B.080 Solicitation W912ER26RA001 - MADF Renovations.pdf
PDF 956 KB Posted
- Solicitation number
- W912ER26RA001
About this file
This is a Request for Proposals (RFP) for the Missile Assembly-Disassembly Facilities (MADF) Renovation project at Camp Subhan, Kuwait, issued by the US Army Corps of Engineers Middle East District. The project is a two-phase design-build construction contract with a total contract value between $10-25 million and an overall performance period of 409 calendar days. The renovation encompasses comprehensive upgrades to an existing missile facility, including modernizing missile assembly/disassembly areas, constructing new offices and storage spaces, and implementing significant infrastructure improvements.
Key renovation elements include a complete overhaul of electrical, communication, mechanical, and fire protection systems to meet National Fire Protection Association (NFPA) and Kuwait Fire Forces standards. The project also involves installing new HVAC, compressed air lines, a paint booth, and two overhead cranes. Exterior enhancements will address irrigation, drainage, sidewalk and brick facade repairs, slope stabilization, and exterior lighting replacement. The contract will be awarded using a two-phase design-build source selection process, with up to five most highly qualified firms selected for Phase II after an initial evaluation of proposals. The solicitation was posted on SAM.gov with proposals due by 8:00 AM Eastern Time on 20 October 2025.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Request for Proposals
Specifications for
MISSILE ASSEMBLY-
DISASSEMBLY FACILITIES
(MADF) RENOVATION, Kuwait
Volume 1 of 3 Contract Clauses and Solicitation
Instructions
US Army Corps of Engineers Middle East District
W912ER26RA001
(See ).
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair) IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR
INFORMATION CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".
SOLICITATION
1. SOLICITATION NUMBER
5. REQUISITION/PURCHASE REQUEST NUMBER
CODE
6. PROJECT NUMBER
8. ADDRESS OFFER TO
4. CONTRACT NUMBER
7. ISSUED BY
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)
11. The contractor shall begin performance within
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES", indicate within how many calendar days after award in Item 12b.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and
b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d. Offers providing less than
STANDARD FORM 1442 (REV. 12/2022)
Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
is, is not required.
local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.
calendar days and complete it within calendar days after receiving
a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
12b. CALENDAR DAYS
2. TYPE OF SOLICITATION
SEALED BID (IFB)
INVITATION FOR BID
NEGOTIATED (RFP)
REQUEST FOR PROPOSAL
3. DATE ISSUED PAGE OF PAGES
Created On:
19 Sep 2025, 15:39 PM Central Daylight Time
AWARD (To be completed by Government)
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
OFFER (Must be fully completed by offeror)
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT
NUMBER
DATE
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)
CODE FACILITY CODE
15. TELEPHONE NUMBER (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14.)
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)
21. ITEMS ACCEPTED:
22. AMOUNT
26. ADMINISTERED BY
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)
31c. DATE
STANDARD FORM 1442 (REV. 12/2022) BACK
31b. UNITED STATES OF AMERICA
BY
31a. NAME OF CONTRACTING OFFICER (Type or print)
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30b. SIGNATURE 30c. DATE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office.) Contractor agrees to furnish
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
23. ACCOUNTING AND APPROPRIATION DATA
ITEM
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES
CODE AT
27. PAYMENT WILL BE MADE BY
10 U.S.C. 3204(a) ( ) 41 U.S.C. 3304(a) ( )
20b. SIGNATURE 20c. OFFER DATE
Section 00 00 00 - Procurement and Contracting Requirements
Missile Assembly Disassembly Facility (MADF)
Section 00 10 00 - Solicitation, Contract Line Item Number (CLIN) Schedule
Additional Information/Notes
Item Supplies/Service Quantity Unit Unit Price Amount
Mobilization and Demobilization in accordance with the contract documents
Pricing Arrangement: Firm Fixed Price
1 Job
Geotechnical Investigation and Report in accordance with the contract documents
Pricing Arrangement: Firm Fixed Price
1 Job
Design in accordance with the contract documents
Pricing Arrangement: Firm Fixed Price
1 Job
Demolition in accordance with the contract documents
Pricing Arrangement: Firm Fixed Price
1 Job
Construct Fire Protection in accordance with the contract documents
Pricing Arrangement: Firm Fixed Price
1 Job
HVAC System Replacement in accordance with the contract documents
Pricing Arrangement: Firm Fixed Price
1 Job
Electrical System Upgrade in accordance with the contract documents
Pricing Arrangement: Firm Fixed Price
1 Job
Remove and Re-install Paint booth in accordance with the contract documents
Pricing Arrangement: Firm Fixed Price
1 Job
Repair Settled Slab and Fully Renovate Entire Building in accordance with the contract documents
Pricing Arrangement: Firm Fixed Price
1 Job
Construct Exterior Enclosure and Complete Interior Finish of the MADF Canopy in accordance with the contract documents
Pricing Arrangement: Firm Fixed Price
1 Job
Construct Site Civil / Exterior Improvements and Drainage in accordance with the contract documents
Pricing Arrangement: Firm Fixed Price
1 Job
Compressed Air System Expansion in accordance with the contract documents
Pricing Arrangement: Firm Fixed Price
1 Job
Security System Upgrade in accordance with the contract documents
Pricing Arrangement: Firm Fixed Price
1 Job
Section 00 21 00 - Instructions
APPENDIX A
1. GENERAL INFORMATION.
This solicitation pertains to a Full and Open Firm Fixed-Price Contract for design-build construction services in support of the U.S. Army Corps of Engineers (USACE) Middle East District W912ER26A001 Missile Assembly / Disassembly Facility (MADF) Renovation project.
This solicitation will utilize Two-Phase Design-Build source selection procedures in accordance with Federal Acquisition Regulation (FAR) Subpart 36.6. This Request for Proposal (RFP) is for Phase I. Only proposals for Phase I will be accepted in response to this RFP. Phase II proposals will be requested by an amendment to this RFP from a maximum of the (5) most highly qualified offerors selected from Phase I. Instructions for Phase I proposal submissions are in SECTION 00 21 16 INSTRUCTIONS TO PROPOSERS.
1.1. GENERAL DESCRIPTION OF WORK
The U.S. Army Corps of Engineers (USACE), Middle East District, is executing a Foreign Military Sales (FMS) case KU-B-UMG to renovate the Missile Assembly/Disassembly Facility at Camp Subhan, Kuwait, in support of the Kuwaiti Patriot missile program. The renovation encompasses comprehensive upgrades to the existing facility, including modernization of missile assembly/disassembly and canning/decanning areas, as well as the construction of new offices, restrooms, and storage areas.
Significant infrastructure improvements are included, with a complete overhaul of electrical, communication, mechanical, and fire protection systems to meet current National Fire Protection Association (NFPA) and Kuwait Fire Forces (KFF) standards. This also includes the installation of new HVAC, compressed air lines, and a paint booth. Exterior enhancements will address irrigation refurbishment, drainage improvements with a new French drain, sidewalk and brick facade repairs, slope stabilization, and replacement of exterior lighting.
Finally, the project includes enclosure of the existing canopy with a pre-engineered building (PEB)-approved design and installation of two overhead cranes.
The project will be constructed with applicable current building and safety codes, security standards, including Kuwait and U.S. codes and standards.
The contractor provide all management, administration, quality control, labor, transportation, equipment, shall materials, vehicles, heavy equipment, supplies and other items as necessary to perform the services contained in the scope of work.
The overall Period of Performance (PoP) be four hundred and nine (409) calendar days. shall
1.2. MAGNITUDE OF CONSTRUCTION
The construction magnitude is between $10,000,000 and $25,000,000.
1.3. COPIES OF SOLICITATION DOCUMENTS AND AMENDMENTS
The RFP will be posted on https://sam.gov/. The posted RFP will include Standard Form 1442 Solicitation Offer and Award, specifications and drawings, submittal requirements, and the evaluation factors. The Phase I RFP will be posted on sam.gov at https://sam.gov. However, only up to a maximum of five (5) most highly qualified firms as evaluated in Phase I will receive the Phase II RFP and be requested to provide a Phase II proposal. The Government will send the Phase II RFP via amendment to only those offerors selected to participate in Phase II. Any subsequent amendments will also be posted; however, proposals will only be accepted from those firms invited to participate in Phase II. The file exchange will be password protected, and the RFP can be downloaded only once. The directions for submitting proposals for Phase I are in 1.9 below.
1.4. ACCURACY OF PROPOSALS
Offerors verify that the information submitted is current, correct, and complete, including names of points shall of contact, email addresses, and telephone numbers. Proposals have full, accurate, and complete must information as required by this RFP, including all appendices and attachments. The penalty for making false statements is prescribed in 18 U.S.C. 1001.
1.5. SMALL BUSINESS SIZE STANDARD / NAICS CODE
See Section 00 45 00, FAR 52.204-8 for the small business size standard/NAICS Code.
1.6. SYSTEM FOR AWARD MANAGEMENT (SAM)
Offerors comply with System for Award Management (SAM) registration requirements in FAR Clause must 52.204-7 and be determined responsible prior to award. For more information, see the SAM website at https://sam.gov/. Please ensure that NAICS code Commercial and Institutional Building Construction 236220 -is listed in your SAM registration. Those offerors registering for SAM for purposes of this acquisition are cautioned to be cognizant of the corporate name used for SAM registration purposes.
1.7. PROPOSAL EXPENSES AND PRE-CONTRACT COSTS
The Government will not reimburse any costs incurred or associated with preparation and submission of any responses to this solicitation.
1.8. PROPOSAL REQUIREMENTS
1.8.1. Offerors not modify the terms and conditions of the solicitation in either the non-price (technical) or shall price proposal or add conditions or qualifications to their offers. Should an offeror include terms and conditions that conflict with the terms and conditions of the solicitation, that offeror may be determined ineligible for award. The offeror should resolve any questions related to specific terms and conditions contained within the solicitation prior to submission of their offer. Any oral explanations or instructions to offerors, if made, are not binding. Any information given to an offeror which impacts the solicitation and/or offer will be given in the form of a written amendment to the solicitation.
1.8.2. References to "confidential" projects cannot be submitted to demonstrate capability unless all the information required for evaluation as specified herein can be provided to the Government as part of an offeror's technical proposal. Offerors that include information in their proposals they do not want disclosed to the public for any purpose, or used by the Government except for evaluation purposes, clearly mark their proposals in shall accordance with the instructions at FAR clause 52.215-1, Instructions to Offerors-Competitive Acquisition, paragraph (e), Restriction on Disclosure and Use of Data.
1.8.3. Use of the words " ", " ", or " " indicates a mandatory requirement. Failure to comply with a will shall must mandatory requirement at the time and date for submission of proposals result in an offeror's proposal shall being disqualified from consideration for award, unless the Government determines to conduct discussions in accordance with FAR 15.306, thereby providing a means by which appropriate corrections by the offeror(s) involved could be made. Failure to comply with requirements annotated with the words "should" or "may" could result in an unacceptable rating of an offeror's non-pricing ratings and may have a significant effect upon an offeror being selected for contract award. Time periods if stated as days, are calendar days unless a number of otherwise specified.
1.9. PROPOSAL CONTENT
1.9.1. Offerors are required to submit proposals with at least the minimum content specified herein. A proposal without the minimum content may result in a determination that the proposal is unacceptable, non-compliant, or does not indicate a responsible offeror. The Government will not make assumptions concerning intent, capabilities, or experiences. Clear identification of proposal details is the sole responsibility of an offeror.
1.9.2. All information intended to be evaluated as part of the technical proposal be submitted within the shall technical proposal. Do not include references to material or information not found within the technical proposal.
Referencing information not found within the proposal could lead to a proposal being determined unacceptable if materially incomplete in any aspect.
1.9.3. Proposals be submitted electronically and be comprised of 3 Volumes (files in Adobe portable shall shall document format (pdf) unless otherwise directed). Phase I will include Volume I Non-Price Proposal. Phase II will include Volume II Phase II Non-Price Proposal and Volume III Price and Responsibility Information. The information in any non-price volume.offeror not include pricing shall All documents must be numbered and searchable.
1.9.4. The Government will not evaluate any material that exceeds the page limits specified within each evaluation factor. For the evaluation of each factor, all pages, unless otherwise specified, contribute to the page limit. Elaborately prepared proposals are not required
1.9.5 Failing to submit or completely fill out the solicitation attachments may result in a determination that the proposal is unacceptable. Therefore, offerors are urged to follow instructions and raise questions through the Bidder Inquiry process (via ProjNet) described below.
2. PROPOSAL FORMAT
2.1. Proposals, including all appendices and supporting documents, be typed and submitted in English. must Proposals submitted in a language other than English are unacceptable. Letters of Commitment, partnership agreements, licenses, and other supporting documents if not written in English, be accompanied by an must English translated copy with a signed statement, in English, by an authorized representative who can bind the entity of each partner that the English translation is true and correct. Any documents submitted in a language other than English will not be evaluated.
2.2. An offeror's proposal be submitted as separate volumes (in PDF or as directed) as identified in must Paragraph 2, PROPOSAL CONTENT. Page limits be adhered to. Proposals be sized to print on THE must shall EQUIVALENT TO 8 1/2" X 11" I.E. A4 (THE EQUIVALENT TO 11" X 17" for I.E. A3, paper; drawings;
WITH THE EXCEPTION FOR THE PRELIMINARY SCHEDULE WHICH MAY BE PRINTED ON THE
EQUIVALENT TO 24" X 36"; I.E. CADD SIZE D DRAWING OR THE EQUIVALENT TO 30" X 42"; I.E.
CADD SIZE E DRAWING). THE DRAWINGS ASSOCIATED WITH THE PRELIMINARY SCHEDULE
ARE NOT INCLUDED IN THE PAGE LIMITATION. Margins be no smaller than a half inch (1/2"), font shall face be no smaller than Arial10-point. Page is defined as a single sheet of paper with text on one side. shall Pages furnished for organizational purposes, such as a cover page, tabs or separator , or a table of contents pages included in the page limitation.are
Note: Corporate Certificates, Partnership Agreements, Joint Venture Agreements, Letters of Commitment, Certifications, Organizational Charts, and Licenses are not included in page limitations and be included as must an appendix at the end of the technical proposal.
2.3. Offerors that include in their proposals data that they do not want disclosed to the public for any purpose, or used by the Government except for evaluation purposes, follow the requirements stated on FAR 52.215-1 shall
(e) Instructions to Offerors-Competitive Acquisition.
2.4. All information be confined to the appropriate volume. Information presented should be organized to must pertain to only the evaluation factor in the section that the information is presented. Information pertaining to more than one evaluation factor should be repeated in each section for each factor. The offeror should limit the proposal to the required information sufficient to provide the Government an adequate basis for evaluation.
Offerors are responsible for including sufficient details, in a concise manner, to permit a complete and accurate evaluation of the proposal. Each volume of the proposal contain a table of contents, summary section with must a brief abstract of the volume, and the narrative discussion. Proprietary information be clearly marked. must
3. PROPOSAL SUBMISSION INSTRUCTIONS
3.1 The Government will accept proposals submitted in hard copy or via facsimile. NOT
3.2. Proposals submitted electronically using the PIEE Solicitation module. MUST BE
3.3. Registration with PIEE is required to submit a proposal: https://pieetraining.eb.mil/wbt/portal/portal /Vendor_Registration.pdf
3.4. Registration is a multi-step process requiring self-validation of roles, please allow for sufficient system processing time. Offerors must establish an account in PIEE, and complete vendor activation requirements specified in the Vendors Getting Started section of the Help/Training page.
3.5. Self-register as a Vendor or Contractor with the user's CAGE code(s).
3.6. Select "SOL-Solicitation" in the drop-down list and choose the "Proposal Manager" role to submit proposal in PIEE.
3.7. File Size Limitations: Offerors must follow the PIEE instructions for uploading files. PIEE supports up to
1.9 GB per file, an unlimited number of uploaded files, and supports multiple (but not all) file formats. If necessary, Offerors must separate files into smaller sections to upload them to the system. Please divide the sections into logical portions and clearly name the files with the following naming convention:
W912ER26RA001-FIRMNAME-VOLUME I
W912ER26RA001-FIRMNAME-VOLUME II
W912ER26RA001-FIRMNAME-VOLUME III
When required to separate files into smaller sections, use the following naming convention:
W912ER26RA001-FIRMNAME-Volume I PART 1
3.8. Further training is available at: https://pieetraining.eb.mil/wbt/xhtml/wbt/sol/index.xhtml, regarding the Solicitation application in PIEE and the different roles available.
3.9. An Overview of the Proposal Manager function and instructions on submitting a proposal are available at:
https://pieetraining.eb.mil/wbt/xhtml/wbt/sol/solicitation/proposals.xhtml
W912ER26RA001
https://pieetraining.eb.mil/wbt/xhtml/wbt/sol/solicitation/proposals.xhtml https://pieetraining.eb.mil/wbt/xhtml/wbt/sol/solicitation/proposals.xhtml
3.10. Offerors are encouraged to submit offer files early to mitigate potential issues that include (but are not limited to) accessing PIEE, correcting data entry errors, encountering system issues, or technical difficulties.
3.11. Offerors immediately notify the Contracting Officer if PIEE is inaccessible before the submission shall deadline. Contractor notification be in writing and include verbal notification, but verbal notification alone shall is sufficient.NOT
3.12. Each potential offeror submit its proposals via PIEE no later than 8:00 AM Eastern Time (ET) on 20 must October 2025 Company information include the official business name as it appears in the System for must Award Management (SAM), email address, SAM UEI and CAGE Code. The Government will verify the offeror is registered in the SAM. It is an offeror's responsibility to ensure its proposal is received by the Government system by the date and time of the proposal deadline. Undeliverable messages due to an offeror's proposal size or IT issues are not the responsibility of the Government. It is recommended that offerors submit their proposals with sufficient time remaining so the electronic files are received, and confirmation of receipt can be obtained.
3.13. Solicitation points of contact are:
Sabrina S. Booker, Contracting Officer, sabrina.s.booker@usace.army.mil
AND
Anna N. Holcomb, Contract Specialist, anna.n.holcomb@usace.army.mil
3.14. Late Proposals. Any proposal, modification, or revision received by the Government after the exact time specified for receipt of offers is "late" and will not be considered unless it is received before award is made and the contracting officer determines that accepting the late proposal would not unduly delay the acquisition; it and was the only proposal received; it is a late modification of an otherwise successful proposal that makes its OR terms more favorable to the Government.
4. SOLICITATION INQUIRIES
4.1. All inquiries regarding this solicitation be submitted via Bidder Inquiry through ProjNet at must https://www.projnet.org/projnet/. Telephone and email inquiries will not be accepted. submit DO NOT proposals via ProjNet. To submit and review bidder inquiry items, bidders will need to be a current registered user or self-register in the system.
4.2. Offerors only submit one question per inquiry. All inquiries containing multiple questions will be shall rejected. Offerors are requested to review all documents in their entirety and to review the Bidder Inquiry System for answers prior to submission of a new inquiry.
4.3. Offerors will receive an acknowledgement of their question(s) via email, followed by an answer after it has been processed by our technical team. Offerors may view all bidder inquiries through ProjNet.
4.4. Inquiries be submitted to the proposal due date. The inquiry must no later than 10 calendar days prior system in ProjNet will be closed at that time and will not accept further inquiry postings.
4.5. To submit and review bid inquiries, prospective offerors will need to use the Bidder Inquiry Key presented below and follow the instructions listed below the key for access. The Bidder Inquiry Key is: JSP95C-
U3WMM6
4.6. Specific Instructions for ProjNet Bid Inquiry Access:
W912ER26RA001
mailto:sabrina.s.booker@usace.army.mil mailto:anna.n.holcomb@usace.army.mil
1. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.
2. Identify the Agency as USACE.
3. Key. Enter the listed above. Bidder Inquiry Key
4. Email. Enter the email address you would like to use for communication.
5. Click Continue. A page will then open saying that a user account was not found and will ask you to create one using the provided form.
6. Enter your First Name, Last Name, Company, City, State, Phone, Email, Secret Question, Secret Answer, and Time Zone. Make sure to remember your Secret Question and Answer as they will be used from this point on to access the ProjNet system.
7. Select Add User. Once this is completed you are now registered within ProjNet and are currently logged into the system.
4.7. Specific Instructions for Future ProjNet Bid Inquiry Access:
1. For future access to ProjNet, you will not be emailed any type of password. You will utilize your Secret Question and Secret Answer to log in.
2. From the ProjNet home page listed above, click on Quick Add on the upper right side of the screen.
3. Identify the Agency. This should be marked as USACE.
4. Key. Enter the Bidder Inquiry Key listed above.
5. Email. Enter the email address used to register previously in ProjNet.
6. Select Continue. A page will open asking you to enter the answer to your Secret Question.
7. Enter your Secret Answer and click Login. Once this is completed you are now logged into the system.
From this page you may view all bidder inquires or add an inquiry.
4.8. Government responses to technical inquiries and questions relating to proposal procedures or bonds that are submitted to ProjNet in accordance with the procedures above are not binding on the Government unless an amendment is issued on Standard Form 30. In the case of any conflicts, the solicitation governs. Any changes or revisions to the solicitation will be made by formal amendment. Government responses will be limited to: (a) Notice that an amendment will be issued; (b) Reference to an existing requirement contained in the solicitation;
or (c) Notice that a response is not necessary.
4.9. For specific step-by-step for POSTING YOUR INQUIRIES, see the Reference link on the Contract Viewer.
4.10. For questions about the ProjNet, please contact the Call Center help desk at 1-800-428-HELP, which operates from 8AM to 5PM (Central US time zone). ProjNet questions can also be emailed to the helpdesk at staff@rcesupport.com.
4.11. Pre-proposal Conference and Site Visit. The Government does intend to conduct a Pre-proposal Conference or Site Visit for Phase I.
FAR Clauses Incorporated by Reference
Number Title Effective Date
Alternate/ Deviation
Variation Effective Date
52.204-7 System for Award Management. Nov 2024 52.204-16 Commercial and Government Entity Code Reporting. Aug 2020 52.204-22 Alternative Line Item Proposal. Jan 2017 52.215-1 Instructions to Offerors-Competitive Acquisition. Nov 2021
DFARS Clauses Incorporated by Reference
Number Title Effective Date
Alternate/ Deviation
Variation Effective Date
252.204-7019 Notice of NIST SP 800-171 DoD Assessment Requirements. Nov 2023 252.204-7024 Notice on the Use of the Supplier Performance Risk System. Mar 2023 252.215-7009 Proposal Adequacy Checklist. Mar 2023 252.215-7013 Supplies and Services Provided by Nontraditional Defense Contractors. Jan 2023 252.215-7016 Notification to Offerors-Postaward Debriefings. Dec 2022 252.233-7001 Choice of Law (Overseas). Jun 1997
FAR Clauses Incorporated by Full Text
52.216-1 Type of Contract. (Apr 1984)
Type of Contract (Apr 1984)
The Government contemplates award of a contract resulting from this solicitation.Firm Fixed-Price (FFP), Design-Build (DB)
(End of provision)
52.233-2 Service of Protest. (Sep 2006)
Service of Protest (Sept 2006)
Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that (a) are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from
Ms. Sabrina Booker
Procuring Contracting Officer
U.S. Army Corps of Engineers, Middle East District
201 Prince Frederick Drive
Winchester, VA 22602.
All Protest must be sent to tam.protests@usace.army.mil and sabrina.s.booker@usace.army.mil
The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.(b)
(End of provision)
52.252-1 Solicitation Provisions Incorporated by Reference. (Feb 1998)
Solicitation Provisions Incorporated by Reference (Feb 1998)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):
FAR at https://www.acquisition.gov/
DFARS at https://www.acquisition.gov/dfars
Class Deviations at https://www.acq.osd.mil/dpap/drs/class_deviations.html
(End of provision)
52.252-5 Authorized Deviations in Provisions. (Nov 2020)
Authorized Deviations in Provisions (Nov 2020)
The use in this solicitation of any Federal Acquisition Regulation (48 CFR Chapter 1) provision with an authorized deviation is indicated by the (a) addition of "(DEVIATION)" after the date of the provision.
The use in this solicitation of any provision with an authorized deviation (b) Defense Federal Acquisition Regulation Supplement (48 CFR Chapter ) 2 is indicated by the addition of "(DEVIATION)" after the name of the regulation.
(End of provision)
DFARS Clauses Incorporated by Full Text
252.215-7008 Only One Offer. (Dec 2022)
ONLY ONE OFFER (DEC 2022)
(a) . After initial submission of offers, if the Contracting Officer notifies the Offeror that only one offer was Cost or pricing data requirements received, the Offeror agrees to-
(1) Submit any additional cost or pricing data that is required in order to determine whether the price is fair and reasonable (10 U.S.C. 3705) or to comply with the statutory requirement for certified cost or pricing data (10 U.S.C. 3702 and FAR 15.403-3); and
(2) Except as provided in paragraph (b) of this provision, if the acquisition exceeds the certified cost or pricing data threshold and an exception to the requirement for certified cost or pricing data at FAR 15.403-1(b)(2) through (5) does not apply, certify all cost or pricing data in accordance with paragraph (c) of DFARS provision 252.215-7010, Requirements for Certified Cost or Pricing Data and Data Other Than Certified Cost or Pricing Data, of this solicitation.
(b) . If the Offeror is the Canadian Commercial Corporation, certified cost or pricing data are not required. If Canadian Commercial Corporation the Contracting Officer notifies the Canadian Commercial Corporation that additional data other than certified cost or pricing data are required in accordance with DFARS 225.870-4(c), the Canadian Commercial Corporation shall obtain and provide the following:
(1) Profit rate or fee (as applicable).
(2) Analysis provided by Public Works and Government Services Canada to the Canadian Commercial Corporation to determine a fair and reasonable price (comparable to the analysis required at FAR 15.404-1).
(3) Data other than certified cost or pricing data necessary to permit a determination by the U.S. Contracting Officer that the proposed price is fair and reasonable TBD, if necessary.
(4) As specified in FAR 15.403-3(a)(4), an offeror who does not comply with a requirement to submit data that the U.S. Contracting Officer has deemed necessary to determine price reasonableness or cost realism is ineligible for award unless the head of the contracting activity determines that it is in the best interest of the Government to make the award to that offeror.
(c) . Unless the Offeror is the Canadian Commercial Corporation, the Offeror shall insert the substance of this provision, including Subcontracts this paragraph (c), in all subcontracts exceeding the simplified acquisition threshold defined in FAR part 2.
(End of provision)
W912ER26RA001
https://www.acquisition.gov/ https://www.acquisition.gov/dfars https://www.acq.osd.mil/dpap/drs/class_deviations.html
Section 00 21 16 - Instructions to Proposers
APPENDIX B
1. BASIS OF PHASE ONE EVALUATION
1.1 Subject to the provisions contained herein, the Government will evaluate proposals to determine offerors that are: compliant with the solicitation requirements; and whose proposals, judged by an overall assessment of the evaluation criteria and other considerations specified in this solicitation, are determined to be acceptable across all non-price factors.
1.2 The Government intends to advance a maximum of five (5) of the most highly qualified offerors to Phase Two from which it anticipates awarding one firm-fixed-price contract. It may advance fewer than five offerors and will exercise discretion in determining the number of offerors to be advanced to Phase Two. The Source Selection Authority (SSA) will the Government's interest in competition and its interests in take into account awarding to a highly qualified contractor, and in preventing avoidable expenditure on Phase Two proposal preparation by offerors without realistic prospects of award.
2.0. PHASE ONE VOLUME I PROPOSAL SUBMISSION REQUIREMENTS AND EVALUATION
FACTORS
2.1. RELATIVE IMPORTANCE OF EVALUATION FACTORS
The Phase II Solicitation will include information on the relative importance of evaluation factors for purposes the best value tradeoff. For purposes of the Government's Phase I down-selection decision, the Phase I factors are listed in descending order of importance as follows:
- Phase I Factor II Past Performance
- Phase I Factor I Design Strategy
2.2. DEFINITIONS
Significant Strength. An aspect of an offeror's proposal that has appreciable merit or appreciably exceeds specified performance or capability requirements in a way that will be appreciably advantageous to the Government during contract performance.
Strength. An aspect of an offerors' proposal that has merit or exceeds specified performance or capability requirements in a way that will be advantageous to the Government during contract performance.
Weakness. A flaw in the proposal that increases the risk of unsuccessful contract performance. See FAR 15.001.
Significant Weakness. A flaw in the proposal that appreciably increases the risk of unsuccessful contract performance. See FAR 15.001.
Deficiency. A material failure of a proposal to meet a government requirement or a combination of significant weaknesses in a proposal that increases the risk of unsuccessful contract performance to an unacceptable level.
See FAR 15.001.
Uncertainty. Any aspect of a non-cost/price factor proposal for which the intent of the offer is unclear (e.g., more than one way to interpret the offer or inconsistencies in the proposal indicating that there may have been an error, omission or mistake).
. Past performance information that supports a less than satisfactory rating on any Adverse Past Performance evaluation.
2.3. PHASE ONE EVALUATION FACTORS
Evaluation factors may contain certain mandatory or minimum requirements to be met for evaluation. There are also contained within the described factors certain documents for submission. Failure to satisfy any mandatory or minimum requirement may result in a determination that a proposal is unacceptable. A final determination that a proposal is unacceptable means that the offeror will not be selected as a most highly qualified offeror, and the Government will not request that the offeror submit a Phase Two proposal. This does not limit the Government's discretion to exclude offerors without any "unacceptable" ratings from Phase Two because they were not found to be among the most highly qualified offerors.
All of the submission items to be evaluated pertain to the offeror and its major subcontractors. A minimum shall of twenty percent (20%) of the work associated with this project is required to be performed by the contract awardee.
Subcontractors: The Government recognizes that completion of a project is often a team effort. An offeror that intends to utilize one or more major subcontractor(s), submit a firm, unequivocal letter of commitment shall signed by each major subcontractor. A major subcontractor is defined as a subcontractor that performs twenty percent (20%) or more of the total on-site management and construction efforts or one that performs twenty percent or more of the total dollar value of the project. Offerors that propose to use a Designer of Record (DOR) are also required to submit firm, unequivocal letters of commitment signed by their DOR(s). An offeror's technical proposal will largely be diminished in the evaluation and selection process unless a required letter of commitment is provided which establishes the likelihood that the proposed subcontractor(s) will actually be available for this project. If an offeror's accepted proposal includes the use of any major subcontractors or DORs, the offeror not change major subcontractors or DORs without the Contracting Officer's approval. shall Approval will not be given unless the Contracting Officer considers the proposed substitute to be equal or better in all respects to the originally proposed major subcontractor or DOR and that the substitution is in the best interests of the Government.
Joint Ventures: A Joint Venture (JV) is defined as a legal business entity formed between two or more companies to undertake the performance activities of a contract together.
An offeror proposing as a JV provide evidence that the JV as a legal entity has been duly formed. A JVs shall offeror include a copy of its legal JV agreement signed by an authorized representative who can bind the shall entity of each coventurer, with the chief executive of each entity identified. A prospective offeror that submits a proposal as a JV may not change either/any of the joint venturers, if selected for award.
For technical factors other than Past Performance, the Combined Technical/Risk Ratings below will be used:
Table 1. Combined Technical/Risk Rating Method
Color Rating Adjectival Rating
Description
Blue
Outstanding
Proposal demonstrates an exceptional approach and understanding of the requirements and contains multiple strengths and/or at least one significant strength, and risk of unsuccessful performance is low.
Purple
Good
Proposal indicates a thorough approach and understanding of the requirements and contains at least one strength or significant strength, and risk of unsuccessful performance is low to moderate.
Green Acceptable Proposal meets requirements and indicates an adequate approach and understanding of the requirements, and risk of unsuccessful performance is no worse than moderate.
Yellow Marginal Proposal has not demonstrated an adequate approach and understanding of the requirements, and/or risk of unsuccessful performance is high.
Red
Unacceptable
Proposal does not meet requirements of the solicitation and, thus, contains one or more deficiencies and is unawardable, and/or risk of performance is unacceptably high.
2.3.1. FACTOR I - DESIGN STRATEGY
2.3.1.1. Submission Requirements. The narrative shall demonstrate the offeror's proposed capabilities to perform the design-build construction effort and shall not to exceed 10 pages, that explains the offeror's intended approach to perform full design services utilizing the conceptual design to be provided by the Government The narrative should describe the offeror's understanding and plans of the following:.
- Applicable design codes and standards to be utilized.
- Design Quality Control and Independent Technical Review procedures.
- Management of design submissions, design review periods, and comment resolution and closure.
- Name of the design firm(s) proposed to perform the full design effort.
- A detailed explanation of the proposed contractual relationship(s) between the offeror and any listed design firm(s).
- Examples of previous designs by any listed design firm(s) to demonstrate proficiency with facility design.
- Describe, with specific examples, how the proposed design firm(s) have demonstrably learned from challenges encountered on prior projects of similar scope and complexity, and how those lessons will directly contribute to the successful completion of this project?
- Detail the proposed process between the offeror and the design firm(s) to ensure full compliance with all design technical requirements while proactively managing budgetary constraints. Specifically, address how Value Engineering, cost tracking, and change management will be integrated throughout the project lifecycle.
2.3.1.2. Evaluation Criteria. An offeror's design strategy will be evaluated in its entirety to determine the offeror's understanding of requirements and strength of the offeror's proposed design strategy. The Government will evaluate the design strategy and consider the level of risk the offeror's strategy presents to successful project completion. The Government may consider elements such as the following:
- The level of detail and accuracy the offeror demonstrates regarding applicable codes and standards, design processes, and Design Quality Control procedures.
- The strength of experience of proposed design firms.
- The relevance of the demonstrated capability of proposed design firms with the scope of this project.
- The extent to which design firms and/or the offeror have worked together on previous design or design-build construction projects.
A single rating will be assigned under the Design Strategy factor. In rating the offeror, the Government will focus on the strengths, deficiencies, weaknesses, risk, and uncertainties. The Combined Technical/Risk Rating in Paragraph 2.2 will be applied based on the offeror's approach as well as the offeror's demonstrated understanding of the requirements.
2.3.2. FACTOR II - PAST PERFORMANCE
The Past Performance evaluation is an assessment of an offeror's probability of meeting the solicitation requirements and results in an assignment of a single performance confidence assessment rating based on an offeror's past performance record.
For the purposes of this evaluation:
A project is defined as a project, in a , with a "relevant" "recently completed" "similar geographic region" and with to the project that is the subject of this solicitation. The "similar scope" "similar cost magnitude"
Government use any evidence of negative past performance to assign a lower past performance confidence may rating if it is determined there is a reasonable expectation that negative performance is indicative of potential negative performance on this requirement. Projects performed by the offeror as a prime contractor or by the same JV offeror may be considered more relevant than projects where the offeror performed as a subcontractor or as part of a different JV.
A project is defined as a project for which construction Substantial Completion (SC) has "recently completed" been issued within six (6) years of the proposal due date for this solicitation or is currently under construction and is at least 75% complete as of the proposal due date.
"Similar geographic region" is defined as a project constructed in the Gulf Cooperative Council (GCC) member countries that include, Bahrain, Kuwait, Oman, Qatar, Saudi Arabia, and the United Arab Emirates
(UAE).
"Similar scope" is defined as renovation of a commercial, institutional, or military facility with replacement of 75% or more of the facility's foundation or concrete slab on grade without compromising the structural integrity of the building and one or more of the following:
- Fire suppression system installation, repair, or replacement
- Interior demolition without compromising the structural integrity of the building
- Removal and re-installation of a paint booth
Submitted facilities should be of similar size, type, and complexity of this requirement.
"Similar cost magnitude" A project will be considered of similar cost magnitude if its total contract value falls within the range defined as the "Magnitude of Construction Capacity" in SECTION 00 21 00, Paragraph 1.2.
Projects with a total contract value up to 30% above or below this range will also be considered similar in magnitude.
Offerors clearly delineate their responsibilities and associated cost magnitude for each submitted project. If shall the offeror performed work as a subcontractor, only the scope and cost magnitude for which it held responsibility as a subcontractor will be considered.
If an offeror is submitting Indefinite Delivery Contract (IDC) or other ordering contracts for consideration, the offeror submit each individual project, whether it is a task order or a standalone contract, ensuring it meets shall minimum requirements for cost magnitude. The total amount of the Indefinite Delivery Contract (IDC) will not be taken into account.
2.3.2.1. . Submission Requirements The offeror submit Past Performance information for at least two (2) shall projects and no more than five (5) performed by the offeror. Additional projects will not be considered for evaluation. An offeror may submit projects for evaluation for which it performed as a prime contractor, as part of a joint venture, or as a subcontractor. With each submitted project the offeror clearly identify or must describe the specific work performed by the offeror.
- Submitted Projects. An offeror may submit projects for evaluation for which it performed as a prime contractor, as part of a joint venture, or as a subcontractor. With each submitted project the offeror must clearly identify or describe the specific work performed by the offeror.
If past performance by a subcontractor is submitted for consideration as part of the proposal, the offeror should include a commitment signed by offeror and subcontractor certifying that if a contract is awarded resulting from the proposal, the parties commit to joint performance as proposed. If the signed commitment is not fully executed by both parties and provided with the Past Performance Proposal, subcontractor references will not be evaluated or considered. The offeror also identify the percentage of work to be accomplished by the must subcontractor. Past performance by a subcontractor may not be given the same weight as past performance by the offeror, and a weakness may be assigned if an offeror (the prime contractor) has no experience.
If past performance by an affiliate is submitted for consideration as part of the proposal, the offeror should include a commitment signed by offeror and the affiliate certifying that if a contract is awarded resulting from the proposal, the parties commit to joint performance as proposed. If the signed commitment is not fully executed by both parties and provided with the Past Performance Proposal, affiliate references will not be evaluated or considered. The offeror also identify the percentage of work to be accomplished by the must affiliate. Past performance by an affiliate may not be given the same weight as past performance by the offeror, and a weakness may be assigned if an offeror (the prime contractor) has no experience
2.3.2.2. . Contractor Performance Assessment Reporting System (CPARS) evaluations, Submission Format whether interim or final, be submitted for all US Government projects. For non-Government projects, Past shall Performance Questionnaires (PPQ) (ATTACHMENT H) be submitted. If the offeror is unable to obtain shall PPQ feedback from their non-Government client, the offeror complete and submit with its proposal the shall first page of the PPQ (including blocks 5 and 6). If, at time of evaluation, a contractor performance evaluation exists in CPARS, and the offeror submits a PPQ, there is no obligation to review the PPQ. Information such as awards, certificates, customer letters of commendation, and any other forms of performance recognition shall not be submitted or evaluated.
An offeror should submit recently completed, relevant projects on the following documents:
- Past Performance Overview Sheet
- Project Summary Form, and
- Past Performance Questionnaire (PPQ) (for non-Government projects) or Contractor Performance Assessment Reporting System (CPARS) evaluations (for Government projects).
On the Project Summary form the offeror include a project description with a project scope and cost shall magnitude, detailed enough to evaluate the project's relevance and recency.
Additionally, the offeror should:
- Provide details for any past performance problems encountered and the corrective actions taken.
- Provide the name and contact information of English-speaking references who have first-hand knowledge of the offeror's past performance. References should be independent, willing, and available to answer questions, and knowledgeable personnel within the contracting agency or entity that administers the contract such as the construction agent, owner, or Government representative.
References may be asked to comment on specific aspects of the offeror's performance, such as, but not limited to: quality of construction, timeliness, management of the work, subcontractor management including timely payment to subcontractors or suppliers, safety, relations between owner and designer or contractor, level of support for such elements as as-built documentation, correcting design or construction errors, and warranty work.
- Notify the reference that he or she may be contacted for the purposes of the evaluation.
- Contractor Performance Assessment Reporting System (CPARS) evaluations be submitted for all shall Government projects.
For non-Government projects, Past Performance Questionnaires (PPQ) be submitted. If the offeror is shall unable to obtain PPQ feedback from their non- government client, the offeror complete and submit with its shall proposal the first page of the PPQ (including blocks 5 and 6).
Past performance information such as awards, certificates, customer letters of commendation, and any other forms of performance recognition not be submitted, as this information will not be evaluated shall
FALSIFIED PAST PERFORMANCE INFORMATION (INCLUDING PPQs) MAY BE GROUNDS
FOR DISQUALIFICATION OF AN OFFEROR'S PROPOSAL, REFERRAL OF THE OFFEROR FOR
SUSPENSION OR DEBARMENT, AND…
This is the start of the file's text. The full file is on GovTribe.