About this file

This document provides a justification for a single source award in accordance with FAR 13.106-1. The United States Marshals Service required fencing inclusive of installation, maintenance labor, material and equipment for perimeter protection of the Mark O. Hatfield Courthouse in Portland, Oregon. The estimated amount for the contract is $271,150. Due to the unusual and compelling urgency to reinstall perimeter fencing immediately following its removal on March 12, 2021, when the property and local businesses were repeatedly targeted and damaged, the justification cites only the original contractor can fulfill the urgent requirement by the needed delivery date. Market research was not conducted as the Marshals Service relied on previous research performed by the Federal Protective Service identifying this contractor as the only source able to provide the fencing on the required schedule. The justification was approved on April 19, 2021 and the contract was awarded on April 22, 2021 for an unknown amount to an unknown vendor to fulfill the urgent need.

View the file

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Page 1 of 1 Rev. 01/19

U.S. Department of Justice United States Marshals Service Justification for Single Source Awards IAW FAR 13.106-1

NOTE: All awards up to the Simplified Acquisition Threshold (SAT) of $250,000

IAW FAR13.104,

is the most advantageous to the Government, considering the administrative cost of the purchase. When competition is not practicable, IAW source if the CO determines that the circumstances of the contract action deem only one source reasonably available (e.g., urgency, exclusive licensing agreements, brand-name or industrial mobilization). IAW explaining the absence of competition (see the simplified acquisition threshold (does not apply to an acquisition of utility services available from only one source) or supporting the award to obtain supplies and services from the source whose offer

FAR13.106-1(b), FAR13.106-3(b)(3), 13.106-1 single source awards IAW FAR13.106-3(b)(3), meet the required delivery date" are inadequate to support a sole source purchase.

decision if other than price-related factors were considered in selecting the supplier. This template when completed can be used to document

COs must promote competition to the maximum extent practicable

COs solicit from a single source of purchases not exceeding the simplified acquisition threshold. COs may solicit from one

COs are required to include additional statements for brand name purchases) if only one source is solicited and the acquisition does not exceed

Note: Statements such as "only known source" or "only source which can

1b. Estimated Amount:

$271,150.00

2. Brief description of supplies or services required and the intended use:

Fencing inclusive of installation and maintenance labor, material and equipment for perimeter protection of the Mark O. Hatfield Courthouse in Portland OR.

1. MIQ Request Number:

M-21-A32-R-000935

1a. Purchase Order Number:

15M20021PA32OS004

2a. Select applicable category of category of services or other:

Other (provide brief description of supplies or services)

Commercial Supply - Fencing inclusive of installation and maintenance labor, material and equipment

3. Unique characteristics that limit availability to only one source, with reasons to support why no other supplies or services can be used:

Urgency

See National Civil Unrest Summary for 12 March - immediate re installation of fencing required for perimeter protection

4. Reason that suggested source is the only source which can provide the supplies or services:

The fencing was erected around the Mark O. Hatfield Courthouse for the past 8 mo. by DHS FPS. Fencing removed March 12, upon removal persons repeatedly targeted and damaged both federal property and local businesses.

5. Description of market research conducted and results or statement why it was not conducted:

The USMS relied upon the market research previously conducted by the Federal Protective Service (FPS) and determined due to the unusual and compelling urgency to re-install the perimeter fencing from the same contractor for a limited period of performance

CONTRACTING OFFICER'S CERTIFICATION: Purchase is approved in accordance with FAR 13.106-1(b). I certify that the foregoing justification is accurate and complete to the best of my knowledge and belief.

Name:

, Contracting Officer

Signature: Date:

4/19/2021

SUPERVISORY CONTRACT SPECIALIST CONCURRENCE:

Name:

, Contracting Officer

Date:

MIQ Request Number: M-21-A32-R-000935