B.08.02 W9123722Q0163.pdf

PDF 1 MB Posted

Attached to
Bulltown Historic Area
Solicitation number
W91237-22-Q-0163
Issued by

View the file

Other files

File Type Posted
A.03.09 Exhibit A photo_maps_drawings_REV_1.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BURNSVILLE LAKE

RICHARD PINGLEY

2550 S MAIN STREET

BURNSVILLE WV 26335-7516

TEL: 304-853-2371 FAX:

W81F8E22025500

REQUEST FOR QUOTATIONS

(THIS IS NOT AN ORDER) 1

PAGE OF PAGES

1. REQUEST NO. 2. DATE ISSUED RATING

W9123722Q0163 30-Aug-2022 5a. ISSUED BY

8. TO: NAME AND ADDRESS, INCLUDING ZIP CODE

IMPORTANT: This is a request for information, and quotations furnished are not offers. If you are unable to quote, please so indicate on this form and return it to the address in Block 5a. This request does not commit the Government to pay any costs incurred in the preparation of the submission of this quotation or to contract for supplies or services. Supplies are of domestic origin unless otherwise indicated by quoter. Any representations and/or certifications attached to this

Request for Quotations must be completed by the quoter.

11. SCHEDULE (Include applicable Federal, State, and local taxes)

ITEM NO.

(a)

SUPPLIES/ SERVICES

(b)

QUANTITY

(c)

UNIT

(d)

UNIT PRICE

(e) (f)

SEE SCHEDULE

AMOUNT

% No. %

NOTE: Additional provisions and representations [ ] are [ ] are not attached.

13. NAME AND ADDRESS OF QUOTER (Street, City, County, State, and ZIP Code)

14. SIGNATURE OF PERSON AUTHORIZED TO

SIGN QUOTATION

15. DATE OF

QUOTATION

16. NAME AND TITLE OF SIGNER (Type or print) (Include area code)

TELEPHONE NO.

AUTHORIZED FOR LOCAL REPRODUCTION STANDARD FORM 18 (REV. 6-95)

PREVIOUS EDITION NOT USABLE Prescribed by GSA FAR (48 CFR) 53.215-1(a)

THIS RFQ X[ ] IS [ ] IS NOT A SMALL BUSINESS SET-ASIDE

6. DELIVER BY (Date)

SEE SCHEDULE

AND/OR DMS REG. 1

UNDER BDSA REG. 2

4. CERT. FOR NAT. DEF.3. REQUISITION/PURCHASE

REQUEST NO.

USACE, CONTRACTING DIVISION

AMY B. ORWIG, 502 8TH STREET

HUNTINGTON WV 25701

9. DESTINATION (Consignee and address, including ZIP Code)

7. DELIVERY

[ ]X FOB

DESTINATION

[ ] OTHER

(See Schedule)

15-Sep-2022(Date)

PLEASE FURNISH QUOTATIONS TO THE ISSUING OFFICE IN BLOCK 5a ON OR BEFORE CLOSE OF BUSINESS:10.

304.399.5183AMY B ORWIG

(Name and Telephone no.) (No collect calls)5b. FOR INFORMATION CALL:

d. CALENDAR DAYSc. 30 CALENDAR DAYSb. 20 CALENDAR DAYS12. DISCOUNT FOR PROMPT PAYMENT a. 10 CALENDAR DAYS

W9123722Q0163

Section B - Supplies or Services and Prices

ADDITIONAL INFORMATION

ADDITIONAL INFORMATION

*SITE VISITS ARE HIGHLY RECOMMENDED PRIOR TO PROVIDING A

QUOTE. SEE CLAUSE 52.236-27 FOR ADDITIONAL INFORMATION.

*PLEASE DIRECT ALL QUESTIONS TO AMY ORWIG AT (304) 399-5664 or amy.b.orwig@usace.army.mil. ANY INFORMATION RECEIVED AT THE SITE

VISIT WHICH CONFLICTS WITH THIS SOLICITATION SHOULD BE

BROUGHT TO THE ATTENTION OF MRS. ORWIG. THE SOLICITATION AND

RESULTING CONTRACT SHALL BE THE GOVERNING DOCUMENT IN ALL

CASES.

**QUOTES CAN ONLY BE E-MAILED TO AMY ORWIG AT amy.b.orwig@usace.army.mil by the date referenced on page one of the SF18.

Per FAR 36.204 the estimated price range for this project is between $100,000 and $250,000.

NOTE: Award will be made to the lowest price offeror who meets the technical requirements of the solicitation and is deemed responsible by the contracting officer.

The intent is to award without discussions.

NOTE: this procurement is 100% Total Set-Aside for Small Business. For more information see FAR Clause 52.219-6.

QUOTATION INSTRUCTIONS (Provide the following with your quote):

Company Name and Address:

Phone Number: Fax Number:

Email Address:

Business Size (select all that apply):

Large Business Small Business HUBZone Business 8A

Woman-Owned Service-Disabled Veteran-Owned

If subcontractor will be used for this work, please provide company name and credentials/qualifications:

IMPORTANT NOTICE: Effective September 26, 2018 and in accordance with FAR Clause 52.204- 7, “an Offeror is required to be registered in SAM when submitting an offer or quotation, and shall continue to be registered until time of award, during performance, and through final payment of any contract, basic agreement, basic ordering agreement, or blanket purchasing agreement resulting from this solicitation.” Vendors are highly encouraged to check their registration status and plan accordingly prior to submitting an offer.

Please note, as of April 2018, GSA's System for Award Management (SAM) system is requiring new registrations and renewals of existing registrations to submit an original signed notarized letter identifying the authorized Entity Administrator. Vendors are encouraged to check their entity's status in SAM.gov and plan accordingly. If the prospective contractor is not registered in the SAM database, the Contracting Officer will following the procedures at FAR 4.1103. Contact the supporting Federal Service Desk at www.fsd.gov, or by telephone at 866- 606-8220 (toll free) or 334-206-7828 (internationally) Monday through Friday from 8 a.m. to 8 p.m. (EDT), for FREE assistance.

Contractor is registered with SAM:

YES NO (See FAR 52.204-7)

Provide business Unique Entity Identifier number:

(phone 800-333-0505 for Unique Entity Identifier number).

Provide business CAGE code:

Provide Tax Identification Number:

All work under this contract shall be in performance with all local, state, and federal laws, regulations, and codes.

Only the awarded contractor shall provide a copy of their insurance certificate required by State and Local Governments that has been acquired for the time period covered under this contract to the Contracting Officer within 10 business days after award. No further insurance requirements will be imposed by the Corps of Engineers for this contract.

Contractors are not required to submit an Accident Prevention Plan (APP) with their quote.

The successful offeror will be required to submit this document upon award. The APP must be accepted by the Government Designated Authority prior to the preconstruction conference. The contractor that receives this award will have 10 calendar days to provide an Accident Prevention Plan (APP). If this deadline is not met, the contractor will be given a cure notice stating that they will have 10 calendar days to submit an APP, otherwise the contract may be terminated for default.

Only the awarded contractor shall is required to submit back FAR Clause 52.204-24 with signed award. Please answer the two questions that are within the clause by placing an X in the box for does or does not OR will or will not, whichever applies to you as the contractor.

Please submit back within 10 business days after award.

PRICE BREAKOUT SCHEDULE

Line Item No. Description of Requirement Qty/Unit of Measure Extended Price

0001 Reimbursement of actual cost of payment bond for quotes in excess of $35,000.00 and performance bond for quotes in excess of $150,000.00

JOB $__________

'0002 Mobilization & de-mobilization JOB $__________ of equipment required in accordance with the attached Scope of Work.

0003 Labor required for repair work at the Cunningham House at Bulltown Historic Area at Burnsville Lake in accordance with attached Scope of Work

0004 Supplies, materials, and equipment required for repair work at the Cunningham House at Bulltown Historic Area at Burnsville Lake in accordance with attached Scope of Work.

Base Total Total $__________

0005 Reimbursement of actual cost for increase in payment protection for Option 1

0006 Labor required to straighten chimney and install gutters and downspouts on Cunningham House and to rebuild the Cat and Clay section of the chimney at the Johnson House at the Bulltown Historic Area at Burnsville Lake in accordance with attached scope of work

0007 Supplies, materials, and equipment required for repair work at the Cunningham House and Johnson House at Bulltown Historic Area at Burnsville Lake in accordance with attached scope of work.

Option 1 Total Total $__________

GRAND TOTAL GRAND TOTAL $__________

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Job BASE Cunningham House Foundation & Floor

FFP

Contractor shall provide all necessary labor, equipment, and materials to Bulltown Historic Area located at Burnsville Lake, Napier, WV in accordance with the attached Statement of Work FOB: Destination

PURCHASE REQUEST NUMBER: W81F8E22025500

PSC CD: Y1PZ

NET AMT

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0002 1 Job OPTION Opt 1 Cunningham & Johnson House

FFP

Contractor shall provide all necessary labor, equipment, and materials to Bulltown Historic Area located at Burnsville Lake, Napier, WV in accordance with the attached Statement of Work FOB: Destination

PURCHASE REQUEST NUMBER: W81F8E22025500

PSC CD: Y1PZ

NET AMT

Section C - Descriptions and Specifications

SCOPE OF WORK

STATEMENT OF WORK

Burnsville Lake

BULLTOWN HISTORIC AREA STRUCTURE REPAIR

Furnish all equipment, material, labor, supplies, and supervision needed to repair the foundation and floor system, straighten the chimney, and install gutters in the historic Cunningham House, and rebuild the Cat and Clay section of the Johnson House Chimney in accordance with the attached scope of work and attached plan drawings.

Expected Start Date: Work shall commence within 30 calendar days of issuance of Notice to Proceed

(NTP).

Contract Duration: Project shall be completed within 90 calendar days of work commencement.

Project Location: Bulltown Historic Area, 55 Bulltown Campground Road, Napier, WV 26331.

See vicinity maps in plans.

1.0 SCOPE OF WORK

1.1 General Description: The Cunningham House is in the Bulltown Historic Area at Burnsville Lake. The structure is over 150 years old, was in existence during the Civil War Battle of Bulltown, and is on the National Register of Historic Places. The Southwest corner of the building has settled because logs and beams supporting the structure have settled. The stone chimney on the West side of the building has settled. Gutters must be installed to prevent further damage.

The Johnson House is a relocated log structure that was moved from the original location on Burnsville Lake property to it’s current location in the Bulltown Historic Area. The Cat and Clay section of the chimney has deteriorated and must be replaced.

1.2 General Requirements: All visible repairs shall be made in a manner that is historically correct. Repairs that are made under the floor, reinstallation of the floor, straightening the chimney, adding gutters, and rebuilding the Cat and Clay chimney shall be made professionally using methods common to the trade of restoring historic structures. The Contractor shall maintain a clear and safe means of ingress and egress from the work area at all times. The use of the site for staging shall be coordinated with the on-site Government representative.

2.0 SUBMITTALS AND SUBMITTAL PROCEDURES

2.1 General: The Contractor shall provide the submittals listed herein to the Government for approval. Units of weights and measures used on all submittals are to be the same as those used in the contract drawings and scope of work. Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements.

Submittals shall be submitted to the Contracting Officer within 30 calendar days of Contract award. Proposed deviations from the contract requirements are to be clearly identified. Include within submittals items such as:

Contractor's, manufacturer's, or fabricator's drawings; descriptive literature and other such required submittals.

2.2 Required Submittals: Preconstruction submittals are required following Notice of Award and prior to the issuance of the Notice to Proceed.

Required submittals are:

1. List of proposed SubContractors (if used)

2. Health and Safety Plan (Accident Prevention Plan)

3. Activity Hazard Analysis

4. Work Plan

5. Quality Control Plan

2.3 Disapproved or Rejected Submittals: Contractor shall make corrections required by the Contracting Officer.

If the Contractor considers any correction or notation on the return submittals to constitute a change to the contract drawings or specifications; notice as required under the clause entitled, "Changes," is to be given to the Contracting Officer. Contractor is responsible for the dimensions and design of connection details and construction of work.

Failure to point out deviations may result in the Government requiring rejection and removal of such work at the Contractor's expense. If changes are necessary to submittals, the Contractor shall make such revisions and submission of the submittals in accordance with the procedures above. No item of work requiring a submittal change is to be accomplished until the changed submittals are approved.

2.4 Approved/Accepted Submittals: The Contracting Officer's approval or acceptance of submittals is not to be construed as a complete check, and indicates only that design, general method of construction, materials, detailing, and other information appear to meet the Solicitation and Accepted Proposal. Approval or acceptance will not relieve the Contractor of the responsibility for any error which may exist, as the Contractor under the Contractor Quality Control (CQC) requirements of this contract is responsible for design, dimensions, all design extensions, etc., and the satisfactory construction of all work. After submittals have been approved or accepted by the Contracting Officer, no resubmittal for the purpose of substituting will be considered unless accompanied by an explanation of why a substitution is necessary.

2.5 Withholding of Payment: No payment for materials incorporated in the work will be made if all required Government approvals have not been obtained. No payment will be made for any materials incorporated into the work for any conformance review submittals or information only submittals found to contain errors or deviations from the Solicitation or Accepted Proposal.

3.0 CONTRACTOR QUALITY CONTROL

The Contractor shall establish a quality control program to assure the requirements of the contract are provided as specified. The Contractor shall furnish for review by the Contracting Officer, not later than ten (10) days after receipt of notice of award, the Contractor Quality Control (CQC) Plan proposed to implement the requirements of Contract Clause 52.246.12 INSPECTION OF CONSTRUCTION. The CQC plan must be accepted prior to Notice to Proceed. The CQC plan shall identify all personnel, procedures, control, instructions, test, records, and forms to be used. Construction will be permitted to begin only after acceptance of the CQC Plan. If the Contractor fails to submit an acceptable CQC plan within the time herein prescribed, the Contracting Officer may refuse to allow construction operations to begin.

3.1 Acceptance of Plan: Acceptance of the Contractor's plan is required prior to NTP. Acceptance is conditional and shall be predicated on satisfactory performance during the construction. The Government reserves the right to require the Contractor to make changes in his CQC plan and operations including removal of personnel, as necessary, to obtain the quality specified.

3.2 Control: Contractor Quality Control is the means by which the Contractor ensures that the construction, to include that of subContractors and suppliers, complies with the requirements of the contract. The controls shall be adequate to cover all construction operations, including both on-site and off-site fabrication, and will be keyed to the proposed construction sequence. The controls shall include at least three (3) phases of control to be conducted by the CQC Manager for all definable features of work.

3.3 Documentation: The Contractor shall maintain current records of quality control operations, activities, and tests performed, including the work of subContractors and suppliers. These records shall be on an acceptable form and shall include factual evidence that required quality control activities and tests have been performed.

3.4 Quality Assurance: The Government will monitor the Contractor's performance in this contract and reserves the rights to use whatever additional surveillance procedures are deemed appropriate. A Government employee shall not be considered an Inspector unless he identifies himself as such to the Contractor, the Government Representative, or Quality Control Inspector. No Inspector is authorized to change any provision of the specifications without written authorization of the Contracting Officer, nor shall the presence or absence of an inspector relieve the Contractor from any requirements of the Contract.

4.0 ENVIRONMENTAL PROTECTION

4.1 General: For the purpose of this specification, environmental protection is defined as the retention of the environment in its natural state to the greatest possible extent during project construction and to enhance the natural appearance in its final condition. Environmental protection requires consideration of air, water, and land and involves noise and solid waste management, as well as other pollutants. In order to prevent and to provide for abatement and control of, any environmental pollution arising from the construction activities in the performance of this contract, the Contractor and its subContractors shall comply with all applicable Federal, State, and local laws and regulations concerning environmental pollution control and abatement. The Contractor's attention is invited to Drawing Numbers GI002 and EP001 concerning environmental protection measures. The Contractor shall comply with all applicable local, state, and federal environmental laws and regulations.

5.0 SUBMISSION OF OFFERS

5.1 Offer Format: The contract shall be quoted as a contract with additive Options. The price for all work required for the Base Contract and each Option shall be included in the respective line item. All incidental work shall be included under the bid item to which it most closely pertains. No other payments will be made. A Price Breakout Schedule is included and needs to be completed.

Award of a contract does not guarantee that the Government will order all of the work listed from the Contractor.

Line item 1 is the Base; Line item 2 is an Option item and will be awarded at time of award subject to availability of funds.

5.2 Line Item Description:

Base Contract: The Base Contract includes all labor, supplies, materials, and equipment required to make foundation repairs, replace deteriorated logs, floor joists, and flooring in the living room, and to reinstall interior walls and windows of the Cunningham House as described below.

More specifically, Bid Item 1 includes all supplies, materials, labor, equipment, and overhead costs necessary to complete the work described below and shown on the plan drawings. This shall include, but not be limited to:

Performance and Payment Bonds, Accident Prevention Plans, Activity Hazard Analysis, Quality Control Plans, Work Plans, Environmental Protection Plans, Material Submittals, Overhead costs, Insurance costs, Project Meetings, Temporary Facilities, Closeout Submittals, Environmental Protection Measures, etc., as well as performing the following repairs to the Cunningham House as described below:

Removal of Inside Walls, Window, and Bracing Porch

In order to view the logs and sills that may be deteriorated, interior wall boards shall be removed in the area around the South and West side of the living room in the area that will be repaired. They shall be removed to a height of at least 3’. Boards shall be numbered to enable them to be replaced in the same place they were removed from. Care shall be taken to remove the boards so they can later be reinstalled.

The window sashes shall be removed from the area to be repaired. Care shall be taken to remove the sashes so they can later be reinstalled.

The porch roof shall be braced to secure the roof while the building repairs are made.

Foundation

Under the floor of the living room in the existing structure, on the Southwest corner, the Contractor shall remove loose soil so that there is at least 16 inches of clearance between the earth and any wooden building components.

In order to support the building temporarily, the Contractor shall place cribbing under all beams and log walls under the living room. If any sections of the sill have settled so they are not level with other sills under the room, the Contractor shall jack the corner up that has sunk so it is level with the sills in the rest of the building. Care shall be taken to brace any walls so there is no chance that a log could shift. Any jacking shall be done professionally using methods common to the trade.

Where the soil has settled under the room where load-bearing supports touch the ground, the Contractor shall install a concrete footing under any affected sections of the foundation. The proper height for the top of the foundation shall be determined, and then any rocks from the existing pier shall be removed. Dirt shall be excavated where the footing will be placed. Half inch rebar shall be placed in any areas where the bearing soil is unstable. The footing shall be at least 12” thick and 24” wide, and the length shall be determined by the length of the area that will be repaired and will need to be supported. Three #4 rebars shall be installed in footer. Rebar shall be evenly spaced and no closer than 1 inch from any edge, with #3 ties installed 24” center to center. If necessary, the pad shall be made larger so it extends at least six inches on all sides past the edge of any support piers or foundation parts. The bottom of the footing shall rest below the frost line. Concrete blocks (8”x8”x16”) shall form new piers that extend to the height of the levelled logs and support beams. Cores of blocks shall be filled with concrete. J bolts shall be installed 48” center to center to be used to anchor a white oak timber that shall be installed over the blocks and under the log wall. On the top of this oak timber, a galvanized shield shall be installed. This shield shall not be visible from outside the building. The rows of blocks that support the joist beams shall have a 2”x8” ACQ treated plate installed, with a galvanized shield between the wood and the blocks. This plate shall be secured to the blocks using ¼” timber screws suitable for use with ACQ treated wood. Care shall be taken to assure the height is correct so that once installed, the new floor is the same height as the floor that was removed. Any surfaces of the blocks that will be visible outside after the repairs are complete shall be veneered with rocks / mortar that match the rest of the stonework on the building.

Sills

Square-hewn beams lay on top of the foundation. These sills support the entire building, including the first-floor joists, the door bucks, and the end logs.

These sills shall be removed in the deteriorated section, and supports shall be made using 8” x 8” x 16” concrete blocks topped with ACQ Pressure Treated 2” x 8” lumber. A metal shield shall be inserted between the masonry and wood. Wooden shims may need to be used to fill any gaps.

Once the above repairs have been made, all temporary supports and temporary beams shall be removed.

Wall Logs

Detailed information on this process may be found at: https://www.nps.gov/tps/how-to-preserve/briefs/26-log-buildings.htm.

Repairing or replacing only a segment of a log is not always possible. Replacement of an entire log may be the only solution if it has been substantially lost to decay and collapsed under the weight of logs above it. Log replacement is begun by temporarily supporting the logs above, and then jacking them up just enough to insert the new log.

Potential danger to the structure may include creating inadequate temporary bearing points, and crushing chinking and interior finishes which may have settled slowly into non-original positions that cannot withstand jacking.

There are two ways to lift a log wall. The first involves passing steel plates through the wall from outside to inside, just above the log to be replaced. The building is then lifted by positioning a jack under each end of the plate inside and outside of the building. The drawback to this method is that the log cannot simply be rolled out of the way. T must be removed by pulling it out by one end.

The second method of l ifting a log wall is cribbing – sandwiching the wall b e tween a series of vertical lumber supports, or cribs, that are secured through the wall with threaded rods, washers and nuts and then "snugged" to hold the logs tight. Jacks are placed under the cribs and the wall section is lifted until the rotten log is freed and rolled out of position.

To begin the process of log replacement, the entire length of the log must be inspected from the exterior and the interior of the structure to determine whether it supports any structural members or features, and how their load can be taken up by bracing during jacking and removal.

On the exterior, sheathing such as weatherboard, and adjacent chinking, must be removed along the length of the log to perform this inspection. Likewise, on the interior, abutting partition walls and plaster may also need to be removed around the log to determine what, if any, features are supported by or tied into the log to be removed.

If only a section of a log needs replaced, all the deteriorated wood shall be removed. This will leave a rectangular cavity. The cavity shall be measured, and a new replacement piece shall be constructed using ACQ Pressure Treated 2” lumber nailed together with nails rated for use with ACQ wood rated for ground contact to make a log sized similar to the existing log.

If large sections of a log have rotted, the log has lost its structural integrity, and is no longer able to bear its load, the Contractor shall replace it in its entirely. The entire affected wall, as well as part of the second floor and the room, must be temporarily supported while repairs are made. The area shall be jacked up to bear the joists. Care shall be taken to brace any walls so there is no chance that a log could shift, causing the structure to collapse. After the wall is raised, the old log shall be removed. A new log shall be constructed using ACQ Pressure Treated 2” lumber rated for ground contact nailed together with nails rated for use with ACQ wood to make a log sized similar to the existing log. A correct fit often requires a bit of fine tuning. It is not uncommon to raise and lower a wall section several times, or even to remove the replacement log for adjustment and reinstallation.

Floor Joists

Floor joist beams were typically trees approximately 6” to 12” in diameter. These timbers had half lapped joints at each end that allowed them to rest solidly on the sills. The sleepers were not fastened to the sills; gravity and the flooring boards were nailed to them to keep them in place.

New “sister” floor joist beams shall be constructed using ACQ Pressure Treated 2” x 12” lumber rated for ground contact on each side of the log joist. These 2” x 12” boards shall be bolted with ¾” bolts rated for use with ACQ wood to the log joists by drilling through the 2” x 12” lumber and the log joist. One bolt shall join all three pieces together. These bolts shall be spaced 32” center to center. If a log section is missing, wood blocks shall be placed in the spaces. The beams shall be notched to fit over the blocks / plate and shall be placed and spaced 24 inches apart. Care shall be taken to assure the height is correct so that once installed, the new floor is the same height as the floor that was removed.

Once the joist beams are placed and the dirt is leveled, a vapor barrier at least 6 mil thick shall be placed over all exposed dirt under the joists. All edges shall be sealed to the wall liner with tape, and also sealed to the wall liner at all piers.

Treatment

The Contractor shall apply borate salts at a 3:1 ratio, properly diluted for initial application. This shall be used to thoroughly saturate all log joist beams, sill beams, and lower logs that are accessible.

Flooring

If the previously-removed flooring is reusable, it shall be reinstalled professionally. If it is not reusable, the Contractor shall obtain flooring to match existing flooring in the building. New flooring shall be attached using the same method as other flooring in the building. Once complete, it shall not be detectible what areas have new flooring vs. original flooring. Any trim shall be replaced to match existing trim in the building and shall be attached with fasteners to match existing trim.

Replacement of Interior Walls and Windows

All interior walls that were previously removed shall be re-installed to exactly match surrounding interior walls. If necessary to patch holes, a waterproof patch shall be used. Surfaces shall be painted to match adjacent siding / interior walls. Windows shall be reinstalled and adjusted so they work properly. Bracing shall be removed from the porch, it shall be levelled, and porch foundation stones shall be replaced.

Cleanup

The Contractor shall clean the work area at the end of each workday. Upon completion of the repairs, the Contractor shall clean all debris and waste resulting from the repair operations and restore all surfaces, structures, and property in accordance with the attached plans, or to its original condition, to the satisfaction of the Government representative. All waste materials shall be disposed at an approved landfill facility.

Option 1: The delineation of Option 1 is described hereafter. Option 1 includes labor, supplies, materials, and equipment required to straighten the chimney on the west end of the Cunningham House, install gutters on the Cunningham House, and rebuild the Cat and Clay section of the chimney on the Johnson House.

More specifically, Option 1 includes all supplies, materials, labor, equipment, and overhead costs necessary to complete the work described below and shown on the plan drawings. This shall include, but not be limited to: Any incremental increase in the cost of Performance and Payment Bonds, Accident Prevention Plans, Activity Hazard Analysis, Quality Control Plans, Work Plans, Environmental Protection Plans, Material Submittals, Overhead costs, Insurance costs, Project Meetings, Temporary Facilities, Closeout Submittals, Environmental Protection Measures, etc., as well as performing the following repairs to the Cunningham House and Johnson House as described below:

Straightening Chimney

The cut stone chimney on the West side of the Cunningham House has settled. This chimney shall be moved so the base is level. Using the methods described above, brace, jack, and crib the chimney so it is secure. Care shall be taken to properly brace the chimney so nothing moves inadvertently. Once the chimney is properly braced, cribbed, and secured, excavate under a small section of the chimney and install a footing down to the frostline. Allow the concrete to cure, and excavate under another section. Continue excavating and pouring the footing in small sections until the chimney has a continuous concrete footing under the entire chimney to adequately support the rocks. Once the footing has properly cured, remove all bracing.

Installation of Gutters

In accordance with the attached drawing, install 5” half round galvanized gutters and downspouts with a minimum steel thickness 24 gauge, with appropriate galvanized tie-ins, connectors, elbows, mounting brackets, etc.

Guttering, downspouts, and all associated parts shall be galvanized. All parts used shall be historically correct for and appropriate for use on a historic structure of this period. The guttering shall be installed in accordance with professional methods common to the trade and manufacturer’s instructions. Schedule 40 4” drains shall be connected to the downspouts and shall be routed to nearby drains. The plastic Schedule 40 drains shall not be visible in any location, and all connections shall appear to be historically correct.

Repair of Johnson House Chimney

The chimney on the Johnson House is a Cat and Clay chimney. Please see the pictures of the building and chimney in the drawings. This chimney has a stone base. Above the base is the Cat and Clay section. The Cat and Clay section of the chimney has deteriorated and must be re-done. This section is formed by cutting strips out of wood, and then daubing between the strips with clay chinking designed for use on log structures. The color shall be tan to match existing chinking on buildings on site. The chinking shall be a flexible, textured log home chinking that seals open gaps between wood and shall be pure acrylic that adheres to wood and stretches to maintain a tight seal by following wood movement. The chinking shall be installed in accordance with manufacturer’s instructions and using professional methods common to the historical preservation trade.

The Contractor shall carefully measure the existing chimney, record the measurements, and then disassemble the Cat and Clay section.

The chimney shall be reconstructed to be the same size and height as the removed chimney. The Contractor shall provide dry oak strips to reconstruct the chimney. Strips shall be cut the same size as existing deteriorated strips.

Before the strips are installed, the Contractor shall apply borate salts at a 3:1 ratio, properly diluted for initial application. This mixture shall be used to thoroughly saturate all surfaces of each strip.

Inside the Cat and Clay section is flue liners. These liners shall be re-used if possible and if they are in a good condition. If it is not feasible to save and re-use them, the Contractor shall provide new liners and install them properly so they are sealed to the fireplace below and each liner is properly sealed together. The flue liner shall not be visible where it exits the chimney, and the area between the liner and the Cat and Clay chimney shall be properly sealed to keep rain or snow from entering the space between the liner and the chimney.

Once the frame is constructed, acrylic chinking shall be used to fill the voids between the strips. Care shall be taken to keep the acrylic chinking from covering the exposed faces of the strips.

Cleanup

The Contractor shall clean the work area at the end of each workday. Upon completion of the repairs, the Contractor shall clean all debris and waste resulting from the repair operations and restore all surfaces, structures, and property in accordance with the attached plans, or to its original condition, to the satisfaction of the Government representative. All waste materials shall be disposed at an approved landfill facility.

6.0 SPECIAL CONTRACT REQUIREMENTS

6.1 Site Visit: Offerors are highly encouraged to make a site visit prior to quoting to ascertain the complete requirements of the contract. Offerors shall contact the following before coming on- site:

Richard K. Pingley – Resource Manager / On-Site Government Representative William R. Pierson – Maintenance Leader

U.S. Army Corps of Engineers Burnsville Lake Project Office 2550 South Main Street Burnsville, WV 26335 Telephone: 304-853-2371

6.2 Hours of Operation

a. The Contractor shall perform all work during the following hours: Monday through Friday, 0700-1530 Eastern Time (ET), except Federal holidays. Contractor shall submit work schedule to Resource Manager two (2) weeks prior to work activities for review and approval.

b. Federal Holidays: When one of the designated holidays falls on a Sunday the following Monday is observed as a legal holiday. When a legal holiday falls on a Saturday, the preceding Friday is observed as a holiday.

Work that interferes with other ongoing functions at the project shall be scheduled around normal working hours to be approved by Project Manager. Work shall be scheduled around the Federal holidays listed below unless approved in advance. Eleven Federal holidays observed are as follows:

New Year’s Day (January 1st) Martin Luther King Day (3rd Monday in January) President’s Day (3rd Monday in February) Memorial Day (Last Monday in May) Juneteenth (June 19th) Independence Day (July 4th) Labor Day (1st Monday in September) Columbus Day (2nd Monday in October) Veterans Day (November 11th) Thanksgiving Day (4th Thursday in November) Christmas Day (December 25th)

6.3 Contractor's Responsibilities: The Contractor shall be held responsible for any and all damages attributable to the actions of the Contractor or its subContractors outside the limits of construction, shown on the drawings or designated by the Contracting Officer. This shall include damage to existing roads, drainage structures, electrical or telephone facilities, pavement, and other structures and facilities. All such damage shall be repaired to the satisfaction of the Government or proper municipal or state authorities by the Contractor and at his expense.

6.4 Pre-Construction Conference: The Contractor shall attend a pre-construction conference prior to the initiation of any work at the site. The Contractor’s Accident Prevention Plan (APP) and Quality Control Plan (QCP) must be accepted prior to this meeting. The location of this meeting (construction site or office) will be determined after contract award.

6.5 Veterans Employment Emphasis for U.S. Army Corps of Engineers (COE) Contracts:

In addition to complying with the requirements outlined in FAR Part 22.13, FAR Provision 52.222-38, FAR Clause 52.222-35, FAR Clause 52.222-37, DFARS 222.13 and Department of Labor regulations, U.S. Army Corps of Engineers (USACE) Contractors and subContractors at all tiers are encouraged to promote the training and employment of U.S. veterans while performing under a USACE contract. While no set-aside, evaluation preference, or incentive applies to the solicitation or performance under the resultant contract, USACE Contractors are encouraged to seek out highly qualified veterans to perform services under this contract. The following resources are available to assist USACE Contractors in their outreach efforts:

U.S. Department of Labor Veterans’ Employment and Training Service (VETS):

https://www.dol.gov/vets/Federal

Veteran Employment Information: https://www.fedshirevets.gov/ Veterans Opportunity to Work (VOW) Program: https://www.benefits.va.gov/vow/ U.S. Army Warrior Transition Command Employment Index:

https://wct.army.mil/modules/employers/index.html Hiring Our Heroes: https://www.uschamberfoundation.org/hiring-our-heroes

7.1 SECURITY REQUIREMENTS

SECURITY REQUIREMENTS

All Contractors and subcontractor employee(s) working on this contract who require access in and/or around any Huntington District facilities shall receive authorization to be on site at these facilities based upon a favorable background investigation in accordance with “Homeland Security Presidential Directive 12: Policy for a Common Identification Standard for Federal Employees and Contractors” (HSPD 12). The Huntington District Security Management Office shall submit contractor(s) personal information to complete the basic background investigation in order to make a recommendation to the Contracting Office of an employee’s suitability for work on Government property. The Procuring Contracting Officer (PCO) has the right to deny any contractor or subcontractor employee from working on the contract based upon the results of the background investigation provided by the Huntington District Security Management Office. The Government, Contractor, and subcontractors shall not permit any employee(s) access to drawings, blueprints, records, photos, sites, or projects until the Huntington District Security Management Office has completed an Operations Security (OPSEC) review of such items and determined they can be released.

FOR ALL CONTRACTS 1-YEAR AND SUBSEQUENT OPTION YEARS:

Contractors shall submit a complete investigation packet for each contractor and subcontractor employee to the Huntington District Security Management office within 10 working days after award of any contract, or prior to the individual being permitted unescorted access in or on District facilities.

The Contractor must also provide the following: (1) Name of the Contract Specialist with whom he/she is working,

(2) Project Name, (3) Contract Number (4) Task Order Number when applicable, and (5) Security Information sheet on each employee working on site must be submitted directly to the Huntington District Security Office.

The Contractor must provide a full legal name, complete SSN#, Date of Birth, Place of Birth (City and State) and Driver’s license number if available. It is the Contractor’s responsibility to ensure the above information is accurate and legible, otherwise delays may occur.

Contractors shall have background checks completed for their employees annually in the case of Contracts with option periods. For instance, if the employee was cleared in May of 2018, they shall be cleared again in May of 2019. It is the Contractor’s responsibility to ensure that each employee’s security is up to date. Failure to comply may lead to possible removal from the project/jobsite.

The Contractor must ensure if new employees are brought in to work on an existing Contract with the U.S. Army Corps of Engineers (USACE), they must process the employee through the Huntington District USACE Security Management Office for background purposes.

FOR CONTRACTORS REQUIRING DOD COMMON ACCESS CARDS (CAC)

The documents listed below are required:

SF 85, Questionnaire for Non-Sensitive Positions (see http://www.opm.gov/forms/ to print form). FD 258, Contractor Fingerprint Card (one card for digital prints, two for ink prints) (NOTE: a trained/qualified individual must take prints, ORI block on the FD 258 must be USOPM000Z) (Contractor Fingerprint Cards (FD-258) may be obtained by Contracting Division by contacting the Huntington District Security Management Office).

Contractor shall report any changes in personnel, or at any time conditions change at least 5 working days prior to individual(s) need to have access to the site. The Contractor shall provide the same information as listed above for all new employees.

Following submission of paperwork, the Huntington District Security Management Office will conduct an initial criminal check based upon the information provided. If there are no issues, the Huntington District Security Management Office will make recommendations to the PCO or their Designated Representative. The Huntington District Security Management Office cannot give approval due to unfavorable report(s). The Huntington District Security Management Office shall coordinate with Office of Counsel and will jointly make recommendations to the PCO and/or the Designated Representative should a background investigation come back with derogatory information. The PCO will make the determination whether to allow the Contractor personnel to work on the site based on Security and Office of Counsel recommendations, and the PCO will advise the Contractor of the decision.

FOREIGN NATIONALS

The Contractor shall provide the package listed above, as well as additional materials noted below for all Foreign Nationals. The Contractor is to expect additional time in the approval process for all Foreign Nationals due to the level of review and elevation of the review to Headquarters staff to complete. All Foreign Nationals must comply with the following paragraph:

In accordance with Engineering Regulation 380-1-18, “Technology Transfer, Disclosure of Information and Contacts with Foreign Representatives” dated 1 August 1996, Section 4, all foreign nationals who work on Corps of Engineers’ contracts shall be approved by the Headquarters US Army Corps of Engineers (HQ USACE) Foreign Disclosure Officer before beginning work on this contract; this regulation includes subcontractor employees. The Contractor shall submit to the Security Management Office, the names of all foreign nationals proposed for performance under this contract, along with documentation to verify legal admittance into the United States. Such documentation shall include at least one of the following: a U.S. passport, Certificate of U.S. Citizenship (INS Form N-560 or N-561), Certificate of Naturalization (INS Form N-550 or N-570), Alien Registration Card with photograph (INS Form I-151 or I-551), Employment Authorization Card (INS Form I-688A), etc.

In order to assure forms are properly completed, and to minimize time delays, the Contractor is encouraged to work closely with the Huntington District Security Management Office. The Government will return for correction incomplete forms, illegible forms, etc. which will delay the contractor / subcontractor from beginning work.

Security requirements are subject to change in accordance with HSPD-12, Office of Personnel Management, regulation or policy changes, etc. The Government shall add any changes to security requirements by modification to the contract.

The Contractor shall contact the Huntington District Security Management Office by phone, letter, or email at the following numbers/addresses:

CELRH-SM

502 Eighth Street Huntington, WV 25701

Stephen R. Curry, phone (304) 399-5695; email stephen.r.curry@usace.army.mil Matthew D. Green, phone (304) 399-5294; email matthew.d.green@usace.army.mil Scott E. Grandon, phone (304) 399-5661; email scott.e.grandon@usace.army.mil

7.2 AT/OPSEC Requirements: The following shall be accomplished by the Contractor within the timeframes established below for each requirement:

General security requirements and guidance: The security requirements described below apply to all contract personnel (including employees of the prime Contractor (“Contractor”) and all subcontractor employees) supporting the performance requirements of this contract. The Contractor is responsible for compliance with these security requirements. Questions regarding security matters shall be addressed to the designated Government representative (e.g., Contracting Officer Representative (COR), Requiring Activity (RA) representative, or Contracting Officer (if a COR or other RA representative is not appointed)). Contract personnel are critical to the overall security and safety of US Army Corps of Engineers (USACE) installations, facilities and activities, and security awareness training contributes to those efforts. The Department of Defense (DoD) and Army security training requirements specified below, if applicable, are performance requirements; all applicable contract personnel shall complete initial training within 30 days of contract award or the date new contract personnel begin performance on the contract. Within five business days from the completion of training, the Contractor shall provide written documentation (e.g., email or memorandum) to the Government representative. The documentation shall include the names of contract personnel trained and which training they completed; the Contractor shall maintain training records as part of their contract files and be prepared to provide copies of training certificates to the Government representative. Contractor personnel and vehicles are subject to search when entering federal installations. Additionally, all contract personnel shall comply with Force Protection Condition (FPCON) measures, Random Antiterrorism Measures (commonly referred to as “RAMs”), and Health Protection Condition (HPCON) measures. The Contractor is responsible for meeting performance requirements during elevated FPCON and/or HPCON levels in accordance with applicable RA plans and procedures—this includes identifying mission essential and non-mission essential personnel. In addition to the changes otherwise authorized by the changes clause of this contract, should the FPCON or HPCON levels at any individual facility or installation change, the Government may implement security changes that affect contract personnel. The Contractor shall ensure all contract personnel are aware of their security responsibilities, including any site-specific requirements identified in local policies or procedures.

Antiterrorism (AT) Level I training: All contract personnel requiring routine access to Army installations, facilities, and controlled access areas, or requiring network access shall complete initial and annual refresher AT Level I awareness training. Online AT Level I awareness training is available at https://jko.jten.mil/ (website subject to change).

Physical security and access control requirements: All contract personnel requiring physical access to a federal installation or facility shall comply with the access control procedures of that location. Contract personnel requiring unescorted access to meet contract performance requirements on a DoD installation in the US shall be vetted by the installation/facility Provost Marshal/Directorate of Emergency Services/Security Office using the National Crime Information Center-Interstate Identification Index (commonly referred to as “NCIC-III”) and Terrorist Screening Database (commonly referred to as “TSDB”). Contract personnel shall comply with all personal identity verification requirements specified in installation/facility policies and procedures. Contract personnel who do not meet requirements for unescorted access to USACE facilities shall coordinate escorted access with the Government representative, as needed. Contract personnel who receive keys, access cards, or lock combinations that provide access to government-owned property shall comply with key and lock control procedures of the RA.

Suspicious Activity Reporting training (e.g. iWATCH, CorpsWatch, or See Something, Say Something): All contract personnel shall receive initial and annual refresher training from the RA representative on the local suspicious activity reporting program. This locally developed training provides contract personnel with general information on suspicious behavior, and guidance on reporting suspicious activity to the project manager, security representative or law enforcement entity.

Contracts requiring a formal OPSEC program: The Contractor shall develop an OPSEC SOP/Plan within 90 days of contract award. The OPSEC SOP/Plan shall be reviewed and accepted by the RA OPSEC Officer. This plan will include a process to identify critical information, where it is located, who is responsible for it, how to protect it, and why it needs to be protected.