B08_-_140P4322R0003_ATTACHMENT_NUMBER_001_LOWE_Rehabilitate_Central_Street_Canal_Walkway_SOW.docx

DOCX document 13 KB Posted

Attached to
LOWE REHABILITATE CENTRAL STREET WALKWAY
Solicitation number
140P4322R0003
Issued by

About this file

This scope of work document outlines a rehabilitation project for an existing canal walkway in two sections. The first section involves rehabilitating two sets of concrete steps connecting a 65-foot long brick walkway, including masonry repointing, concrete and railing repairs, and resetting pavers and a drainage structure. The second section requires selective demolition and replacement of a 167-foot long cantilevered walkway, starting with demolition and removal of the existing surface and steel structure, followed by installation of new structural decking and reinforced concrete walkway, and reusing and painting the existing guardrail system. The related federal contract opportunity is solicitation number 140P4322R0003 from the Department of the Interior National Park Service Northeast Region to rehabilitate the Central Street walkway.

View the file

Other files

File Type Posted
Sol_140P4322R0003_Amd_0005.pdf PDF
Sol_140P4322R0003_Amd_0004.pdf PDF
B08_-_140P4322R0003_LOWE_ATTACHMENT_NUMBER_012_090190_52_Maint_Repainting_LOWE_241738_0004.pdf PDF
B08_-_140P4322R0003_LOWE_ATTACHMENT_NUMBER_013_Site_Visit_Sign_in_Sheet_0004.pdf PDF
Sol_140P4322R0003_Amd_0003.pdf PDF
B08_-_140P4322R0003_LOWE_ATTACHMENT_NUMBER_011_BINDER_1_CENTRAL_STREET_ADDITIONAL_PHOTOS_0003.pdf PDF
Sol_140P4322R0003_Amd_0002.pdf PDF
Sol_140P4322R0003_Amd_0001.pdf PDF
B08_-_140P4322R0003_LOWE_ATTACHMENT_NUMBER_010_CENTRAL_STREET_SITE_MTG_LOCATION_0001.pdf PDF
B08_-_140P4322R0003_LOWE_ATTACHMENT_NUMBER_007__FAR_52_204-26_Covered_Telecommunications_Equipment_or_Services-Representation.pdf PDF
B08_-_140P4322R0003_LOWE_ATTACHMENT_NUMBER_009_LmtOnSubconRpt.xlsx XLSX spreadsheet
B08_-_140P4322R0003_LOWE_ATTACHMENT_NUMBER_003_Rehabilitate_Central_Street_Canal_Walkway_2108-06-28_drawings.pdf PDF
B08_-_140P4322R0003_LOWE_ATTACHMENT_NUMBER_004_Rehabilitate_Central_Street_Canal_Walkway__DOL_DBA_GD_MA20220008__MA_Heavy_01072022.pdf PDF
B08_-_140P4322R0003_LOWE_ATTACHMENT_NUMBER_002_Rehabilitate_Central_Street_Canal_Walkway_Specifications_-_Updated_2_9_2022.pdf PDF
B08_-_140P4322R0003_LOWE_ATTACHMENT_NUMBER_006_FAR_52_212-3_Offer_Representations_and_Certifications_-_Commercial_Products_and_Commercial_Services.pdf PDF
B08_-_140P4322R0003_LOWE_ATTACHMENT_NUMBER_008_FAR_52_204-24___REPRESENTATION_REGARDING_CERTAIN_TELECOMMUNICATIONS_AND_VIDEO.pdf PDF
Sol_140P4322R0003.pdf PDF
B08_-_140P4322R0003_LOWE_ATTACHMENT_NUMBER_005_Rehabilitate_Central_Street_Canal_Walkway_Guidance_on_Preparing_Workplace_for_COVID_19.pdf PDF
Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

140P4322R0003 LOWE REHAB CENTRAL STREET WALKWAY 241738 B

SCOPE OF WORK

The project involves the rehabilitation of an existing canal walkway that connects a pedestrian walkway approximately 232 linear feet in length from Central Street reconnecting with canal walk plaza near the Leo A. Roy Parking Facility.

The walkway consists of two sections of work. The first section (CLIN 00010) consists of rehabilitation of two sets of concrete steps, granite clad, connecting a 65’ long, brick paved walkway with steel handrails and guardrails. Included in the rehabilitation work is masonry repointing, concrete repairs, railing repairs and repainting, and re-setting brick pavers and a drainage structure. The second section (CLIN 00020) involves the selective demolition and replacement of a 167’ long, cantilevered canal walkway, starting with selective demolition and removal of existing walkway surface, retaining steel structure, installation of new structural decking and reinforced concrete walkway and re-use and painting of existing guardrail system.

File details come from the government source that posted it. Updated .