B.08.02 Section 011010_Att#8_SOW_07APR2022.pdf
PDF 380 KB Posted
- Attached to
- Skriveri Nursing Home Renovation: Latvia
- Solicitation number
- W912GB22R0025
- Issued by
-
Department of the Army European Command
About this file
This is a solicitation announcement for a design-build construction contract. The U.S. Army Corps of Engineers Europe District is soliciting proposals to complete the 100% design and construction of renovations to the Skriveri Nursing Home located in Skriveri, Latvia. Offerors must attend a mandatory site visit on May 11, 2022 and submit both price and non-price proposals by the deadline specified in the solicitation. Eligible offerors must be registered in the System for Award Management. The project involves demolishing two existing buildings and constructing a new single-story nursing home to accommodate up to 16 residents. The scope of work includes architectural, structural, civil, mechanical and electrical engineering design and construction services.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Army Corps of Engineers Europe District
APO AE 09049
lt20
Statement of Work Project Number:
Proj. No.: IEU-22-0011 Fiscal Year: 2022
Nursing Home Construction Skriveri, Latvia
Prepared by:
Design Section
Engineering Branch
07APR2022
01 10 10 Statement of Work Nursing Home Construction - Skriveri, Latvia
7-Apr-22 Page 2 of 57
SECTION 01 10 10
STATEMENT OF WORK
SECTION TABLE OF CONTENTS:
1 GENERAL
2 CIVIL AND GEOTECHNICAL
3 ARCHITECTURAL
4 STRUCTURAL
5 ELECTRICAL & COMMUNICATIONS
6 MECHANICAL & PLUMBING
7 FIRE PROTECTION (covered in other sections)
ATTACHMENTS
Attachment # 1 Location Map Attachment # 2 Conceptual Site Plan Attachment # 3 Conceptual Architecture Drawings Attachment # 4 Structural Calculations Guideline Attachment # 5 Utility Map Attachment # 6 Dedication Plaque
1.0 GENERAL
1.1 PROJECT DESCRIPTION
The Request for Proposal (RFP) provides parameters for a design-build project for the demolition of two small housing units and the construction of a facility in Skriveri, Latvia; Latitude 56°37'21.8"N, Longitude 25° 04'05.8"E (Refer to the attached Location Map.)
Demolish existing Nursing Homes #6 and #7 and construct a new single-story, concrete masonry building with sloped roof that will serve as nursing Home for up to sixteen (16) people. The new Nursing Home will assist senior citizens and provide sixteen single bedrooms, one bedroom must be designed to be wheelchair accessible IAW Host Nation Codes and Requirements. A group of four (4) bedrooms will form a unit that will share a bathroom, a toilet room, and a common room with kitchenette.
The project includes the following general items of work, detailed requirements are contained elsewhere in this Statement of Work:
a. Demolish buildings #6 and #7
b. Clear, grub, and grade the site
c. Construct new Nursing Home (for up to 16 people)
d. Provide site improvements including walkways to each unit
1.2 GENERAL REQUIREMENTS
The Contractor must deliver fully functional, turnkey type facilities (without mobile furniture) as described in this document. The work includes - but is not limited to - design, demolition, fabrication, delivery, installation, construction, and site work.
The facility in this project must be complete and usable to meet codes and technical and functional requirements per this Statement of Work (SOW). The proposal price must include all design, calculations, approvals, certificates, fees, labor, material, equipment, direct overhead, indirect overhead, general and administrative expenses (G&A) and general conditions to complete this project as described in the SOW.
7-Apr-22 Page 3 of 57
These design and product requirements are minimum requisites. Compliance with the provisions of this section by subcontractors is the responsibility of the Contractor.
1.2.1 BASE ITEMS AND OPTIONAL ITEMS
This Statement of Work addresses the technical requirements necessary to complete all work associated with this project. For information and requirements regarding the allocation of pricing between elements of the work, refer to Specification Section 01 22 00 PRICE AND PAYMENT PROCEDURES. The Schedule of Items identifies the breakdown between the individual base items and optional items for all work identified in this Statement of Work, associated drawings, and attachments. All work as described in these documents is included in either the Base or Optional Items. Consider all items not specifically identified in the Optional Items as part of the Base Items.
1.3 FUNCTIONAL AREAS
Refer to the attached drawings for a depiction of the required functional areas and spatial adjacencies for the site and new facilities/structures.
Provide the following functional areas within the facility:
1.3.1 GROUND FLOOR
Room Number Room Name Notes Approximate
Net Area (sqm)
General Spaces 104 Entry 4.00 105 Lobby Including Elect distribution panel 9.20 106 Utility 8.40
Unit 1 Hallway 1 17.60 Common Room
Unit 1 Including small kitchenette (no stove)
18.30
Bathroom 1 6.10 Toilet 2.60 Bedroom 1.1 12.60 Bedroom 1.2 12.70 Bedroom 1.3 12.70 Bedroom 1.4 12.60
Unit 2 Hallway 2 With exit door or separate entrance door 17.60
Common Room Unit 2
Including small kitchenette (no stove)
18.20
Bathroom 2 6.10 Toilet 2.60 Bedroom 2.1 12.60 Bedroom 2.2 12.70 Bedroom 2.3 12.70 Bedroom 2.4 12.30
Unit 3 Hallway 3 With exit door or separate entrance door 18.10
7-Apr-22 Page 4 of 57
Common Room Unit 3
Including small kitchenette (no stove)
18.00
Bathroom 3 6.00 Toilet 2.60 Bedroom 3.1 12.60 Bedroom 3.2 12.70 Bedroom 3.3 12.70 Bedroom 3.4 12.60
Unit 4 Hallway 4 With exit door or separate entrance door 18.00
Common Room Unit 4
Including small kitchenette (no stove)
17.90
Bathroom 4 6.00 Toilet 2.60 Bedroom 4.1 12.60 Bedroom 4.2 12.70 Bedroom 4.3 12.70 Bedroom 4.4 12.30
Total usable net area: 401.50 m2 (approximately 477.60 m2 gross area)
1.4 SUBMITTALS
Designer of Record approval is required for submittals with a “DA” designation.
Government approval is required for submittals with a “G” or “GA” designation.
Submittals having an “FIO” designation are for Contractor Quality Control approval. Submit the following to the Contracting Officer (KO) in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Demolition Plan; G
SD-05 Design Data
65% Pre-Final Design; DA/GA
95% Final Design; DA/GA
100% Corrected Final Design; DA/GA
SD-06 Test Reports
Test Results and Reports; FIO
1.4.1 DESIGN SUBMITTALS
Provide a complete design package at each milestone, as described in RFP Section 01 33 16-DESIGN AFTER AWARD. The milestones for this project are indicated above in Section 1.4 SUBMITTALS. The specific requirements of each milestone are described in each discipline-specific section of this Specification.
1.4.2 TEST REPORTS
Provide all test results and reports identified in this SOW to the Government as a submittal in accordance with RFP Section 01 33 00-SUBMITTAL PROCEDURES. Submittals will be considered for information only (FIO) submittals unless specifically
7-Apr-22 Page 5 of 57 identified as a submittal requiring government approval. Coordinate with the KO after award for the specific items to be included in the submittal register.
1.5 MATERIALS AND EQUIPMENT
Materials and products used must be durable, heavy duty, industry standard. The equipment must be the manufacturer’s standard quality and must be compatible with all other equipment and materials within the system or assembly. Equipment and materials must include all connections and accessories necessary to ensure operability and correct installation according to manufacturer’s requirements.
Provide a nameplate secured to each major piece of equipment. Each nameplate must have the manufacturer’s name, address, contact information, type or style, model or serial number, and catalog number. The definition of a “major piece of equipment” is at the discretion of the KO.
1.5.1 LIFE-SPAN
The facility and the installed equipment must be permanent construction with an expected lifespan of more than 25 years.
1.5.2 MAINTAINABILITY
Provide low maintenance materials and systems appropriate for the project climate and location.
1.5.3 OPERABILITY
Systems (including but not limited to architectural, electrical, communications, and mechanical systems) must be simple to operate and easy to maintain.
1.5.4 STANDARDIZATION
Provide standardized materials, products, equipment, and systems to minimize the requirements for replacement parts, storage facilities, and service requirements.
1.6 DESIGN DIMENSIONS
Develop the design using the metric system.
1.7 DESIGN CRITERIA
Project design, site facilities, utility systems and material standards must be in accordance with Host Nation building codes (current versions as of the date of RFP, unless otherwise indicated). In the absence of Host Nation building codes, use the International Building Code (IBC) and the codes, technical standards, and regulations referenced in this RFP.
While this RFP references various source standards and specifications, all design documents must meet Host Nation codes and requirements. It is the designer's responsibility to demonstrate that the Host Nation standard is equal to the cited standard or specifications being supplanted. Apply the more restrictive standards when conflicts arise between the requirements of this RFP and any referenced or other applicable codes, standards or regulations. If equivalency cannot be met, use the more stringent requirement and quote both codes verbatim in correspondence to the KO. The designer is responsible to determine the required material and execution standards where specific standards are not indicated.
Provide an electronic copy of the local Host Nation standards and building codes in their original language as related to facility design and construction.
1.8 SPECIAL CONSTRUCTION REQUIREMENTS
1.8.1 DEMOLITION
The Contractor is responsible for all required demolition as indicated in this scope.
7-Apr-22 Page 6 of 57
Submit a Demolition Plan to be tracked via the submittal register indicating all demolition, abatement, and disposal methods.
1.8.1.1 ABATEMENT AND DISPOSAL
All demolished materials, including hazardous materials identified below, must be abated and disposed of in accordance with local laws, codes and regulations. The Contractor is responsible for all required testing before, during and after demolitions as well as for all required compliance with safety standards.
1.8.1.2 LOCATION OF HAZARDOUS MATERIAL
The Contractor is responsible to survey the site and determine if hazardous materials exist. If hazardous materials are found to exist, immediately notify the KO and provide the results of the relevant sampling and testing. Provide the hazardous material report no later than 30 days after Notice to Proceed (NTP) for information and approval.
END OF SECTION
7-Apr-22 Page 7 of 57
2.0 CIVIL AND GEOTECHNICAL
Provide and perform civil engineering design and construction services as required to provide a complete, accessible, functional, and usable project. The Contractor is required to extensively coordinate civil design and construction work with the scope of the other disciplines described in this SOW.
2.1 SCOPE SUMMARY
Civil works for this project include, but are not limited to, site survey, geotechnical investigation, site layout, demolition, earthwork, pavement, and outdoor furnishings. Refer to the bid schedule for which of these are base bid or optional.
2.2 EXISTING CONDITIONS
2.2.1 TOPOGRAPHY
There is no known topographic survey for the project site. The existing site contains buildings, pavement, utilities, fences, and vegetation as shown on the attached Conceptual Site Plan. The site generally slopes down 3% to the south and is level east to west. The existing information shown on the attached Conceptual Site Plan was compiled from as-builts, Google Earth, and site photos.
2.2.2 UTILITIES
Storm system consists of rainfall discharging from the existing building downspouts to the ground.
There is an existing 32 millimeter water connection located within 100 meters to the east of the existing buildings. New water pipes were installed to buildings 5, 6, and 7 in 2021.
There is an existing 40 millimeter central heating water line that was installed to buildings 5, 6, and 7 in 2021.
There is an existing sanitary system that serves buildings 5, 6, and 7. It is located behind building 7 and runs to the east. This sanitary sewer pipe is old but functioning.
Electrical power and communications are available on site. Refer to the other sections of this SOW for details of these existing utilities.
There are existing utilities connected to the buildings as shown on the attached Utility Map. Contractor must verify all utility locations (surface and subsurface) in the field prior to the first design submittal.
2.2.3 GEOTECHNICAL
There is no geotechnical information available for the project site.
2.2.4 ENVIRONMENTAL
There are no known environmental protection areas or archeological preservation areas on the project site.
There is no prior knowledge of any hazardous or contaminated materials in the site’s soil or pavement.
2.2.5 UNEXPLODED ORDNANCE (UXO)
There is no prior knowledge of UXO in the site’s soil.
2.2.6 EXISTING CONDITIONS INVESTIGATION
Prior to bid, investigate the general and local conditions which can affect the work and/or its cost, including but not limited to:
a. Weather, earthquakes, or similar physical conditions at the site.
7-Apr-22 Page 8 of 57
b. Surface and subsurface materials or obstacles to be encountered insofar as this information is reasonably ascertainable from an inspection of the site and due diligence research of as-built drawings, geotechnical reports, environmental reports, and publicly available information on the site.
c. Mobilization and staging constraints.
2.3 DESIGN SUBMITTALS
Provide civil design submittals in accordance with RFP Section 01 33 16-DESIGN AFTER AWARD and in compliance with SOW Section 1.0 – GENERAL.
35% Design Submittal:
a. Preliminary Design Analysis of civil features.
b. Final Site Survey (include in the Design Analysis).
c. Final Geotechnical Report (include in the Design Analysis).
d. Final Existing Conditions Plan.
e. Preliminary Demolition Plan
f. Preliminary Site Layout Plans - Indicate existing and proposed Civil features.
Include other disciplines’ features (faded back) that affect the Civil Design (buildings, mechanical structures, electrical utilities, etc.).
g. Preliminary Grading Plans, including contours, finish floor elevations, and retaining walls.
h. Preliminary Pavement Plans
i. Preliminary Utility Plans (Storm, Sanitary, and Water).
j. Preliminary Fencing and Outdoor Furnishings Plans
k. Preliminary Civil Specifications (Table of Contents only).
65% Design Submittal:
a. Update all items from the 35% Design Submittal to 65% (Pre-Final) Design.
Incorporate all 35% design comments.
b. Pre-Final Grading Profiles, Cross Sections, and Details. Include spot grades and slopes in Grading Plan. Include retaining wall profiles, cross sections, and details. Include erosion control design.
c. Pre-Final Pavement Profiles, Cross Sections, and Details
d. Pre-Final Utility (Storm, Sanitary, and Water) Profiles, Cross Sections, and
Details.
e. Pre-Final Fencing and Outdoor Furnishings Details
f. Pre-Final Landscape Plan and Details, including seed mix and seed coverage rate
g. Pre-Final Civil Specifications
95% Design Submittal:
Update all items from the 65% Design Submittal to 95% (Final) Design. Incorporate all design comments.
100% Submittal:
The 100% Submittal provides a complete and final set of contract documents ready for construction. Update all Final submittals from 95% to a corrected Final submittal. Address all previous government review comments before submitting.
As-Built Drawing Submittal:
In addition to the as-built requirements discussed in RFP Section 01 78 00- CLOSEOUT SUBMITTALS, provide a topographical survey of the site per requirements of SOW Section 2.6-SITE SURVEY. Include existing utility lines or structures (both modified and unmodified) encountered in the construction footprint that were not located on the original Site Survey.
2.3.1 DESIGN ANALYSIS
Submit a Design Analysis in accordance with RFP Section 01 33 16-DESIGN AFTER AWARD. Provide a Design Analysis for all Civil features that documents significant
7-Apr-22 Page 9 of 57 design choices and substantiates design compliance with contract requirements, applicable codes and standards. Documentation includes narrative, calculations, photographs, sketches, and catalog cut sheets. Reference all applicable regulations, standards, and criteria for the design. Reference sources are subject to Government approval. Provide design assumptions. For design choices, discuss alternative systems considered, and provide rationale for the selected alternative.
The Design Analysis includes but is not limited to:
a. Discussion of Site Layout constraints and design decisions, including but not limited to, land use, vehicle and pedestrian access, orientation of features on-site, setbacks from site features, minimizing utility lengths, minimizing earthwork and tree removal, and future expansion.
b. Discussion of Demolition constraints and design decisions. Include discussion on how access will be provided during construction, and how each utility will be maintained and operated during construction.
c. Discussion of Earthwork and Site Grading constraints and design decisions.
Provide cut and fill calculations. Provide retaining wall calculations.
Provide slope stability calculations for slopes steeper than 2H:1V or slopes supporting proposed structures. Include pertinent geotechnical information that affects earthwork.
d. Discussion of Storm system constraints and design decisions.
e. Discussion of Sanitary system constraints and design decisions. For each section of pipe, include analyses indicating pipe size, friction factor, length, elevations at each end of pipe, slope, design flow (Q), maximum flow capacity, design depth of flow, design percentage full, and design flow velocity. Provide calculations on the pipe’s structural capacity if the pipe is shallower than required in section 2.10-Utilities. Include pertinent geotechnical information that affects the sanitary system. Confirm that the existing receiving system has adequate capacity to receive the additional sanitary flow generated by the project.
f. Discussion of Water system constraints, design decisions and source. Provide calculations to demonstrate water system meets project requirements. Provide calculations on the pipe’s structural capacity if the pipe is shallower than required in section 2.10-Utilities.
g. Discussion of Pavement constraints and design decisions. Include pertinent geotechnical information that affects the pavement design.
h. Discussion of Outdoor Furnishings constraints and design decisions. Provide structural calculations for foundations if the foundation is designed by the Designer of Record. Calculations are not necessary if the foundation design is from an industry standard detail.
i. Discussion of Landscaping constraints and design decisions.
j. Site Survey as an appendix.
k. Geotechnical Investigation and Report as an appendix.
2.3.2 DESIGN DRAWINGS
Provide Civil design drawings of sufficient detail to address the requirements of each design submittal. Civil drawings include plans, profiles, cross sections, and details of Civil features for the project. Civil drawings also include temporary construction plans/methods that affect the design and construction of the project.
These temporary plans include mobilization, traffic control, erosion control, dewatering, shoring, construction sequence, etc. Design drawings include all necessary information (labeling, dimensioning, legend, details, notes, etc.) to allow for complete understanding and constructability of all proposed features.
Provide comprehensible differentiation between features that are proposed, existing, future, or proposed to be demolished by use of appropriate choice of line styles, line weights, and/or colors. Reference USACE A/E/C Graphics Standard for graphic requirements.
7-Apr-22 Page 10 of 57
2.3.3 SPECIFICATIONS
Provide Civil specifications of sufficient detail to address the requirements of each design submittal. Specifications, when combined with the design drawings, allow for complete understanding and constructability of all proposed Civil features.
2.4 DESIGN CRITERIA
Provide civil design in accordance with Host Nation codes. In the absence of Host Nation codes, use the latest release of the International Building Code (IBC) and the following codes and technical standards:
a. Uniform Facility Criteria (UFC) 3-201-01, Civil Engineering
b. UFC 3-220-01, Geotechnical Engineering
c. USACE A/E/C Graphics Standard (ERDC/ITL TR-12-1)
d. UFC 3-230-01, Water Storage, Distribution, and Transmission
e. UFC 3-240-01, Wastewater Collection
f. Architectural Barriers Act (ABA)
2.5 GEOTECHNICAL INVESTIGATION AND REPORT
Perform a geotechnical investigation and assessment of the project site to determine the subsurface conditions and geotechnical parameters for foundation, grading, and utility design. Perform the necessary amount of testing, borings and test pits at depths suitable for the project improvements. Include geotechnical investigation in areas where borrow material will be used. The Geotechnical work must be performed under the supervision of a professional geotechnical engineer registered with the jurisdiction having authority, and the report must be signed by the Geotechnical Engineer. In the absence of Host Nation codes, perform the geotechnical investigation and report per UFC 3-220-01, Geotechnical Engineering and IBC.
Coordinate testing locations with the KO to avoid impact to existing utilities and facility operations. Utility locates, permits, pavement removal and vegetation clearing is the Contractor’s responsibility. Repair disturbed areas with a concrete patch in paved areas, and compacted soil in non-paved areas. The repaired area must be flush with the adjacent surface. Following restoration, stake and flag each of the hole locations with boring identification numbers. In paved areas, use white paint on the paved surface to mark hole locations. Provide a map indicating the borehole and test pit locations.
2.5.1 REPORT
Include, as a minimum, the following information:
a. Description of field work completed and equipment used; names, signatures and stamps of licensed professionals involved; name of drilling company.
b. A description of site subsurface conditions, regional geology, and seismic conditions at the site.
c. Site map of borehole and test pit locations.
d. High resolution color digital photographs of each borehole and test pit location.
e. Test pit logs with classification of all subsurface materials. The logs must distinguish fill materials from native materials, include all in‐situ test results, and include groundwater depth information, if groundwater is encountered. Distinguish between bedrock and rock boulders.
f. Reports of all the field and laboratory testing.
g. Recommendations for allowable bearing capacity, expected settlement, type of foundation, minimum footing and grade beam dimensions, lateral earth pressure parameters, and minimum depth of foundation for footing and grade beams.
h. Recommendations for preparation, placement, and compaction of onsite soils, borrow material, soil replacement, soil amendment/treatment, structural fill, 7-Apr-22 Page 11 of 57 topsoil, and trench backfill. Include dewatering and temporary retaining structure needs.
i. Soil Resistivity.
j. Frost Depth.
k. Deep foundation information.
l. Recommendations for pavement design and construction.
m. Calculations to support conclusions and recommendations.
2.5.2 DESIGN DRAWINGS AND SPECIFICATIONS
On the design drawings and/or specifications, include geotechnical information that affect the design of the project, including but is not limited to, boring locations, boring logs, groundwater and frost depths, and any details that convey requirements for site preparation.
2.6 SITE SURVEY
Conduct and provide a topographic survey from a licensed surveyor that includes all existing site information needed to design and construct the project. Survey must be conducted prior to the first design submittal. Include x, y, and z coordinates to the nearest 0.005 meters, dimensions, material, and basic characteristics of all features within the project site limits, as well as all features outside of the project site limits that will affect the design and construction of the project. Research record drawings to obtain utility and pavement information that is not visible from the surface. Provide notes indicating the sources and any limitations or assumptions of the data. Provide a copy of the survey in CAD, in addition to the paper/electronic requirements of the Design Analysis. Locate and show on the topographic survey the following information:
a. Property boundary, public right of way, and easements. Include the address numbers, street names, and easement records.
b. Survey monuments. Include description.
c. Spot elevations covering the entire survey limits showing high points, low points, grade changes, and at sufficient intervals to represent the general character of the terrain.
d. Contours in intervals of 0.25 meters.
e. Buildings and other miscellaneous structures. Provide finish floor elevation.
f. Pavements. Include pavement type, thicknesses, joint patterns, and pavement markings. Include top of curb and gutter elevations.
g. Surface Drainage Features. Indicate normal water level for water bodies.
h. Utility lines and structures. Include rim elevations and invert elevations for utility structures; identification of lines as underground or aboveground;
pipe sizes and materials.
i. Fences. Include height, material, direction of outrigger, gate locations and types.
j. Signs. Include sign text.
k. Railroads.
l. Trees/Woods: In wooded areas that trees are to be protected, locate outside drip line of wooded area, include general density and type of trees. For wooded areas with proposed tree removal, identify trees per Host Nation permitting requirements. Where selective clearing will be proposed, locate trees over 150 millimeter diameter at chest height, and include tree species, diameter at chest height, and dripline diameter.
m. Geotechnical boring locations.
n. Locate environmentally sensitive areas (determined and marked by others).
o. North arrow and scale of drawing.
p. Legend depicting the symbols and abbreviations used on the drawing.
q. Horizontal and vertical coordinate systems, date of survey, licensed surveyor name and license number.
7-Apr-22 Page 12 of 57
Site information provided to the Contractor by the Government is not to be considered accurate Site Survey information. Utility field locates and as-built research are the responsibility of the Contractor.
Upon completion of construction, update the original survey with an As-built survey of the site as constructed, including underground utility locations and depths. Submit the As-built survey to the KO for approval.
Reference UFC 3-201-01, Civil Engineering, Section 2-2.2-SURVEYING for survey requirements. Use the Universal Transverse Mercator (UTM) coordinate system. State which vertical coordinate system will be used.
2.7 SITE LAYOUT
Locate the proposed building and other improvements as indicated on the attached Conceptual Site Plan. Amend the site layout as determined by the site-specific constraints, the owner’s preferences, accessibility, future expansion, and opportunities that are identified and evaluated as part of the Contractor’s scope of work. Locate the proposed building a minimum of 3 meters away from existing buildings. Locate the proposed building outside the dripline of existing trees.
Align the proposed building on the same axis as adjacent buildings and property lines.
The Contractor is responsible for all aspects of the project whether they are shown on the conceptual plan or not.
2.8 DEMOLITION
Remove existing structures, utilities within 3.0 m of proposed building foundation, pavement, vegetation, and any other features to construct the proposed improvements. Remove trees with driplines within the footprint of the proposed improvements. Provide straight, neat sawcuts at limits of pavement removal. All contaminated soils discovered require special testing and disposal per Host Nation requirements.
2.8.1 CONSTRUCTION LIMITS
Do not disturb the project site beyond necessary for installation of proposed construction. Do not disturb any areas past the site’s property line. Show demolition work and limits of disturbance in the drawings. Stake-out the limits of disturbance on-site with temporary fencing before beginning construction.
2.8.2 ITEMS TO REMAIN IN PLACE WITHIN CONSTRUCTION LIMITS
Take necessary precautions to avoid damage to existing items to remain in place, to be reused, or to remain the property of the Government. Repair or replace damaged items as required by the KO. Construct and maintain shoring, bracing, and supports as required. Ensure that structural elements are not overloaded. Provide new supports and reinforcement for existing construction weakened by demolition, deconstruction, or removal work. Repairs, reinforcement, or structural replacement require approval by the KO prior to performing said work.
2.8.3 TREES
Unless otherwise noted on the attached Conceptual Site plan, protect trees which might be damaged during construction, with a 1.8 meter high fence around the dripline of the tree(s), which is assumed to be the extent of the tree’s roots.
Trees are defined as larger than 150mm diameter at 1.3 meters above existing grade. Mitigate for tree removal per Host Nation requirements.
2.8.4 UTILITIES
Any existing utilities encountered that are impacted by this project must be protected, or relocated if protection is not feasible. Remove existing and abandoned utilities under or within 3.0 m of the foundation of any proposed https://en.wikipedia.org/wiki/Universal_Transverse_Mercator_coordinate_system https://en.wikipedia.org/wiki/Universal_Transverse_Mercator_coordinate_system
7-Apr-22 Page 13 of 57 facility or building foundation. Reroute existing utilities to remain in accordance with SOW Section 2.10-UTILITIES. Abandoned utilities must be removed up to the utility main (or next utility main junction) and capped. Manholes or underground structures to be abandoned must be removed to a minimum depth of 50 centimeters below finish grade. Fill abandoned manhole or structure per Section 2.9-EARTHWORK requirements.
2.8.5 DUST, DEBRIS, AND EROSION CONTROL
Prevent the spread of dust, debris, and erosion from the project site. Install erosion control measures before beginning construction. Sweep pavements as often as necessary to control the spread of debris. Do not use water if it results in hazardous or objectionable conditions such as, but not limited to, ice, flooding, erosion, or pollution. Remove snow, dust, dirt, and debris from work areas daily.
Remove and transport the debris in a manner that prevents spillage on streets or adjacent areas. Apply local regulations regarding hauling and disposal.
2.8.6 ADDITIONAL REQUIREMENTS
Reference RFP Section 00 74 01-SPECIAL CONDITIONS, and 01 30 01-GENERAL REQUIREMENTS for additional demolition, protection, and permitting requirements.
2.9 EARTHWORK
Perform all earth work necessary for the installation of the proposed improvements.
2.9.1 PLANS AND SPECIFICATIONS
Define earthwork requirements in the plans and specifications. Include requirements for satisfactory material, borrow material, structural fill, topsoil, utility trenches, replacement and improvement of on-site soils, soil compaction (for subgrades of structures, paving, and landscaped areas), compaction for utility trenches, maximum lift depths, density testing frequency, maximum temporary and permanent slopes, and engineered support systems. The earthwork requirements must not conflict with the recommendations in the Contractor-provided Geotechnical Report.
2.9.2 UNEXPLODED ORDNANCE (UXO) CLEARANCE
UXO survey is not required.
2.9.3 CONTAMINATED SOIL
Inspect and test all soil according to Host Nation requirements. If hazardous materials are discovered, cease excavation, secure the area, and notify the KO for further guidance.
2.9.4 CULTURAL RESOURCES
Cultural resources, such as archaeological remains, may be uncovered during excavation operations. If suspected cultural remains are found, cease excavation, secure the area, and notify the KO for further guidance.
2.9.5 TOPSOIL
Remove and save topsoil (approximately first 20 centimeters of excavation).
Separate out subsoil, brush, litter, weeds, roots, stones larger than 25 mm in diameter, and other materials that would interfere with planting and maintenance operations. When restoring the site to finish grade, place topsoil back in excavated areas that do not include proposed paving or structures.
2.9.6 SATISFACTORY MATERIAL
Excavated material (below topsoil), if satisfactory for reuse per the Contractor’s Geotechnical Engineer, may be used on the project site where fill is required.
Unsatisfactory material, and surplus excavated material not required for fill, must be disposed of offsite, and is the responsibility of the Contractor. Borrow
7-Apr-22 Page 14 of 57 material may be required for construction from sources off site. Borrow materials are to be free of hazardous materials and contaminants. Any soil brought in from off-site sources must be certified clean.
2.9.7 BACKFILL COMPACTION
In the absence of Host Nation requirements and geotechnical recommendations, fill and backfill must be placed in layers of 20 centimeters loose thickness and compacted to a minimum 95% of the maximum dry density as determined by Host Nation test method equivalent to ASTM D-1557 (Modified Proctor test). Provide density tests on all lifts at a frequency of 1 test per 40 square meters for foundations and parking, and 1 test per 30 meters of road and utility trench. Round up to nearest whole number (i.e. a 25 square meter foundation requires one test). The location of all tests must be selected by the Contractor’s geotechnical engineer, and copies of all test results must be furnished to the KO. All structure foundation excavations must be inspected and approved by the Contractor’s Geotechnical Engineer prior to placing concrete. Repair earthwork areas as recommended by the Contractor’s Geotechnical Engineer, and approved by the KO.
2.9.8 ENGINEERED SOIL SUPPORT SYSTEMS
Provide engineered soil support systems (i.e. shoring) as required for the construction of the proposed improvements. The Contractor is responsible for all dewatering necessary for earthwork.
2.9.9 SITE GRADING
Provide site grading that directs storm water runoff away from buildings and structures either by drainage systems or by grading as follows:
a. Finished grades of earth/grass/gravel surfaces adjacent to buildings and structures must slope away from all exterior edges with a minimum slope of 5% for the first 2 meters.
b. Finished grades of paved surfaces adjacent to buildings and structures must slope away from all exterior edges with a minimum slope of 2% for the first 2 meters.
c. Finished grades must not create stagnating water or ponding anywhere on the project site, nor create ponding on adjacent properties. Provide storm improvements if ponding is unavoidable.
d. In accordance with requirements of UFC 3-201-01, Chapter 2-8 Grading
e. Set finished floor elevations a minimum of 15 centimeters above finished grade at the perimeter of the building, with the exception of finished grade at entry points.
f. Set building finish floor elevations at a minimum of 30 centimeters above the local 100 year flood level.
Site grading around the building must meet Host Nation accessibility guidelines.
The Contractor must limit proposed landscape slopes to a maximum 4H:1V for grass areas requiring mowing and 2H:1V for non-grass areas, which require non-erodible surface (i.e. rock, shrubs with mulch).
2.10 UTILITIES
This section applies to all project underground utilities located outside the building, including but not limited to, sanitary sewer, water supply, electrical, communications, and heat. See Sections 5.0-ELECTRICAL & COMMUNICATIONS, Section 6.0-MECHANICAL, and Section 7.0-FIRE PROTECTION for additional utility requirements.
Proposed utility main alignments must be at least 3.0 meters from facility or building foundations, except for building connections. Provide horizontal and vertical separation between new and existing utilities for rehabilitation, maintenance, repair or replacement. Provide utility line depths, bedding, and
7-Apr-22 Page 15 of 57 backfill as required by applicable requirements and geotechnical recommendations.
Minimum cover over pipes is 0.6 meters; greater than frost penetration; or sufficient to support imposed dead and live loads for the pipe materials used;
whichever is more stringent. Place plastic warning tape along the route of the buried pipe after installation at a height of 0.3 meters above the pipe.
Coordinate all required installation, relocation, improvement and protection of utilities held by third party (e.g. public or private utility). This includes coordination of any work to be performed by the utility owner. Choice of materials and products for utility installation must be coordinated with the utility owner (customer or third party) to ensure proper integration and compliance with existing systems and allow for easy maintenance and repair of the utilities in the future.
Provide utility materials per IBC requirements. Provide corrosion protection for utilities that provides the minimum life expectancy specified in Section 1.0- GENERAL. Any piping or equipment exposed to sunlight must be coated with protective coatings suitable for UV exposure with a minimum expected coating life of 10 years before recoating.
2.10.1 STORM SYSTEM
Connect building downspouts to splash blocks that drain away from foundations a minimum of 2 meters. Utilize grading to direct runoff away from improvements, eliminate ponding, and prevent erosion.
2.10.2 SANITARY SYSTEM
Provide a connection from the proposed building to the existing sanitary system adjacent to the site as shown in the attached Conceptual Site Plan.
Allowable sanitary pipe materials include polyvinyl chloride (PVC), high density polyethylene (HDPE), or ductile iron. Sanitary structures must be concrete, with traffic rated cast iron or ductile iron frames and covers. In the absence of Host Nation standards, design the sanitary system per UFC 3-240-01, Wastewater Collection.
After installation, test sanitary lines and structures for leakage and deflection per local codes. Provide test results to the KO. Locate and repair any sections failing to pass the required tests. Repeat the specified tests and inspections on the repaired sections.
See SOW Section 6.0 – MECHANICAL for indoor sanitary scope.
2.10.3 WATER SYSTEM
Provide a connection from the proposed building to the site’s existing water system as shown in the attached Conceptual Site Plan and utility plan. Provide a meter at the water connection point that is accessible by a third party utility.
All new water distribution piping must have a minimum horizontal separation of 3 m from all new or existing gravity sanitary systems.
After installation, test water supply lines according to local codes for leakage.
Before the water supply line is put into final operation, disinfect the line, and then flush the line to remove traces of the sterilization agent. Test treated line for coliform bacteria. Provide test results to the KO. Locate and repair any sections failing to pass the required tests. Repeat the specified tests and inspections on the repaired sections.
See SOW Section 6.0 – MECHANICAL for indoor water scope.
7-Apr-22 Page 16 of 57
2.11 PAVEMENT
Proposed pavements for the project include:
a. Paving block pedestrian access to the building exterior doors. The path for the main entrance must be a minimum 5m wide and support delivery vehicles. The other pedestrian paths must be a minimum 2m wide.
b. PCC slabs for dumpsters, generators, transformers, HVAC systems and other proposed outdoor features that serve the proposed facility. Provide medium broom finish on PCC concrete.
c. Replace existing pavement sections where the trenching occurs for utility installation. Sawcut a minimum 30 centimeters beyond edge of trench.
In the absence of Host Nation standards, design pavements per UFC 3-201-01, Civil Engineering.
2.12 FENCE
No fence required in this project.
2.13 OUTDOOR FURNISHINGS
2.13.1 BOLLARDS
No bollards required.
2.13.2 SIGNS
Provide facility signage in accordance with Host Nation standards and matching other facility sign style. Size messages and graphics on signs according to the functional viewing distance. Typically, at least 25 millimeter of letter height per 7.62 meters of viewing distance is required for readability.
2.14 LANDSCAPING
Provide grass seed and 20 centimeters of topsoil on the site in areas that do not have pavement or a building within the limits of disturbance. Seeds must be locally sourced from a certified plant nursery, and native to the area. Provide seed coverage density per manufacturer/supplier’s recommendations. Provide watering, weeding, and any other necessary care to establish growth. Limit planting to times of the year per local codes and/or manufacturer/supplier’s recommendations. Replace topsoil and seeds, at Contractor’s expense, in areas which do not have new growth coverage of 75% before the warranty period ends.
Replace any trees removed according to Host Nation requirements.
2.15 MOBILIZATION / STAGING / PERMITS
Locate mobilization and staging to areas that do not disrupt operations at the facility. Reference RFP Section 00 74 01-SPECIAL CONDITIONS for other mobilization, access, and permit requirements.
7-Apr-22 Page 17 of 57
3.0 ARCHITECTURAL
3.1 PROJECT DESCRIPTION
Provide and perform architectural design and construction services to provide a complete, accessible, functional, and usable Nursing Home.
Demolish existing Nursing Homes #6 and #7 and construct a new single-story, concrete masonry building with sloped roof that will serve as nursing Home for up to sixteen (16) people. The new Nursing Home will assist senior citizens and provide sixteen single bedrooms. A group of four (4) bedrooms will form a unit that will share a bathroom, a toilet room, and a common room with kitchenette. One bedroom must be designed to be wheelchair accessible IAW Host Nation Codes and Requirements.
Extensive coordination is required between the architectural work and the work of other disciplines described in this SOW.
3.1.1 DESIGN
Provide a design and construction package that uses the space allocations, functional adjacencies, design details, and features given or referenced in this RFP. The design must incorporate all referenced codes and regulations. The Contractor is responsible for creating additional details as required to complete a full design. All details must conform to the requirements of this RFP and are subject to the approval of the KO. A schematic design has been attached for reference. The schematic plans are provided for diagrammatic purposes only and do not necessarily represent an approved floor plan or design. The Contractor is responsible for providing a design that meets all requirements of the User and the codes and criteria referenced in this Statement or Work.
3.1.2 DESIGN SUBMITTALS
Provide all architectural submittals after contract award in accordance with RFP Section 01 33 16-DESIGN AFTER AWARD and 01 33 00-SUBMITTAL PROCEDURES. Prepare and submit the documents listed below at the submittals indicated.
3.1.2.1 65% DESIGN SUBMISSION
Include the following drawings and reports as applicable to the project:
a. Code Summary – Provide a tabular code compliance summary indicating Host Nation or IBC life safety requirements for all new facilities.
b. Life Safety Plans – Provide plans depicting smoke/fire resistance ratings, egress routes, dead-end corridors, exits, and other aspects of life safety pertaining to the design.
c. Demolition Plans – Provide existing floor plans for existing buildings to be demolished, indicating all demolition required.
d. Floor Plans – Provide all floor plans, indicating room names, areas, and basic dimensions, scale 1:50.
e. Ceiling Plans – Provide reflected ceiling plans for all rooms, indicating ceiling materials and fixtures, scale 1:50.
f. Building Elevations – Provide all building elevations indicating all exterior materials.
g. Roof Plan – Provide a plan of all roof areas, indicating direction of slope and method of drainage.
h. Building Section – Indicate heights of critical building elements.
i. Wall Section - Provide a typical interior and exterior wall section for each building – describe wall materials.
j. Interior Elevations – Provide interior elevations of all bathrooms and built-in casework and kitchenettes, indicate critical heights of surfaces and plumbing fixtures and describe all materials and finishes.
k. Pre-Final Design Analysis – Provide a narrative explaining the design and indicating how the design and materials meet the requirements of this SOW.
l. Pre-Final Specifications – Provide detailed explanations of requirements for
7-Apr-22 Page 18 of 57 all performed work or provide product specific manufacturer information (brochures, technical information, cut sheets) for all materials and products to be provided/installed.
3.1.2.2 95% DESIGN SUBMISSION
The 95% Submittal provides a complete and final set of contract documents essentially ready for construction by the D/B Contractor. All previous government review comments must have been addressed. Include the following drawings and reports as applicable to the project:
a. All documents from the 65% submittal updated to incorporate 65% review comments.
b. Floor Plans – Provide all floor plans, indicating room names, areas, and dimensions, scale 1:50.
c. Building Elevations – Provide all building elevations indicating all exterior materials.
d. Roof Plan – Provide a plan of all roof areas, indicating direction of slope and method of drainage.
e. Building Section – Indicate heights.
f. Wall Sections – Provide sufficient wall section(s) to indicate all materials and different conditions.
g. Section and Plan Details – Provide details of critical building intersections.
h. Window and Door Schedule – Provide a schedule of all windows and doors, indicating sizes, hardware, and operation.
i. Finish Schedule – Indicate all proposed finishes.
j. Final Design Analysis – Provide a finalized narrative describing all work to be performed on the project and how it meets the functional and code requirements of the project. Provide product specific manufacturer information (brochures, technical information, cut sheets) for all materials and products to be provided/installed.
k. Final Specifications – Provide line items and detailed descriptions of all work to be performed.
3.1.2.3 100% DESIGN SUBMISSION
The 100% Submittal provides a complete and final set of contract documents ready for construction by the D/B Contractor. All previous government review comments must have been addressed. Include all drawings, specifications and calculations from the 95% Submittal updated to incorporate all previous review comments.
3.2 TECHNICAL CRITERIA AND STANDARDS
Design and construct the project in accordance with the requirements outlined in Section 1.7 DESIGN CRITERIA.
3.2.1 LIFE SAFETY REQUIREMENTS
The Design must meet all Host Nation and local Fire Suppression System codes and requirements. All new structures must have exits and means of egress that comply with current Host Nation codes and standards. In the absence of Host Nation codes and standards, for individual concerns of Life Safety the Contractor must follow the International Building Code (IBC).
3.2.2 HANDICAPPED ACCESSIBILITY REQUIREMENTS
All facilities must meet applicable Host Nation handicapped accessibility requirements.
3.3 GENERAL SCOPE OF WORK
Design the architectural elements of this facility to withstand all site-specific environmental conditions such as wide seasonal temperature swings, local wind, rain, snow and earthquake conditions. All architectural features must be appropriately braced for anticipated seismic activity. The Contractor may propose
7-Apr-22 Page 19 of 57 alternate building materials to meet the facility’s requirements, but final selection of materials is subject to the approval of the KO. Consider economics not only in the initial acquisition, but also in the future maintenance of the materials, when selecting materials and building systems to be incorporated into the project. When requested, the Contractor must provide documentation demonstrating that a chosen alternative material is life cycle cost effective.
3.4 DETAILED SCOPE OF WORK
The Contractor is responsible for the following specific tasks required for the construction of this facility.
3.4.1 DEMOLITION
Demolition work includes, but is not limited to, the following items:
a. Demolish and remove existing Nursing Home Buildings #6 and #7, see attached location map for reference.
3.4.2 BUILDING SYSTEM AND MATERIALS
The intent of this RFP is to allow the Contractor the maximum flexibility to design and construct this facility in an economical manner without sacrificing good engineering practices, quality materials and systems. The Government requires low or no maintenance finish materials to the greatest extent possible. Provide a design informed by the modular size of selected materials. Building materials as described herein are minimum requirements and may require revision based on code compliance and criteria.
3.4.2.1 FIRE PROTECTION RATINGS OF INTERIOR FINISHES
All interior finishes must conform to Host Nation fire protection standards/requirements or equivalent US standards/requirements.
3.4.2.2 ACOUSTICAL DESIGN
Doors, walls, floors, and ceilings must meet the minimum sound protection per Host Nation requirements.
3.4.2.3 THERMAL INSULATION
Provide thermal insulation in accordance with Host Nation and local requirements.
3.4.2.4 CORROSION PREVENTION
All exterior materials and finishes must be appropriate for continuous exterior exposure. All materials susceptible to UV degradation must contain UV inhibitors.
Provide corrosion resistant coatings on all materials susceptible to corrosion.
Coatings must be applied in the factory prior to delivery to the maximum extent practicable. Physically separate dissimilar metals with non-conductive hardware.
Do not install aluminum in direct contact with concrete. Treat all wood with preservatives where it is contact with concrete or exposed to the exterior. Cover all exterior wood with metal flashing or exterior grade paint. Do not install wood in contact with soil.
3.4.3 EXTERIOR CONSTRUCTION WORK
Provide the following exterior architectural systems.
3.4.3.1 EXTERIOR WALLS
Design and construct new exterior walls in accordance with (IAW) the requirements of this SOW. Refer to Section 4.0 STRUCTURAL.
This is the start of the file's text. The full file is on GovTribe.