking to extend the existing upper level: The steel decking to extend the existing upper level floor deck (steel deck with plywood on top of

it) shall match the existing steel decking. The extended deck section shall be framed used 8-inch ASTM A36 steel channel welded to the existing steel frame of the upper level. This deck extension shall have plywood installed on the new steel decking that matches the thickness of the existing plywood surface of the upper level.

J. Stairs: OSHA compliant industrial stairs and handrails made of ASTM A36 steel (minimum.)

Stairs shall be comprised of bar grating treads with open riser. Handrails shall be combination hand/stair rail on both the right and left hand sides. Stairs and handrails shall be painted with a gray primer coat and a blue-colored commercial paint for use in water treatment facilities where chlorine is used.

K. Air-exchange unit (aka confined space exhaust fan): The air-exchange unit must have a high speed with a capacity of at least 1,000 cubic feet per minute and a low speed with a capacity of at least 30 cubic feet per minute but not more than 50 cubic feet per minute. The new unit must be able to be installed on the existing 10-inch ductwork (circular cross-section.) An electronic actuated starter switch must be installed on the new entryway door to activate the air-exchange unit to turn on the high-speed setting when the door is first opened and then have a timer feature to shut off the air-exchange unit’s high speed setting after a set duration of time has passed. The air-exchange unit electrical controls shall be configured to normally run the air-exchange unit continuously on the low-speed setting. All electrical components must be compliant with the NEC. A one-way (from outside to inside the building) fresh air supply vent with copper/brass insect mesh screen to be installed in the panel above the single door (to be demolished) next to the ventilation ductwork passing through this panel.

L. PVC pipe & appurtenances for re-plumbing the calcite tank and backwash tanks: PVC schedule 80 pipe and fittings. Match the diameter of the existing process piping connections to these two tanks.

M. Chemical tank riser-pad: A rectangular concrete riser-pad using 3,000 psi concrete with two reinforcing steel mats (60 ksi, #3 rebar at 6” on center each way) – one reinforcing steel mat being 3” above the existing concrete floor and the second mat being 3” from the top surface of the new concrete pad – giving 3” of concrete cover. The concrete pad must be no more than 6” larger in both horizontal directions than the diameter of the circular storage tank that will be installed on top of the concrete pad. The seismic restraints for the circular storage tanks shall be fabricated from 2-inch wide by 3/16” thick ASTM A36 steel. The seismic restraint shall be configured with one circular band around the tank’s circumference at 12” above the base of the tank and a second circular band around the tank’s circumference at a point 12” above the mid-height of the tank measured along the tank’s vertical axis – ¼” neoprene rubber padding must be fixed between the horizontal steel bands and the tank to prevent the steel band from being in direct contact with the exterior surface of the tank. There must be four vertical bands of the 2” wide by 3/16” ASTM A36 steel equally spaced from each other (in the 12 o’clock position, 3 o’clock position, 6 o’clock position, and the 9 o’clock position) that are welded to both of the horizontally oriented circular steel bands and that extend done to the existing concrete floor slab where the steel strip will have a 90-degree bend creating a 3” inches long “foot.” Each of these four “feet” will be anchored to the existing concrete floor slab using a high-performance ¼’” diameter anchor rod for use with injectable hybrid/epoxy anchors (carbon steel, ASTM F1554 grade 36, hot-dip galvanized.)

N. Air handler unit with heat pump: The air handler unit must be Energy Star rated, sized for

16,560 cubic feet of interior building volume, and employ energy recovery ventilator technology. Heat pump unit must be Energy Star rated and have a capacity of 6 tons. All the electrical components associated with the installation of the air handler with heat pump must be compliant with the NEC.

O. Free-standing-workstation-overhead-bridge crane: See Appendix A.

8. EXECUTION OF WORK:

A. Outline of activities for the installation of the metal deck to the ceilings of the upper level and lower level of the RO treatment building:

1. Remove all existing temporary pole shores and plywood from the lower level ceiling.

These materials are to remain the property of the government.

2. Remove all light fixtures, electrical conduit, and any other features mounted to the upper level ceiling and beams and the lower level ceiling and beam to allow for the installation of the metal decking.

3. Install metal decking up tight against the upper level ceiling and lower level ceiling with the ends of the metal decking supported on angle steel fasted to the sides of the reinforced concrete beam that support the concrete ceiling slabs. There must not be any electrical conduit or other materials between the concrete surface of the ceiling and the new metal decking. The surface of the metal decking painted white shall be installed facing downward – visible to a person looking up at the ceiling when standing on the floor of the lower level.

4. The metal decking is to be installed on all concrete ceiling surfaces in the RO treatment plant building except for the ceiling (of the upper level) inside of the elevator shaft.

B. Outline of activities for the replacement of the existing single door entryway with a new double door entryway:

1. Demolish the existing entry door to also include demolishing the door frame. The small rectangular opening above the doorframe with the air-exchange duct must remain and not be damaged.

2. Install plate steel and steel angles around the concrete column on the southside of the single door’s frame (after demolition) forming a steel jacket around this column.

3. Fasten steel plate to the concrete along the north side of the opening left after the removal of the single door and install a 4-inch section of channel steel across the top (below the small rectangular panel above the doorway through which the air-exchange ductwork runs), then install 4-inch channel steel sections in an “X” patten within this opening welding the channel sections at the top and bottom to the steel plate installed on the concrete and where the two channel sections cross at the midpoint of the “X” configuration. Then install aluminum sheet to the flanges of the channel sections on both the inside and outside of the building to permanently close off this opening.

4. Remove the two sections of existing windows immediately to the west of the single doorway. Also demolish the reinforced concrete wall underneath these two window sections down to the outside floor level in what is the old delivery bay of the building.

5. Install 8-inch steel channel section vertically on the west end of the opening for the double doors butting up against the window frame of the remaining windows.

6. Extend the steel deck of the upper level to the west approximately two feet so that the west end of this steel deck aligns with the west end of the double door frame.

7. Extend the hand railing around the steel deck to enclose the newly added section on the west end.

8. Install the door frame for the double doors.

9. Install the double doors and the associated appurtenances.

10. Install the electrical control device for switching on the new air-exchange unit when the active lefthand door of the double doors is opened.

C. Outline of activities for the installation of the new (OSHA compliant) steel stairway with steel handrailing from the upper level steel deck down to the reinforced concrete floor of the lower level:

1. Demolish existing stairs and handrailing and dispose of outside of the Park.

2. Dimension new stairs to fit within the existing space between the southern end of the upper level steel deck (and its supporting structure) and the building’s reinforced concrete south wall.

3. The landing section of the new stairs shall be configured to allow for access to the stairs from the floor (steel decking) of the upper storing.

4. Install new stairs and hand/stair railings (lefthand and righthand) securing the stairs structure to the upper level structure, the east and south reinforced concrete walls of the building, and the reinforced concrete floor of the lower level.

D. Outline of activities for the installation of the new air-exchange unit:

1. Demolish existing air-exchange unit installed inline on the ductwork. The government shall retain possession of this existing air-exchange unit.

2. Install the new air-exchange unit and its associated electrical components/connections to the building power circuit breaker panel and the switching at the entry door. If the installation of the new air-exchange unit will not be in the location that the existing was in, submit a shop drawing of the suggested new installation configuration for review and approval by the Contracting Officer.

3. Install one-way (flow into the building from outside) vent in the panel above where the single door frame had been before being demolished. The vent shall be installed in the section of the panel next to the air-exchange ductwork.

E. Outline of activities for the relocation of the calcite tank and the backwash tank:

1. Disconnect the existing process piping to both the calcite tank and the backwash tank and temporarily relocate the tanks to an out of the way location in the lower level of the building.

2. Confirm the locations and elevations of the base for each of the two tanks with the Contracting Officer.

3. Install the concrete tank pads at the confirmed locations for each of the two tanks – the concrete for these two pads is to be poured in concrete forms directly on top of the concrete flow of the lower level. The thickness of each of the two concrete pads shall be such that the base of the tank will be at the required elevation confirmed by the Contracting Officer.

4. Allow the concrete pads to cure for five days. After five days, place each tank on its tank pad and install the seismic restraint device to be fabricated from 2” X 3/16” steel plate. Anchor the seismic restraint devices to the existing concrete floor of the lower level of the building – DO NOT anchor the seismic restraint devices to the newly constructed concrete tank pads.

5. Reconnect the process piping to each of the two tanks providing the necessary reconfiguration of the process piping to accommodate the new locations of the two tanks.

F. Outline of activities for the installation of aluminum plate sheets:

1. Install aluminum sheets over the designated openings in the reinforced concrete walls at the lower level pertaining to the now unused elevation system.

2. The seams of the aluminum sheets can be oriented either vertically or horizontally.

The seams shall be intermittently tack welded to maintain both sheets of any one seam are maintained in the same vertical plane.

3. Fasten the aluminum sheets to the reinforced concrete walls using concrete anchors.

G. Outline of activities for the installation of the new LED lighting:

1. Demolish existing fluorescent lighting fixtures and their appurtenances attached to the ceiling slabs and the associated concrete beams of the lower level and the upper level.

2. Install two LED lighting fixtures in each of the ceiling bays of the upper level and lower level – the lower level has seven ceiling bays and the upper level has eight ceiling bays.

3. LED lighting fixtures shall be fastened to the new metal decking.

4. The two LED lighting fixtures shall be installed end to end (not side by side) within each ceiling bay and centered both along the east-west axis and the north-south axis.

5. Re-use the existing light switches to control the new LED lighting fixtures where it exists, and where there is no existing switches to re-use, install new switches.

6. Connect the LED lighting fixtures to the electrical breakers using copper electrical conductors inserted into electrical conduit in accordance with the NEC.

7. Make necessary configuration changes to the electrical panel wiring and circuit breakers as necessary to provide power to the new LED lighting fixtures in accordance with the NEC.

8. No LED lighting fixtures shall be fastened to the bottoms or sides of any reinforced concrete beams of the upper level or the lower level ceilings.

H. Outline of activities for the installation of the new air handler with heat pump.

1. Demolish the existing York air handler (inside the building) and the associated compressor (outside of the building) and dispose of these two outside of the Park.

2. Install the new air handler with heat pump following the manufacturer’s recommendations. Provide to the Contracting Officer a submittal of the shop drawings detailing the installation of the air handler with heat pump for review and approval.

I. Outline of activities for grading around the RO treatment building:

1. The grading around the RO treatment building (on the north, south, and east sides) is required to contour the soil surface so that surface water (resulting from precipitation) flows by gravity away from the building and into the surrounding natural drainage features.

2. The soil surface along the exterior face of the building’s walls must be at least two inches or more below the top of the building’s walls along the north, south, and east sides of the building.

3. Low soil berms shall be created along the north and south sides of the upper section of the recessed dirt access road to the RO treatment building coming off of Mosaic Canyon road. The berms shall be configured to prevent surface water from flowing from the upper section of the embankment down the embankment to the road surface. The berms shall be extended to approximately six feet east of the west end of the RO treatment plant’s northwest and southwest corners.

4. The grading shall be done conforming to best practices for controlling soil erosion and sediment transport.

5. A site grading plan must be submitted to the Contracting Officer for review and approval prior to commencement of the site grading work. The site grading plan must include the Contractor’s under-an-acre Pollution Prevention Plan.

J. Free-standing-workstation-overhead-bridge crane:

1. See Appendix A.

9. GENERAL REQUIREMENTS (DIVISION 01):

A. Archeological Monitor shall have access to observe all ground-disturbing site work during the site grading work, from a safe location mutually agreed on by Contractor and Monitor. As new ground is broken, Monitor will examine excavated materials, using construction layout centerline and perimeter staking as a reference point to record locations of findings.

B. If Archeological Monitor discovers resources, immediate relocation of the work to another area may be required to allow Monitor to take soil samples and record resources. While Archeological Monitor is documenting resources, Contractor shall relocate work to non-sensitive areas where monitoring is not normally required.

C. If resources are discovered while Archeological Monitor is absent, stop work immediately and report the discovery to the Contracting Officer.

D. All heavy equipment and machinery: Prior to entry into the Park, the Contractor shall be responsible for ensuring all vehicles, equipment and machinery are clean and free of dirt, mud, straw, or other material that could bring weed seeds or other invasive species into the Park.

1. The Contracting Officer shall be notified a minimum of 72 hours prior to entry of vehicles, machinery and or equipment into the Park.

2. All vehicles, machinery and equipment entering the Park must be clean of plant seeds, mud, and soil and free from oil leaks. Pressure wash all construction vehicles, equipment and heavy machinery to thoroughly remove all dirt, plant, and other foreign material prior to bringing these into the Park. Particular attention must be shown to the under carriage, wheels, tracks, and any other surface where soil containing non-native plant seeds may be present.

3. Arrange for the Contracting Officer’s Representative (COR) to inspect each vehicle, piece of equipment, and machinery before these are brought into the Park. Vehicles, equipment, and machinery that has not been adequately cleaned will be turned away.

Vehicles, equipment and machinery found operating at the project site that have not been inspected or have oil leaks will be shut down and subject to citation and removal from the Park – at no cost to the government.

4. Any vehicle, equipment or machinery leaving the park must be inspected outside of the Park prior to reentry into the park.

E. Construction Camp: Establishment of a camp within the park will not be permitted.

F. There is electrical service available at the project site. Contractor shall have access to the electrical power serving the RO treatment plant building.

G. No telephone service is available on site for Contractor’s use. The Contractor must confirm what level of cellular telephone service, if any, is available at the site. The Contractor is responsible for making arrangements to have some form of telephone service within a reasonable distance to the project site. Landline telephone service is available at the motels in Stovepipe Wells Village.

H. Up to 500 gallons per day of construction water is available for the Contractor’s use from the Stovepipe Wells potable water system. The Contractor must make arrangements with the Park’s water operator supervisor on how and where the construction water can be drawn from the water system.

I. Place portable temporary sanitary facilities in approved locations secluded from public observation and convenient to workstations. Relocate as work progress requires. Maintain and clean toilet facilities at least weekly.

J. Completely remove from the Park portable temporary sanitary facilities on completion of work.

K. Dispose of excess excavated material (including rocks and boulders) that cannot be used in construction at a location, as directed by the Contracting Officer, within the disturbed footprint around the RO treatment building. Unless otherwise specified, all removed material becomes the property of the Contractor and shall be disposed of legally outside the park. Immediately remove hazardous rubbish from project site. Place other construction debris in refuse containers at least daily. Dispose of refuse at least weekly, in a legal manner, at public or private dumping areas outside the park. Do not burn or bury refuse inside the park.

L. Before scheduling the final inspection, remove all tools, equipment, surplus materials, and rubbish. Restore or refinish surfaces that are damaged due to work of this contract to original condition. Remove grease, dirt, stains, foreign materials, and labels from finished surfaces.

Thoroughly clean the areas inside of the RO treatment building where work was done. Pick up and remove all construction debris from the site. At the time of the final inspection, the project site shall be thoroughly clean and ready for use.

M. Keep dust to a minimum at the project site and on the unimproved access roads to the project site. Use sprinklers or water trucks as necessary.

N. Contractor shall at all times conduct their operations to ensure the least inconvenience to the public.

O. Work Limits and Equipment Access: The Contractor shall limit all work and storage of materials to the work limits of this project. The work limits are:

1. The existing disturbed footprint around the RO treatment building.

P. Construction Operations: For the safety and convenience of the NPS water operators, the Contractor will conduct his operations in a concise and timely manner. The Contractor will complete and clean up each phase of the work within a reasonable time from starting. The

Contractor shall provide advance notification if their work activities inside of the RO treatment building will require the shutdown of any equipment or electrical circuits that will result in the RO treatment plant operation being stopped. A reasonable time is approximately 14 calendar days typically, but contextual circumstances can lengthen or lessen this number. Consistent communication with the Contract Administration Team is critical for successful coordination of work that will impact the functionality of the RO treatment plant operation.

Q. Public Traffic: Public traffic will be allowed on Mosaic Canyon Road during construction.

Conditions for maintaining public traffic shall be as follows:

1. Signs shall be provided at all times during in-road activities. All signs and traffic control devices shall conform to the Manual of Uniform Traffic Control Devises, Federal Highway Administration, ANSI D6.1. Work shall not start until signs are in place.

2. One lane of traffic shall be maintained along all roads during daylight operations. At night and during weekends, two lanes shall be open to traffic. Barriers shall be erected around all open excavations and material stockpiles.

R. Preservation of Natural Features: Confine all operations to work limits of the project. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.

1. Provide temporary barriers to protect existing plants and root zones.

2. Do not remove, injure, or destroy plants without prior approval. Consult with

Contracting Officer and remove agreed-on plants and roots that interfere with construction.

3. Do not fasten ropes, cables, or guys to existing plants.

4. Carefully supervise excavating, grading, filling, and other construction operations near plants to prevent damage.

S. Existing Utilities: Notify Contracting Officer of proposed locations and times for excavation. If damage occurs to a known existing utility, repair utility at no additional expense to the Government.

1. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the General Provisions.

2. Interruption of Existing Utility Service: The Contracting Officer shall be notified in writing at least 48 hours in advance of any shutdown of the existing electrical system or water system. Such shutdowns shall be planned and scheduled such that the shutdown period is minimized. Shutdowns to make connections to the existing systems shall not exceed 4-hours for each.

T. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials. Load restrictions on park roads are identical to the state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.

U. Permits: A general building permit is not required for work on NPS land.

V. Prohibited Items: The following items are prohibited:

1. Firearms / weapons / ammunition;

2. Alcohol and illicit drugs;

3. Pets.

W. Smoking Policy: Smoking is prohibited within the boundaries of the project site – both inside and outside of the RO treatment building.

X. Protection of RO Treatment Plant Features and Process Equipment:

1. Throughout all Phases of the Work, confine all operations to Project Site limits and protect RO treatment plant features and process equipment not scheduled to be impacted by the Work.

2. In the event that damage occurs, Contractor shall restore damaged RO treatment plant features and process equipment, repairing or replacing damaged RO treatment plant features and process equipment to their original condition, at no additional expense to the Government.

10. QUALITY ASSURANCE REQUIREMENT:

The contractor shall develop and maintain a quality assurance program to ensure services are performed in accordance with commonly accepted standard practices and in compliance with all applicable code. The contractor shall develop and implement procedures to identify and prevent defective workmanship. As a minimum the contractor shall develop quality control procedures addressing the critical areas identified in this statement of work. The government will periodically evaluate the contractor’s performance in accordance with the statement of work.

Codes & Standards: The Contractor shall complete all work in accordance with the latest versions of applicable codes, standards, and regulations. The following codes and standards are directly related to the project:

A. NFPA 101 (National Fire Protection Association’s Life Safety Code) (latest edition) B. NFPA 70 National Electric Code (NEC) (latest edition) C. Occupational Safety and Health Administration (OSHA) requirements D. California Code of Regulations E. AWWA Standards F. ASTM Standards G. ASCE 7 Structural Loads

Additional Requirements:

A. All affected areas must be restored to their original condition from before the work began. Any damages will be fixed and repaired at no cost to the government.

B. All new equipment must conform to the manufacturer’s instructions and guidelines.

C. Contractor’s Quality Control (CQC) Plan:

1. The Contractor shall provide a written Contractor Quality Control (CQC) Plan to the Government for approval prior to mobilization:

a. The Government reserves the right to require changes in the plan prior to approval;

b. The Government reserves the right to require changes in the plan during the

Contract Period as required to ensure the specified quality of Work;

c. Following approval, no change in the CQC Plan may be made by the

Contractor without written concurrence by the Government.

2. At a minimum the CQC plan shall include, but may not be limited to, the following:

a. A list of personnel responsible for QC and their assigned duties;

b. Methods of performing, documenting, and enforcing QC of all Work;

c. Methods of monitoring and controlling environmental pollution and contamination as required by regulations and laws.

D. Contractor's Quality Control Daily Reports (CQCDR):

1. The Contractor shall submit CQCDR on a daily basis and these shall include the following:

a. Daily weather conditions;

b. Personnel and subcontractors on site each day;

c. Tasks undertaken and/or completed each day;

d. Off-site fabrication (where applicable);

e. Inspections;

f. Testing.

2. Use form acceptable to the Government;

3. Include a minimum of five (5) photos of each CLIN’s work activities with each

CQCDR. See PART 3 Article “Photo Documentation” herein for further requirements.

4. If the CQC Plan and CQCR’s are not submitted as specified herein, the Government may retain all or a portion of payments until such time as a plan is accepted and implemented and/or all outstanding CQCR are received.

11. SUBMITTALS:

A. Division 01 documents: The following items must be submitted a minimum of one week prior to the Preconstruction Conference. Contracting Officer will notify Contractor of tentative date for the Pre-Construction Conference.

1. Letter designating Project Superintendent.

2. Construction Schedule.

3. A comprehensive breakdown of the Schedule of Values.

4. Safety Plan.

5. A list of Subcontractors for this project.

6. Written statements from subcontractors certifying compliance with applicable labor standard clauses.

7. Satisfactory evidence of liability insurance coverage and workman’s compensation for the Contactor and all subcontractors.

8. Quality Control Plan.

9. Under-An-Acre Pollution Prevention Plan.

B. Technical Documents Submittals: The following documents shall be submitted to the

Contracting Officer prior to construction mobilization. If these documents have not been received and approved by the NPS prior to construction, the construction start date may be delayed.

1. Product Data – Submit product cut sheets / material data on all products to be used for approval. Indicate the size, model, or type of each recommended product.

2. Samples – When requested, submit a physical sample of a product or an array of color choices for approval, if applicable.

3. Shop Drawings - Submit shop drawings that embody all major elements of the work.

a. Drawings shall be developed in AutoCAD or similar drafting software.

b. Drawings shall include details, dimensions, notational information and other data to ensure the contractor has a complete understanding of the work.

c. Drawings shall be submitted to the Contracting Officer in PDF format. Allow 7 calendar days for the drawings to be reviewed by NPS. The Contractor shall incorporate review comments into the shop drawings and resubmit for final approval.

C. Any work done or orders for materials or services placed before obtaining the

Contracting Officer’s approval shall be at the Contractor’s own risk.

D. Provide a one-year warranty for workmanship, materials, and equipment.

E. O&M Binder submittal organized with tabs and containing the record information

(manufacturer’s cutsheets, O&M requirements, warrantees, etc.) that detail the materials, manufacturers, models, and related data/information needed to carry out the operation and maintenance requirements of the systems’ components installed under the Contract.

12. GOVERNMENT-FURNISHED PROPERTY, MATERIAL, EQUIPMENT, OR

INFORMATION (GFP, GFM, GFE, OR GFI):

There is no GFP on this project.

13. SAFETY REQUIREMENTS:

A. This contractor is to follow at a minimum all OHSA rules and procedures. A required safety plan must be submitted and approved before any work is to begin. This plan shall identify any hazards related to the work and provide measures to follow to mitigate risk.

1. First Aid Equipment: Provide adequate first aid equipment for all contract employees for the hazards associated with the types of ongoing construction work at the site.

2. First Aid Training: Provide adequate training to all Contractor personnel to ensure prompt and efficient application of first aid.

3. Personal Protective Equipment (PPE): Provide personal protective equipment (PPE) that meets applicable OSHA and ANSI standards for all contract employees.

4. Hazardous Materials: Hazardous materials are defined as explosive, flammable, poisonous, corrosive, oxidizing, irritating, or otherwise harmful substances that could cause death or injury. Store hazardous materials in accordance with manufacturer’s and OSHA recommendations. Maintain MSDS onsite for each chemical used on the jobsite. Immediately report all spills of hazardous materials to the contracting officer.

5. Confined space procedures and required equipment.

6. Safety Meetings: At a minimum, conduct weekly "toolbox" safety meetings. These meetings shall be conducted by a job superintendent or crew leader and attended by all construction personnel at the worksite. Topics need to coincide with work scheduled for the week.

7. Emergency Contacts: Post telephone numbers and reporting instructions for ambulance, hospital, fire department, police, and park dispatch in conspicuous locations at the site.

B. Fire Protection During Construction: The important historic buildings on the historic site DO NOT have the protection afforded from a fire department available – there is no fire department on the island. The buildings and site shall be protected against fire at all times throughout the performance of the Work.

1. Provide fire extinguishers, of appropriate type, at each building throughout course of

Work.

C. Hot Work:

A. In the event Hot Work must be performed to accomplish the Work, the Contractor shall obtain a Hot Work Permit from the Government.

a. Hot Work shall only be performed in “designated” and/or “permit-required” areas.

b. A Hot Work Permit is required for Work in a “designated” area.

c. A Hot Work Permit is required for Work in a “permit-required” area.

d. The Contractor shall obtained a signed Hot Work Permit, issued by the Park

Structural Fire Coordinator or his/her designee, for Work performed in a “permit-required” area.

e. A separate permit will be required for each Hot Work event.

f. Apply for Hot Work Permits a minimum of seventy-two (72) hours prior to the hot work event.

B. Definitions:

a. Designated Area: An area specifically designated for or approved by the Park Structural Fire Coordinator or his/her designee, for Hot Work.

i. A designated area can be a maintenance shop or a detached outside location that is of noncombustible or fire-resistive construction, essentially free of combustible and flammable contents, and suitably segregated from adjacent areas. All designated areas shall have been inspected and approved by the Park Structural Fire Coordinator or his/her designee.

b. Permit-Required Area: A permit-required area shall be an area that is made fire safe and authorized by the issuance of a signed NPS Hot Work Permit.

c. Non-permissible Areas: Hot work shall not be allowed in the following areas:

i. Areas not authorized by the Park Structural Fire Coordinator or his/her designee;

ii. Sprinklered buildings while such protection is impaired;

iii. Areas with explosive atmospheres (that is, where mixtures of flammable gases, vapors, liquids, or dusts with air exist);

iv. Areas with explosive atmospheres that can develop inside unclean or improperly prepared drums, tanks, or other containers and equipment that have previously contained such materials;

v. Areas with explosive atmospheres that can develop in areas with an accumulation of combustible dusts.

C. Reportable Accidents: A project reportable accident is defined as death, occupational disease and/or traumatic injury to Contractor personnel, Government employees or the public, fires, and/or property damage in excess of $100.

1. Notify Government immediately in the event of a Reportable Accident;

2. Within seven (7) days of a Reportable Accident, fill out and forward to Government an Accident/Property Damage Report (Form CM-22).

a. Form may be obtained from the Government.

14. TEMPORATY FACILITIES AND CONTROLS:

Work sites will be secure at the end of the day. Entry into the RO treatment building must be by authorized personnel only. The RO treatment building must have secured access for entry into the building at all times. The Contractor will be responsible for the hazmat clean-up of any hazardous material spills or discharges cause by the Contractor.

15. TRAVEL:

Contractor shall be responsible for all travel related expenses for this project, including mobilization/demobilization of equipment, tools, materials, manpower, as well as lodging, meals, and per diem for Contractor’s personnel and their subcontractors.