B01 Attachment 1 SOW HHCC Quarters Polacca.pdf
PDF 138 KB Posted
- Attached to
- HHCC Qtrs Construction - Amendment 5 Federal contract opportunity
- Solicitation number
- 75H70123R00040
About this file
This scope of work document outlines requirements for the construction of new staff quarters residential housing units at the Hopi Health Care Center in Polacca, Arizona. The contractor will be responsible for providing all equipment, materials, labor and other expenses to complete the project in accordance with the attached construction documents. Key deliverables include constructing the quarters according to the attached plans and specifications, and providing as-built drawings and AutoCAD files. The contractor must also adhere to industry codes and safety standards, obtain necessary licenses and permits, and submit required documents such as schedules, safety plans, and certified payrolls. The performance period is 248 days from notice to proceed. The solicitation was issued by the Department of Health and Human Services Indian Health Service for project HHCC Qtrs Construction.
View the file
Other files for this federal contract opportunity
Show all 17
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SCOPE OF WORK: HHCC QUARTERS CONSTRUCTION, PROJECT PH19KC01Q3
I. DESCRIPTION
A. Construct new Staff Quarters Residential Housing Units at the Hopi Health Care Center located at Highway 264 Mile Post 388, Polacca, Arizona, 86042 in accordance with the attached construction documents.
B. The Contractor shall be responsible for all equipment, parts, material, labor, travel, per diem, Tribal Employment Rights Office (TERO) fees and other expenses required to complete the project as described in this scope of work.
II. SUMMARY OF REQUIREMENTS AND OBJECTIVES
A. Refer to Attachment A for project drawings. Refer to Attachment B for project specifications. Additional requirements and objectives for the project are presented in this scope of work.
III. DELIVERABLES: CONSTRUCTION
A. Construct the Quarters in accordance with the attached plans and specifications.
B. Provide comprehensive As‐Builts/Project Record Drawings/AutoCAD Drawings
1. One hard copy set of full size sheets (24” x 36”) with updates and modifications clearly noted in legible handwritten drafting quality text.
2. Project Record Drawings: Maintain one complete full‐size set of contract drawings.
Clearly mark changes, deletions, and additions to show actual constructed conditions. Keep record drawings current. Certification of accuracy and completeness will be required for monthly payment request. On completion of the total project, submit complete record drawings including AutoCAD drawings.
IV. GENERAL CONDITIONS
A. Proof of qualifications. Provide qualification packet which shall include business capability, list of similar projects completed, licenses held, list of representative agreements, certification held and a list of qualified technicians who will perform the work.
B. Codes and Standards. The Contractor shall adhere to the following code requirements for work performed, including testing and inspection:
1. International Residential Code (latest edition)
2. Occupational Safety and Health Act – CFR1926
C. Project Safety
1. All work will comply with Occupational Safety and Health Act – CFR1926.
2. Contractor shall supply all required worksite safety equipment.
3. Contractors will be required to submit and adhere to the following items including but not limited to:
a) SDS construction binder for all products used onsite.
b) Project specific site safety plan.
4. Contractor shall be responsible for complete and strict compliance with all Hopi Health Care Center Facility policies including the safety policy.
D. Submittals: Furnish submittals for all building materials. Provide in scanned PDF format for formal approval.
1. SDS Sheets for all products.
E. Quality Assurance/Quality Control.
1. All materials shall be approved by owner.
2. All materials shall be installed per manufacturer’s instructions and all applicable codes, and good work practices.
3. Housekeeping will be accomplished on a daily basis. All debris and trash generated by this project will be disposed of in a trash dumpster provided by the owner for this project at no extra cost to the contractor/installer.
4. Qualifications: All electrical, plumbing, HVAC, cabinet and trim work shall be performed by an appropriately licensed contractor specializing in the specific trade required.
F. Execution
1. Construction activities shall be coordinated with Hospital Facility Management Staff to ensure that there are no detrimental impacts on the day to day operations of the Hospital or staff safety.
G. Inspection
1. The Government reserves the right to inspect all aspects of work performed, including hiring a third party inspector to verify proper installation and operation.
2. Contractor is required to demonstrate full and complete operation of all work performed.
3. Final acceptance will be based on an acceptable final inspection, including final verification testing of all material and workmanship.
H. Project Schedule
1. The contactor shall provide a detailed schedule indicating the date that each phase of construction will be completed.
2. Facility day time hours of operation are 8:00 AM – 5:00 PM, Monday through Friday (excluding Federal holidays). Work outside of these hours must be submitted in writing to the Facility Manager for approval not less than 48 hours in advance of the proposed modified schedule.
3. Schedule shall be in Microsoft Project format or approved equal.
I. Performance Period: The Government shall allow 248 days from the date of NTP.
J. TERO, Insurance and Bonding Requirements.
1. Contractors are required to contact the Hopi Tribe’s Tribal Employment Rights Ordinance (TERO) Office upon receipt of notification of award. Compliance with the tribal employment ordinance is required prior to starting work on any project performed on Tribal Land including payment of associated TERO fees/permits.
2. Obtain a business license from the TERO Office. The general contractor and each subcontractor are required to obtain the business license on each project. Submit required paperwork and pay business license fees.
3. Phone: (928) 734‐3162/3163.
K. Certified Payroll shall be submitted to the Contract Officer through the Project Manager.
Subcontractors are required to ensure that all non‐exempt employees for this work are compensated in accordance with the approved Davis Bacon Wage Act and proper certified payroll reports are completed and submitted.
L. Final Payment.
1. Final Payment will not be authorized until all work is complete (including punch list), the final inspection has been made and Warranty Documents have been received.
M. Warranty
1. Contractor shall warrant all work for one year from date of acceptance.
END OF SECTION
File details come from the government source that posted it. Updated .