B027-12 Tank Removal.pdf
PDF 313 KB Posted
- Attached to
- Engine #2 Tank Removal
- Solicitation number
- B027-12
- Issued by
- New Haven County, Connecticut
About this file
Summary
This is an Invitation to Bid document issued by the City of Meriden, Connecticut for the removal and disposal of an underground storage tank at Engine Company #2, located at 168 Chamberlain Highway, Meriden, Connecticut. The project involves the complete removal, decontamination, and disposal of a 4,000-gallon double-wall underground storage tank (UST) system with concrete bottom and top slabs, including associated piping and ancillary equipment, along with backfilling and restoration of the disturbed area. Contractors must submit electronic bids through the City eProcurement Portal (https://procurement.opengov.com/portal/meridenct) by 11:00 a.m. on September 9, 2026. The question submission deadline is September 2, 2026 at 4:00 p.m. Bidders are required to conduct a site visit and familiarize themselves with all existing conditions prior to submitting their bid. No formal bidders conference is specified in the document. Bids must remain open for ninety (90) days from the bid opening date, and the contract will be awarded to the lowest responsible bidder meeting all specifications and qualifications.
The pricing proposal requests a lump sum fee for the total scope of work, with compensation for contaminated soil removal paid as a separate unit cost that includes testing, excavation, stockpiling, transportation, and disposal. The City of Meriden is exempt from federal excise taxes and Connecticut sales and use taxes, and these taxes should not be included in the bid price. Each bid must be accompanied by a bid bond equal to ten percent (10%) of the amount bid. The successful bidder will be required to provide a Performance Bond and Labor and Material Payment Bond each equal to one hundred percent (100%) of the contract price. The contractor must have a minimum of two years of tank removal experience and be certified by the State of Connecticut for tank removal work. Local preference provisions apply, allowing City-based businesses submitting bids within ten percent (10%) of the low bid to accept the award at the low bid amount. Liquidated damages of $500 per day will apply for any delay beyond the specified completion deadline. The City will make payment no less than thirty (30) days following completion of services.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| B027-12_Aug_12_26_solicitation_doc.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
For more information, please visit our online supplier portal, located at https://procurement.opengov.com/portal/meridenct
City of Meriden Purchasing Department
142 East Main St. Room 210 Meriden, CT 06450
B027-12 ENGINE #2 TANK REMOVAL
Project ID: B027-12
RELEASE DATE: August 12, 2026
RESPONSE DEADLINE: September 9, 2026, 11:00 am
Please refer to the project timeline in this document for all important deadlines.
Invitation To Bid #B027-12 Title: B027-12 Engine #2 Tank Removal
Table Of Contents
1. LEGAL NOTICE
2. INFORMATION TO BIDDERS
3. SCOPE OF WORK
4. PRICING PROPOSAL
5. VENDOR SUBMISSION FORMS
Attachments:
A - Eng #2 Tank Removal Drawing
C - CMG Report 1-26
D - TradeBe Report
E - Construction Contract-Sample
F - EJCDC General & Supplemental
G - General Insurance
H - Sample Performance Bond
I - Sample Payment Bond
LEGAL NOTICE
INVITATION TO BID
The City of Meriden is accepting electronic bids for:
B027-12 Engine #2 Tank Removal
The City of Meriden is soliciting bids in seeking the services of a contractor to to remove the underground fuel tank at Engine Co #2, 168 Chamberlain Hwy, Meriden, CT 06451.
Bids shall be submitted as electronic bids per specifications obtained via the City eProcurement Portal: https://procurement.opengov.com/portal/meridenct and on the State of Connecticut Department of Administrative Services website (https://webprocure.proactiscloud.com).
Bids may be received up to but not later than 11:00 am, Wednesday, September 9, 2026 via the City eProcurement Portal located at https://procurement.opengov.com/portal/meridenct. The City eProcurement Portal Clock is the official clock for the determination of all deadline dates and times. Without exception, responses will not be accepted after the submission deadline regardless of any technical difficulties. Please submit electronic responses via the City eProcurement Portal:
https://procurement.opengov.com/portal/meridenct by way of the eProcurement Portal, responses will be locked and digitally encrypted until the submission deadline passes.
Each bid shall be accompanied by a Bid Bond in the amount of Ten (10%) percent of the amount bid.
The right is reserved to reject any or all bids, in whole or in part, to award any item, group of items, or total bid, and to waive informality or technical defects, if it is deemed to be in the best interest of the City of Meriden. No bidder may withdraw its bid within ninety (90) days of the date of the bid opening.
Labor and Material Payment Bond and a Performance Bond for One Hundred Percent (100%) of the contract price, with a corporate surety approved by the City of Meriden, will be required of the lowest responsible bidder.
The City of Meriden is an Affirmative Action/Equal Opportunity Employer. Disadvantaged, minority, small, and women business enterprises are encouraged to respond.
Rawle Dummett Purchasing Officer City of Meriden, CT 06450-8022 Dated: August 12, 2026 https://procurement.opengov.com/po1tal/meridenct https://webprocure.proactiscloud.com/
INFORMATION TO BIDDERS
1. SUMMARY
The City of Meriden is accepting bids for the fuel tank removal at Engine Co #2, 168 Chamberlain Highway, Meriden, CT 06451.
The Contractor shall develop, implement, maintain, and supervise as part of the work, a comprehensive plan for tank removal and related operations. The work consists of removal, decontamination and disposal of underground storage tank, associated piping and ancillary equipment as well as backfilling & restoring/seeding of the area. The Work Plan shall be based on work experience, on the guidance provided in this specification.
The Contractor shall have a minimum of 2 years of tank removal experience and shall be certified by the State of Connecticut for tank removal work.
2. TIMELINE
Project Release Date: August 12, 2026
Question Submission Deadline: September 2, 2026, 4:00pm
Submission Deadline: September 9, 2026, 11:00am
3. BIDDING PROCEDURES
The City will only be accepting electronic submissions of bids and proposals. Please submit electronic responses via the City eProcurement Portal: https://procurement.opengov.com/portal/meridenct. By way of the eProcurement Portal, responses will be locked and digitally encrypted until the submission deadline passes.
Bids are due for submission no later than 11:00 am, Wednesday, September 9, 2026.
4. BIDS
Bids are to be submitted as follows:.
a. Bids must be made out and signed in the corporate, or other, name of Bidder, and must be fully and properly executed by an authorized person.
b. The City of Meriden, CT will only be accepting electronic submissions of the enclosed bid sheet via the City eProcurement portal partner, OpenGov: https://procurement.opengov.com/portal/meridenct.
c. Bids received later than the time and date specified will not be considered.
d. Amendments to or withdrawal of bids received later than the date and time set forth in the bid opening will not be considered.
5. EXAMINATION OF BIDDING DOCUMENTS
Bidders are to examine all documents and visit the site in order to make a thorough examination of the conditions so that the bidder may familiarize itself with all of the existing requirements, conditions, and difficulties that will affect the execution of the work in order to determine the amount of work necessary to carry out the true intent of the specifications and work shown on the drawings.
The City of Meriden and its agents do not have any responsibility for the accuracy, completeness, or sufficiency of any bid document obtained from any other source other than from the City eProcurement Portal:
https://procurement.opengov.com/portal/meridenct. Obtaining documents from any other source(s) may result in obtaining incomplete and inaccurate information. Obtaining documents from any other source may also result in failure to receive any addenda, corrections, or other revisions to the documents that may be issued.
No request shall be honored if such request is made less than seven (7) calendar days prior to the date fixed for the opening of bids. Any and all such interpretations, and any supplementary instructions, will be in the form of a written addenda to the specifications which, if issued, will be made available via the City eProcurement Portal, located at https://procurement.opengov.com/portal/meridenct for addenda. Failure of any bidder to receive any such addenda shall not relieve any bidder from any obligations under its bid as submitted.
Bidders shall submit all inquiries regarding this bid via the City eProcurement Portal, located at https://procurement.opengov.com/portal/meridenct. Please note the deadline for submitting inquiries. All answers to inquiries will be posted on the City eProcurement Portal. Bidders may also click “Follow” on this bid to receive an email notification when answers are posted. It is the responsibility of the bidder to check the website for answers to inquiries.
6. BIDS TO REMAIN OPEN
No bidder may withdraw its bid within ninety (90) days of the date of the bid opening. Should there be reason why the contract cannot be awarded within the specified period, the time may be extended by mutual agreement between the City of Meriden and the successful bidder.
7. CITY OF MERIDEN, LOCAL PREFERENCE
In determining the lowest responsible bidder, the Purchasing Department shall also consider Local Preference.
This section shall not apply in those instances where the bid requested involves a cooperative purchasing arrangement between the City of Meriden and other municipalities or the State of Connecticut.
Bidders are specifically advised that the City of Meriden has adopted Section 3-14 of the Code of the City of Meriden which requires, but is not limited to, a local preference requiring, in part, that a “City-based business” shall mean a business with its principal place of business located within the boundaries of the City of Meriden.
A business shall not be considered a “City-based business” unless evidence has been submitted, satisfactory to the Purchasing Department, with each bid (forms included in bidding documents) to establish that the bidder has a bona fide principal place of business, operates out of, or pays property taxes on personal property in the City of Meriden.
Any City-based business bidder which has submitted a bid not more than ten (10) percent higher than the low bid provided such City-based business bidder agrees to accept the award of the bid at the amount of the low bid.
The acceptance shall be submitted in writing to the Purchasing Department no later than next business day following the opening of the bid. For example, a bid opened at 11:00 a.m. on a Monday must be accepted by the City-based bidder no later than 11:00 a.m. on Tuesday. If more than one City-based business bidder has submitted bids not more than ten (10) percent higher than the low bid and has agreed to accept the award of the bid at the amount of the low bid, the lowest responsible bidder shall be one of the City-based business bidders which has submitted the lowest bid.
Bidders claiming status under the local preference are hereby required to submit with its bid an additional form, titled “Request for Status as a Meriden Based Business.”
8. TIME
Inasmuch as the contract concerns a public improvement, the provisions of the contract relating to the time of performance and completion of the work are of the essence of the contract. Accordingly, the successful bidder/contractor (“Contractor”) shall begin work on the day specified in paragraph 2.04 of the General Conditions and shall perform the work diligently so as to permit full use not later than the first day following the construction period established in the Contract. (See paragraph 10 entitled “Liquidated Damages” of the Construction Contract between City of Meriden, as owner, and the Contractor).
9. TAXES
The City of Meriden is exempt under Connecticut General Statutes from the payment of the excise taxes imposed by the federal government and the Sales and Use Tax of the State of Connecticut; such taxes should not be included in the bid price. Upon request, exemption certificates will be furnished to the successful bidder.
10. FAIR EMPLOYMENT PRACTICES
The Contractor shall agree that neither it or its subcontractors, except in the case of a bona fide occupational qualification or need, to refuse to hire or employ or to bar or to discharge from employment any individual or to discriminate against such individual in compensation or in terms, conditions or privileges of employment because of the individual's race, color, religious creed, age, sex, gender identity or expression, marital status, national origin, ancestry, present or past history of mental disability, intellectual disability, learning disability, physical disability, including, but not limited to, blindness or status as a veteran. The aforementioned terms are obtained from Connecticut General Statutes Section 46a-60, et seq., entitled “Discriminatory employment practices prohibited,” as amended.
11. FORM OF AGREEMENT BETWEEN CITY OF MERIDEN AND CONTRACTOR
The Agreement for the work will be via Purchase Order and Standard Construction Agreement including
EJCDC.
12. LOCAL SUBCONTRACTORS, SUPPLIERS, etc.
Local subcontractors, material suppliers, and labor in the City of Meriden should be considered and sought out insofar as it is practical in the performance of this project.
13. CITY OF MERIDEN CODE OF ETHICS
The City of Meriden has adopted a Code of Ethics located in Chapter 21 of the Code of the City of Meriden, sections 21-1 through 21-15, inclusive, which are expressly incorporated herein by reference. The terms of the Code of Ethics shall constitute a part of any contract or agreement entered into by the City of Meriden as a result of this bid as if those terms were fully set forth in such contract or agreement.
Bidders are specifically advised that the Code of Ethics prohibits public officers and employees, as well as their immediate families and businesses, with which they are associated from participating in any transaction which is incompatible with the proper discharge of official duties or responsibilities. Bidders are also advised that the Code of Ethics contain provisions with respect to paid contractors and former employees and officials.
BIDDERS SHOULD NOTE THAT BIDS, CONTRACTS, AND AGREEMENTS ENTERED INTO OR
AWARDED IN VIOLATION OF THE CODE OF ETHICS ARE VOIDABLE BY RESOLUTION OF
THE CITY COUNCIL OF THE CITY OF MERIDEN.
Copies of the Code of Ethics may be obtained from the office of the City Clerk or may be found online on the City of Meriden’s website.
14. NON-COLLUSION STATEMENT
Each bidder submitting a bid to the City of Meriden for any portion of the work contemplated by the documents on which bidding is based shall execute and attach thereto the sworn Non-Collusive Bid Statement, to the effect that the bidder has not colluded with any other person, firm, or corporation in the submission of the bid.
15. AWARD IN CASE OF A TIE
In the event there are two or more responsive bidders, the decision to award will be based by the following criteria and in the following order:
a. The incumbent will be awarded the bid over that of another bidder.
b. In the case of a multi-item bid, if one bidder has been awarded other items from the same bid and the other bidder has not, the bidder with the multiple awards will be awarded the bid over that of another bidder.
c. The bidder located in the State of Connecticut will be awarded the bid over that of another bidder.
d. The winner of a coin toss will be awarded the bid over that of another bidder.
The above-referenced provisions do not apply to those situations in which more than one City-based business responsible bidder has submitted bids not more than ten (10) percent higher than the lowest bid and has agreed to accept the award of the bid at the amount of the lowest bid. Under such circumstances, the provisions of the Code of the City of Meriden, section 3-14, are controlling, as set forth under Section 8 of this ‘Information to Bidders.’
16. LIQUIDATED DAMAGES
The Contractor recognizes that time is of the essence with this project and the City of Meriden will suffer financial loss if the Work is not completed within the anticipated times specified therefore, the Contractor agrees that as liquidated damages for any delay the Contractor will pay the City of Meriden Five Hundred Dollars ($500.00) for each day that expires after the time specified in for Substantial Completion until the Work is substantially complete.
In addition, after Substantial Completion, if Contractor shall neglect, refuse or fail to complete the remaining Work within the time specified for completion and readiness for final payment or any proper extension thereof granted by the City of Meriden, the Contractor shall pay the City of Meriden Five Hundred Dollars ($500.00) for each day that expires after the time specified for completion and readiness for final payment.
17. AWARD OF CONTRACT
The Purchasing Officer reserves the right to make an award on the bid which, by the Purchasing Officer’s judgment and recommendation from the Director of Facilities following bid evaluations, best meets the specifications and is deemed to be in the best interest of the City of Meriden.
The contract will not be awarded to any corporation, firm, or individual which/who is in arrears to the City of Meriden by debt or contract, or who is in default as security or otherwise by any obligation to the City of Meriden.
The right is reserved to reject any or all bids, in whole or in part, to award any item, group of items, or total bid, and to waive informality or technical defects, if it is deemed to be in the best interest of the City of Meriden.
18. BID PROTEST PROCEDURE
In the event that any bidder wishes to protest the potential award of a bid, or any procedure of act in the advertising or soliciting of the bids, said bidder must make said protest in writing, which shall state the reason therefore and request a conference with respect thereto. Said protest must be received in the City Purchasing Office within FIVE (5) business days after the delivery of bid results or decisions. A conference with respect to said protest shall be scheduled by the Purchasing Officer forthwith and shall be attended by him or his designee and such other persons as the Purchasing Officer and the City Manager shall require to attend. The subject matter of said conference shall be limited to the reasons for the protest specified in the written request for said conference. Said conference shall also include a discussion of all possibilities for a resolution of dispute. The City shall make a decision in writing within three (3) business days after said conference and forward the same to the protesting bidder forthwith. In the event that any protesting bidder wishes to take legal action against the City, they must fully comply with all of these instructions to bidders.
19. ASSIGNMENT OF CONTRACT
No contract may be assigned without the written consent of the Purchasing Officer or designee.
20. PERMITS
The Contractor shall be responsible for obtaining any and all necessary permits required by the City of Meriden prior to the commencement of work. The Contractor may contact the City of Meriden Building Department for permit information at (203) 630-4091. For all other required permits, contact the City of Meriden Engineering Department at (203) 630-4018.
**Please note-This is a City of Meriden property therefore City permit fees will be waived BUT the State Training and Education Fund Fees/Permit will NOT be waived.
21. BID PRICE AND PAYMENT
The City of Meriden is exempt from the payment of the excise taxes imposed by the Federal government and the Sales and Use Tax of the State of Connecticut under Connecticut General Statutes; accordingly, such taxes shall not be included in the bid price.
The City of Meriden, unless stated otherwise in the bidding documents or Contract, will make payment to the Contractor not less than thirty (30) days following completion of services.
22. LICENSES AND CERTIFICATIONS
The successful firm(s) shall ensure that any appropriate licenses or certifications required by the State of Connecticut are maintained for the duration of the project. The firm must meet all municipal, state and federal affirmative action and equal employment opportunity practices.
The Contractor shall have a minimum of 2 years of tank removal experience and shall be certified by the State of Connecticut for tank removal work.
23. QUALITY
All materials, equipment, supplies, and services shall be subject to rigid inspection. If defective material, equipment, supplies, or services are discovered, the Contractor shall remove or make good such material, equipment, or supplies without extra compensation. It is expressly understood and agreed that any inspection by the City of Meriden will in no way lessen the responsibility of the Contractor or release Contractor from the obligation to perform and deliver to the City sound and satisfactory materials, equipment, supplies, or allow the cost to be deducted from any monies due it from the City of Meriden. All services will be performed in a workmanlike manner.
24. INSURANCE
The successful bidder shall be required to provide a Certificate of Insurance denoting general liability, automobile liability, workers compensation liability, and other coverage required by the City’s Risk Manager.
SCOPE OF WORK
PROJECT DETAILS
1. PART 1 - GENERAL
1.1 REFERENCES
A. The publications listed below form a part of this section to the extent referenced. The publications are referenced in the text by basic designation only.
1. AMERICAN PETROLEUM INSTITUTE (API)
2. AMERICAN SOCIETY FOR TESTING AND MATERIALS (ASTM)
3. CODE OF FEDERAL REGULATIONS (CFR)
4. ENVIRONMENTAL PROTECTION AGENCY (EPA)
5. LOCAL ORDINANCE K-2
1.2 MEASUREMENT AND PAYMENT
A. Compensation for removal of contaminated soil shall be paid as a unit cost. This unit cost includes testing, excavation, stockpiling, transportation and disposal of the contaminated soil and backfilling with non-contaminated soil. Payment for all other work shall be under the base bid for the tank removal and shall constitute full payment for all work defined in the contract documents including testing of the contents, excavation and disposal of the tank, and testing of the underlying soil.
1.3 SUBMITTALS
A. The following shall be submitted in accordance with the requirements of Division l of the specifications.
1. Work Plan
a. The Contractor shall develop, implement, maintain, and supervise as part of the work, a comprehensive plan for tank removal and related operations. The Work Plan shall be based on work experience, on the guidance provided in this specification, and on the following references:
API RP 1604.
API RP 2015.
API RP 2003
API Publ 2217.
API Publ 2219.
b. The Work Plan shall be submitted within 30 days after notice to proceed. No work at the site, with the exception of site inspections and mobilization, shall be performed until the Work Plan is approved. The Contractor shall allow 30 days in the schedule for the owner's review and approval.
c. No adjustment for time or money will be made for resubmittals required as a result of noncompliance. At a minimum the Work Plan shall include:
Scheduling and operational sequencing.
Discussion of the approach, tank cleaning, and tank cutting procedures.
A Chemical Data Acquisition Plan which describes sampling procedures and lists analysis parameters, methods, laboratory or laboratories and:
Soil sampling locations and rationale for locations.
Explanation of how the analytical results will be used.
Identification of applicable regulatory requirements and permits.
Methods to be employed for residue, vapor, liquid, and contaminated water removal, purging and storage and methods proposed for control of surface water.
Identification of waste, tank and contaminated soil transporters and means of transportation.
Disposal facilities and alternate disposal facilities and means of disposal or remediation.
Borrow source.
Spill prevention plan.
Spill contingency plan.
Decontamination procedures.
2. Qualifications:
a. A written statement that the Contractor meets the requirements in paragraph
QUALIFICATIONS.
3. Test Reports:
a. Test results for the fill material, underlying soil, contents of the tank and discharged water. The reports shall include the chain-of-custody records.
4. Records:
a. Shipping Manifest: Manifest in accordance with CFR 40 Part 262 Section 23 and State regulations.
b. Closure Record: A report prepared in accordance with paragraph TANK CLOSURE REPORT.
1.4 QUALIFICATIONS
A. The Contractor shall have a minimum of 2 years of tank removal experience and shall be certified by the State of Connecticut for tank removal work.
1.5 REGULATORY REQUIREMENTS
A. Statutes and Regulations
1. Tank closure shall be carried out in accordance with the requirements identified in CFR 40 Part 280 as well as the applicable local and State of Connecticut regulations. Hazardous material shall be transported in accordance with CFR 40 Part 263 to disposal facilities that operate in accordance with CFR 40 Part 264 and CFR 40 Part 265.
B. Notification
1. The Contractor shall notify the Owner's representative 10 days prior to tank removal. The Contractor shall be responsible for contacting the Authorities having jurisdiction in accordance with the applicable reporting requirements.
1.6 PROJECT/SITE CONDITIONS
A. The work consists of removal, decontamination and disposal of underground storage tank, associated piping and ancillary equipment. The tank is constructed of steel and is at the location shown on the drawings. The tank was used for storing fuel oil. Prior to removal and disposal of the tank, the tank shall be emptied of any remaining fuel oil. Existing 4,000 gallon double wall UST system with concrete bottom and top slabs. Residue remaining in the tank is considered a hazardous waste. The Contractor is responsible for verifying all actual site conditions prior to submitting a bid. Contractor is responsible for removing existing UST system and piping and restoring disburbed area.
1.7 CITY PROJECT REQUIREMENTS
A. The Contractor shall schedule a pre-construction meeting with City Engineering staff prior to commencing construction.
B. Layout of improvements shall be staked out in the field and approved by City Engineering staff prior to initiating work.
2. PART 2 - PRODUCTS
2.1 BACKFILL MATERIAL
A. Non-contaminated material removed from the excavation may be used for backfill in accordance with Paragraph BACKFILLING, additional backfill material shall be obtained from off-site. Backfill shall be classified in accordance with ASTM D 2487 as GW, GP, GM, GC, SW, SP, SM, SC, MH, CL, or CH and shall be free from roots and other organic matter, trash, debris, snow, ice or frozen materials. If off-site materials are used, soil classification test results shall be approved prior to bringing the material onsite.
B. All grass areas to be loamed and seeded by the Contractor.
3. PART 3-EXECUTION
3.1 GENERAL
A. Safety Guidelines
1. Personnel working inside and in the general vicinity of the tank shall be trained and thoroughly familiar with the safety precautions, procedures, and equipment required for controlling the potential hazards associated with this work.
2. Personnel shall use proper protection and safety equipment during work in and around the tank as specified in API Publ 2217, API RP l 604, and the contract clauses.
B. Burning and Explosives
1. Use of explosives or burning debris will not be allowed.
3.2 TANK CONTENTS VERIFICATION
A. Sampling
1. Sampling of tank residues and liquids is not required where the contents of the tank is adequately documented. If contents of the tank are unknown or the records indicating the materials stored are unavailable, the Contractor shall provide sampling and analysis to the extent required by the approved off-site permitted treatment, storage or disposal (TSD) facility receiving the material.
B. Analysis
1. Where tank contents testing is required, the Contractor shall have samples tested for the parameters listed herein. Analyses shall be in accordance with EPA SW-846 and include total recoverable petroleum hydrocarbons (TRPH).
C. Characterization
1. Prior to removing any of the tank contents, the contents shall be characterized to determine if the tank contents must be disposed as a hazardous waste based on local, state, and Federal disposal regulations. The liquid shall be characterized in accordance with CFR 40 Part 26 l, Subpart C. The waste contents determination and accompanying test results for each phase present in the tank shall be submitted to the Engineer. The Contractor shall be responsible for any additional requirements identified by the disposal facility. The tank contents shall not be removed until approval is given by the Engineer.
3.3 TOPSOIL
A. Uncontaminated topsoil shall be stripped and stockpiled separately for reuse at a location approved the Owner if it meets the requirements of clean fill given in Paragraph BACKFILLING.
3.4 TANK REMOVAL
A. Before excavating, residue liquids, piping, and ancillary equipment shall be removed from the Lank and the tank shall be purged and vented in accordance with API RP 1604 and as specific I herein.
1. Removal of Tank Liquid, Residue, and Contaminated Water
a. Tank liquids, residues, and contaminated water, shall be contained and stored onsite prior to disposal. Contaminated water hall be treated as specified. Residue, liquids and contaminated water shall be analyzed and segregated to recover reusable products by the contractor prior to being transported to the approved treatment, storage and disposal (TSD facility. Tank liquids residues, and contaminated water shall be removed and disposed of by the Contractor. Th Contractor shall be respo11siblc for obtaining all required permits. Usable product shall be the property of the Owner. The contractor shall provide approved containers, vehicles, equipment, labor, signs, labels and manifests necessary for accomplishment of the work including materials necessary for cleaning up spills that may occur from tank removal operations.
B. Contaminated Water Disposal
1. General
a. Sampling and analysis shall be perfo1med prior to disposal for every 500 gallons of liquid treated. Analyses for contaminated water to be taken to an off-site treatment facility shall conform to the requirements of the treatment facility with documentation of all analysis performed furnished to the Engineer in accordance with Paragraph Records. Liquids shall be contained, stored onsite, and analyzed prior to being transported to the approved treatment, storage and disposal facility and disposed of by the contractor in accordance with applicable federal and state disposal regulations.
b. The on tractor shall provide approved containers, vehicles, equipment, labor, signs, labels and manifest, necessary for accomplishment of the work. Sampling and analyses of contaminated water and treated water and the contractor and laboratory quality assurance program shall be in accordance with EPA SW-846.
2. Treatment
a. Contaminated water shall be treated off-site in accordance with all applicable codes. If the tank contents are to be treated onsite the proposed treatment shall be specified in the Work Plan.
Temporary storage and treatment equipment shall be installed in the general vicinity of the tanks.
Treated effluent shall be sampled and analyzed and the results approved by the Engineer before discharge to the surface. Treated effluent shall be adjusted to have a PH between 6 and 9.
C. Purging
1. Prior to excavation beyond the top of the tank, flammable and toxic vapors shall be purged from the tank in accordance with API RP 1604 with the exceptions that filling with water shall not be used and if dry ice is employed the contractor shall use a minimum of 1.8 kg per 500 L (3 pounds per 100 gallons) of tank volume. The tank atmosphere shall be continuously monitored for combustible vapor.
D. Excavation
1. Excavation
a. Exploratory trenches shall be excavated as necessary to determine the tank location, limits and the location of ancillary equipment.
2. Tank Excavation
a. Excavation around the perimeter of the tank shall be performed in a manner that will limit the amount of potentially contaminated soil that could be mixed with previously uncontaminated soil. Contaminated soil shall be segregated in separate stockpiles.
b. Surface water shall be diverted to prevent direct entry into the excavation. Dewatering of the excavation will be limited to that necessary to assure adequate access to the tank and piping and to assure a safe excavation. Dewatering may result in the production of contaminated water and/or free product. Free product shall be recovered from the groundwater only as part of necessary dewatering.
3. Open Excavations
a. Open excavations and stockpile areas shall be secured while awaiting verification test results from the soil beneath the tank. The excavation shall not be back filled without approval from the Engineer and the code authorities having jurisdiction. The contractor shall divert surface water around excavations to prevent water from directly entering into the excavation.
4. Stockpiles
a. Uncontaminated excavated soil shall be stockpiled and used for backfill in the tank excavation prior to using borrow material. Excavated material which is visibly stained and which has an obvious petroleum odor or as required by the State of Connecticut shall be considered contaminated and shall be stockpiled for sampling in accordance with Paragraph Stockpiled Material Sampling. Uncontaminated soil shall be stockpiled separately at a safe distance from the contaminated soil, but adjacent to, the excavation. Contaminated soil shall be placed on an impermeable geomembrane a minimum of 0.762 mm (30 mil thick, and covered with a. 0.254 mm (IO mil) sheet of geomembrane. The geomembrane shall be placed such that the stockpiled soil does not come into contact with surface water run-off. The 0.254 mm (10mil) geomembrane cover shall prevent rain or surface water from coming into contact with the contaminated soil, as well as limit the escape of the volatile constituents in the stockpile.
E. Removal
1. Tank: The tank shall be removed from the excavation and the exterior cleaned to remove all soil and inspected for signs of corrosion, structural damage, or leakage. All materials coming into contact with the tank, or in the vicinity of the excavation such as shovels, slings and tools shall be of the non-sparking type. After removal from the excavation the tank shall be removed from site.
2. Contaminated Soil: After the tank has been removed from the ground the adjacent and underlying soil shall be examined for any evidence of leakage. The soil shall be visually inspected for staining and also screened for the presence of contamination using a real time vapor monitoring instrument.
Contaminated soil shall be transported off-site for disposal.
F. Tank Cleaning
1. Exterior: Uncontaminated soil shall be removed from the tank exterior to eliminate soil deposition on roadways during transportation to a temporary storage area, ensure markings will adhere to the tank surface, and simplify tank cutting. Soil shall be removed using non-sparking tools. Soil removal shall be compiled on a geomembrane adjacent to the tank removal site approved by the Engineer. Uncontaminated soil removed from the tank exterior shall be recovered and used as backfill in the former tank excavation. Soil believed to be contaminated shall be removed and collected on a 0.762 mm (30 mil) impermeable geomembrane and stockpiled with other contaminated soil removed from the excavation.
2. Interior
a. The tank interior shall be cleaned using a high pressure (greater than 3.45 MPa (500 psi) low volume (less than 0.13 L/s (2 gpm) water spray or steam cleaned until all loose scale and residue is removed, and contamination in the form of a sheen is no longer visible in the effluent stream.
All contaminated water resulting from cleaning operations shall be handled in accordance with Paragraph Contaminated Water Disposal. Cleaning shall be accomplished in a manner that eliminates the need for personnel to enter the tank to the greatest extent possible. Cleaning shall be done using specially designed tank cleaning equipment which allows the tank to be cleaned prior to cutting into sections without requiring personnel to enter the tank or, if less specialized equipment is used, the tank shall be partially dissected to overcome confined space entry hazards by removing the end walls. In either case, the cutting operation shall be accomplished using non-sparking or non-heat producing equipment.
3.5 SOIL EXAMINATION, TESTING, AND ANALYSIS
A. General: After soil excavation is complete, the excavation shall be sampled in accordance with State regulations. Samples may be obtained from the pits using a backhoe with a Shelby tube attached to the bucket. Sample preservation and analytical procedures shall conform to EPA SW-846.
B. Stockpiled Material Sampling: Stockpiled contaminated soil shall be sampled and preserved in accordance with EPA SW-846. Sampling locations, number and specific procedures shall be as required by the State and the disposal facility.
C. Analysis: Soil samples from the excavation and stockpiled material shall be tested in accordance with EPA SW-846 for the following parameters: total recoverable petroleum hydrocarbons (TRPH). Copies of all test results shall be provided to the Engineer. The maximum allowable laboratory detection limits shall be 10 ppm for TRPH. The testing laboratory and Contractor shall adhere to the quality control program, including spikes, blanks, and duplicates, of EP . W-846.
3.6 BACKFILLING
A. The tank area and any other excavations shall be backfilled only after the soil test results have been approved. The excavation shall be dewatered if necessary. Stockpiled material subjected to chemical confirmation testing shall be used as backfill if it is found to conform to the requirements of clean fill per appropriate state and local regulations ppm of total recoverable petroleum hydrocarbons. The excavation shall be backfilled within 48 hours after the bottom of the tank excavation is determined to have soil contamination levels below the state standards or after being directed to do so by the state inspector. Backfill consisting of clean fill shall be placed in layers with a maximum loose thickness of 200 mm, (8 inches), and compacted to 90 percent maximum density for cohesive soils and 95 percent maximum density for cohesion less soils. Density tests shall be performed by an approved commercial testing laboratory or by facilities furnished by the contractor. A minimum of one density test shall be performed on each lift. Laboratory tests for moisture density relations shall be determined in accordance with ASTM D 1557, Method B, C, or D or ASTM D 3017. A mechanical tamper may be provided that the results are correlated with those obtained by the referenced hand tamper. Field in-place density shall be determined in accordance with ASTM D 1556, ASTM D 2922, or ASTM D 2167.
3.7 DISPOSAL REQUIREMENTS
A. General
1. Disposal of hazardous wastes shall be in accordance with all local, State, and Federal solid and hazardous waste laws and regulations, as well as be Resource Conservation and Recovery Act (RCRA), and conditions specified herein. These services shall include all necessary personnel, labor, transportation, packaging, detailed analyses (if required for disposal, manifesting or completing waste profile sheets), equipment, and reports.
2. Liquids remove from the tank. hall be recycled to the greatest degree practicable. All contaminated soil shall be treated as a hazardous waste. The tanks removed shall be disposed of at a state approved facility.
B. Tank and Ancillary Equipment Disposal
1. After the tank, piping, and ancillary equipment have been removed from the excavation and the tank cleaned, the tank shall be cut into sections with no dimension greater than 1500 mm. (5 feet). Tank and piping sections shall be disposed of in a State approved offsite disposal facility. The tank shall be cut into sections prior to being taken from the tank removal site. The Contactor shall not sell the tank intact. Ancillary equipment shall be disposed of at an approved off-site disposal facility. Piping shall be disconnected from the tank and removed unless otherwise indicated.
C. Transportation of Waste: Transportation shall be provided in accordance with Department of Transportation (DOT) Hazardous Material Regulations and State and lo al requirements, including obtaining all necessary permits, licenses, and approvals. Evidence that a State licensed waste transporter is being used shall be included in the SUBMTTTALS.
D. Salvage Rights: The Contractor shall retain the rights to salvage value of wastes, so long as the requirements of CFR 40 Part 266, or the applicable State requirements are met.
E. Records
1. Records shall be maintained of all waste determinations including appropriate results of analyses performed, substances and sample location, the time of collection, and other pertinent data as required by CFR 40 Part 280, Section 74 and CFR 40 Part 262 Subpart D. Transportation, treatment, disposal method and date , the quantities of waste, the names and addresses of each transporter and the disposal or reclamation facility, shall also be recorded and available for inspection, as weII as copies or originals of the following documents:
a. Manifests.
b. Waste analyses or waste profile sheets.
c. Certifications of final treatment/disposal signed by the responsible disposal facility official.
following contract close out, the records shall become the property of the Government.
F. Hazardous/Special Waste Manifests
1. For hazardous waste the Contractor shall utilize the U.S. EPA approved manifest system so that the wastes can be tracked from generation to ultimate disposal. The manifests shall comply with all of the provisions of the transportation and disposal regulations. The contractor shall be responsible for preparing manifests for each load and obtaining the appropriate identification numbers and signatures. Prior to transportation of the hazardous waste, all of the established pre-transport requirements shall be met. The wastes shall be transported by a certified hazardous waste hauler (i.e., the hauler must have a U.S. EPA or appropriate state hazardous waste identification number) in approved containers. All transporters must sign the appropriate portions of the manifest and must comply with all of the provisions established in DOT and RCRA regulation.
G. Documentation of Treatment or Disposal
1. The wastes shall be taken to a treatment, storage, or disposal facility which has EPA or appropriate state permits and hazardous waste identification numbers and complies with all of the provisions of the disposal regulations. Documentation of acceptance of special waste by a facility legally permitted to treat or dispose of those materials shall be furnished to the Engineer not later than 5 working days following the delivery of those materials to the facility and a copy included in the Tank Closure Report. A statement of agreement from the proposed treatment, storage or disposal facility and certified transporter to accept hazardous wastes shall be furnished in the Work Plan. If the Contractor selects a different facility than is identified in the Work Plan, documentation shall be provided or approval to certify that the facility is authorized and meets the standards specified in CFR 40 Part 264.
3.8 SPILLS
A. Spill Responsibility: Immediate containment actions shall be taken as necessary to minimize effect of any spill or leak. Cleanup shall be in accordance with applicable Federal, State, and local laws and regulations at no additional cost to the Government.
B. Contractor Reporting Requirements
1. If a spill occurs the Contractor shall immediately notify the Owner and the Engineer. Off the site, the Contractor shall report spills related to project activities to the National Response Center (NRC), the Owner, and the Engineer immediately following-discovery and shall also comply with applicable State requirements. A written follow-up shall be submitted to the Engineer not later than 7 days after the initial report. The written report shall be in na1rntive form and as a minimum include the following:
a. Description of the material spilled (including identity, quantity, and manifest number).
b. Whether amount spilled is EPA/State reportable and when and to whom, it was reported.
c. Exact time and location of spill, including description of the area involved.
d. Receiving stream or waters.
e. Cause of incide1it and equipment and personnel involved.
f. Injuries or properly damage.
g. Duration of discharge.
h. Containment procedures initiated
i. Summary of any· communications Contractor has with press, agencies, or Government officials other than COR.
j. Description of cleanup procedures employed or to be employed at the site, including disposal location of spill residue.
3.9 TANK CLOSURE REPORT
A. For each UST site opened, a Tank Closure Report shall be prepared in a standard three ring binder and submitted within 14 days of completing work at each site. Tank Closure Reports shall include the following information as a minimum:
1. A cover letter signed by a Professional Engineer registered in the State of Connecticut certifying that all services involved have been performed in accordance with the terms and conditions of this specification.
2. A narrative report describing what was encountered at each site, including:
a. The condition of the UST.
b. Any visible evidence of leaks or stained soils.
c. Results of vapor monitoring readings.
d. Actions taken including quantities of materials treated or removed.
e. Reasons for selecting sample locations.
f. Sample locations.
g. Collection data such as time of collection and method of preservation
h. Reasons for backfilling site.
i. Whether or not groundwater was encountered.
j. Copies of all analyses performed for disposal.
k. Copies of all waste analyses or waste profile sheets.
l. Copies of all certifications of final disposal signed by the responsible disposal facility official.
m. Information on who sampled, analyzed, transported, and accepted all wastes encountered and copies of manifests.
n. Copies of all analysis performed for verification that underlying soil is not contaminated, with copies of chain-of-custody for each sample. All analysis shall give the identification number of the sample used. Sample identification numbers shall correspond to those provided in the one-line drawings.
o. Scaled one-line drawings showing tank locations, limits of excavation, limits of contamination, underground utilities within 15 m, (50 feet), sample locations, and sample identification numbers.
PRICING PROPOSAL
ENGINE CO #2 TANK REMOVAL
Complete Removal & Disposal of Existing Tank and Backfilling & Restoring of Disturbed Area
Line Item Description Total Scope Fee Lump Sum
1 Total Scope of Work 1
VENDOR SUBMISSION FORMS
1. NON-COLLUSIVE STATEMENT/AFFIDAVIT*
Please download the document below, complete and upload. **MUST be Notarized & Sealed/Stamped**
• Non-Collusive_Bid_Statement...
*Response required
2. REQUEST FOR STATUS AS A MERIDEN BASED BUSINESS*
Please download the below documents, complete, and upload. If this is NOT APPLICABLE Please Upload a Blank Form w/NA written on it.
• Meriden_Based_Business.pdf
*Response required
3. BIDDER'S QUALIFICATION STATEMENT*
Please download the document below, complete and upload.
• Bidders_Qualification.pdf
*Response required
4. BID BOND
Please download the document below, complete and upload.
• Bid_Bond.pdf
5. FORM OF SURETY GUARANTY*
Please download the below documents, complete and upload.
• Surety.pdf
*Response required https://government-project.s3.us-west-2.amazonaws.com/185261/27e40bae-fea8-4589-88ec-673f947be0c3_Non-Collusive_Bid_Statement.pdf https://government-project.s3.us-west-2.amazonaws.com/185261/24a098a6-fcdd-48aa-b383-e31d61c7689b_Meriden_Based_Business.pdf https://government-project.s3.us-west-2.amazonaws.com/185261/0b547ce7-2bce-4130-af34-e66f19a25d3d_Bidders_Qualification.pdf https://government-project.s3.us-west-2.amazonaws.com/185261/5a51b0db-6545-4b9b-b798-bcdf7e278e7d_Bid_Bond.pdf https://government-project.s3.us-west-2.amazonaws.com/185261/b98ed397-2abd-4ad5-ac4f-76d986d778c2_Surety.pdf
| LEGAL NOTICE |
| INFORMATION TO BIDDERS |
| 1. SUMMARY |
| 2. TIMELINE |
| 3. BIDDING PROCEDURES |
| 4. BIDS |
| 5. EXAMINATION OF BIDDING DOCUMENTS |
| 6. BIDS TO REMAIN OPEN |
| 7. CITY OF MERIDEN, LOCAL PREFERENCE |
| 8. TIME |
| 9. TAXES |
| 10. FAIR EMPLOYMENT PRACTICES |
| 11. FORM OF AGREEMENT BETWEEN CITY OF MERIDEN AND CONTRACTOR |
| 12. LOCAL SUBCONTRACTORS, SUPPLIERS, etc. |
| 13. CITY OF MERIDEN CODE OF ETHICS |
| 14. NON-COLLUSION STATEMENT |
| 15. AWARD IN CASE OF A TIE |
| 16. LIQUIDATED DAMAGES |
| 17. AWARD OF CONTRACT |
| 18. BID PROTEST PROCEDURE |
| 19. ASSIGNMENT OF CONTRACT |
| 20. PERMITS |
| 21. BID PRICE AND PAYMENT |
| 22. LICENSES AND CERTIFICATIONS |
| 23. QUALITY |
| 24. INSURANCE |
| SCOPE OF WORK |
| 1. PART 1 - GENERAL |
| 2. PART 2 - PRODUCTS |
| 3. PART 3-EXECUTION |
| PRICING PROPOSAL |
| VENDOR SUBMISSION FORMS |
| 1. NON-COLLUSIVE STATEMENT/AFFIDAVIT* |
| 2. REQUEST FOR STATUS AS A MERIDEN BASED BUSINESS* |
| 3. BIDDER'S QUALIFICATION STATEMENT* |
| 4. BID BOND |
| 5. FORM OF SURETY GUARANTY* |
File details come from the government source that posted it. Updated .