B08_24R0036_Attachment_2_-_Drawings.pdf
PDF 14 MB Posted
- Attached to
- FAIRBANKS DISTRICT OFFICE ROOF REPLACEMENT
- Solicitation number
- 140L0624R0036
About this file
The provided document is Attachment 2 - Drawings for the Solicitation Number 140L0624R0036 for the BLM Fairbanks District Office Roof Replacement project.
This solicitation is for all labor, materials, equipment, and supervision required to replace the roof on the BLM Fairbanks District Office located at 222 University Avenue, Fairbanks, Alaska. The work includes complete construction of the roof assembly and all related mobilization and demobilization efforts. This attachment contains the drawings that provide technical specifications and details for the required roof replacement work.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1 View Name 1/8" = 1'-0"A101
Room name
GENERAL SYMBOLS
NAME
NUMBER
SHEET LOCATION
SCALE
TRUE NORTH
GRID LINE
ROOM NAME
ROOM NUMBER
PLAN NORTH
REVISION
SEE DISCIPLINES FOR SPECIFIC SYMBOLS
PROJECT TEAM
OWNERS REPRESENTATIVE
BUREAU OF LAND MANAGEMENT
POINT OF CONTACT: CURT FORTENBERRY
222 UNIVERSITY AVE
FAIRBANKS, ALASKA 99709
907 474-2206
CFORTENB@BLM.GOV
DESIGNERS REPRESENTATIVE
DESIGN ALASKA
POINT OF CONTACT: JAMES BARTLETT
601 COLLEGE ROAD
FAIRBANKS, ALASKA 99701
907 452-1241
JAMESB@DESIGNALASKA.COM
ALASKA MAP
PACIFIC OCEAN
ARCTIC OCEAN
BERING
SEA
KODIAK
ARCTIC CIRCLE
SEWARD
SITKA
JUNEAU
HAINES
WHITEHORSE YT
DAWSON YT
HAINES
JCT
HOMER
ANCHORAGE
EAGLE
CORDOVA
VALDEZ
GLENNALLEN
TOK
NORTH
POLE
FAIRBANKS
NENANA
TANANA CIRCLE
NOME
KOTZEBUE
UTQIAGVIK
(BARROW)
PRUDHOE BAY
U N
IT
ED
S
TA
TE
S
R U
SS
IA U
N
ITED
STATES
C
AN
AD
A
PROJECT
LOCATION
CODE INFORMATION
GOVERNING CODES
INTERNATIONAL BUILDING CODE (IBC) 2012
INTERNATIONAL FIRE CODE (IFC) 2012
INTERNATIONAL MECHANICAL CODE (IMC) 2012
NATIONAL ELECTRICAL CODE (NEC) 2017
AUTHORITY HAVING JURISDICTION
BUREAU OF LAND MANAGEMENT
CODE SUMMARY
OCCUPANCY TYPE : GROUP B, NO CHANGE OF OCCUPANCY
ROOF REPLACEMENT: ALTERATIONS LEVEL 1
U N
IV
ER
SI
TY
A
VE
N U
E
CONTRACTOR ROOF ACCESSCONTRACTOR
STAGING AREA
VICINITY MAP
PROJECT
LOCATION
CH
EN
A
RI
VE
R
U N
IV
ER
SI
TY
A
VE
N U
E
AIRPORT WAY
BOAT STREET
SPORTSMAN W
AY
GERAGHTY AVENUE
CHENA RIVER
AKAF AL
TS
TA E O
49 TH
S
JAMES D. BARTLETT
No. A10413
REGISTEREDPROFESSIONALARCHIT
EC
D E S I G N
A L
A S
K
AT
U.S. DEPARTMENT OF THE INTERIOR
BUREAU OF LAND MANAGEMENT
ISSUE DATE
COMM. NUMBER
DESIGNED BY
DRAWN BY
SCALE 0" 1"
Architects Engineers Surveyors 601 College Road Fairbanks AK 99701
907.452.1241 designalaska.com
20 SEP 2021
FAIRBANKS
DISTRICT OFFICE
ROOF
REPLACEMENT
902102
AECC511
NATIONAL SYSTEM OF PUBLIC LANDS
20-SEP-2021
9/17/2021 4:03:46 PM
GENERAL
INFORMATION
G001
FAIRBANKS DISTRICT OFFICE
ROOF REPLACEMENT
FAIRBANKS, ALASKA
BUREAU OF LAND MANAGEMENT
ARCHITECTURAL
A001 ARCHITECTURAL INFORMATION
A100 DEMOLITION PLAN - PENTHOUSE AND ROOF
A200 RENOVATION PLAN - PENTHOUSE AND ROOF
A500 EXTERIOR DETAIL - ASSEMBLY TYPE
A510 EXTERIOR DETAIL - TYPICAL
A620 INTERIOR PLAN - CEILING - 2ND FLOOR
GENERAL
G001 GENERAL INFORMATION
SHEET INDEX
ELECTRICAL
E001 ELECTRICAL SYMBOLS, LEGENDS AND DETAILS
E100 ELECTRICAL ROOF PLAN
MECHANICAL
M001 MECHANICAL ABBREVIATIONS, LEGENDS,
SCHEDULES, AND DETAILS
M100 LOWER ROOF PLUMBING DEMOLITION PLAN
M200 ROOF PLUMBING PLAN
CIVIL
C200 SITE PLAN
4" DOWNSPOUT
GRASS
CO
NC. SIDEW
ALK
CHAIN LINK FENCE
BLM BUILDING 2 STORY
BLOCK CONSTRUCTION
FRAME
SHOP
GRASS
GRAVEL PARKING LOT
DEMO APPROX. 200
SF CONC. SIDEWALK
SAWCUT CONC. AT
NEAREST JOINT
SWALE
LIGHT POST (TYP)
(E) 4" DOWNSPOUT
(E) GRASS
(E) CO
NC. SIDEW
ALK
(E) CHAIN LINK FENCE
(E) BLM BUILDING 2
STORY BLOCK
CONSTRUCTION
(E) FRAME
SHOP
(E) GRASS
(E) GRAVEL PARKING LOT
'-6
GRADE GRASS LINED
SWALE AT 2% FROM
BUILDING DOWNSPOUT
AND DRAIN TO EXISTING
SWALE
MATCH EXISTING CONC.
SIDEWALK ELEVATIONS
AND WIDTH
GRADE
BREAK
2%
2%
CONCRETE CULVERT
C200
SIDEWALK
C200
C200
RIP RAP 4' X 10'
(E) SWALE
TOPSOIL AND SEED
DISTURBED AREAS
(E) LIGHT POST (TYP)
C200
10'-0"
R2'-0"
12" MIN
ROUND
EDGES
6" MIN
9/17/2021 11:19 AM 902102 C200.DWG
902102
20 SEP 2021
COMM. NUMBER
ISSUE DATE
DESIGNED BY
DRAWN BY
1"0" SCALE
601 College Road Fairbanks AK 99701 907.452.1241
Architects SurveyorsEngineers
AECC511 designalaska.com
FDO ROOF
REPLACEMENT
C200
IAL
CCD
SITE PLAN
EXISTING CONDITIONS AND DEMOLITION PLAN1
C200 1" = 10'
SITE IMPROVEMENTS PLAN2
C200 1" = 10'
12"8"
EXISTING NEW
1/2" EXPANSION JOINT MATERIAL
1/2" DEEP SEALANT W/
1/4" RAD AT SURFACE
GREASE 12" DOWEL
SEGMENT PRIOR TO
POURING NEW CONCRETE
#4 SMOOTH DOWEL
CENTERED IN
SECTION. INSTALL
AT 18" O.C. IN SLABS.
SECURE DOWEL WITH EPOXY
IN DRILLED HOLE IN
ACCORDANCE WITH EPOXY
MANUFACTURER'S
RECOMMENDATIONS.
5'-9"
12" STRUCTURAL FILL 1
1. PROVIDE 1/2" EXPANSION JOINTS EVERY 24' AND
AT ANY CORNERS UNLESS OTHERWISE NOTED.
2. PROVIDE CONTROL JOINTS TO MATCH
CONCRETE WIDTH. MAINTAIN APPROXIMATELY
SQUARE SECTIONS, MAX DIMENSIONS TO BE 10',
OR AS DIRECTED.
NOTES
COMMON
FILL
COMMON
FILL
6x6 W2.1xW2.1 WWF 4" CONC. SIDEWALK.
SLOPE PER PLANS.
4" TOPSOIL
& SEED, TYP
INSITU
SOILS
EXISTING TO NEW CONCRETE3
C200 NO SCALE
SIDEWALK SECTION4
C200 NO SCALE
CONCRETE CULVERT5
C200 NO SCALE
5'-9"
2% MIN
4"
A
A
4" C
O N
C . S
ID
EW
AL
K, T
YP
12"
1TYP
4" TYP
#3 CONT, TYP
PROFILE VIEW
SECTION A-A
#3 @ 18" O.C.
EACH WAY
1/2" GALVANIZED ANGLE
HEADED ANCHOR
STUDS @ 12" O.C.
3/8" GALVANIZED STEEL
PLATE, NON SKID RAISED
SURFACE
12" STRUCTURAL FILL
GRADE AT 2% TO MATCH
EXISTING SWALE
COMMON FILL
RIP RAP SEE DETAIL
2/C200 FOR DIMENSIONS
6"
4"
D E S I G N
A L
A S
K A
Charles Cutter Degerlund
No. CE124811 17-Sep-2021
GRASS LINED SWALE6
C200 NO SCALE
CONCRETE
GYPSUM
RIGID INSULATION
MASONRY CONCRETE
PLYWOOD
MATERIAL LEGEND
BATT INSULATION
SPRAY FOAM INSULATION
EXISTING
CONSTRUCTION
NO ARCHITECTURAL WORK
THIS AREA
RIGID MINERAL FIBER
BATT/BLOWN INSULATION
TEMPORARY
CONSTRUCTION
EXISTING
CONSTRUCTION DETAIL
ARCHITECTURAL SYMBOL LEGEND
150 SF
Room Name
DETAIL NAME
DETAIL NUMBER
SHEET LOCATION
DETAIL SCALE
TRUE NORTH
GRID LINE
ROOM NAME
ROOM NUMBER
PLAN NORTH
DETAIL NUMBER
SHEET LOCATION
SIMILAR
REVISION
SPOT ELEVATION
SEE OTHER DISCIPLINES FOR ADDITIONAL SYMBOLS
KEYED NOTE
DOOR TAG
A100
A100
EXTERIOR ELEVATION
SHEET LOCATION
DETAIL NUMBER
INTERIOR ELEVATION
SHEET LOCATION
DETAIL NUMBER
DETAIL NUMBER 4
A
BUILDING SECTION
DETAIL NUMBER
SHEET LOCATION
SIMILAR
WALL SECTION
WINDOW TYPE
ROOM AREA
1/8" = 1'-0"A101 View Name
1/4" / 1'-0"
.SPOT SLOPE
101ROOM NUMBER
A101
SIM
A101
SIM
101A
1. SEE OTHER DISCIPLINES FOR ADDITIONAL ABBREVIATIONS.
2. SEE GENERAL SHEETS FOR CODE ABBREVIATIONS.
3. SEE ASSEMBLY TYPES FOR HYPHENATED ASSEMBLY TAGS
(I.E. C-A1, W01-3A, AND WX-3A).
4. SEE MATERIAL SCHEDULE FOR HYPHENATED MATERIAL TAGS
(I.E. ACT-1, CPT-1, AND RB-1).
5. SEE ROOM AND DOOR SCHEDULE FOR SPECIFIC RELEVANT
ABBREVIATIONS.
6. SOME ABBREVIATIONS LISTED BELOW MAY NOT BE USED IN
THIS PROJECT.
(E) EXISTING
ADA AMERICAN DISABILITIES ACT
AFF ABOVE FINISHED FLOOR
CFCI CONTRACTOR FURNISHED CONTRACTOR INSTALLED
CFOI CONTRACTOR FURNISHED OWNER INSTALLED
CMU CONCRETE MASONRY UNIT
CONC CONCRETE
ELEC ELECTRICAL
FV FIELD VERIFY
GA GYPSUM ASSOCIATION
GYP GYPSUM BOARD
IBC INTERNATIONAL BUILDING CODE
INSUL INSULATION
ITSP INSULATED TRANSLUCENT SANDWICH PANEL
MAX MAXIMUM
MECH MECHANICAL
MFSD MANUFACTURER'S STANDARD
MIN MINIMUM
NIC NOT IN CONTRACT
OC ON CENTER
OD OVERFLOW DRAIN
OFOI OWNER FURNISHED OWNER INSTALLED
OFCI OWNER FURNISHED CONTRACTOR INSTALLED
OSB ORIENTED STRAND BOARD
OTS OPEN TO STRUCTURE
PLY PLYWOOD
RD ROOF DRAIN
SIP STRUCTURAL INSULATED PANEL
SPEC SPECIFICATION
STC SOUND TRANSMISSION CLASS
STRUC STRUCTURAL
TBD TO BE DETERMINED
TYP TYPICAL
UL UNDERWRITERS LABORATORY
VTR VENT THROUGH ROOF
ARCHITECTURAL STANDARD ABBREVIATIONS
ARCHITECTURAL PROJECT SPECIFIC ABBREVIATIONS
NA NOT APPLICABLE
WX-A1
WALL ASSEMBLY CATEGORY - FUNCTION
WALL BUILDING ENVELOPE DESIGNATION
WALL ASSEMBLY MODIFIER
WALL ASSEMBLY CATEGORY - FUNCTION
PROJECTS MAY NOT INCLUDE ALL ASSEMBLY CATEGORIES.
WF WALL - FOUNDATION
WP WALL - PARAPET
WR WALL - RETAINING
WX WALL - EXTERIOR
WALL BUILDING ENVELOPE DESIGNATION
A EIFS / EPDM / FOUNDATION
B RAINSCREEN / ATTIC
C IMP
D OTHER
WALL ASSEMBLY MODIFIER
NUMBERS REPRESENT DESCRIPTIONS OF ASSEMBLY TYPES.
THE BELOW ARE COMMONLY USED EXAMPLES. SEE
ASSEMBLY TYPES FOR ADDITIONAL MODIFIERS.
1 TYPICAL
EXTERIOR ASSEMBLY TAG LEGEND - WALL
R-A1
ROOF ASSEMBLY CATEGORY - FUNCTION
ROOF ASSEMBLY MODIFIER
ROOF ASSEMBLY CATEGORY - FUNCTION
R ROOF
RS ROOF - SOFFIT
ROOF BUILDING ENVELOPE DESIGNATION
A EIFS / EPDM / FOUNDATION
B RAINSCREEN / ATTIC
C IMP
D OTHER
WALL ASSEMBLY MODIFIER
NUMBERS REPRESENT DESCRIPTIONS OF ASSEMBLY
TYPES. THE BELOW ARE COMMONLY USED EXAMPLES.
SEE ASSEMBLY TYPES FOR ADDITIONAL MODIFIERS.
1 TYPICAL
EXTERIOR ASSEMBLY TAG LEGEND - ROOF
ROOF BUILDING ENVELOPE DESIGNATION
BUILDING ENVELOPE LEGEND
SEE EXTERIOR ASSEMBLY TYPES, EXTERIOR DETAILS,
MATERIAL SCHEDULE, AND SPECIFICATIONS FOR
ADDITIONAL INFORMATION. PROJECTS MAY NOT INCLUDE
ALL BUILDING ENVELOPE CATEGORIES.
DIRECTION
OF DRYING
BE-1 OR 2: FOUNDATION MEMBRANE
BE-4: INTERIOR AIR/VAPOR BARRIER
BE-5 OR 6: EXTERIOR AIR/WATER BARRIER
BE-7,8, OR 9: ROOF UNDLERLAY
BUILDING ENVELOPE COMPONENT
BUILDING ENVELOPE METAL FLASHING
DESCRIBES THE DIRECTION OF AIRFLOW IN A
VENTED OR VENTILATED ASSEMBLY
DESCRIBES THE DIRECTION AN ASSEMBLY
WILL DRY. PERMEABLE MATERIALS REQUIRED
TO DRY AS SHOWN
A.
B.
C.
D.
E.
F.
G.
H.
I.
J.
K.
L.
M.
N.
O.
P.
Q.
R.
S.
ARCHITECTURAL NOTES CONVEY INTENT OF WORK
COMPRISING THE ENTIRE ARCHITECTURAL DISCIPLINE.
SHEET NOTES CONVEY INTENT OF WORK COMPRISING
THE ENTIRE SHEET ON WHICH THE NOTES APPEAR
INCLUDING SHEETS ON WHICH THE NOTES ARE
REFERENCED.
CONSTRUCTION DOCUMENTS ARE PREPARED FOR THE
PURPOSES OF COMMUNICATING DESIGN INTENT.
DRAWINGS ARE GRAPHIC REPRESENTATIONS INTENDED
TO CONVEY THE QUANTITATIVE EXTENT AND
RELATIONSHIP BETWEEN ELEMENTS.
SPECIFICATIONS ARE WRITTEN REPRESENTATIONS
INTENDED TO CONVEY THE QUALITATIVE REQUIREMENTS
OF PROJECT ELEMENTS.
CONTRACTOR IS RESPONSIBLE FOR PROVIDING A
COMPLETE AND FINISHED PRODUCT FULFILLING THE
INTENT OF THE CONSTRUCTION DOCUMENTS.
THE TERM 'NEW' MAY BE USED TO DISTINGUISH NEW
FROM EXISTING IN SOME INSTANCES. OMISSION OF THE
TERM 'NEW' IS NOT NECESSARILY AN INDICATION THAT
THE ELEMENT IS EXISTING.
THE TERM 'ALL' MAY BE USED TO CLARIFY SCOPE.
OMISSION OF THE TERM 'ALL' IS NOT NECESSARILY AN
INDICATION THAT THE SCOPE IS LIMITED.
PROVIDE CONSTRUCTION IN COMPLIANCE WITH OSHA.
COORDINATE ARCHITECTURAL WORK WITH STRUCTURAL,
MECHANICAL, ELECTRICAL, AND OTHER DISCIPLINES.
PATCH, REPAIR, AND REFINISH EXISTING SURFACES TO
REMAIN, AFFECTED BY WORK.
FIELD VERIFY DIMENSIONS SHOWN TO EXISTING
CONSTRUCTION PRIOR TO WORK. NOTIFY ARCHITECT
WHERE DISCREPANCIES ARE DISCOVERED.
DIMENSIONS AT EXISTING CONSTRUCTION ARE
MEASURED FROM FACE OF EXISTING FINISH UNLESS
NOTED OTHERWISE.
DIMENSIONS AT NEW CONSTRUCTION ARE MEASURED
FROM FACE OF FRAMING UNLESS NOTED OTHERWISE.
CONFIRM DIMENSIONS INDICATED WITH 'FIELD VERIFY'
AND/ OR 'FV' PRIOR TO WORK.
DIMENSIONS INDICATED AS 'CLEAR' REQUIRE MINIMUM
CLEARANCE MEASURED TO FINISHED FACES, UNLESS
NOTED OTHERWISE.
DIMENSIONS INDICATED WITH '+/-' ARE INTENDED TO
BRING THE CONTRACTORS ATTENTION TO AREAS WITH
FLEXIBILITY GREATER THAN ADJACENT AREAS NOT
OTHERWISE INDICATED.
SEE SPECIFICATIONS FOR ALLOWABLE TOLERANCES.
CONFIRM MANUFACTURERS INSTRUCTIONS CONFORM TO
SPECIFIED TOLERANCES.
ARCHITECTURAL NOTES
THIS REFERENCE IS INTENDED TO ASSIST WITH THE LOCATION OF
INFORMATION IN A TYPICAL PROJECT. THIS PROJECT MAY VARY
FROM THE REPRESENTATION BELOW. SEE THE SHEET INDEX FOR
SPECIFIC SHEET SEQUENCE.
A0 SHEETS ARCHITECTURAL INFORMATION
A1 SHEETS ARCHITECTURAL DEMOLITION
A2 SHEETS FLOOR AND ROOF PLANS
A3 SHEETS EXTERIOR ELEVATIONS (NOT USED)
A4 SHEETS SECTIONS AND VERTICAL CIRCULATION (NOT USED)
A5 SHEETS EXTERIOR DETAILS AND ASSEMBLIES
A6 SHEETS INTERIOR PLANS
A7 SHEETS INTERIOR ELEVATIONS (NOT USED)
A8 SHEETS INTERIOR DETAILS AND ASSEMBLIES (NOT USED)
A9 SHEETS SCHEDULES (NOT USED)
THE TWO CHARACTER ALPHANUMERIC DESIGNATIONS REPRESENT
ALL SHEETS IN THE SERIES. FOR EXAMPLE, 'A1 SHEETS' DESCRIBES
A100 THROUGH A199.
ARCHITECTURAL SHEET SEQUENCE
AKAF AL
TS
TA E O
49 TH
S
JAMES D. BARTLETT
No. A10413
REGISTEREDPROFESSIONALARCHIT
EC
D E S I G N
A L
A S
K
AT
U.S. DEPARTMENT OF THE INTERIOR
BUREAU OF LAND MANAGEMENT
ISSUE DATE
COMM. NUMBER
DESIGNED BY
DRAWN BY
SCALE 0" 1"
Architects Engineers Surveyors 601 College Road Fairbanks AK 99701
907.452.1241 designalaska.com
20 SEP 2021
FAIRBANKS
DISTRICT OFFICE
ROOF
REPLACEMENT
902102
AECC511
NATIONAL SYSTEM OF PUBLIC LANDS
20-SEP-2021
9/17/2021 3:47:17 PM
JB
GMC
ARCHITECTURAL
INFORMATION
A001
A.
B.
CONSTRUCTION DOCUMENTS ARE GENERALIZED TO
DESCRIBE INTENT OF DEMOLITION WORK. CONTRACTOR IS
RESPONSIBLE FOR PROVIDING SPECIFIC DEMOLITION WORK
REQUIRED TO ACCOMMODATE NEW WORK.
SEE MECHANICAL, AND ELECTRICAL DOCUMENTS FOR
ADDITIONAL DEMOLITION REQUIREMENTS.
DEMOLITION NOTES
KEYNOTES
DEMOLISH EXISTING ROOF PAVERS AND ROOFING
SYSTEM DOWN TO FACE OF POLY BARRIER; EXISTING
POLY, GYPSUM AND DECKING TO REMAIN. SEE A500 FOR
EXISTING ROOF ASSEMBLY.
DEMOLISH EXISTING PARAPET FLASHING, PARAPET WALL
COMPONENTS, AND PENTHOUSE WALL COMPONENTS
DOWN TO SHEATHING, TYPICAL AT PERIMETER OF
BUILDING; EXISTING SHEATHING TO REMAIN
REMOVE EXISTING PARAPET MOUNTED GUARD RAILING
AND SALVAGE FOR REINSTALLATION
REMOVE EXISTING ROOFTOP EQUIPMENT INCLUDING
SOLAR PANELS AND SALVAGE FOR REINSTALLATION
REMOVE EXISTING GROUNDING CABLE AND SALVAGE
FOR REINSTALLATION
EXISTING SCUPPER LOCATIONS TO REMAIN
EXISTING SATELLITE DISHES TO BE REMOVED BY OTHERS
PRIOR TO CONSTRUCTION
A
B
C
D
E
F
G
30'-0"
30'-0"
30'-0"
30'-0"
30'-0"
30'-0" 30 '-0
'-0
'-0
'-0
'-0
'-0
1 1
SLOPE DOWN
SLOPE DOWN
SLOPE DOWN
VALL
EY O
F R
OOF
RID
GE O
F R
OOF
VALL
EY O
F R
OOF
VALLEY OF ROOF
RIDGE OF ROOF
VALLEY OF ROOF
TYPICAL
AT PENTHOUSE
PERIMETER
TYPICAL
AT BUILDING
PERIMETER
WP-1
WX-1(E) WX-1
WX-1
WX-1
WX-1
7 7 7
4 4
4 TYPICAL
(E) WX-1
(E) WX-1
(E) WX-1
(E) WP-1
(E) WP-1
FAN ROOM
PLENUM
X
CONDENSING
ROOM
GENERATOR
ROOM
BOILER
ROOM
DEMOLITION LEGEND
EXISTING CONSTRUCTION
HATCH PATTERN INTENDED TO
CLARIFY SCOPE OF SPECIFIC
KEYNOTES INDICATED HERE
EXISTING WALL AND DOOR TO REMAIN
EXISTING CURB EQUIPMENT
EXISTING VTR
EXISTING ROOF DRAIN
GUARD RAIL
AKAF AL
TS
TA E O
49 TH
S
JAMES D. BARTLETT
No. A10413
REGISTEREDPROFESSIONALARCHIT
EC
D E S I G N
A L
A S
K
AT
U.S. DEPARTMENT OF THE INTERIOR
BUREAU OF LAND MANAGEMENT
ISSUE DATE
COMM. NUMBER
DESIGNED BY
DRAWN BY
SCALE 0" 1"
Architects Engineers Surveyors 601 College Road Fairbanks AK 99701
907.452.1241 designalaska.com
20 SEP 2021
FAIRBANKS
DISTRICT OFFICE
ROOF
REPLACEMENT
902102
AECC511
NATIONAL SYSTEM OF PUBLIC LANDS
20-SEP-2021
9/17/2021 3:47:20 PM
JB
GMC
DEMOLITION PLAN
- PENTHOUSE AND
ROOF
A100 3/32" = 1'-0"A100
1 DEMOLITION PLAN - PENTHOUSE AND ROOF
ROOF PLAN NOTES
B.
C.
PROVIDE CONTINUITY OF BUILDING ENVELOPE PER
ASSEMBLY TYPES AND BUILDING ENVELOPE NOTES ON
A500; AND EXTERIOR DETAILS ON A5 SHEETS.
SEE MECHANICAL, ELECTRICAL, AND OTHER DISCIPLINES
FOR SIZE AND GENERAL LOCATION OF ROOF
PENETRATIONS.
UPON COMPLETION OF PARTIAL OR TOTAL ROOF
REMOVAL THE CONTRACTOR AND OWNER SHALL INSPECT
EXISTING POLY MEMBRANE FOR CONTINUITY AND REPAIR
UNSUITABLE AREAS. ALL REPAIRS TO BE DONE IN
CONFORMANCE WITH MANUFACTURERS INSTALLATION
REQUIREMENTS OF WARRANTIED ROOF ASSEMBLY.
KEYNOTES
PROVIDE COMPOSITE PAVERS OVER LOW SLOPE EPDM
ROOFING SYSTEM AS SHOWN ON A500
REINSTALL SALVAGED PARAPET MOUNTED GUARD
RAILING
REINSTALL SALVAGED ROOFTOP EQUIPMENT INCLUDING
SOLAR PANELS
TAPERED INSULATION SLOPED AT 1/4" : 1'-0", TYPICAL ALL
HATCHED AREAS
EXISTING SCUPPER LOCATION TO REMAIN
REINSTALL PERIMETER GROUNDING CABLE
CONDENSING
ROOM
PLENUM
FAN ROOM
GENERATOR
ROOM
BOILER
ROOM
A
B
C
D
E
F
G
30'-0"
30'-0"
30'-0"
30'-0"
30'-0"
30'-0" 30 '-0
'-0
'-0
'-0
'-0
'-0
WP-1
WX-1
(E) WX-1
WX-1
WX-1
WX-1
TYPICAL
AT PENTHOUSE
PERIMETER
TYPICAL
AT BUILDING
PERIMETER
1 1
SWI
SWS
1/4" : 1'-0"
SWS
1/4" : 1'-0"
SLOPE DOWN
SWS
1/4" : 1'-0"
SWS
1/4" : 1'-0"
1/4" : 1'-0"
SWI
1/4" : 1'-0"
SWS
1/4
1'- 0"
SWS
1/4
1'- 0"
SWS
1/4
1'- 0"
SWS
1/4
1'- 0"
4 TYPICAL ALL
SHADED AREAS
3 3
TYPICAL
6'-2"
TY
PI
C
AL
7' -1
/4
39'-4" +/-
30'-0" +/- 30 '-0
'-0
VALL
EY O
F R
OOF
RID
GE O
F R
OOF
VALL
EY O
F R
OOF
VALLEY OF ROOF
RIDGE OF ROOF
VALLEY OF ROOF
60'-0" +/-
'-4
/- 30
'-0
30'-0" +/-
30'-0" +/-
'-0
A510
2 TYPICAL
WP-1
ROOF PLAN LEGEND
ROOF DRAIN (RD)
SLOPE WITH INSULATION (SWI)
SLOPE WITH STRUCTURE (SWS)
VENT THROUGH ROOF (VTR)
EXISTING SOLAR PANELS
SWS
1/4" : 1'-0"
AKAF AL
TS
TA E O
49 TH
S
JAMES D. BARTLETT
No. A10413
REGISTEREDPROFESSIONALARCHIT
EC
D E S I G N
A L
A S
K
AT
U.S. DEPARTMENT OF THE INTERIOR
BUREAU OF LAND MANAGEMENT
ISSUE DATE
COMM. NUMBER
DESIGNED BY
DRAWN BY
SCALE 0" 1"
Architects Engineers Surveyors 601 College Road Fairbanks AK 99701
907.452.1241 designalaska.com
20 SEP 2021
FAIRBANKS
DISTRICT OFFICE
ROOF
REPLACEMENT
902102
AECC511
NATIONAL SYSTEM OF PUBLIC LANDS
20-SEP-2021
9/17/2021 3:47:22 PM
JB
GMC
RENOVATION
PLAN -
PENTHOUSE AND
ROOF
A200 3/32" = 1'-0"A200
1 RENOVATION PLAN - PENTHOUSE AND ROOF
B.
C.
D.
E.
A.
B.
C.
D.
E.
F.
1 - TYPICAL
ASSEMBLIES ARE DIAGRAMS ONLY, DO NOT SCALE.
ASSEMBLIES ARE INTENDED TO DESCRIBE MATERIALS AND
THEIR RELATIONSHIP WITHIN A GIVEN CEILING, FLOOR, ROOF,
OR WALL. PENETRATIONS, JOINTS, FINISHES, AND
INTERSECTIONS BETWEEN ASSEMBLIES ARE NOT SHOWN.
SEE A0 SHEETS FOR ARCHITECTURAL NOTES, SHEET
SEQUENCE, AND ASSEMBLY TAG LEGENDS.
SEE A2 SHEETS FOR FLOOR PLAN ASSEMBLY LOCATIONS.
SEE A5 SHEETS FOR EXTERIOR DETAILS.
2 - BUILDING ENVELOPE
SEE SPEC DIVISION 07 AND RELATED SPEC SECTIONS.
SEE A001 FOR BUILDING ENVELOPE LEGEND.
BARRIER / RETARDER CONTINUITY IS CRITICAL FOR THE
PERFORMANCE AND DURABILITY OF THE ASSEMBLY.
FLASHING, SEALING, AND INSULATING TRANSITION SPACES
ARE CRITICAL COMPONENTS OF WATER, AIR, AND THERMAL
BARRIER CONTINUITY.
WATER RESISTIVE BARRIER COMPONENTS MUST BE
INSTALLED IN A SHINGLE FASHION (WEATHER LAPPED),
FROM FOOTING TO ROOF, WITH SUFFICIENT OVERLAP AND
NO EXPOSED CORNERS. AVOID TRAPPING MOISTURE IN
TIGHT SPACES OR CREATING FLAT HORIZONTAL AREAS THAT
CAN COLLECT WATER.
NOTIFY ARCHITECT OF BUILDING ENVELOPE COMPONENT
SUBSTITUTIONS. SOME PRODUCTS CAN SIMULTANEOUSLY
ACT AS A WATER RESISTIVE BARRIER, AIR BARRIER, AND/ OR
A VAPOR RETARDER. SUBSTITUTING ASSEMBLY
COMPONENTS WITHOUT ARCHITECTS APPROVAL CAN
DRASTICALLY ALTER THE DURABILITY AND ENERGY
PERFORMANCE OF THE ASSEMBLY.
EXTERIOR ASSEMBLY NOTES
INTERIOR EXTERIOR
DIRECTION
OF DRYING
EXISTING - WALL PARAPET - TYPICAL(E) WP-1
(E) R-1 ROOF ASSEMBLY - EXISTING
INTERIOR
EXTERIOR EXISTING R-38 UNIFORM THICKNESS RIGID
INSULATION (2 LAYERS)
EXISTING FILTER FABRIC
EXISTING BALLAST PAVERS
R-E2 ROOF ASSEMBLY - EPDM
INTERIOR
EXTERIOR
CONTINUOUS BE-8 MECHANICALLY FASTENED
MULTI LAYERED INSULATION R-43.
JOINTS STAGGERED
MINIMUM 5" AT ROOF DRAINS
EXISTING 5/8" DECK BOARD
INSULATION COVER BOARD
EPDM ROOFING AS SPECIFIED
EXISTING METAL DECK TO REMAIN
INTERIOR EXTERIOR
DIRECTION
OF DRYING
EXISTING - WALL EXTERIOR - AT PENTHOUSE(E) WX-1
EXISTING POLY SHEETING
EXISTING 1/2" PLYWOOD SHEATHING
EXISTING 3/16" NEOPRENE SPACERS
EXISTING VAPOR BARRIER
EXISTING 8" METAL STUDS WITH
R-30 BATT INSULATION
EXISTING 1/2" PLYWOOD SHEATHING
EXISTING 1/2" RESILIENT CHANNELS @ 16" O.C.
EXISTING 1" AIR SPACE
EXISTING 4" SPLIT FACE CMU
(SMOOTH FACE ACCENT BANDS)
EXISTING ROOF MEMBRANE AND ADHESIVE
EXISTING 5/8" TYPE 'X' GYPSUM BOARD
EXISTING VAPOR BARRIER
EXISTING 6" METAL STUDS WITH
R-19 BATT INSULATION
EXISTING 1/2" GYPSUM SHEATHING
EXISTING COATED INSULATION
BOARD
EPDM ROOF MEMBRANE SYSTEM
DRAINAGE LAYER
PAVER GRID
COMPOSITE PAVER
EXISTING PLYWOOD SHEATHING
EXISTING PREFINISHED METAL
FLASHING
INTERIOR EXTERIOR
DIRECTION
OF DRYING
WALL PARAPET - TYPICALWP-1
EXISTING 1/2" PLYWOOD SHEATHING
EXISTING 3/16" NEOPRENE SPACERS
EXISTING VAPOR BARRIER
EXISTING 8" METAL STUDS WITH
R-30 BATT INSULATION
EXISTING 1/2" PLYWOOD SHEATHING
EXISTING 1/2" RESILIENT CHANNELS @ 16" O.C.
EXISTING 1" AIR SPACE
EXISTING 4" SPLIT FACE CMU
(SMOOTH FACE ACCENT BANDS)
EPDM ROOFING AS SPECIFIED TO
WRAP UP PARAPET WALL
EXISTING GYPSUM WALL BOARD
EXISTING STEEL DECK
INTERIOR EXTERIOR
DIRECTION
OF DRYING
WALL EXTERIOR - AT PENTHOUSE WX-1
EXISTING 5/8" TYPE 'X' GYPSUM BOARD
EXISTING VAPOR BARRIER
EXISTING 6" METAL STUDS WITH
R-19 BATT INSULATION
EXISTING 1/2" GYPSUM SHEATHING
EXISTING COATED INSULATION
BOARD
EXISTING PLYWOOD SHEATHING
EXISTING PREFINISHED METAL
FLASHING
EXISTING ROOF MEMBRANE EPDM ROOFING AS SPECIFIED
AKAF AL
TS
TA E O
49 TH
S
JAMES D. BARTLETT
No. A10413
REGISTEREDPROFESSIONALARCHIT
EC
D E S I G N
A L
A S
K
AT
U.S. DEPARTMENT OF THE INTERIOR
BUREAU OF LAND MANAGEMENT
ISSUE DATE
COMM. NUMBER
DESIGNED BY
DRAWN BY
SCALE 0" 1"
Architects Engineers Surveyors 601 College Road Fairbanks AK 99701
907.452.1241 designalaska.com
20 SEP 2021
FAIRBANKS
DISTRICT OFFICE
ROOF
REPLACEMENT
902102
AECC511
NATIONAL SYSTEM OF PUBLIC LANDS
20-SEP-2021
9/17/2021 3:47:23 PM
JB
GMC
EXTERIOR DETAIL
- ASSEMBLY TYPE
A500
BUILDING ENVELOPE INDEX
TYPE BASIS OF DESIGN - PER MATERIAL SCHEDULE
BE-8 GRACE ICE AND WATER SHIELD
EXTERIOR DETAIL NOTES
B.
C.
D.
E.
F.
SEE A0 SHEETS FOR NOTES AND LEGENDS.
EXTERIOR DETAILS ARE INTENDED TO SHOW BUILDING
ENVELOPE LAYER CONTINUITY AT TRANSITIONS.
CONSTRUCTION COMPONENTS MAY BE SIMPLIFIED OR
OMITTED FOR CLARITY.
SEE ELECTRICAL FOR EXTERIOR MOUNTED ITEMS,
INCLUDING, BUT NOT LIMITED TO LIGHTING,
RECEPTACLES, SENSORS, SIGNAGE, ANTENNAE, PANELS,
CONDUIT, AND JUNCTION BOXES. PROVIDE TREATED
BLOCKING, ATTACH TO PRIMARY FRAMING MEMBER, AND
WEATHER SEAL.
SEE MECHANICAL FOR EXTERIOR PENETRATIONS
INCLUDING BUT NOT LIMITED TO LOUVERS, DUCTS, PIPES,
FLUES, HOSE BIBBS, AND UTILITIES. PROVIDE TREATED
BLOCKING, ATTACH TO PRIMARY FRAMING MEMBER, AND
WEATHER SEAL.
PROVIDE PRE-FINISHED METAL FLASHING UNLESS NOTED
OTHERWISE. PERFORATE AT VENTED ASSEMBLIES.
PROVIDE TREATED 2x WOOD BLOCKING AT ROUGH
OPENINGS UNLESS NOTED OTHERWISE.
ROOF DRAIN
ROOF DRAIN
BOX
ROOF DRAIN
SUMP
SLOPE,
TYPICAL
4'-0"
2'-0"
4' -0
2' -0
NOTE: DRAIN SUMP DETAILS ARE
DIAGRAMMATIC IN NATURE. SEE ROOF PLAN
FOR SLOPES. SEE ASSEMBLIES FOR ROOF
CONSTRUCTION.
A510
EDGE OF
COMPOSITE
PAVERS,
GRID, AND
DRAINAGE
SHEET
4' -8
4'-8"
EPDM
MEMBRANE
GALVANIZED METAL FLASHING SYSTEM
APPROVED BY ROOF MANUFACTURER
LOW SLOPE ROOF PER ASSEMBLY
TYPE SEALED TO PIPE
BARRIER PER ASSEMBLY TYPE
SEALED TO PIPE
SEAL BASE PER ROOF MANUFACTURER
PIPE INSULATION AND GALVANIZED
METAL JACKETING PER MECHPER
ASSEMBLY
TYPE
PE
R
M
EC
H
AN
IC
AL
PRE-MOLDED PIPE BOOT FLASHING
SEAL TO PIPE PER ROOF MANUFACTURER
SEAL BE-8 TO DRAIN PIPE
AT SUMP
1'-0" TYPICAL
PER ASSEMBLY TYPE
ROOF/OVERFLOW DRAIN PER
MECHANICAL
INSTALL DRAIN BODY AT
DRAINBOX PER MANUFACTURER
INSTALL ROOFING MEMBRANE AT
DRAIN PER MANUFACTURER
3/4" PT PLYWOOD DRAINBOX TOP
RIP PT 2x TO MATCH SLOPE OF
DECK AND HEIGHT OF
INSULATION AT BASE OF SUMP
FILL ENTIRE VOID WITH
MINERAL WOOL
INSULATION. STAGGER
JOINTS AND DO NOT
COMPRESS BATTS.
CONTINUE MEMBRANE AT DRAIN BOX
INCREASE ROOF SLOPE AT SUMP
MECHANICALLY FASTEN
LIGHT GAUGE METAL
ANGLE TO DECK AND
DRAIN BOX
SLOPE PER ROOF PLAN
EPDM CONTINUOUS OVER CURB
2x STUD CONSTRUCTION.
FILL STUD CAVITY WITH
FOAM INSULATION
PRE-FINISHED METAL
FLASHING WITH CONTINUOUS
CLEAT AND DRIP EDGEEXISTING PENTHOUSE
EQUIPMENT
SEAL WEATHERTIGHT PER
EQUIPMENT MANUFACTURERS
INSTRUCTIONS
R-E2 R-E2
INTERIOR EXTERIOR
WP-1
RE-2
EXISTING
HANDRAIL
SYSTEM
PRE-FINISHED
METAL FLASHING
AKAF AL
TS
TA E O
49 TH
S
JAMES D. BARTLETT
No. A10413
REGISTEREDPROFESSIONALARCHIT
EC
D E S I G N
A L
A S
K
AT
U.S. DEPARTMENT OF THE INTERIOR
BUREAU OF LAND MANAGEMENT
ISSUE DATE
COMM. NUMBER
DESIGNED BY
DRAWN BY
SCALE 0" 1"
Architects Engineers Surveyors 601 College Road Fairbanks AK 99701
907.452.1241 designalaska.com
20 SEP 2021
FAIRBANKS
DISTRICT OFFICE
ROOF
REPLACEMENT
902102
AECC511
NATIONAL SYSTEM OF PUBLIC LANDS
20-SEP-2021
9/17/2021 3:47:24 PM
JB
GMC
EXTERIOR DETAIL
- TYPICAL
A510
BUILDING ENVELOPE INDEX
TYPE BASIS OF DESIGN - PER MATERIAL SCHEDULE
BE-8 GRACE ICE AND WATER SHIELD
3/4" = 1'-0"A510
2 EXTERIOR DETAIL - ROOF - EPDM - DRAIN PLAN
1 1/2" = 1'-0"A510
3 EXTERIOR DETAIL - ROOF - EPDM - STEEL - INSULATED VTR PENETRATION
1 1/2" = 1'-0"A510
4 EXTERIOR DETAIL - ROOF - EPDM - STEEL - DRAIN SECTION
1 1/2" = 1'-0"A510
1 EXTERIOR DETAIL - ROOF - EPDM - MECHANICAL PENTHOUSE SECTION
1 1/2" = 1'-0"
EXTERIOR DETAIL - ROOF - PARAPET5
A510
CEILING PLAN NOTES
B.
C.
COORDINATE MECHANICAL ELEMENTS INCLUDING, BUT
NOT LIMITED TO DIFFUSERS, RETURN AIR SLOTS, ACCESS
PANELS, AND EQUIPMENT WITH MECHANICAL
DOCUMENTS.
COORDINATE ELECTRICAL ELEMENTS INCLUDING, BUT
NOT LIMITED TO LIGHTING, SENSORS, SPEAKERS,
SIGNAGE, ACCESS PANELS, AND EQUIPMENT WITH
ELECTRICAL DOCUMENTS.
COORDINATE FIRE ALARM AND FIRE SUPPRESSION
ELEMENTS INCLUDING, BUT NOT LIMITED TO SMOKE
DETECTORS, SPRINKLERS, ACCESS PANELS, AND
EQUIPMENT WITH FIRE PROTECTION, MECHANICAL, AND
ELECTRICAL DOCUMENTS.
CEILING PLAN LEGEND
EXISTING ACOUSTICAL CEILING TILE
OPEN TO STRUCTURE
NO WORK AREA
EXISTING GYPSUM BOARD CEILING
SECURE
STORAGE
COPY ROOM
ELECTRICAL
ELECTRICAL
COPY ROOM
MEN
CONFERENCE
CONFERENCE
GIS
COMPUTER
EQUIPMENT
CHIEF 3
WORD
PROCESSING
JANITOR
ARCH./PAL.
LAB
CHIEF 2
CHIEF 1
RECEPTION
CORRIDOR
LAND
MANAGMENT
UNIT 3
LAND
MANAGMENT
UNIT 4
LAND
MANAGMENT
UNIT 2
CORRDIOR
ELEVATOR
LOBBY
RECEPTION
CORRIDOR
WOMENS
CHIEF 4
ACTIVE
FILES
LIBRARY.WORK
AREA
CONFERENCE
CONFERENCE
CORRIDOR
LAND
MANAGEMENT
UNIT 1
CORRIDOR
226OPEN TO
BELOW
OPEN TO
BELOW
STAIR 2 STAIR 3
STAIR 1
CONFERENCE
ROOM
225.1
CONFERENCE
ROOM
225.2
OFFICE
201.1
KEYNOTES
ROOF DRAIN LOCATION ABOVE. PROVIDE CEILING WORK
AS REQUIRED TO ACCOMMODATE ROOF WORK.
AKAF AL
TS
TA E O
49 TH
S
JAMES D. BARTLETT
No. A10413
REGISTEREDPROFESSIONALARCHIT
EC
D E S I G N
A L
A S
K
AT
U.S. DEPARTMENT OF THE INTERIOR
BUREAU OF LAND MANAGEMENT
ISSUE DATE
COMM. NUMBER
DESIGNED BY
DRAWN BY
SCALE 0" 1"
Architects Engineers Surveyors 601 College Road Fairbanks AK 99701
907.452.1241 designalaska.com
20 SEP 2021
FAIRBANKS
DISTRICT OFFICE
ROOF
REPLACEMENT
902102
AECC511
NATIONAL SYSTEM OF PUBLIC LANDS
20-SEP-2021
9/17/2021 3:47:27 PM
JB
GMC
INTERIOR PLAN -
CEILING - 2ND
FLOOR
A620 3/32" = 1'-0"A620
1 INTERIOR PLAN - CEILING - 2ND FLOOR
ABBREVIATION FULL NAME
RL RAIN LEADER
EXISTING
EXISTING TO BE REMOVED
MECHANICAL - LINETYPES
LINETYPE
UNION
MECHANICAL SYMBOLS
PIPE CONNECTION
PIPE ELBOW TURNED DOWN
PIPE ELBOW TURNED UP
PIPE TEE DOWN
PIPE FLOW ARROW
CONNECTION TO EXISTING
PIPE CAP
PIPE BREAK
PLUMBING SCHEDULE
SYMBOL FIXTURE
DESCRIPTION
RD-1 ROOF DRAIN,
PRIMARY
WASTE
CONNECTION
SIZE (IN)
REMARKS
1. SEE SPECIFICATION FOR BASIS OF
DESIGN
INSULATE RAIN LEADER PIPING FOR 5 FT
FROM CONNECTION TO ROOF DRAIN BODY
TO INSIDE THE BUILDING. PROVIDE
FIBERGLASS INSULATION PREFORMED FOR
THE SPECIFIC PIPE SIZE WITH WHITE FACED
ASJ WITH VAPOR BARRIER COATING.
BUSHING TAP FOR ELECTRICAL
FITTING BY MANUFACTURER, TYP
6 POINT DE-ICING SYSTEM
CONTINUE THROUGH 6-POINT
DE-ICING SYSTEM, TYP
PRIMARY ROOF DRAIN6 POINT DE-ICING
SYSTEM
HEAT TRACE CABLE, (TYP)
LOOP AT ENDS, THEN FEED
BACK THROUGH CHANNELS,
(TYP)
ROOF DRAIN & DRAIN
BODY, TYP
PROVIDE AND MODIFY EXISTING
RAINLEADER PIPING AS REQUIRED TO
INSTALL WYE FITTING. WYE FITTING
MAY BE INSTALLED IN HORIZONTAL
PIPING PROVIDED FITTING AND
BUSHING FOR ELECTRICAL
CONNECTION IS ABOVE THE PIPE
CENTERLINE.
ROUTE HEAT TRACE TAPE THROUGH WYE
FITTING, LOOP CABLE. PROVIDE END FITTING
PER MANUFACTURER'S RECOMMENDATIONS.
POWER CONNECTION, SEAL FITTING
WITH GROMMET BY MFG, TYP
EXISTING RAIN LEADER PIPING
JUNCTION BOX, SEE
ELECTRICAL FOR ADDITIONAL
INFORMATION
HEATING CABLE FEEDS
THROUGH DRAIN BODY
18"
HEAT TRACE METAL CHANNEL
ROOFING PER ARCHITECTURE
U.S. DEPARTMENT OF THE INTERIOR
BUREAU OF LAND MANAGEMENT
ISSUE DATE
COMM. NUMBER
DESIGNED BY
DRAWN BY
SCALE 0" 1"
Architects Engineers Surveyors
601 College Road Fairbanks AK 99701
907.452.1241 designalaska.com
20 SEP 2021
FAIRBANKS
DISTRICT OFFICE
ROOF
REPLACEMENT
902102
AECC511
NATIONAL SYSTEM OF PUBLIC LANDS
9/17/2021 3:30:27 PM
MPC
ERM
MECHANICAL
ABBREVIATIONS,
LEGENDS,
SCHEDULES, AND
DETAILS
M001
KEY NAME ABBREVIATIONS
# NUMBER
& AND
(D) DEMOLITION
(E) EXISTING
(N) NEW
@ AT
AFF ABOVE FINISHED FLOOR
APPR APPROVED
APPROX APPROXIMATE
ARCH ARCHITECTURAL
ASSOC ASSOCIATED
C COMMON
CI CAST IRON
CO CLEAN OUT
DI DUCTILE IRON
DIA DIAMETER
DN DOWN
ELEC ELECTRICAL
EXIST EXISTING
GA GAUGE
GALV GALVANIZED
GI GALVANIZED IRON
ID INSIDE DIAMETER
IE INVERT ELEVATION
INSUL INSULATION
IPS IRON PIPE SIZE
MECH MECHANICAL
MIN MINIMUM
NIC NOT IN CONTRACT
NTS NOT TO SCALE
OFCI OWNER FURNISHED, CONTRACTOR INSTALLED
OFOI OWNER FURNISHED, OWNER INSTALLED
ORD OVERFLOW ROOF DRAIN
ORL OVERFLOW RAIN LEADER
RD ROOF DRAIN
RHW RECIRCULATING HOT WATER
RL RAIN LEADER
SIM SIMILAR
SPEC SPECIFICATIONS
SS STAINLESS STEEL
TYP TYPICAL
V VENT
VOL VOLUME
VTR VENT THROUGH ROOF
W WASTE
W/ WITH
W/O WITHOUT
WCO WALL CLEAN OUT
MECHANICAL ABBREVIATIONS
M001 NO SCALE
1 ROOF DRAIN HEAT TRACE
A K
AF AL
T S
T A
E O
49 TH
S
R E
G
ISTERED
PROFESS IONAL
ENG
IN
E
E R
D E
S I G
N
A L
A S
K
A17-SEP-2021
Marcus P. Curley
ME 14660
A
B
C
D
E
F
G
SPECIFIC NOTES
DEMOLISH EXISTING ROOF DRAIN.
(E) VENT THROUGH ROOF TO REMAIN.2
1 1
(E) PENTHOUSE ROOF DRAINAGE IS VIA GUTTERS
ON TO LOWER ROOF, GUTTERS TO REMAIN AS-IS
(E) EXHAUST FAN AND CURB TO REMAIN3
(E) EXHAUST HOOD TO REMAIN. 4
U.S. DEPARTMENT OF THE INTERIOR
BUREAU OF LAND MANAGEMENT
ISSUE DATE
COMM. NUMBER
DESIGNED BY
DRAWN BY
SCALE 0" 1"
Architects Engineers Surveyors
601 College Road Fairbanks AK 99701
907.452.1241 designalaska.com
20 SEP 2021
FAIRBANKS
DISTRICT OFFICE
ROOF
REPLACEMENT
902102
AECC511
NATIONAL SYSTEM OF PUBLIC LANDS
9/17/2021 3:30:28 PM
MPC
ERM
LOWER ROOF
PLUMBING
DEMOLITION PLAN
M100M100 3/32" = 1'-0"
1 LOWER ROOF PLUMBING DEMOLITION PLAN
A K
AF AL
T S
T A
E O
49 TH
S
R E
G
ISTERED
PROFESS IONAL
ENG
IN
E
E R
D E
S I G
N
A L
A S
K
A17-SEP-2021
A
B
C
D
E
F
G
RD-1, TYP
M001
SPECIFIC NOTES
(E) VENT THROUGH ROOF.1
(E) EXHAUST FAN AND CURB.2
(E) EXHAUST HOOD.3
U.S. DEPARTMENT OF THE INTERIOR
BUREAU OF LAND MANAGEMENT
ISSUE DATE
COMM. NUMBER
DESIGNED BY
DRAWN BY
SCALE 0" 1"
Architects Engineers Surveyors
601 College Road Fairbanks AK 99701
907.452.1241 designalaska.com
20 SEP 2021
FAIRBANKS
DISTRICT OFFICE
ROOF
REPLACEMENT
902102
AECC511
NATIONAL SYSTEM OF PUBLIC LANDS
9/17/2021 3:30:29 PM
MPC
MPC
ROOF PLUMBING
PLAN
M200M200 3/32" = 1'-0"
1 LOWER ROOF PLUMBING PLAN
A K
AF AL
T S
T A
E O
49 TH
S
R E
G
ISTERED
PROFESS IONAL
ENG
IN
E
E R
D E
S I G
N
A L
A S
K
A17-SEP-2021
ELECTRICAL SYMBOL LEGEND
J JUNCTION BOX
MOTOR (HP, VOLTAGE & PHASE NOTED ON DRAWING)
PANELBOARD
POWER SYMBOLS
RECEPTACLE; DUPLEX, QUADPLEX
+2'-0" AFF UON
GFCI RECEPTACLE; QUADPLEX, DUPLEX
+4'-0" AFF UON
SPECIAL RECEPTACLE
(NEMA TYPE NOTED ON DRAWING)
+4'-0" AFF UON
NON-FUSIBLE DISCONNECT
M
ANNOTATION SYMBOLS
L1-12
L1-12
AHU-1
PANEL & CIRCUIT IDENTIFICATION
PANEL & CIRCUIT IDENTIFICATION
B LIGHTING FIXTURE TAG (SEE LIGHTING FIXTURE SCHEDULE)
'L1' DENOTES PANEL NAME, '24' DENOTES CIRCUIT NUMBERL1-24
SPECIFIC NOTE KEY
(REFERENCE # UNDER 'SPECIFC NOTES' ON EACH SHEET)
a
SWITCH IDENTIFICATION TAG
a SWITCH IDENTIFIER
EQUIPMENT IDENTIFIER, SEE MECHANICAL ELECTRICAL SCHEDULE
AKAF AL
TS
TA E O
49 TH
S
D E S I G N
A L
A S
K A
REGISTERED PROFESSIONAL ENGIN
EE
R
U.S. DEPARTMENT OF THE INTERIOR
BUREAU OF LAND MANAGEMENT
ISSUE DATE
COMM. NUMBER
DESIGNED BY
DRAWN BY
SCALE 0" 1"
Architects Engineers Surveyors 601 College Road Fairbanks AK 99701
907.452.1241 designalaska.com
20 SEP 2021
FAIRBANKS
DISTRICT OFFICE
ROOF
REPLACEMENT
902102
AECC511
NATIONAL SYSTEM OF PUBLIC LANDS
20-SEPT-2021
Donald L Hopkins
EE 10582
9/16/2021 8:15:53 AM
DLH
DLH
ELECTRICAL
SYMBOLS,
LEGENDS AND
DETAILS
E001
SPECIFIC SHEET NOTES
1 REPLACE EXISTING BREAKER WITH NEW 20A GFPE BREAKER TO FEED DRAIN
BODY HEAT TRACE. WHERE NO SPARE BREAKER EXISTS AND P-2 IS FEEDING
LOADS, REPLACE BREAKER P-4 WITH A DUPLEX BREAKER AND CONNECT LOADS
FROM P-2 AND P-4 TO THIS NEW BREAKER.
NOTES:
CH CHILLER [NEC 2017, ARTICLE 440.33] 0 VA 0.00% 0 VA
H HBO [NEC 2017, ARTICLE 220.14(A)] 0 VA 0.00% 0 VA
A APPLIANCE [NEC 2017, ARTICLE 220.56] 0 VA 0.00% 0 VA
M MOTOR [NEC 2017, ARTICLE 430.24] 0 VA 0.00% 0 VA
R RECEPTACLES [NEC 2017, ARTICLE 220.44] 0 VA 0.00% 0 VA
L LIGHTING [NEC 2017, ARTICLE 215.2(A)(1)] 0 VA 0.00% 0 VA DEMAND LOAD: 0 VA 0 A
E NON-CONTINUOUS [NEC 2017, ARTICLE 215.2(A)(1)] 0 VA 0.00% 0 VA CONNECTED LOAD: 0 VA 0 A
C CONTINUOUS [NEC 2017, ARTICLE 215.2(A)(1)] 0 VA 0.00% 0 VA LOAD AMPS
LOAD CLASSIFICATION CONNECTED LOAD DEMAND FACTOR DEMAND LOAD PANEL TOTALS
TOTAL AMPS: 0 A 0 A 0 A
TOTAL LOAD: 0 VA 0 VA 0 VA
11 F/A R/B (LOCKING DEVICE ON BREAKER) -- 15 1 0 0 1 20 -- GUTTER HEAT TRACE (GFPE) 12 9 STATC PRESS CONT F-1 AIR HANDLER -- 15 1 0 0 1 20 -- U.P.S. DGPS NAVIGATOR ANT SYS. 10
7 OUTLET RECEPTACLE BELOW PANEL BOX P -- 15 1 0 0 1 20 -- REFRIGERATOR 8
5 HOT WATER HEATER & BURNER ASSY. -- 15 1 0 0 1 20 -- EMERGENCY GEN PERK HEATER 6
3 HOT WATER CIRC. PUMP #13 -- 15 1 0 0 1 20 -- BATTERY CHARDE FOR EMERG. GEN 4
1 FUME HOOD (EF-1) -- 15 1 0 0 1 20 -- (N) DRAIN BODY HEAT TRACE (GFPE) 2
CKT CIRCUIT DESCRIPTION LOAD
CLASS TRIP P A B C P TRIP LOAD
CLASS CIRCUIT DESCRIPTION CKT
ENCLOSURE: TYPE 1 MCB RATING: 100 A
MOUNTING: SURFACE WIRES: 4 MAINS RATING: 100 A
SUPPLY FROM: PHASES: 3 MAINS TYPE: MCB
LOCATION: BOILER ROOM 302 VOLTS: 208Y/120V A.I.C. RATING: 10000
PANEL: P
J J JJ
M
M
PV ARRAY 22 PANELS
5-SETS (4-RACK), 1 SET (2-RACK)
264W/PANEL = 5808W
3-PHASE CONNECTIONS
PV ARRAY 22 PANELS
5-SETS (4-RACK), 1 SET (2-RACK)
264W/PANEL = 5808W
3-PHASE CONNECTIONS
TREATED WOOD SLEEPER WITH RIGID
CONDUIT AND JUNCTION BOXES FOR
ROUTING DC CABLES FROM PV ARRAY
PV ARRAY ON
SECTIONED RACKS
WITH PAVER BALLASTS
CONDUIT SUPPORTED BY
CONSTRUCTION STRUT
AFFIXED TO PARAPET
CONDUIT SUPPORTED BY
CONSTRUCTION STRUT
SLEEPERS ON ROOF
LIQUID TIGHT FLEXIBLE CONDUIT BETWEEN
CONDUITS AND DISCONNECT SWITCH
DISCONNECT SWITCH
TREATED WOOD SLEEPER WITH RIGID
CONDUIT AND JUNCTION BOXES FOR
ROUTING DC CABLES FROM PV ARRAY
LIQUID TIGHT FLEXIBLE CONDUIT BETWEEN
CONDUITS AND DISCONNECT SWITCH
CONDUIT SUPPORTED BY
CONSTRUCTION STRUT
AFFIXED TO PARAPET
PV ARRAY GROUNDING
CONDUCTOR BARE CU ROUTED
ALONG PARAPET THEN DOWN WALL
TO GROUND ROD AT GROUND LEVEL
EF-1
EF-2
WEST
ARRAY
INVERTER
EAST
ARRAY
INVERTER
PV DISCONNECTS
PV DISCONNECTS
PNL P
PNL PP
PNL MCCN
BUCKET EF-2
IN MCCN
BREAKER EF-1
PANEL P
1 1
CONDULETS AT PENETRATION
TO ROUTE ROOFTOP EQUIPMENT
5 5
G
F
E
D
C
B
A 1
DISCONNECT - WEST SIDE PV ARRAY
CONDUIT ROUTING ON SLEEPERS - WEST SIDE
PV ARRAY - WEST SIDE
PV INVERTERS IN PENTHOUSE
PV ARRAY - EAST SIDE
CONDUIT ROUTING ON SLEEPERS - WEST SIDE DISCONNECT - EAST SIDE & PARAPET CONDUIT
VIEW BEHIND WEST PV ARRAY SHOWING
MOUNTING RACKS AND BALLASTED FOOTERS
GROUND ROD LOCATION
(GROUND LEVEL)
EAST SIDE PV ARRAY & CONDUIT SUPPORT
RAIN GUTTER & DOWNSPOUT
(HEAT TRACED ~120' 12 W/FT)
(TYPICAL BOTH SIDES)
AKAF AL
TS
TA E O
49 TH
S
D E S I G N
A L
A S
K A
REGISTERED PROFESSIONAL ENGIN
EE
R
U.S. DEPARTMENT OF THE INTERIOR
BUREAU OF LAND MANAGEMENT
ISSUE DATE
COMM. NUMBER
DESIGNED BY
DRAWN BY
SCALE 0" 1"
Architects Engineers Surveyors 601 College Road Fairbanks AK 99701
907.452.1241 designalaska.com
20 SEP 2021
FAIRBANKS
DISTRICT OFFICE
ROOF
REPLACEMENT
902102
AECC511
NATIONAL SYSTEM OF PUBLIC LANDS
20-SEPT-2021
Donald L Hopkins
EE 10582
9/16/2021 8:16:16 AM
DLH
DLH
ELECTRICAL
ROOF PLAN
E100 E100 3/32" = 1'-0"
1 ROOF PLAN & DETAILS
SPECIFIC SHEET NOTES
1 CONTRACTOR TO PROVIDE NEW SLEEPERS THROUGHOUT FOR SUPPORTING OF CONDUITS ON NEW ROOF SYSTEM.
RE-USE OF THE EXISTING UNITS SHALL NOT BE ACCEPTABLE. NEW SLEEPERS SHALL BE EATON DURA BLOCK, nVENT CADDY OR OTHER EQUIVALENT RUBBER TYPE PIPE SUPPORT SYSTEM EQUAL AND NOT FABRICATED FROM INDIVIDUAL STRUT COMPONENTS AND TREATED WOOD AS THE EXISTING UNITS ARE. DISTANCE BETWEEN SLEEPERS SHALL NOT BE GREATER THAN 8' REGARDLESS OF NEC CONDUIT SUPPORT CRITERIA. WHERE DISTANCE ALONG ROOF OF CONDUITS ON SLEEPERS ARE FIXED ON TWO ENDS AND GREATER THAN 50 FEET, THE CONDUIT SHALL HAVE A BEND
OR EXPANSION FITTING TO ALLOW FOR THERMAL CHANGES IN THE RUN.
2 MOUNTING STRUT ON PARAPET TO BE REMOVED TO ACCOMMODATE THE ROOF WORK AND REPLACED. SPACING SHALL BE PER THE NEC FOR SUPPORTING OF THE CONDUITS WHEN RE-INSTALLED. CONTRACTOR SHALL SUPPORT ENDS OF
CONDUITS WITHIN 6" OF TRANSITIONS TO FLEXIBLE CONDUITS.
3 TREATED WOOD SUPPORTING THE CONDUITS ALONG THE FRONT OF THE PV ARRAYS SHALL NOT BE RE-USED AND
REPLACED WITH NEW MATERIALS.
4 CONTRACTOR SHALL CAREFULLY PAY ATTENTION TO PV ARRAY POWER SYSTEMS WHEN RE-CONNECTIONS TO ENSURE
THE POSITIVE AND NEGATIVE LEADS ARE NOT REVERSED IN THE INVERTER.
5 CONTRACTOR TO REMOVE FROM ROOF OR RELOCATE TO AREA ON ROOF THE PV ARRAYS, RACKING AND BALLAST AS NEEDED TO ACCOMMODATE NEW ROOF REPLACEMENT. CONDUITS MAY BE RE-USED, BUT CONDUCTORS TO BE REPLACED WHERE ANY DAMAGE OCCURS DURING THIS PROCESS. ONCE ROOF IS REPLACED, THE PV ARRAYS TO BE
LOCATED IN APPROXIMATELY THE SAME LOCATION AS IS CURRENTLY INSTALLED.
6 ROOF DRAIN BODY TO BE HEAT TRACED. PROVIDE NEW CONTROLLER FOR DRAIN BODIES TO PROVIDE HEAT TO THE DRAIN BODIES BETWEEN AMBIENT AIR TEMPERATURES OF 10 DEGREES F AND 40 DEGREES F. AT TEMPERATURES ABOVE OR BELOW THESE AMBIENT AIR TEMPERATURES THE HEATING CABLES TO BE DE-ENERGIZED TO SAVE ENERGY.
| G001 |
| C200 |
| A001 |
| A100 |
| A200 |
| A500 |
| A510 |
| A620 |
| M001 |
| M100 |
| M200 |
| E001 |
| E100 |
File details come from the government source that posted it. Updated .