B01 Section J Attachment 7 Seed Project Statement of Work.docx
DOCX document 16 KB Posted
- Attached to
- Albuquerque SFC MATOC Federal contract opportunity
- Solicitation number
- 75H70120R00011
About this file
This statement of work and related federal contract opportunity outline requirements for a sewer main extension project on tribal lands and an indefinite delivery, indefinite quantity multiple award task order contract vehicle. The statement of work details tasks for constructing approximately 14,822 linear feet of 8-inch gravity sewer main, 49 manholes, connections to existing infrastructure, equipment purchases, and training for tribal utility staff. A 120-day period of performance and preliminary construction schedule are specified. The federal contract opportunity is for sanitation facilities construction services across New Mexico and allows for issuing task orders under blanket contracts with 3 to 5 awardees. The Department of Health and Human Services Indian Health Service will issue task orders as work is required over a base period and up to four option years.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| B05 Amendment 2 Final.pdf | ||
| B05 Amendment 1 Final.pdf | ||
| B01 Section J Attachment 5 - Contractor Surety Information.docx | DOCX document | |
| B01 Section J Attachment 3 - Self Performance Calculation Sheet.docx | DOCX document | |
| B01 Section J Attachment 8 Seed Project Specs.pdf | ||
| B01 Section J Attachment 9 Seed Project Supplemenetal Specs.docx | DOCX document | |
| B01 Section J Attachment 4 - Financial Institution Reference Sheet.pdf | ||
| B01 RFP ABQ SFC MATOC.pdf | ||
| B01 Section J Attachment 6 - PPQ.docx | DOCX document | |
| B01 Section J Attachment 10 Seed Project Drawings.pdf | ||
| B01 Section J Attachment 1 Seed Project Bid Schedule.xls | XLS spreadsheet | |
| B01 Section J Attachment 2 - Application for Payment Form.xls | XLS spreadsheet | |
| B01 Section J Attachment 11 Seed Project WD.pdf |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION C: STATEMENT OF WORK
IHS PROJECT AL-19-B37
GOAT SUMMIT SEWER MAIN EXTENSION
MESCALERO APACHE TRIBE, NEW MEXICO
GR 1.01 GENERAL REQUIREMENTS
1. Introduction/Background:
The work to be performed under these provisions shall include the furnishing of all labor, tools, equipment, materials, work facilities, supervisory efforts, testing, and all necessary incidentals for the following:
AL-19-B37 Goat Summit Sewer Main Extension: Construction of new gravity sewer main, connections to existing sewer main, new manholes, new discharge manhole, rock excavation, new sewer service line connections, abandonment of existing septic systems, new road bore and jack with steel encasement, and purchase of new sewer system O&M equipment. Refer to the attached Technical Provisions, Supplemental Technical Provisions, Construction Drawings, List of Quantities (proposal/bid schedule) for detailed requirements of the contract.
2. Project Description:
The work located in Mescalero, New Mexico. The work required for the Goat Summit Sewer Main Extension includes, but is not limited to, the following:
a. Mobilize to site
b. Construct approximately 14,822 linear feet of 8-inch PVC gravity sewer main, approximately 49 manholes, and one sewer main terminal cleanout
c. Install on road bore with steel encasement.
d. Connection to existing sewer mains, sewer manholes, and sewer force mains.
e. Removal of approximately 500 cubic yards of rock for the successful installation of the new sewer main.
f. Purchase and furnishing of a new trailer mounted sewer jetter, sewer inspection camera, and accessories for the Mescalero Utility Operations staff.
g. Conduct training and startup with the Utility Operations staff.
h. Submit all required testing, documentation, O&M manuals, certifications, and as-built drawings.
i. Demobilize and clean-up site
3. Tasks/Deliverables/Services to be Provided:
Contractor shall be responsible for construction of approximately 14,822 linear feet of 8-inch PVC gravity sewer main and associated appurtenances, pressure testing, exfiltration testing, approximately 49 manholes; purchase, delivery, and training of sewer system O&M equipment (sewer jetter, camera, and line locater) in accordance with the IHS/SFC Technical Provisions and Supplemental Technical Provisions, and all necessary incidentals required as shown in the construction drawings, Technical Provisions, and Supplemental Technical Provisions.
4. Period of Performance: 120 days from the Notice to Proceed
5. Schedule: Contractor shall submit a proposed construction schedule 10 days prior to the NTP date for review and approval by the COR. Construction schedule shall include all major work items as outlined in the scope of work.
6. Any Attachment to Scope if Applicable: Construction Drawings, dated 7/30/2020 (17 sheets total), Supplemental Technical Provisions (4 sheets total), IHS/AAO/SFC Standard Technical Provisions (301 pages).
7. Point of Contact
1. Bradley Sherer, P.E., COR-II Indian Health Service OEHE/SFC 801 Vassar Drive NE Albuquerque, NM 87106 505-248-7624 office 505-660-1050 mobile Bradley.sherer@ihs.gov
2. Alternate: Mike Buck Elk, COR-II Indian Health Service OEHE/SFC 801 Vassar Drive NE
| Albuquerque, NM 87106 |
| 505-248-7649 office |
| 505-379-5780 mobile |
| Mike.buckelk@ihs.gov |
File details come from the government source that posted it. Updated .