This pre-solicitation notice provides advance information about an upcoming request for proposal to rehabilitate the Madison Junction Water Treatment and Spring Collection System in Yellowstone National Park, Wyoming. The project scope involves constructing a new water collection system infrastructure including collection boxes, a pump house, and installing approximately 700 and 400 lineal feet of 6-inch and 4-inch diameter water collection pipe. It will also include a telemetry-based SCADA control system and demolition of existing infrastructure. Offerors must have experience with wetland permits, dewatering systems, spring collection infrastructure for potable water, installing HDPE pipe using trenching and trenchless methods, installing water treatment equipment, and constructing comparable buildings. The anticipated single award, firm-fixed price contract will be solicited in November 2022 via request for proposal #140P1422R0006, with a period of performance from July 2023 to July 2024.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PRE-SOLICITATION NOTICE
YELLOWSTONE NATIONAL PARK
REHABILITATE THE MADISON JUNCTION WATER TREATMENT
AND SPRING COLLECTION SYSTEM
#140P1422R0006
This Presolicitation Notice is issued solely for informational, market research, and planning purposes only. It does not constitute an Invitation for Bid (IFB) or a Request for Proposal (RFP) or a promise to issue an IFB or RFP in the future. This Presolicitation Notice does not commit the Government to contract for any construction services whatsoever. Further, the Northern Rockies Major Acquisition Contracting Office is not at this time seeking proposals and will not accept unsolicited proposals. Respondents are advised that the United States (U.S) Government will not pay for any information or administrative cost incurred in response to this Presolicitation Notice. All costs associated with responding to this Presolicitation Notice will be solely at the responding party's expense. Responses to the Presolicitation Notice will not be returned. Please be advised that all submissions become Government property and will not be returned. Not responding to this Presolicitation Notice does not preclude participation in any future RFP, if any is issued. Responses to this notice are not offers and cannot be accepted by the U.S Government to form a binding contract. It is the responsibility of the interested parties to continue to monitor the posting site at www.sam.gov for future solicitation postings.
PROJECT DESCRIPTION: Rehabilitate the Madison Junction Water Treatment and Spring Collection System at Yellowstone National Park, Wyoming 82190.
The location of the project is Madison Junction, Yellowstone National Park (YELL), Teton County, WY, U.S.A.
Work will include the following:
Construction of a new water collection system infrastructure including collection boxes, a Pump House building with mechanical components and chemical treatment, installation of approximately 700 and 400 lineal feet of 6-inch and 4-inch diameter water collection pipe and telemetry-based SCADA control system. The Work includes demolition of existing water system infrastructure including six (6) collection boxes, the Pump House, and existing utility vaults.
The complete Project Specifications will be included with the Solicitation. All questions will be answered in writing via amendments to the Solicitation. NO PHONE CALLS PLEASE.
MINIMUM QUALIFICATIONS:
Contractors shall have prior experience with the following:
Working in wetland areas on projects involving wetland permits from the U.S. Environmental Protection Agency (EPA), as well as state regulatory agencies. Contractor shall have experience with setting up dewatering systems involving pretreatment prior to discharge, including using filtration and settling basins.
Installing spring collection infrastructure for potable water systems.
Installing HDPE pipe using both trenching and trenchless methods.
Installing water treatment equipment, specifically cartridge filtration and disinfection systems.
Constructing buildings of comparable size to or larger than the building planned for this project (approximately 16’ x 30’).
Again, this is not an Invitation for Bid (IFB) or Request for Proposal (RFP) and does not constitute any commitment by the Government to issue any solicitation. All interested firms shall respond to future solicitation announcements separately from responses to this Market Research. This solicitation is anticipated to be issued as a Request for Proposal (RFP) resulting in the award of a Single Award, Firm-Fixed Price Contract.
The RFP is anticipated to be issued approximately in late November, on https://sam.gov/ under Solicitation #140P1422R0006.
The approximate Period of Performance: July 15, 2022, through July 14, 2023.