B08_A1_SOW_FIRE_DOORS_SAN_ILDEFONSO.pdf

PDF 213 KB Posted

Attached to
FIRE DOORS SAN ILDEFONSO-
Solicitation number
140A2326Q0084
Issued by

About this file

This is a Statement of Work (SOW) for fire-rated door and hardware replacement at San Ildefonso Day School in Santa Fe, New Mexico. The project involves removal and replacement of 37 existing door assemblies (15 exterior, 22 interior) throughout the school campus, with a completion timeline of 30 business days after notice to proceed.

The contractor must remove and dispose of existing door assemblies and install new fire-rated metal door assemblies with complete hardware packages compliant with NFPA 80, New Mexico Building Code, ADA accessibility standards, and all applicable federal codes. Exterior doors (3'-0" x 7'-0") require panic exit devices, heavy-duty closers, kick plates, automatic door sweeps, and aluminum thresholds; interior doors (3'-0" x 6'-8") require ADA-compliant lever locksets, commercial-grade closers, and door stops. All doors must feature a minimum 90-minute fire rating with UL, FM, or Intertek certification. Hardware specifications include three ball-bearing hinges per door (satin chrome finish), door closers meeting UL and ANSI/BHMA Grade 1 standards, and acceptance of manufacturers including Steelcraft (Allegion), Republic Doors, Curries (ASSA ABLOY), and Ceco Door Products. The contractor must integrate new hardware with the school's existing master key system using interchangeable cores, conduct field measurements and verification prior to procurement, and coordinate all work during non-school hours when feasible to minimize disruption. Deliverables include manufacturer certifications, operations and maintenance manuals, warranty documentation registered in the school's name, and field quality control reports. The contractor must provide proof of installer qualifications (DHI certification or equivalent), with a minimum five years of documented fire door installation experience, and submit daily progress reports to the Bureau of Indian Education (BIE) project manager Nancy Lewis at nancy.lewis@bie.edu.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work San Ildefonso Day School Fire Doors and Other Opening Protective Equipment Santa Fe, New Mexico, NM 87506 December 24, 2025

A. GENERAL

1. Purpose:

The San Ildefonso Day School is soliciting proposals from qualified and experienced contractors for the requires the replacement of fire-rated door assemblies throughout San Ildefonso Day School campus in Santa Fe, New Mexico. This project encompasses the removal, disposal, and replacement of existing door assemblies with new fire-rated doors, frames, and complete hardware packages in accordance with applicable fire and life safety codes.

Project Scope Summary:

• Remove and dispose of 37 existing door assemblies (15 exterior, 22 interior)

• Install 15 new exterior fire-rated door assemblies with panic hardware, thresholds, and weather sealing

• Install 22 new interior fire-rated door assemblies with ADA-compliant lever hardware

• Integrate all new hardware with existing master key system using facility's interchangeable cores

Contractors are expected to provide all labor, materials, equipment, and supervision necessary to complete the work in accordance with the project specifications, manufacturer recommendations, and applicable building codes. Attention to detail, adherence to schedule, and coordination with school operations will be essential to minimize disruption to facility use.

The objectives of this project are to:

• Restore and enhance life-safety performance of fire-rated door assemblies

• Ensure code compliance with fire, life-safety, and accessibility requirements

• Improve security, durability, and maintainability of door hardware

• Provide uniformity of hardware across the facility

• Maintain continuity of the school’s existing master key system

• Minimize disruption to school operations during construction

• Replace non-compliant or deteriorated fire-rated door assemblies

• Install new fire-rated door hardware meeting current ADA accessibility requirements

• Ensure all assemblies meet NFPA 80 and applicable New Mexico state building codes

The selected Contractor shall be responsible for providing all necessary services, including but not limited to selective design, construction, installation, and supervision, in accordance with the requirements outlined in this statement of work, along with the contract terms, conditions, specifications, and any specific requirements.

It is imperative that the Contractor adheres to all relevant codes, including architectural, civil, structural, mechanical, electrical, plumbing, and other applicable codes as determined by BIA/BIE. All work performed must conform to the prescribed Codes and Standards, ensuring safety, quality, and compliance of the project.

The contractor shall confirm field measurements as part of the bidding process. Contractor must satisfy themselves, by personal examination of the location of the proposed work, and by such other means as they may prefer as to the actual conditions and requirements of the work, and inform themselves fully of the conditions relating to construction and labor under which the work will be or is now being performed, and this Contractor must employ, so far as possible, such methods and means in the carrying out of his work as will not cause any interruption or interference with any other contractor and a minimum of inconvenience and injury to other persons and property. All field visits must be coordinated with the school point of contact within 48 hours from all site visits.

The purpose of this Statement of Work (SOW) is to invite proposals from potential qualified contractors for the work required at this location. It is important to note that this SOW does not constitute an award or a commitment to award the project. Instead, it serves as an initial step in the procurement process, allowing interested parties to submit their proposals for consideration. The final selection and award of the contract will be based on a thorough evaluation of the received proposals and compliance with all relevant procurement procedures and criteria.

2 PROJECT LOCATION:

Project is located at 36 Tunyo Po Santa Fe, New Mexico.

3. ACRONYMS:

“ADAABAAG” means “Americans with Disabilities Act and Architectural Barriers Act Accessibility Guidelines”.

“A-E” refers to the Architectural and/or Engineering firm. “AHJ” refers to the Authority Having Jurisdiction

“ASTM” refers to the American Society for Testing and Materials.

“ASME” refers to American Society of Mechanical Engineers

“BIA” refers to the Bureau of Indian Affairs.

“BIE” refers to the Bureau of Indian Education.

“CO” refers to the BIA or BIE Contracting Officer.

“COR” refers to the Contracting Officer’s Representative.

“Design Handbook” refers to the current edition of the BIA School Facilities Design Handbook.

“DOI” refers to the U.S. Department of the Interior.

“DSRM” refers to the “Division of Safety and Risk Management” which is the Authority Having Jurisdiction and located in Albuquerque, NM.

“Plan Review Procedure” refers to the October 10, 2012, Rev. No. 8, “Safety, Health and Accessibility Design Guidelines for Architects, Engineers and Design Firms”.

“SOW” refers to Statement of Work.

4. CODES AND STANDARDS

Incorporation by reference –

The referenced portions of all documents and publications (such as manuals, handbooks, codes, standards and specifications) issued by any technical society, trade or professional organization or association, or regulatory or governmental authority which are cited in this statement of work for the purpose of establishing requirements applicable to equipment, materials or workmanship under this contract, shall be deemed to be incorporated herein as fully as if printed and bound with the specifications of this contract, in accordance with the following: Wherever reference is made to any such document, the Contractor shall comply with the requirements set out in the edition specified in this contract, or if not specified, the latest edition or revision thereof, as well as the latest amendment or supplement thereto, in effect on the date of the solicitation for this project, except as modified by, as otherwise provided in, or as limited to type, class or grade, by the specifications of this contract.

Copies to be provided by Contractor - The Contractor shall have available online and at the Project site, for inspection and reference by the COR, a copy of each manual, handbook, code, standard or specification which is incorporated by reference in this statement of work and which governs quality and workmanship

The Contractor shall provide a multi-disciplined team to furnish the services required to complete the work. Each responsible team member must be knowledgeable of and provide work in compliance with the most current editions of all applicable codes, standards, design handbooks, plan review procedures, and guidelines as adopted by BIA.

• Indian Affairs (IA) Design Handbook for BIE School Facilities (Sep 18, 2025)

• ICC/IBC - International Building Code

• The ICC A117.1 Standard for Accessible and Usable Buildings and Facilities

• American National Standards Institute - ANSI 156.18 - Materials and Finishes

• ANSI/ICC A117.1 - American National Standard for Accessible and Usable Buildings and Facilities;

International Code Council; 2009.

• ANSI/BHMA A156.26- (2021) Continuous Hinges

• UL 1784 - Air Leakage Tests of Door Assemblies

• ANSI/UL 437- Key Locks.

• New Mexico Building Code

• Occupational Safety Health Administration (OSHA) - Federal Regulations

• EPA - Tribal, State, Federal Regulations

• ANSI/WDMA I.S.1A - Interior Architectural Wood Flush Doors

• DHI - Door and Hardware Institute

• UL 305 - Panic Hardware

• NFPA 70 - National Electrical Code.

• NFPA 105 - Installation of Smoke Door Assemblies.

• NFPA 80 - Standard for Fire Doors and Other Opening Protectives; 2016

• NFPA 101 - Life Safety Code; 2015.

•ULC-S132, Emergency Exit and Emergency Fire Exit Hardware

• Standard Doors and Frames: ANSI/SDI A250.8.

• ANSI/SDI A250.6 Recommended Practice for Hardware Reinforcing on Standard Steel Doors and Frames

• Standard Test Method for Laboratory Measurement of Airborne Sound Transmission Loss of Building Partitions and Elements

• SDI-117: Manufacturing Tolerances for Standard Steel Doors and Frames

• ASTM E2226- (2024) Standard Practice for Application of Hose Stream

• 40 CFR 770 Formaldehyde Standards for Composite Wood Products

• NAAWS 4.0 (2021 Errata Edition) North American Architectural Woodwork Standards

• ASTM E2074: Standard Test Method for Fire Tests of Door Assemblies

• IA Industry Standard for Architectural Wood Flush Doors

• Architectural Woodwork Institute (AWI) Quality Standards

• 42 CFR § 137.379- Davis Bacon Act and Wage Rate

• ANSI/BHMA A156.1 – (2022) Butts and Hinges

• Americans with Disabilities Act of 2010

• Occupational Safety and Health Act

•Division of Safety and Risk Management, Safety: Health and Accessibility Design Guidelines for Architects, Engineers, and Design Firms May 2020

•Indian Affairs Safety and Health Adopted Codes, Policy and Mandatory Standards March 2019

Where applicable, the Contractor shall adhere to all federal and state statutes pertaining to archaeological, historical, and environmental clearances which may affect this project. Strict adherence to the National Environmental Protection Act (NEPA) and the National Historic Preservation Act (NHPA), Section 106, will be mandatory.

5. OR EQUAL CLAUSE

References in the Specifications/Statement of Work to materials, products, or equipment by trade name, make, or catalog number, or to specific processes, shall be regarded as establishing a standard of quality and shall not be construed as limiting competition. The Contractor may propose for approval or rejection by the Contracting Officer the substitution of any material, product, equipment, or process that the Contractor believes to be equal to or better than that named in the Specifications/Statement of Work, unless otherwise specifically provided in this contract.

List of accepted manufacturers: Door Closures USA, USA Fire Door, Steelcraft (Allegion), Republic Doors, Curries (ASSA ABLOY), Ceco Door Products, Pioneer Industries

6. SCOPE OF WORK

1. The contractor shall Contractor shall provide all labor, materials, equipment, tools, transportation, supervision, and incidentals necessary to execute the scope of work. All work shall comply with current OSHA, IBC, ASTM, NFPA, ADA, ANSI, UL, EPA and all applicable local, state, and federal codes.

2. Field verification of existing conditions and measurements is mandatory prior to procurement.

Field verify existing doors and frames receiving new hardware and existing conditions receiving new openings. Verify that new hardware is compatible with existing door and frame preparation and existing conditions. The installer shall notify BIE, in writing, of all unacceptable conditions that could affect the proper operation of the finish hardware. Proceed with installation only after unsatisfactory situations are remedied. All non-compatible or non-coordinated installations shall be replaced at no cost to the BIE and Northern San Ildefonso Day School.

3. Contractor to fill/patch any old hardware preparations in existing frames that will no longer be used with new door/hardware. Contractor is responsible for any new mortises/cylindrical hardware preparation to existing frame to accommodate new doors and hardware.

4. The Contractor shall carefully and professionally remove and dispose of the existing fire-rated door assemblies, including all hardware, frames, and associated components. Protect adjacent walls, floors, and ceilings during removal operations. Properly dispose of all removed materials in accordance with local waste management regulations. Clean work areas daily and maintain site cleanliness throughout project duration.

5. All demolition work shall be performed in a manner that preserves adjacent building elements for reuse or new installation as specified. All materials shall be legally disposed of off-site in strict accordance with tribal, local and federal laws. The contractor shall provide waste manifests or disposal receipts upon request to BIE or School POC.

6. Install all fire rated doors in strict accordance with the door manufacturer's printed installation instructions, details and applicable codes.

7. Examine door openings for structural soundness, plumb, level, and square. Conduct minor repairs as needed (defined as patching holes, grinding, repointing up to 2 sq. ft., or minor surface preparation).

8. Notify the BIE and School POC of any conditions requiring major structural repair or unanticipated work.

9. Wind Load Compliance: Must meet or exceed applicable local wind load codes in New Mexico

10. Test all doors for proper operation, including fire ratings, accessibility, and security features.

11. The Exterior Door Assemblies (15 Doors) shall be installed in the Main building, entrances and exits, Emergency egress doors and Service and utility access doors. The components shall meet the following specifications:

a. 3'-0" x 7'-0" fire-rated metal doors with insulated cores

b. Heavy-gauge galvanized steel frames with weatherstripping

c. Three (3) heavy-duty ball bearing hinges per door, NRP finish

d. 36" rim panic exit devices with exterior lever trim

e. Heavy-duty exterior-rated door closers, ADA compliant

f. 10" x 34" stainless steel kick plates

g. Automatic door bottom sweeps with weather seal

h. Aluminum thresholds with anchors, ADA compliant

12. The Interior Door Assemblies (22 Doors) shall be installed Classrooms, Restrooms, Principal's office, Electrical and data rooms, Boiler room, Janitor/supply closets, Library, Kitchen. The components shall meet the following specifications:

a. 3'-0" x 6'-8" fire-rated metal doors with mineral cores

b. 20-gauge galvanized steel frames, knock-down type

c. Three (3) ball bearing hinges per door, NRP finish

d. ADA-compliant lever locksets (classroom, storeroom, or passage function as appropriate)

e. Commercial-grade door closers, ADA compliant

f. 10" x 34" stainless steel kick plates

g. Wall-mounted door stops

h. Floor-mounted (kick) door stops

13. The Contractor shall carefully remove all existing door assemblies, hardware, and frames.

Protect surrounding finishes during removal operations. Salvage any hardware requested by the Owner for retention. Transport and dispose of all removed materials at approved disposal facilities. Provide documentation of proper disposal as required by local regulations. Maintain clean and safe work areas throughout the project

14. TECHNICAL SPECIFICATIONS Fire-Rated Doors

a. Exterior Doors: Construction: 20-gauge galvanized steel face sheets, insulated mineral core

b. Thickness: 1-3/4 inches

c. Rating: Minimum 90-minute fire rating with temperature rise limitation

d. Labels: UL, FM, or Intertek fire-rated door label

e. Factory preparation: Machined for all hardware, including reinforcement plates

f. Weather-stripping: Continuous perimeter weather seal, fire-rated

15. The technical specifications for Interior Doors shall:

a. 20-gauge galvanized steel face sheets, mineral core

b. Thickness: 1-3/4 inches

c. Rating: Minimum 90-minute fire rating

d. Labels: UL, FM, or Intertek fire-rated door label

e. Factory preparation: Machined for all hardware

Acceptable Manufacturers: Steelcraft (Allegion), Republic Doors and Frames, Curries (ASSA ABLOY), Ceco Door Products Or approved equal

16. Door Frames Material shall be 16-gauge galvanized steel (exterior), 16-gauge galvanized steel (interior). Knock-down frames with mortar/grout guards. Factory-prepped for hinges, strikes, and closer reinforcement. Steel anchors suitable for masonry, spacing not to exceed 12 inches on center. The Fire Rating shall match door assembly rating. The Finish shall be factory prime coat, suitable for field painting (unless specified as pre-finished)

17. Hardware Specifications: Hinges

a. Size: 4.5" x 4.5" (exterior heavy-duty), 4.5" x 4.5" (interior standard)

b. Type: Full mortise, ball bearing, five-knuckle design

c. Configuration: Non-removable pin (NRP)

d. Finish: Satin chrome (US26D)

e. Standards: ANSI/BHMA A156.1, UL listed for fire-rated assemblies

f. Quantity: Three (3) per door

g. Manufacturers: McKinney (ASSA ABLOY), Hager Companies, Stanley, Bommer

Industries, or approved equal

18. The Door Closers shall meet the following specifications:

a. Type: Heavy-duty, rack-and-pinion mechanism

b. Mounting: Surface-mounted or concealed as appropriate for location

c. ADA Compliance: Opening force not to exceed 5 pounds

d. Adjustment: Spring tension, sweep speed, and latch speed independently adjustable

e. Features: Hold-open capability (where permitted by code), back-check

f. Finish: Satin chrome or aluminum (as appropriate for door type)

g. Standards: UL listed for fire door assemblies, ANSI/BHMA A156.4 Grade 1

h. Manufacturers: LCN Closers (Allegion), Norton Door Controls (ASSA ABLOY), Yale

Security, or approved equal

19. Panic Exit Devices (Exterior Doors) shall meet the following specifications:

a. Type: Rim panic exit device with exterior lever trim

b. Size: 36 inches nominal

c. Grade: ANSI/BHMA Grade 1

d. Operation: Push bar actuates latch, exterior lever requires key or operates freely

(as per building requirements)

e. Finish: Satin chrome (US26D)

f. Standards: UL listed for fire-rated doors, NFPA 101 compliant, ANSI/BHMA

A156.3

g. Weather Protection: Exterior-rated with sealed components

h. Manufacturers: Von Duprin (Allegion), Precision Hardware (ASSA ABLOY), Yale

Security, or approved equal

20. The Lever Locksets (Interior Doors) shall meet the following specifications:

a. Type: Heavy-duty commercial lever lockset

b. Function: Classroom function, storeroom function, or passage function as appropriate

c. Core: Accepts facility's existing interchangeable cores (IC cores)

d. Lever Design: ADA-compliant, return to horizontal position

e. Grade: ANSI/BHMA Grade 1

f. Finish: Satin chrome (US26D)

g. Standards: UL listed for fire-rated applications, ANSI/BHMA A156.2

h. Manufacturers: Schlage Commercial (Allegion), Corbin Russwin (ASSA ABLOY), Yale Security, or approved equal

21. The Additional Hardware shall meet the following specifications:

a. Kick Plates: Material: Type 304 stainless steel, 0.050" thick

b. Size: 10" high x 34" wide (standard for 36" doors)

c. Edges: Beveled and polished

d. Fasteners: Concealed fasteners, stainless steel

e. Manufacturers: Rockwood Manufacturing, Trimco, Ives Hardware, Burns

Manufacturing

22. The Door Sweeps (Exterior) shall meet the following specifications:

a. Type: Automatic drop seal

b. Size: 36" nominal

c. Function: Automatically drops when door closes, sealing bottom gap

d. Rating: Fire-rated for use on labeled doors

e. Manufacturers: Pemko Manufacturing, National Guard Products

23. The Thresholds (Exterior) shall meet the following specifications:

a. Material: Extruded aluminum with vinyl seal insert

b. Size: 36" nominal, height compliant with ADA (maximum 1/2" rise)

c. Anchors: Stainless steel anchors included

d. Finish: Mill finish aluminum

e. Manufacturers: Pemko Manufacturing, National Guard Products

24. Wall Stops: Heavy-duty commercial grade with rubber or vinyl bumper, satin chrome finish.

Floor Stops: Heavy-duty commercial grade (kick-down type), satin chrome finish. Manufacturers:

Rockwood Manufacturing, Ives Hardware, Trimco

7. INSTALLATION PROCEDURES

7.1 Pre-Installation Requirements

• Verify field measurements and existing opening dimensions

• Inspect all materials for damage prior to installation

• Verify fire rating labels are present on all door assemblies

• Store materials in dry, protected area until installation

7.2 Door Frame Installation

• Set frames plumb, level, and square within 1/16" tolerance

• Anchor frames securely per manufacturer specifications (typically 12" on center maximum)

• Grout frames solid with non-shrink mortar or approved fire-rated material

• Allow adequate cure time before door hanging

7.3 Door Hanging and Hardware Installation

• Hang doors with uniform reveals: 1/8" at head and jambs, 3/4" maximum at bottom

• Install three (3) hinges per door at proper locations (7" from top, 11" from bottom, centered)

• Install locksets at 38" above finished floor to centerline of lever

• Mount door closers per manufacturer specifications with proper spring tension

• Install panic devices 36" to 44" above finished floor to centerline of push bar

• Attach kick plates 2" from bottom of door, centered horizontally

• Ensure all hardware is fire-rated and compatible with door assembly listing

7.4 ADA Compliance Verification

• Verify opening force does not exceed 5 pounds force (lbf) as measured by force gauge

• Ensure clear opening width meets 32" minimum requirement

• Confirm hardware operates with closed fist (no tight grasping or twisting)

• Document compliance measurements for each door assembly

7.5 Adjustment and Testing

• Adjust door closers for smooth operation and positive latching

• Test all locking mechanisms for proper operation

• Verify panic devices release with 15 pounds maximum force

• Ensure doors self-close and latch from any open position

• Conduct operational testing with Owner representative present

8. QUALITY ASSURANCE AND INSPECTION REQUIREMENTS

8.1 Qualification Requirements

• Installer shall be DHI certified or possess equivalent fire door installation credentials

• Locksmith shall hold valid locksmith certification or minimum 5 years documented experience

• Contractor shall provide proof of qualifications prior to commencing work

8.2 Material Quality Control

• All doors and frames shall bear UL, FM, or equivalent listing label

• Hardware shall be Grade 1 commercial quality per ANSI/BHMA standards

• Submit manufacturer certifications confirming fire ratings and ADA compliance

• Reject and replace any damaged or non-conforming materials

8.3 Installation Inspections

• Conduct in-progress inspections per NFPA 80 requirements

• Verify proper clearances using NFPA 80 gap measurement specifications

• Document compliance with DHI installation standards using inspection checklists

• Coordinate required inspections with local fire marshal and building official

8.4 Final Acceptance Testing

• Perform complete operational testing of all door assemblies

• Verify ADA opening force requirements using calibrated force gauge

• Test all locks with master key and individual keys

• Demonstrate proper operation to Owner representative

• Obtain final approval from Authority Having Jurisdiction

8.5 Warranty Requirements

• Provide minimum one (1) year warranty on all materials and workmanship

• Manufacturer warranties to be assigned to Owner

• Warranty shall commence upon final acceptance by Owner

9. SAFETY CONSIDERATIONS

Safety is paramount on this educational facility project. The Contractor shall implement comprehensive safety protocols to protect workers, students, staff, and visitors.

9.1 Site Safety Requirements

1. Establish physical barriers around work areas using safety cones, caution tape, and barricades

2. Post warning signs indicating construction zone and restricted access

3. Maintain clear egress paths at all times per NFPA 101 requirements

4. Coordinate work during non-school hours when feasible to minimize student exposure

5. Ensure adequate lighting in work areas and temporary egress routes

9.2 Personal Protective Equipment (PPE)

6. All workers shall wear appropriate PPE: safety glasses, work gloves, and steel-toed boots

7. Hard hats required when overhead work or falling object hazards exist

8. Hearing protection required during cutting, drilling, or other high-noise operations

9. Respiratory protection when grinding, cutting, or working with adhesives in enclosed spaces

9.3 Tool and Equipment Safety

10. Use only properly maintained and inspected tools

11. Secure electrical cords to prevent tripping hazards

12. Follow manufacturer safety guidelines for all power tools

13. Store tools and materials securely when not in use

9.4 Hazardous Materials Management

14. Properly label all chemicals and adhesives

15. Maintain Safety Data Sheets (SDS) on-site for all materials

16. Dispose of waste materials per local environmental regulations

17. Contain and clean up spills immediately

9.5 Emergency Procedures

18. Maintain first aid kit on-site with designated first aid provider

19. Post emergency contact numbers including 911, facility management, and project supervisor

20. Coordinate emergency evacuation procedures with school administration

21. Report all injuries and near-miss incidents immediately to Owner

9.6 Compliance and Training

22. Comply with OSHA regulations for construction safety (29 CFR 1926)

23. Conduct daily toolbox talks addressing specific safety concerns

24. Ensure all workers complete required safety training before starting work. Maintain project safety log documenting all safety meetings

10. SCHEDULE

Working hours: Regular (8 AM – 5 PM, Monday–Friday) Nights/Weekends (If necessary, subject to approval). Coordinate closely with School POC to avoid interference with school operations.

11.PROJECT MANAGEMENT AND COMMUNICATION: Contractor shall appoint a single point of contact (Project Manager or Superintendent). The project manager shall submit daily progress reports to the BIE and school POC.

12. PERMITTING AND INSPECTIONS

The contractor is responsible for obtaining and paying for all applicable permits. The contractor shall coordinate with local inspection authorities and School POC for all required inspections and approvals.

13. WARRANTY

Submit manufacturer's warranty and ensure that forms have been completed in San Idelfonso Day Schools's name and registered with manufacturer.

14. INFORMATIONAL SUBMITTALS

Submit the following Informational Submittals for record, quality assurance, and compliance verification:

a. Certificates:

• Manufacturer’s certification of compliance with:

o ANSI/SDI 100 (Standard for Hollow Metal Doors and Frames) o NFPA 80 and NFPA 252 (Fire-rated assemblies, if applicable) o ASTM A653/A653M (Steel sheet standards) o Wind-load and impact-resistance compliance where applicable

b. Operation and Maintenance Data:

• O&M manuals for all door systems, including:

o Operating instructions for door (manual or motorized) o Maintenance requirements for hinges, closers, and hardware o Troubleshooting guidelines and replacement part lists

c. Warranty Documentation:

• Manufacturer’s standard warranty for:

o Warrant doors free of defects as set forth in the door manufacturer's standard door warranty.

o Hardware components Minimum one-year warranty required from date of substantial completion.

d. Installation Qualifications:

• Submit qualifications of installing contractor demonstrating experience with school facility door installations

• Minimum 3 similar door installation projects within the last 5 years

e. Field Quality Control Reports:

• Submit field inspection and installation reports, documenting:

o Conformance with installation tolerances o Proper operation and fit of doors and hardware o Integration with mechanical room security and weatherproofing

15. QUALITY ASSURANCE

A. Standards: In the event that provisions of codes, regulations, safety orders, Contract Documents, referenced manufacturer’s specifications, manufacturer’s instructions, industry standards, and the like, are in conflict, the more restrictive and higher quality shall govern.

B. Manufacturer: Contractor shall obtain products from nationally and industry recognized Manufacturer with ten (10) years minimum of immediately recent, continuous, documented and properly authenticated successful experience of specialization in the manufacture of the product specified herein.

C. Installer or Installers engaged by Contractor must have a minimum of five (5) years of documented and properly authenticated successful experience of specialization in the installation of the items or systems, or both, specified herein.

D. Contractor shall provide a qualified tradesman, skilled in application of commercial grade hardware with a record of successful in-service performance for installing door hardware similar in quantity, type, and quality to that indicated for this Project

16. Submit deliverables to: Contracting Officer/ BIE Project Manager:

Nancy Lewis

Bureau of Indian Education, 1011 Indian School RD NW nancy.lewis@bie.edu, mailto:nancy.lewis@bie.edu

17. PERIOD OF PERFORMANCE

The delivery should be completed within thirty (30) business days after notice to proceed is issued.