This request for proposal (RFP) solicits bids for blast cleaning, painting, and anode replacement of Tainter gates at Mills Dam. The work also includes repairing and replacing specific steel components, as well as miscellaneous grinding and welding. The Army Corps of Engineers seeks a contractor to mobilize within 10 days of notice and complete the work within 730 calendar days, including final cleanup. Liquidated damages of $2,237 per day will be assessed for delays, plus $8,000 per day if a floating plant is required but not available. The RFP includes pricing tables, an option to rehabilitate additional gates, and standard contract clauses. Bids are due by September 5, 2020.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Tainter Gate Painting, Wilbur D. Mills Dam, Pool No. 2, McClellan-Kerr Arkansas River Navigation System, Arkansas County, Arkansas
Project Number: 480415
Magnitude of Construction: Betw een $10,000,000.00 and $25,000,000.00
Set-Aside: To be Determined
NAICS: 237990, Other Heavy and Civil Engineering Construction SBA Size Standard: $39,500,000.00
Bidder Inquiry: A Request for Information (RFI) Review has been set up at w w w .projnet.org for this solicitation. The ProjNet Inquiry Key is M3W2C7-K3RMWE. The review is open from 29 July 2020 to 12 August 2020.
JONATHAN J SAWRIE 501-340-1045
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
05-Aug-2020
(RFP)
(IFB)
X
CALL:
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA
FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________730 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________00 72 00
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
X YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________05 Sep 2020 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time of fers are due.
B. An offer guarantee X is, is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______90 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
CONTRACTING DIVISION
USACE, LITTLE ROCK (W9127S)
700 W. CAPITOL AVE, RM 7315
LITTLE ROCK AR 72201-3225
W9127S
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
10:00 AM (hour)
Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
8. ADDRESS OFFER TO (If Other Than Item 7)
(501) 324-5196FAX:TEL: (501) 340-5720 TEL: FAX:
W9127S20R0011 61
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
W9127S20R0011
Section 00 01 10 - Table of Contents
Exhibit/Attachment Table of Contents
DOCUMENT TYPE DESCRIPTION PAGES DATE
Attachment 1 Specifications 27-JUL-2020 Attachment 2 Plans 27-JUL-2020 Attachment 3 Wage Rates
Section 00 10 00 - Solicitation
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Job Mobilization/Demobilization
FFP
FOB: Destination
PSC CD: Z2KA
NET AMT
0002 1 Job Rehabilitate Tainter Gates 1-4, 6, and 7
FFP
0003 240 Linear
Foot
Replace WT 6X22.5 Brace
FFP
0004 42 Each Replace Girder Stiffener Plate
FFP
0005 36 Each Rib to Girder Connection Repair
FFP
0006 180 Linear
Intermediate Rib Repair (WT8X22.5)
0007 120 Linear
5/16" Fillet Weld Repair
0008 120 Linear
Miscellaneous Grinding
0009 1 Each Flood Demobilization
FFP
0010 1 Job OPTION Rehabilitate 4 Additional Tainter Gates
FFP
0011 1 Job OPTION Rehabilitate 2 Additional Tainter Gates
FFP
0012 1 Job OPTION Rehabilitate 2 Additional Tainter Gates
FFP
0013 1 Job OPTION Rehabilitate 1 Additional Tainter Gates
FFP
0014 1 Each OPTION Replace Side Seal Assembly
FFP
DELIVERY INFORMATION
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
0001 730 dys. ADC 1 WILBUR D. MILLS DAM
1286 WILBUR D. MILLS RD
TICHNOR AR 72166
967158
0002 730 dys. ADC 1 (SAME AS PREVIOUS LOCATION)
0003 730 dys. ADC 240 (SAME AS PREVIOUS LOCATION)
0004 730 dys. ADC 42 (SAME AS PREVIOUS LOCATION)
0005 730 dys. ADC 36 (SAME AS PREVIOUS LOCATION)
0006 730 dys. ADC 180 (SAME AS PREVIOUS LOCATION)
0007 730 dys. ADC 120 (SAME AS PREVIOUS LOCATION)
0008 730 dys. ADC 120 (SAME AS PREVIOUS LOCATION)
0009 730 dys. ADC 1 (SAME AS PREVIOUS LOCATION)
0010 730 dys. ADC 1 (SAME AS PREVIOUS LOCATION)
0011 730 dys. ADC 1 (SAME AS PREVIOUS LOCATION)
0012 730 dys. ADC 1 (SAME AS PREVIOUS LOCATION)
0013 730 dys. ADC 1 (SAME AS PREVIOUS LOCATION)
0014 730 dys. ADC 1 (SAME AS PREVIOUS LOCATION)
BIDDING SCHEDULE
Line Item No.
Description
Estimated Quantity
Unit Measure
Unit Price
Amount
BASE BID
0001 Mobilzation/Demobilization 1 Job XXX $
0002 Rehabilitate Tainter Gates 1,2,3,4,6,and 7 1 Job XXX $
0003 Replace WT 6X22.5 Brace 240 Linear Feet $ $
0004 Replace Girder Stiffener Plate 42 Each $ $
0005 Rib to Girder Connection Repair 36 Each $ $
0006 Intermediate Rib Repair (WT8x22.5) 180 Linear Feet $ $
0007 5/16" Fillet Weld Repair 120 Linear Feet $ $
0008 Miscellaneous Grinding 120 Linear Feet $ $
0009 Flood Demobilization 1 Each $ $
TOTAL BASE BID $ .
OPTIONS
Option 1
0010 Rehabilitate 4 Additional Tatinter Gates 1 Job XXX $
Option 2
0011 Rehabilitate 2 Additional Tatinter Gates 1 Job XXX $
Option 3
0012 Rehabilitate 2 Additional Tatinter Gates 1 Job XXX $
Option 4
0013 Rehabilitate 1 Additional Tatinter Gates 1 Job XXX $
Option 5
0014 Replace Side Seal Assembly 1 Each $ $
TOTAL BASE BID PLUS OPTIONS $
Section 00 21 00 - Instructions
CLAUSES INCORPORATED BY REFERENCE
52.209-7 Information Regarding Responsibility Matters OCT 2018 52.215-1 Instructions to Offerors--Competitive Acquisition JAN 2017 52.215-20 Requirements for Certified Cost or Pricing Data or
Information Other Than Certified Cost or Pricing Data
OCT 2010
52.225-10 Notice of Buy American Requirement--Construction Materials
MAY 2014
52.232-13 Notice Of Progress Payments APR 1984 52.236-28 Preparation of Proposals--Construction OCT 1997 252.215-7010 Requirements for Certified Cost or Pricing Data and Data
Other Than Certified Cost or Pricing Data
JUL 2019
252.215-7011 Requirements for Submission of Proposals to the Administrative Contracting Officer and Contract Auditor.
JAN 2018
CLAUSES INCORPORATED BY FULL TEXT
52.216-1 TYPE OF CONTRACT (APR 1984)
The Government contemplates award of a Firm Fixed Price (FFP) contract resulting from this solicitation.
(End of provision)
52.233-2 SERVICE OF PROTEST (SEP 2006)
(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from
Jonathan J. Sawrie Contracting Officer Post Office Box 867 700 West Capitol, Room 7315 Little Rock, Arkansas 72203
(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the
GAO.
52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):
https://www.acquisition.gov/
52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (APR 1984)
(a) The use in this solicitation of any Federal Acquisition Regulation (48 CFR Chapter 1) provision with an authorized deviation is indicated by the addition of"(DEVIATION)" after the date of the provision.
(b) The use in this solicitation of any Defense Federal Acquisition Regulation Supplement (48 CFR Chapter 2) provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.
Section 00 21 16 - Instructions to Proposers
SUBMISSION REQUIREMENTS
SECTION 00 2 2 16 - PROPOSAL SUBM ISS ION RE QUIREMENTS, EVAL UA TION CRITERIA , AND BAS IS
OF A WARD
GENERAL REQUIREMENTS
The proposal shall describe the capability of the Offeror to perform the requirements of the Specifications. The proposal should be specific and complete in every detail; and should be prepared simply and economically, providing a straightforward and concise description of capabilities to satisfactorily perform the requirements. The proposal should be practical, legible, clear, and coherent.
In order to effectively and equitably evaluate all proposals, the Contracting Officer must receive information containing sufficient detail to allow review and evaluation by the Government. Proposal clarity, organization, and cross-referencing are mandatory. Failure to submit and organize proposals as requested may adversely affects an Offeror's evaluation.
Proposals shall not exceed the page limits described. Provide all information in bookmarked sections. Appendices and/or attachments are not permitted and will not be evaluated.
SUBMISSION FORMAT
METHOD OF SUBMISSION. Offerors shall submit one (1) electronic copy of their proposal in Compact Disc (CD) format.
Each disc shall be externally labeled with the solicitation number, date, and the offeror’s name. Zip disks and USB thumb drives are not permitted.
FILE FORMAT. Files on each CD shall be in Portable Document Format, filename extension: “.pdf” and suitable for viewing in Adobe Reader. There shall only be two files on each offerors’ submitted CD: ‘Volume I, Technical Submission’ and ‘Volume II, Price Submission.’
FONT SIZE. Shall not be less than 10 point. Each page shall be identified with the appropriate page number centered at the bottom of the page.
SHEET SIZE. Shall be 8-1/2 inches x 11 inches; however, if drawings, charts, or other graphics are submitted, sheets no larger than 11 inches x 17 inches shall be used. Sheets that are 11 x 17 inch will be counted as two 8-1/2 inch x 11-inch sheets. All sheets shall be dated and numbered.
COVER SHEET & TABLE OF CONTENTS. Proposals shall consist of two (2) volumes. A cover sheet identifying the Offeror (name, address, point of contact) and solicitation number shall be provided. The second sheet shall be a table of contents. The proposal shall contain a detailed table of contents. Offers that violate these rules unnecessarily delay the evaluation process and may be rejected by the Government after the initial evaluation without receiving any further consideration. Neither the cover sheet nor the table of contents count toward the page limitations.
BOOKMARKS. Proposals shall be bookmarked and labeled as specified in a manner to afford easy identification from the Table of Contents. Additional bookmarks may be provided, but shall be nested under the appropriate tab bookmark.
HYPERLINKS. Hyperlinks are not permitted. This includes hyperlinks within the document, such as Figure or Table references to the page containing that content, and hyperlinks to websites.
ATTACHMENTS. Attachments/appendices are not permitted.
PAGE LIMITS. The proposal shall not exceed the specified page limits. The Government will not review any information in excess of the page limits or information submitted in an appendix or attachment to the proposal. The Offeror shall not submit verbatim sections of this solicitation as part of their proposal. Offers that do not meet these requirements may be subject to rejection.
SUBMISSION REQUIREMENTS
Offerors shall submit their proposals in accordance with the following:
VOLUME 1:
BOOKMARK A— Standard Form 1442 and Proposal Data Sheet. (See the format provided as Attachment A.) Proposal must include offeror’s telephone number, FAX number, email address, and DUNS number. DUNS number will be used to access CPARS Data.
BOOKMARK B - Factor 1 – Performance Capability Sub Factor 1.1 – Specialized Experience Sub Factor 1.2 – Technical Approach Sub Factor 1.3 – Key Personnel Sub Factor 1.4 – Organization BOOKMARK C - Factor 2 – Proposed Contract Duration & Summary Schedule BOOKMARK D – Factor 3 – Past Performance
VOLUME 2:
BOOKMARK A - Price Schedule BOOKMARK B - Offer Guarantee
FACTOR 1 – PERFORMANCE CAPABILITY (VOL 1, BOOKMARK B)
SUB-FACTOR 1.1 – SPECIALIZED EXPERIENCE
Offerors shall provide project information on relevant projects that best demonstrate the breadth and depth of an Offeror’s or Subcontractor’s relevant specialized experience. A minimum of three, but no more than five projects may be submitted that demonstrate past experience. Two of the projects must be valued at over $2,000,000.00. If the offeror submits more than five projects, only the first five, as ordered in the proposal, will be evaluated.
Projects should have been at least 50% completed within 5 years from the date of the RFP. The Government will not evaluate projects if the project has been completed more than five years prior to the date of the RFP.
SUBMISSION REQUIREMENT: Page Limit – Ten (10) Pages. (Two (2) pages per submitted project; maximum of five (5) submitted projects.)
For each project submitted, offerors shall complete the “Company Specialized Experience- Construction or Prime Contractor,” form provided as Attachment B. All blocks must be completed with accurate, current, and complete information. If any information is missing from this form, the offeror will be considered non-responsive, and will be evaluated as Unacceptable for this Subfactor.
If the Offeror proposes to use a Subcontractor for any amount of work under this procurement, the Offeror must submit a signed Letter of Commitment from the subcontractor, which includes the identification of the role of the subcontractor, with the proposal. If the Offeror and the Subcontractor have worked together in the past, include a list of projects or other evidence that the two firms have successfully worked together.
If the Offeror proposes a joint venture for the requirement, the Offeror must submit a joint venture agreement signed by all participating firms. The agreement must identify the role of each party. If the firms participating in the joint venture have worked together in the past, include a list of projects or other evidence that the two firms have successfully worked together.
EVALUATION CRITERIA – The proposal will be evaluated to determine the extent to which it:
-Demonstrates the extent of the Offeror’s, and/or their sub-contractor’s experience in Tainter gate painting work.
-Demonstrates the extent of the successful completion of relevant projects the offeror and subcontractor have worked on together (if applicable).
-Demonstrates the extent of the successful completion of relevant projects the proposed joint venture has worked on (if applicable).
SUB-FACTOR 1.2 – TECHNICAL APPROACH
SUBMISSION REQUIREMENT: Page Limit - Ten (10) Pages.
Offerors shall submit their Technical Approach to execution that includes:
1. Include a detailed discussion describing challenges, risks, and constraints associated with this project and how the offeror intends to address each with means and methods, resources, or internal organizational processes.
2. Include a discussion of the floating plant the offeror intends to utilize: List the type, length, capacity, speed, and availability of any self-propelled plant or vessel planned to move any non- self-propelled plant to be used. Include the river flow reading in cubic feet per second at which the floating plant must be moved away from the dam to safe areas and how the offeror arrived at that value. Define the minimum qualifications required for the Officers and crew of any floating plant to be utilized. The Offeror shall be required to provide the proposed floating plant for construction.
3. Describe the method(s) to be utilized by the offeror to deliver personnel, equipment, and materials to the gates to perform the work as well as the type of work platforms intended to be utilized. If the work platform is intended to be a scaffolding system supported by the dam structure provide a sketch showing the concept including details of attachment to the structure and a narrative as to how the contractor will ensure the scaffolding will be structurally sufficient to support the work. Define the water flow and elevation that would require workers begin removing equipment from any scaffolding system as well as the water flow and elevation at which no personnel would be allowed on the work platform. Include critical assumptions made and uncertainties that the Offeror believes will impact the completion of the work and plan to deal with each.
4. Describe the means and method(s) that the offeror will utilize to measure and document the existing gates stability, location, and dimensions prior to work, how the offeror will ensure the gate maintains stability, location, and its dimensions during construction, and how the offeror will address any changes to the gate location or dimension that do occur as a result of the repair process.
5. Include a discussion about the equipment required for blasting, painting, and testing; the containment and disposal of spent sand blasting media; and how the adjacent structures will be protected.
6. Discuss the means and methods for various repairs not already addressed in paragraphs 1 through 5. Outline the proposed sequencing approach for construction, equipment to be used, etc.
7. Generally describe the items the offeror will self-perform.
-Demonstrates the Offeror’s understanding of the requirements and the technical risks and site constraints associated with the required work.
-Demonstrates the Offeror’s understanding of how major work tasks impact other major work tasks needed to accomplish the work.
-Demonstrates the Offeror’s approach for managing the technical risks and site constraints for each major task of work.
SUB-FACTOR 1.3 – KEY PERSONNEL
The Offeror shall provide resume data for the following key personnel: Construction Project Manager, Quality Control Manager (CQC System Manager), all specialized personnel assisting the Quality Control Manager, Site Superintendent, and Site Safety and Health Officer.
SUBMISSION REQUIREMENT: Page Limit – Two (2) Pages per Resume. For each resume submitted, include the following information, at a minimum:
1. Name and title
2. Project assignment
3. Name of firm with which associated
4. Years of experience in the role identified.
5. Years of experience with this firm and with other firms
6. Education degree(s), year, specialization, if applicable
7. Active professional registration, year first registered, if applicable
8. Other experience and qualifications relevant to same/similar work required under this contract
Minimum experience requirements for personnel shall be in accordance with Division 01 sections. Unless otherwise specified in Division 01, each individual shall have a minimum of seven years of experience in their respective position.
-Demonstrates key personnel meet or exceed minimum qualifications necessary to perform the requirements of the solicitation.
SUB-FACTOR 1.4 – ORGANIZATION
The offeror shall provide information that describes its organizational approach to executing this construction contract in accordance with the requirements herein.
SUBMISSION REQUIREMENT: Page Limit – Three (3) Pages. Include the following information, at a minimum:
1. Organization: Describe what firms, their resources and how their resources will be utilized, their roles and responsibilities and any contractual arrangements that have been established. Clearly describe any teaming or joint venture arrangements, including a clear description of each firm’s roles and responsibilities on the project. A copy of the teaming or joint venture agreement(s) may be appended to the plan (not included in the page limitation). Include a simple organizational chart, illustrating the organization, including the proposed quality control group(s). Present a matrix of responsibilities for each firm in executing the key work breakdown structure activities of the project, including construction activities for each major feature. Identify the firms chosen for the project if not to be self-performed. The Offeror shall be required to obtain the Contracting Officer’s approval for any substitution of firms listed. Describe the proposed management structure for the team, describing how the construction process will be managed and the authorities and the delegations of authority within the team. Include a key personnel organization chart that clearly depicts the key positions and the names of the personnel, their firm affiliations and their job locations, their job/position title within the organization. The key personnel organization chart shall be consistent with the corporate organization chart, with the matrix of responsibilities assigned to the firms, and with the list of key personnel to be provided under the Tab, “Key Personnel.”
2. Quality Control: Describe the team’s quality control approach, corporate systems and capabilities to maintain quality control of the construction. Describe the proposed quality control organization, including the proposed staffing plan. Provide information on how you will handle internal and external requests for information, shop drawings, progress meetings, site visits, contract completion, closeout, as-built, and completion documentation. There is no need to submit a quality control plan as the successful offeror will provide that after award. Describe how the team will meet USACE three phase quality control requirements.
3. Safety Plan: Describe the team’s safety approach, corporate systems and capabilities to maintain safety requirements during construction. Describe the proposed safety organization, including the proposed staffing plan. The intent is to provide enough detail to demonstrate the Offeror’s understanding of the project; however, it is not the intent for the Offeror to provide the amount of detail that will be required in the pre-work submittals contained in Division 01 of this RFP.
-Demonstrates the offeror’s understanding of the requirements detailed in the plans and specifications and the capability to execute the project.
-Demonstrates the organizations’ strength and ability to execute the entire scope of work.
-Demonstrates the offeror’s capabilities and understanding of the quality control processes required for this contract.
-Demonstrates the offeror’s understanding of the safety plan requirements.
FACTOR 2 – PROPOSED CONTRACT DURATION & SUMMARY SCEDULE (VOL 1, BOOKMARK C)
The offeror shall provide a narrative detailing a proposed schedule and contract duration that addresses delays and showcases phases of construction.
SUBMISSION REQUIREMENT: Page Limit – Three (3) Pages Submit a summary level schedule for construction including any construction phasing. Schedules or diagrams may be provided separately in a size that is easily read, but shall be clearly labeled. This summary schedule will, after contract award, be replaced with a project schedule as required by Specification Section PROJECT SCHEDULE. The summary schedule shall be task oriented, indicating the number of calendar days, after notice to proceed, by which milestones are to be achieved. Offeror may use a critical path or other method of his choice; however, schedules shall be graphically represented. The proposed summary schedule shall reflect the proposed contract duration. Give attention to the following features:
1. Overall construction phase for all major item(s)
2. Milestones: Notice to proceed; mandatory sequences activities
3. Completion, inspection, acceptance, and turnover of each gate
4. Graphical representation of critical path
5. Turnover of the project. Identify any proposed phased turnovers (if applicable). The time to complete the project and turnover to the Government must consider the requirement for the Contractor’s CQC completion inspection and the subsequent joint Contractor-Government turnover inspection.
6. As-built submissions
7. Constraints: Offeror must demonstrate the capability and flexibility to plan and schedule the complete project to meet the proposed contract completion period. Clearly identify any constraints on the schedules presented (e.g., labor or material availability, permits, weather, etc.).
-Demonstrates the Offeror’s overall understanding of the Scope of Work by clearly identifying the major tasks in a logical sequence and identifying critical path items.
-Demonstrates that the Offeror’s schedule is realistic considering the schedule constraint contained in FAR Clause 52.211-10 -- COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984).
FACTOR 3 – PAST PERFORMANCE (VOL 1, BOOKMARK D)
SUBMISSION REQUIREMENT: Page Limit - Eighteen (18) Pages. Submit completed Past Performance Questionnaires (Form PPQ-0) (Attachment C) from at least three (3) customers demonstrating past performance completed within the past five (5) years. The Government will use the information to determine the Offeror’s probability of successfully performing the scope of work described in this solicitation.
NOTE: Teaming arrangements and Joint Ventures. Provide a copy of the teaming/joint venture agreement.
Offerors may submit experience of an affiliated entity where that affiliated entity has made a firm commitment to participate meaningfully in the performance of the contract. If required, JV approval must be obtained in accordance with Small Business Administration policy.
EVALUATION CRITERIA:
The Government will evaluate how well the contractor performed on these contracts (See Past Performance Relevancy Ratings and Rating and Performance Confidence Assessments below). The Government may contact sources other than those provided by the Offeror for information with respect to past performance. These other sources may include, but are not limited to, Past Performance Information Retrieval System (PPIRS), Federal Awardee Performance and Integrity Information System (FAPIIS), or other databases; telephone interviews with organizations familiar with the Offeror’s performance, and Government personnel with personal knowledge of the Offeror’s performance capability.
PRICE SCHEDULE (VOL 2, BOOKMARK A)
SUBMISSION REQUIREMENT: Submit the required Price/Bid Schedule (SF 1442); submit a detailed description of the types of costs included in the proposed coefficient factors; provide aggregate construction bonding capacity.
EVALUATION CRITERIA: The Government will perform a price analysis after completion of technical evaluations. Price analysis will be performed in accordance with FAR 15.404-1, to determine completeness, reasonableness, and understanding of the work. The evaluation will determine the adequacy of the offer in fulfilling the requirements of the proposal. Completeness addresses the extent to which the elements of the price proposal are consistent with the requirements of the RFP. Reasonableness will be established using historical price information, price competition information, the IGE, and any other pricing tools necessary. A clear audit trail must be evident as to the conversion of costs to the coefficients to accomplish the tasks described herein. Price will not be rated, but will be a factor in making the final best value determination for award.
OFFER GUARANTEE (VOL 2, BOOKMARK B)
SUBMISSION REQUIREMENT: Submit Standard Form 24. The guarantee shall be submitted in accordance with Contract Clause 52.228-1 Bid Guarantee.
EVALUATION CRITERIA: This item is not rated. The Government will review the Bid Bond for legal sufficiency. The Bond must be legally sufficient. Failure to submit a bid bond may make the Offeror’s proposal ineligible for award.
RATING A DJECTIVES AND DEF IN IT IONS
RATING ADJECTIVES
Outstanding - Proposal indicates an exceptional approach and understanding of the requirements and contains multiple strengths, and risk of unsuccessful performance is low.
Good - Proposal indicates a thorough approach and understanding of the requirements and contains at least one strength, and risk of unsuccessful performance is low to moderate.
Acceptable - Proposal meets requirements and indicates an adequate approach and understanding of the requirements, and risk of unsuccessful performance is no worse than moderate.
Marginal - Proposal has not demonstrated an adequate approach and understanding of the requirements, and/or risk of unsuccessful performance is high.
Unacceptable - Proposal does not meet requirements of the solicitation, and thus, contains one or more deficiencies, and/or risk of unsuccessful performance is unacceptable. Proposal is unawardable.
DEFINITIONS
Clarifications. Limited exchanges between the Government and offerors that may occur when award without discussions is contemplated.
Communications. Exchanges, between the Government and offerors, after receipt of proposals, leading to establishment of the competitive range.
a. Offerors whose past performance information is the determining factor preventing them from being included in the competitive range. Such communications will address adverse past performance information to which the offeror has not had a prior opportunity to respond; and
b. Offerors (other than those discussed above) whose exclusion from or inclusion in the competitive range is uncertain.
c. Communications may be conducted to enhance Government understanding of proposals; allow reasonable interpretation of the proposal; or facilitate the Government’s evaluation process. Communications cannot be used to cure proposal deficiencies or material omissions, materially alter the technical or price elements of the proposal, and/or otherwise revise the technical or price elements of the proposal. Such communications may be considered in rating proposals for the purpose of establishing the competitive range, if required. Communications shall not provide an opportunity for the Offeror to revise their proposal, but may address ambiguities in the proposal or other concerns (e.g. perceived deficiencies, weaknesses, errors, omissions, or mistakes and information relating to relevant past performance).
Discussions. Negotiations conducted in a competitive acquisition. Discussions take place after establishment of the competitive range.
Deficiency - A material failure of a proposal to meet a Government requirement or a combination of significant weaknesses in a proposal that increases the risk of unsuccessful contract performance to an unacceptable level.
Strength - An aspect of an offeror’s proposal that has merit or exceeds specified performance or capability requirements in a way that will be advantageous to the Government during contract performance.
Significant Strength - A significant strength appreciably enhances the merit of a proposal or appreciably increases the probability of successful contract performance.
Weakness - A flaw in the proposal that increases the risk of unsuccessful contract performance.
Significant Weakness - A significant weakness in a proposal is a flaw that appreciably increases the risk of unsuccessful contract performance.
Uncertainty - Any aspect of a non-cost/price factor proposal for which the intent of the offeror is unclear (e.g., more than one way to interpret the offer or inconsistencies in the proposal indicating that there may have been an error, omission or mistake).
PAST PERFORMANCE RELEVENCY RATINGS
In performing the past performance evaluation, evaluators will apply the following relevance levels to assess the relevance of the prior contract effort(s) of offerors.
Very Relevant - Present/past performance effort involved essentially the same scope and magnitude of effort and complexities this solicitation requires.
Relevant - Present /past performance effort involved similar scope and magnitude of effort and complexities this solicitation requires.
Somewhat Relevant - Present/past performance effort involved some of the scope and magnitude of effort and complexities this solicitation requires.
Not Relevant - Present/past performance effort involved little or none of the scope and magnitude of effort and complexities this solicitation requires.
RATING AND PERFORMANCE CONFIDENCE ASSESSMENTS
The government will evaluate past performance information to determine the quality and usefulness as it applies to performance confidence assessment. Each offeror will be assigned one of the ratings below for past performance.
Substantial Confidence— Based on the offeror’s recent/relevant performance record, the Government has a high expectation that the offeror will successfully perform the required effort.
Satisfactory Confidence— Based on the offeror’s recent/relevant performance record, the Government has a reasonable expectation that the offeror will successfully perform the required effort.
Limited Confidence— Based on the offeror’s recent/relevant performance record, the Government has a low expectation that the offeror will successfully perform the required effort.
No Confidence— Based on the offeror’s recent/relevant performance record, the Government has no expectation that the offeror will successfully perform the required effort.
Unknown Confidence (Neutral)— No recent/relevant performance record is available or the offeror’s performance record is so sparse that no meaningful confidence assessment rating can be reasonably assigned.
TECHNICAL EVALUATION WE IGHTS
For the purpose of this evaluation, the following terms will be used to establish the relative importance of the technical factors:
More Important: The criterion is greater in value than another criterion.
Equal in Importance: The criterion is of the same value or nearly the same as another criterion.
Less Important: The criterion is less in value than another criterion.
Weight among technical factors:
Factor/Subfactor Location Description Relative Importance
FACTOR 1 Bookmark B Performance Capability More important than Factors 2 and 3
Subfactor 1.1 Bookmark B Specialized Experience More important than Subfactors 1.2, 1.3, and 1.4
Subfactor 1.2 Bookmark B Technical Approach Less important than Subfactor 1.1; and more important than Subfactors 1.3 & 1.4
Subfactor 1.3 Bookmark B Key Personnel Less important than Subfactors
1.1 and 1.2 and more important than Subfactor 1.4
Subfactor 1.4 Bookmark B Organization Less important than Subfactors 1.1, 1.2, and 1.3
FACTOR 2 Bookmark C Proposed Contract Duration & Summary Schedule
Less important than Factor 1 and more important than Factor 3
FACTOR 3 Bookmark D Past Performance Less important than Factors 1 and
EVALUATION
Each member of the Source Selection Evaluation Board (SSEB) will independently consider all information provided in the technical proposal. Once these individual analyses are completed, the team will meet and determine a rating for each of the evaluation factors by consensus decision. The evaluation team will document strengths (e.g., advantages), weaknesses (e.g., disadvantages), and other comments (e.g., deficiency and/or clarification) to support the rating for each factor, as well as the overall rating. The ratings for Technical Factors will be expressed in an adjectival assessment of Outstanding, Good, Acceptable, Marginal and Unacceptable. Documentation and comments are required for all ratings. This consensus rating will be provided to the Source Selection Authority.
BAS IS OF A WARD
Proposals must meet the criteria stated in the RFP in order to be eligible for award, to include responsiveness, technical acceptability and responsibility.
The Government intends to award without discussions based on initial proposals received; therefore, the proposals shall contain the offeror’s best terms from a cost and technical standpoint. However, the Government reserves the right to conduct discussions in accordance with FAR 52.215-1. The Government reserves the right to address any pertinent issues in the proposals.
The Government will award a firm fixed-price contract to the responsible Offeror(s) whose proposal the Source Selection Authority determines conforms to the request for proposal, is fair and reasonable with regard to pricing, and whose proposal offers the best overall value to the Government. The Government reserves the right to accept other than the lowest priced offer or to reject all offers.
The combination of all technical (non-price) evaluation factors are significantly more important than the price. As technical ratings and relative advantages and disadvantages become less distinct, differences in price between proposals are of increased importance in determining the most advantageous proposal. Conversely, as differences in price become less distinct, differences in rating and relative advantages and disadvantages between proposals are of increased importance to the determination.
ATTACHMENT A
PROPOSAL DATA SHEET
1. Name of Firm:
2. Address:
3. Phone:
4. Fax:
5. E-mail:
6. DUNS # (used for accessing CCASS)
7. If a joint venture or contractor-subcontractor association of firms, list the individual firms and briefly describe the nature of the association.
Firm 1:
Firm 2:
Firm 3:
Nature of Association:
8. AUTHORIZED NEGOTIATORS. FAR 52.215-11
The Offeror represents that the following persons are authorized to negotiate on its behalf with the
Government in connection with this Request for Proposals (RFP).
9. Name of Person Authorized to
Negotiate:
10. Negotiator's Address:
ATTACHMENT B
COMPANY SPECIALIZED EXPERIENCE - CONSTRUCTION OR PRIME CONTRACTOR
Provide the following information to show examples of projects your company constructed within the last five (5) years indicating experience with projects of similar type and scope. Use one form per project.
1. Type of Facility Represented _______________________________________________________________________________________
2. Your Firm’s Name ___________________________________________________________________________________________________
3. Name of Project and Contract Number ____________________________________________________________________________
4. Location of Project __________________________________________________________________________________________________
5. Project Contract Type _______________________________________________________________________________________________
6. Owner _______________________________________________________________________________________________________________
7. General Scope of Construction Project (address how this relates to this solicitation)
8. Your Role (Prime, Joint Venture, or Subcontractor) and Work Your Company Self-Performed (also include any proposed team members that were directly involved in this project, including work performed, roles and responsibilities) :
9. Provide a list of the management team and their responsibility at a minimum include Project Manager, Quality Control Representative, and Construction Superintendent.
10. Construction Cost ____________________________________________________________________________________________________
11. Extent and Type of Work You Subcontracted Out _________________________________________________________________
12. Dates Construction: Began _____________________________ Completed _________________________________________
13. Your Performance Evaluation by Owner, if known _______________________________________________________________
14. Were You Terminated or Assessed Liquidated Damages? _______________________________________ (If either is “Yes”, attach an Explanation)
15. Owner’s Point of Contact for Reference (Name and Company) __________________________________________________
16. Current Telephone Number of Reference POC ____________________________________________________________________
ATTACHMENT C
PAST PERFORMANCE QUESTIONNAIRE
NAVFAC/USACE PAST PERFORMANCE QUESTIONNAIRE (Form PPQ-0)
CONTRACT INFORMATION (Contractor to complete Blocks 1-4)
1. Contractor Information Firm Name: CAGE Code:
Address: DUNs Number:
Phone Number:
Email Address:
Point of Contact: Contact Phone Number:
2. Work Performed as: Prime Contractor Sub Contractor Joint Venture Other (Explain) Percent of project work performed:
If subcontractor, who was the prime (Name/Phone #):
3. Contract Information Contract Number:
Delivery/Task Order Number (if applicable):
Contract Type: Firm Fixed Price Cost Reimbursement Other (Please specify):
Contract Title:
Contract Location:
Award Date (mm/dd/yy):
Contract Completion Date (mm/dd/yy):
Actual Completion Date (mm/dd/yy):
Explain Differences:
Original Contract Price (Award Amount):
Final Contract Price (to include all modifications, if applicable):
Explain Differences:
4. Project Description:
Complexity of Work High Med Routine How is this project relevant to project of submission? (Please provide details such as similar equipment, requirements, conditions, etc.)
CLIENT INFORMATION (Client to complete Blocks 5-8)
5. Client Information Name:
Title:
Phone Number:
Email Address:
6. Describe the client’s role in the project:
7. Date Questionnaire was completed (mm/dd/yy):
8. Client’s Signature:
NOTE: NAVFAC/USACE REQUESTS THAT THE CLIENT COMPLETES THIS QUESTIONNAIRE AND
SUBMITS DIRECTLY BACK TO THE OFFEROR. THE OFFEROR WILL SUBMIT THE COMPLETED
QUESTIONNAIRE TO USACE WITH THEIR PROPOSAL, AND MAY DUPLICATE THIS
QUESTIONNAIRE FOR FUTURE SUBMISSION ON USACE SOLICITATIONS. CLIENTS ARE HIGHLY
ENCOURAGED TO SUBMIT QUESTIONNAIRES DIRECTLY TO THE OFFEROR. HOWEVER,
QUESTIONNAIRES MAY BE SUBMITTED DIRECTLY TO USACE. PLEASE CONTACT THE
OFFEROR FOR USACE POC INFORMATION. THE GOVERNMENT RESERVES THE RIGHT TO
VERIFY ANY AND ALL INFORMATION ON THIS FORM.
ADJECTIVE RATINGS AND DEFINITIONS TO BE USED TO BEST REFLECT
YOUR EVALUATION OF THE CONTRACTOR’S PERFORMANCE
RATING DEFINITION NOTE
(E) Exceptional Performance meets contractual requirements and exceeds many to the Government/Owner’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with few minor problems for which corrective actions taken by the contractor was highly effective.
An Exceptional rating is appropriate when the Contractor successfully performed multiple significant events that were of benefit to the Government/Owner. A singular benefit, however, could be of such magnitude that it alone constitutes an Exceptional rating. Also, there should have been NO significant weaknesses identified.
(VG) Very Good Performance meets contractual requirements and exceeds some to the Government’s/Owner’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with some minor problems for which corrective actions taken by the contractor were effective.
A Very Good rating is appropriate when the Contractor successfully performed a significant event that was a benefit to the Government/Owner. There should have been no significant weaknesses identified.
(S) Satisfactory Performance meets minimum contractual requirements. The contractual performance of the element or sub-element contains some minor problems for which corrective actions taken by the contractor appear or were satisfactory.
A Satisfactory rating is appropriate when there were only minor problems, or major problems that the contractor recovered from without impact to the contract. There should have been NO significant weaknesses identified. Per DOD policy, a fundamental principle of assigning ratings is that contractors will not be assessed a rating lower than Satisfactory solely for not performing beyond the requirements of the contract.
(M) Marginal Performance does not meet some contractual requirements. The contractual performance of the element or sub-element being assessed reflects a serious problem for which the contractor has not yet identified corrective actions. The contractor's proposed actions appear only marginally effective or were not fully implemented.
A Marginal is appropriate when a significant event occurred that the contractor had trouble overcoming which impacted the Government/Owner.
(U) Unsatisfactory
Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the element or sub-element contains serious problem(s) for which the contractor's corrective actions appear or were ineffective.
An Unsatisfactory rating is appropriate when multiple significant events occurred that the contractor had trouble overcoming and which impacted the Government/Owner. A singular problem, however, could be of such serious magnitude that it alone constitutes an unsatisfactory rating.
(N) Not Applicable
No information or did not apply to your contract
Rating will be neither positive nor negative.
TO BE COMPLETED BY CLIENT
PLEASE CIRCLE THE ADJECTIVE RATING WHICH BEST REFLECTS
YOUR EVALUATION OF THE CONTRACTOR’S PERFORMANCE.
1. QUALITY:
a) Quality of technical data/report preparation efforts
E VG S M U
N
b) Ability to meet quality standards specified for technical performance E VG S M U N
c) Timeliness/effectiveness of contract problem resolution without extensive customer guidance
E VG S M U
N
d) Adequacy/effectiveness of quality control program and adherence to contract quality assurance requirements (without adverse effect on performance)
E VG S M U
N
2. SCHEDULE/TIMELINESS OF PERFORMANCE:
a) Compliance with contract delivery/completion schedules including any significant intermediate milestones. (If liquidated damages were assessed or the schedule was not met, please address below)
E VG S M U
N
b) Rate the contractor’s use of available resources to accomplish tasks identified in the contract
E VG S M U
N
3. CUSTOMER SATISFACTION:
a) To what extent were the end users satisfied with the project?
E VG S M U
N
b) Contractor was reasonable and cooperative in dealing with your staff (including the ability to successfully resolve disagreements/disputes;
responsiveness to administrative reports, businesslike and communication)
E VG S M U
N
c) To what extent was the contractor cooperative, businesslike, and concerned with the interests of the customer?
E VG S M U
N
d) Overall customer satisfaction
E VG S M U
N
4. MANAGEMENT/ PERSONNEL/LABOR
a) Effectiveness of on-site management, including management of subcontractors, suppliers, materials, and/or labor force?
E VG S M U N
b) Ability to hire, apply, and retain a qualified workforce to this effort E VG S M U N
c) Government Property Control E VG S M U N
d) Knowledge/expertise demonstrated by contractor personnel E VG S M U N
e) Utilization of Small Business concerns E VG S M U N
f) Ability to simultaneously manage multiple projects with multiple disciplines
E VG S M U N
g) Ability to assimilate and incorporate changes in requirements and/or priority, including planning, execution and response to Government changes
E VG S M U N
h) Effectiveness of overall management (including ability to effectively lead, manage and control the program)
E VG S M U N
5. COST/FINANCIAL MANAGEMENT
a) Ability to meet the terms and conditions within the contractually agreed price(s)?
E VG S M U N
b) Contractor proposed innovative alternative methods/processes that reduced cost, improved maintainability or other factors that benefited the client
E VG S M U N
c) If this is/was a Government cost type contract, please rate the…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .