This statement of work outlines requirements for the design and construction of an entry control facility in Graf Ignatievo, Bulgaria under solicitation number W912GB-23-R-0050 from the Department of the Army European Command. Key requirements include the civil design and construction of two concrete ID check islands, a canopy foundation, guard booths, drop arms, and an active vehicle barrier. The electrical scope involves providing utility power from an on-base transformer substation to a new main distribution panel, LED lighting, and communications infrastructure to connect the facility to an existing guard shack. Other specifications govern structural, architectural, mechanical, and sustainability elements of the project. The submission schedule outlines 35%, 65%, 95%, and 100% design submittals as well as as-built drawings.

View the file

Other files

File Type Posted
B.08.03 W912GB-23-R-0050-0003.pdf PDF
B.07.01 - Sign-In Sheet_Pre-Bid Site Visit_-_Graf ECP Project (26JUL23).pdf PDF
B.08.02 Attachment 13 Price Schedule.docx DOCX document
W912GB-23-R-0050-0002.pdf PDF
W912GB-23-R-0050-0001.pdf PDF
B.08.02 Attachment # 8 - Reinforced Chain Link Fence Drawings as per UFC 4-022-03.pdf PDF
B.08.02 Attachment # 5 - Conceptual Canopy Design.pdf PDF
F.01.03 VAT.FORM.ANNEX B - Blank.March.2020.doc DOC document
B.08.02 Attachment 10 Bank Letter of Guarantee Sample.docx DOCX document
B.08.02 Attachment 11 PPQ.pdf PDF
B.08.02 W912GB-23-R-0050.pdf PDF
B.08.02 Attachment # 1 - Location Map.pdf PDF
B.08.02 Specs Binder IEU-23-0032.pdf PDF
B.08.02 Attachment 9 Bank Letter of Assurance Sample.docx DOCX document
B.08.02 Attachment # 7 - Attachments to BG Air Force Statement on new ECF (Utility Maps).pdf PDF
B.08.02 Attachment # 2 - Conceptual Site Plan.pdf PDF
B.08.02 Attahcment 12 Commitment Letters.docx DOCX document
B.08.02 Attachment # 6 - Location Map of existing Transformer Substation.jpg JPG image
B.08.02 Attachment # 4 - NAU Eng Guideline 01-2016 Preparation of Structural Calculations.pdf PDF
B.08.02 Attachment # 3 - SDDCTEA stop control safety scheme (without median).pdf PDF
Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

US Army Corps of Engineers Europe District

APO AE 09049

bu10

Statement of Work Project Number: P2 498765

FY 21

Entry Control Facility

Graf Ignatievo Military Base, Bulgaria

Prepared by:

Design Section

Engineering Branch 24-July-23

01 10 10 Statement of Work Entry Control Facility

24-Jul-23 Page 2 of 34

SECTION 01 10 10

STATEMENT OF WORK

SECTION TABLE OF CONTENTS:

1 GENERAL

2 CIVIL AND GEOTECHNICAL

3 ARCHITECTURAL (Not applicable)

4 STRUCTURAL

5 ELECTRICAL & COMMUNICATIONS

6 MECHANICAL & PLUMBING (Not applicable) 7 FIRE PROTECTION (Not applicable) 8 SUSTAINABILITY (Not applicable) 9 CYBERSECURITY (Not applicable)

ATTACHMENTS

Attachment # 1 Location Map Attachment # 2 Conceptual Site Plan Attachment # 3 SDDCTEA Stop Control AVB Safety Scheme (without median) Attachment # 4 Structural Calculations Guideline Attachment # 5 Conceptual Canopy Design Attachment # 6 Location Map of existing Transformer Substation Attachment # 7 Attachments to BG Air Force Statement on new ECF

(Utility Maps) Attachment # 8 Reinforced Chain Link Fence Drawings as per UFC 4-022-03

1.0 GENERAL

1.1 PROJECT DESCRIPTION

The Request for Proposal (RFP) provides parameters for a design-build project for construction of an Entry Control Facility (ECF) in Graf Ignatievo Military Base, Bulgaria; Latitude 42°16'53.5"N, Longitude 24°43'47.0"E (Refer to the attached Location Map.)

Layout of the new ECF is based on the “Stop Control AVB Safety Scheme” as per SDDCTEA Pamphlet 55-15 providing one rated active vehicle barrier as final denial barrier. This will allow for safe deployment of the barrier by guard response within 5 seconds in case a vehicle is trying to intrude the base (see Att. # 3).

The new ECF shall only serve for POV processing. A separate truck gate is located elsewhere on the base. However, the approach and the access control zone of the ECF shall accommodate larger vehicles to allow for turning of vehicles rejected at the ID-Check including trucks that may have entered the ECF by mistake. Besides Passenger cars, the ECF shall accommodate emergency vehicles, vans, and small buses.

The new ECF shall consist of an Approach Zone including an entry gate provided by a cable reinforced double swing gate, passive vehicle barriers, asphalt road alignment and walkway connection up to the ID Check area.

The following Access Control Zone shall consist of a raised paved traffic island, a barrier wall for protection of the guards, an optional guard booth, a drop arm, and passive barriers.

Proposed Asphalt pavement shall accommodate ID-check lane, outbound lane, and vehicle rejection.

The proposed response zone shall consist of passive vehicle barriers, asphalt road alignment up to the connection with the existing road system, and the final denial active vehicle barrier.

A second ID-Check Lane providing vehicle search capability is proposed for optional expansion.

24-Jul-23 Page 3 of 34

Foundations to expand the ECF with an optional canopy for the ID Check area shall already be constructed in the scope of this project.

Command and control features as well as visitor control center functions shall be provided in the existing gatehouse.

The existing gravel parking in front of the existing gate shall remain to provide visitor parking.

The ECF shall be provided with lighting and with electric power & telecommunication systems as necessary for the implementation of the “Stop Control AVB Safety Scheme” as per SDDCTEA Pamphlet 55-15.

Sufficient space shall be retained for future extension which may include a new visitor parking and a new building of 12.5 m x 8.0 m footprint provided with aprons and accommodating and combining gatehouse & visitor control center functions.

Design Demand for the ECF is calculated to be 600 vehicles per hour based on traffic data provided by the customer. Provision of 1 ID-Check Lane and the optional 2nd lane is expected to prevent vehicles from cueing into the access road at Force Protection Conditions that match US DoD FPCON Bravo.

An additional Limited Use Gate shall be provided in location of the exiting gate that is controlling access of military trucks to the road south of the new ECF connecting to the existing fuel farm in the west.

The Limited Use Gate shall consist of a cueing area provided by existing pavement, new cable reinforced fencing to separate the gate from the Base by perimeter protection, and a cable reinforced swing gate serving for access control. The Limited Use Gate shall be protected by operational procedures only.

The project includes the following general items of work, detailed requirements are contained elsewhere in this Statement of Work:

a. Clear, grub, and grade the site

b. Provide storm drainage system

c. Construct new asphalt roadways including signage and marking

d. Construct new walkway connection

e. Construct 2 new concrete ID-Check Islands each accommodating tandem checks by two guards (one optional)

f. Construct new concrete pad for Emergency Generator Placement

g. Block off existing gate with passive barriers

h. Install K4 (M30) rated Active Vehicle Barrier (AVB)

i. Install system of passive vehicle barriers

j. Install new security fencing in combination with parts of the passive barriers.

k. Install 2 new cable reinforced double swing gates for vehicle access

l. Install 1 new cable reinforced swing gate for pedestrian access

m. Install 2 new prefab guard booth (optional)

n. Complete ID-Check Islands with 2 drop arms (one optional) and 2 barrier walls (one optional)

o. Construct concrete foundations for the proposed optional canopy

p. Complete optional canopy

q. Install ECF Main Distribution Panel sized for entire project

r. Install Manual Transfer Switch and portable generator connection in close proximity to MDP.

s. Provide Led lighting for entire ECF site to include roadway

t. Provide power and communication/control connections to gates

u. Install general use receptacles in and around guard shack(s).

v. Install data connections in and around guard shacks which are connected to existing guard booth.

24-Jul-23 Page 4 of 34

1.2 GENERAL REQUIREMENTS

The Contractor must deliver fully functional, turnkey type facilities (without mobile furniture) as described in this document. The work includes - but is not limited to - design, demolition, fabrication, delivery, installation, construction, and site work.

The facility in this project must be complete and usable to meet codes and technical and functional requirements per this Statement of Work (SOW). The proposal price must include all design, calculations, approvals, certificates, fees, labor, material, equipment, direct overhead, indirect overhead, general and administrative expenses (G&A) and general conditions to complete this project as described in the SOW.

These design and product requirements are minimum requisites. Compliance with the provisions of this section by subcontractors is the responsibility of the Contractor.

1.2.1 BASE ITEMS AND OPTIONAL ITEMS

This Statement of Work addresses the technical requirements necessary to complete all work associated with this project. For information and requirements regarding the allocation of pricing between elements of the work, refer to Specification Section 01 22 00 PRICE AND PAYMENT PROCEDURES. The Schedule of Items identifies the breakdown between the individual base items and optional items for all work identified in this Statement of Work, associated drawings, and attachments. All work as described in these documents is included in either the Base or Optional Items. Consider all items not specifically identified in the Optional Items as part of the Base Items.

1.3 SUBMITTALS

Designer of Record approval is required for submittals with a “DA” designation.

Government approval is required for submittals with a “G” or “GA” designation.

Submittals having an “FIO” designation are for Contractor Quality Control approval. Submit the following to the Contracting Officer (KO) in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Sequencing Plan; G

SD-05 Design Data

35% Design; DA/GA

65% Pre-Final Design; DA/GA

95% Final Design; DA/GA

100% Corrected Final Design; DA/GA

SD-06 Test Reports

Test Results and Reports; FIO

1.3.1 DESIGN SUBMITTALS

Provide a complete design package at each milestone, as described in RFP Section 01 33 16-DESIGN AFTER AWARD. The milestones for this project are indicated above in Section 1.4 SUBMITTALS. The specific requirements of each milestone are described in each discipline-specific section of this Specification.

24-Jul-23 Page 5 of 34

1.3.2 TEST REPORTS

Provide all test results and reports identified in this SOW to the Government as a submittal in accordance with RFP Section 01 33 00-SUBMITTAL PROCEDURES. Submittals will be considered for information only (FIO) submittals unless specifically identified as a submittal requiring government approval. Coordinate with the KO after award for the specific items to be included in the submittal register.

1.4 MATERIALS AND EQUIPMENT

Materials and products used must be durable, heavy duty, industry standard. The equipment must be the manufacturer’s standard quality and must be compatible with all other equipment and materials within the system or assembly. Equipment and materials must include all connections and accessories necessary to ensure operability and correct installation according to manufacturer’s requirements.

Provide a nameplate secured to each major piece of equipment. Each nameplate must have the manufacturer’s name, address, contact information, type or style, model or serial number, and catalog number. The definition of a “major piece of equipment” is at the discretion of the KO.

1.4.1 LIFE-SPAN

The facility and the installed equipment must be permanent construction with an expected lifespan of more than 25 years

1.4.2 MAINTAINABILITY

Provide low maintenance materials and systems appropriate for the project climate and location.

1.4.3 OPERABILITY

Systems (including but not limited to architectural, electrical, communications, and mechanical systems) must be simple to operate and easy to maintain.

1.4.4 STANDARDIZATION

Provide standardized materials, products, equipment, and systems to minimize the requirements for replacement parts, storage facilities, and service requirements.

1.5 DESIGN DIMENSIONS

Develop the design using the metric system.

1.6 DESIGN CRITERIA

Project design, site facilities, utility systems and material standards must be in accordance with Host Nation building codes (current versions as of the date of RFP, unless otherwise indicated). In the absence of Host Nation building codes, use the International Building Code (IBC) and the codes, technical standards, and regulations referenced in this RFP.

While this RFP references various source standards and specifications, all design documents must meet Host Nation codes and requirements. It is the designer's responsibility to demonstrate that the Host Nation standard is equal to the cited standard or specifications being supplanted. Apply the more restrictive standards when conflicts arise between the requirements of this RFP and any referenced or other applicable codes, standards or regulations. If equivalency cannot be met, use the more stringent requirement and quote both codes verbatim in correspondence to the KO. The designer is responsible to determine the required material and execution standards where specific standards are not indicated.

Provide an electronic copy of the local Host Nation standards and building codes in their original language as related to facility design and construction.

24-Jul-23 Page 6 of 34

1.7 SPECIAL CONSTRUCTION REQUIREMENTS

1.7.1 DEMOLITION

The Contractor is responsible for all required demolition as indicated in this scope.

1.7.1.1 ABATEMENT AND DISPOSAL

All demolished materials, including hazardous materials identified below, must be abated and disposed of in accordance with local laws, codes and regulations. The Contractor is responsible for all required testing before, during and after demolitions as well as for all required compliance with safety standards.

1.7.1.2 LOCATION OF HAZARDOUS MATERIAL

The Contractor is responsible to survey the site and determine if hazardous materials exist. If hazardous materials are found to exist, immediately notify the KO and provide the results of the relevant sampling and testing. Provide the hazardous material report no later than 30 days after Notice to Proceed (NTP) for information and approval.

1.7.2 SEQUENCING OF CONSTRUCTION WORK

The Contractor must sequence construction to ensure functionality of the limited use gate is always provided during construction, either by the existing gate or by the proposed new limited use gate. The existing entry control facility needs to remain operational until the new ECF will be fully commissioned. Utility and communication services must remain functional for all existing facilities.

Provide a Sequencing Plan with the 65% Pre Final Design Submittal. The Sequencing Plan must describe the proposed performance of construction operations to comply with the stated sequencing requirements. The Sequencing Plan must include a graphical depiction of the sequencing of each work area and mobilization/staging area. The Sequencing Plan is in addition to the requirements of RFP Section 01 32 01-PROJECT SCHEDULE or 01 32 16-SMALL PROJECT PROGRESS SCHEDULES (NOTE: Only one of these specifications applies to this contract, refer to other documents for the section applicable to this project).

END OF SECTION

24-Jul-23 Page 7 of 34

2.0 CIVIL AND GEOTECHNICAL

Provide and perform civil engineering design and construction services as required to provide a complete, accessible, functional and usable project. The Contractor is required to extensively coordinate civil design and construction work with the scope of the other disciplines described in this SOW.

2.1 SCOPE SUMMARY

Civil works for this project include, but are not limited to, site survey, geotechnical investigation, site layout, demolition, earthwork, storm system, pavement, fencing, outdoor furnishings, and landscaping. Refer to the bid schedule for which of these are base bid or optional.

2.2 EXISTING CONDITIONS

2.2.1 TOPOGRAPHY

There is no known topographic survey for the project site. The existing site for the most part consists of green space with minor areas of pavement and fencing mainly in location of the existing limited use gate. There are several utilities that run and are proposed to be installed by the base along and inside the existing road system. Two minor structures, a walled shooting position and a maintenance pit, and a few old trees can be found in the eastern part of the site.

The terrain is generally flat with no appreciable slope in any direction. The existing information shown on the attached Conceptual Site Plan was compiled from Google Earth, and site photos.

2.2.2 UTILITIES

Please refer to Attachment # 7 that includes utility maps for existing utilities and for those that are currently projected by the base. Existing and projected utilities include electric power, communication, and sewage lines. An existing fuel pipeline is running above ground along the western and southern perimeter road but will remain untouched by the ECF project. There is no storm system located on or in close vicinity to the site. Storm drainage in the area of the ECF is assumed to be currently managed by sheet flow and surface infiltration.

The contractor must verify all utility locations (surface and subsurface) in the field prior to the first design submittal.

2.2.3 GEOTECHNICAL

There is no geotechnical information available for the project site.

The Contractor must perform a Geotechnical Investigation and submit a Geotechnical Report as part of the Design Analysis. Refer to other sections of this SOW for the requirements of the Geotechnical Investigations and Report.

2.2.4 ENVIRONMENTAL

There are no known environmental protection areas or archeological preservation areas on the project site.

There is no prior knowledge of any hazardous or contaminated materials in the site’s soil or pavement.

2.2.5 UNEXPLODED ORDNANCE (UXO)

There is no prior knowledge of UXO in the site’s soil.

2.2.6 EXISTING CONDITIONS INVESTIGATION

Prior to bid, investigate the general and local conditions which can affect the work and/or its cost, including but not limited to:

a. Weather, or similar physical conditions at the site.

24-Jul-23 Page 8 of 34

b. Surface and subsurface materials or obstacles to be encountered insofar as this information is reasonably ascertainable from an inspection of the site and due diligence research of as-built drawings, geotechnical reports, environmental reports, and publicly available information on the site.

c. Mobilization and staging constraints.

2.3 DESIGN SUBMITTALS

Provide civil design submittals in accordance with RFP Section 01 33 16-DESIGN AFTER AWARD and in compliance with SOW Section 1.0 – GENERAL.

35% Design Submittal:

a. Preliminary Design Analysis of civil features.

b. Final Site Survey (include in the Design Analysis).

c. Final Geotechnical Report (include in the Design Analysis).

d. Final Existing Conditions Plan.

e. Preliminary Demolition Plan.

f. Preliminary Site Layout Plans - Indicate existing and proposed Civil features.

Include other disciplines’ features (faded back) that affect the Civil Design (buildings, mechanical structures, electrical utilities, etc.).

g. Preliminary Grading Plans, including contours, and finish floor elevations.

h. Preliminary Pavement Plans.

i. Preliminary Utility Plans (Storm).

j. Preliminary Fencing and Outdoor Furnishings Plans.

a. Cut Sheets for selected Outdoor Furnishing like active vehicle barrier, drop arms, and guard booths.

k. Preliminary Civil Specifications (Table of Contents only).

65% Design Submittal:

b. Update all items from the 35% Design Submittal to 65% (Pre-Final) Design.

Incorporate all 35% design comments.

c. Pre-Final Grading Profiles, Cross Sections, and Details. Include spot grades and slopes in Grading Plan. Include erosion control design.

d. Pre-Final Pavement Profiles, Cross Sections, and Details.

e. Pre-Final Utility (Storm) Profiles, Cross Sections, and Details.

f. Pre-Final Fencing and Outdoor Furnishings Details.

g. Shop Drawings of selected Outdoor Furnishing like active vehicle barrier, drop arms, and guard booths.

h. Preliminary Landscape Plan and Details, including seed mix and seed coverage rate.

i. Preliminary Civil Specifications.

95% Design Submittal:

Update all items from the 65% Design Submittal to 95% (Final) Design. Incorporate all 65% design comments.

100% Submittal:

The 100% Submittal provides a complete and final set of contract documents ready for construction. Update all Final submittals from 95% to a corrected Final submittal. Address all previous government review comments before submitting.

As Built Drawing Submittal:

In addition to the as-built requirements discussed in RFP Section 01 78 00- CLOSEOUT SUBMITTALS, provide a topographical survey of the site per requirements of SOW Section 2.6-SITE SURVEY. Include existing utility lines or structures (both modified and unmodified) encountered in the construction footprint that were not located on the original Site Survey.

24-Jul-23 Page 9 of 34

2.3.1 DESIGN ANALYSIS

Submit a Design Analysis in accordance with RFP Section 01 33 16-DESIGN AFTER AWARD. Provide a Design Analysis for all Civil features that documents significant design choices and substantiates design compliance with contract requirements, applicable codes and standards. Documentation includes narrative, calculations, photographs, sketches, and catalog cut sheets. Reference all applicable regulations, standards, and criteria for the design. Reference sources are subject to Government approval. Provide design assumptions. For design choices, discuss alternative systems considered, and provide rationale for the selected alternative.

The Design Analysis includes but is not limited to:

a. Discussion of Site Layout constraints and design decisions, including but not limited to, land use, vehicle and pedestrian access and circulation, orientation of features on-site, setbacks from site features, minimizing utility lengths, minimizing earthwork and tree removal, and future expansion.

Perform calculations for all vehicle threat scenarios as per SDDCTEA Pamphlet 55-15, section 8.3 applicable for the proposed ECF. Calculate the vehicle threat scenarios based on Appendix C of the ARMY Access Control Point Standard Design by laying out the threat paths in CAD and making use of the VTDC spreadsheet. Note that Thread Scenarios #1 and #2 are not applicable for the proposed ECF since overspeed detection will not be implemented for the project. Instead, calculations for these scenarios need to be replaced by a calculation that considers the threat vehicle being detected by the guards when passing the drop arm area with the maximum speed able to attain in the approach and the access control zone (including some deceleration needed to not skid out of the next curve).

Baseline Threat Vehicle Characteristic for treat scenario calculations including acceleration rate, deceleration rate, friction factor, maximum velocity, and vehicle mass shall meet characteristics as outlined in Section

1.7.2 of the ARMY Access Control Point Standard Design.

b. Discussion of Demolition constraints and design decisions. Include discussion on how access will be provided during construction, and how each utility will be maintained and operated during construction.

c. Discussion of Earthwork and Site Grading constraints and design decisions.

Provide cut and fill calculations. Provide slope stability calculations for slopes steeper than 2H:1V or slopes supporting proposed structures. Include pertinent geotechnical information that affects earthwork.

d. Discussion of constraints and design decisions in regards of proposed site drainage. Provide a hydrologic and hydraulic analysis of the proposed site drainage, including offsite areas that contribute to and influence the project’s site drainage. Provide drainage basin map(s), rainfall data, and coefficients used. For each section of pipe being part of a proposed storm system, include analyses indicating pipe size, friction factor, length, elevations at each end of pipe, slope, design flow (Q), maximum flow capacity, design depth of flow, design percentage full, and design flow velocity.

Analyze headwater and tailwater of proposed and impacted existing culverts and discharges of proposed storm systems. Provide Inlet design calculations.

Provide calculations for sizing of structures, including detention, infiltration, and LID features. Provide documentation for the 100 year flood elevation determination. Provide Pre and Post Development comparisons for detention/retention facilities. Use the Rational Method or TR-55 for analysis and design. In the absence of Host Nation or Installation requirements, use a minimum 10-year storm frequency for analysis and design. Provide calculations on the pipe’s structural capacity if the pipe is shallower than required in section 2.10-Utilities. Include pertinent geotechnical information that affects the storm system. Confirm that the existing receiving system has adequate capacity to receive the additional stormwater flow generated by the project.

24-Jul-23 Page 10 of 34

e. Discussion of Pavement constraints and design decisions. Provide the design vehicle(s) specifications. Demonstrate the turning path of the largest anticipated vehicle(s) in the most constrained situations on the site plans.

Provide vehicular circulation patterns using AutoTURN or equivalent method.

Provide sight distance calculations and sketches. Provide calculations for the pavement section. Include pertinent geotechnical information that affects the pavement design.

f. Discussion of Fencing and Vehicle Barrier constraints and design decisions.

Provide structural calculations for the fence foundations if the foundation is designed by the Designer of Record. Fence calculations are not necessary if the fence foundation design is from an industry standard detail.

Perform kinetic energy calculations in accordance with UFC 4-022-02 to demonstrate that the proposed vehicle barriers effectively stop the baseline threat vehicle breaking through the ECF’s containment.

g. Discussion of Outdoor Furnishings constraints and design decisions. Provide structural calculations for foundations if the foundation is designed by the Designer of Record. Calculations are not necessary if the foundation design is from an industry standard detail.

h. Discussion of Landscaping constraints and design decisions.

i. Site Survey as an appendix.

j. Geotechnical Investigation and Report as an appendix.

2.3.2 DESIGN DRAWINGS

Provide Civil design drawings of sufficient detail to address the requirements of each design submittal. Civil drawings include plans, profiles, cross sections, and details of Civil features for the project. Civil drawings also include temporary construction plans/methods that affect the design and construction of the project.

These temporary plans include mobilization, traffic control, erosion control, dewatering, shoring, construction sequence, etc. Design drawings include all necessary information (labeling, dimensioning, legend, details, notes, etc.) to allow for complete understanding and constructability of all proposed features.

Provide comprehensible differentiation between features that are proposed, existing, future, or proposed to be demolished by use of appropriate choice of line styles, line weights, and/or colors. In the absence of the Installation’s CAD requirements, Reference USACE A/E/C Graphics Standard for graphic requirements.

2.3.3 SPECIFICATIONS

Provide Civil specifications of sufficient detail to address the requirements of each design submittal. Specifications, when combined with the design drawings, allow for complete understanding and constructability of all proposed Civil features.

2.4 DESIGN CRITERIA

Provide civil design in accordance with Host Nation codes.

In the absence of Host Nation codes, use the latest release of the International Building Code (IBC) and the following codes and technical standards:

a. Uniform Facility Criteria (UFC) 3-201-01, Civil Engineering

b. UFC 3-220-01, Geotechnical Engineering

c. USACE A/E/C Graphics Standard (ERDC/ITL TR-12-1)

d. UFC 3-250-01, Pavement Design for Roads and Parking Areas

e. UFC 4-022-02, Selection and Application of Vehicle Barriers

f. ASTM F2656/F2656M, Standard Test Method for Crash Testing of Vehicle Security

Barriers

2.5 GEOTECHNICAL INVESTIGATION AND REPORT

Perform a geotechnical investigation and assessment of the project site to determine the subsurface conditions and geotechnical parameters for foundation, grading, and utility design. Perform the necessary amount of testing, borings and

24-Jul-23 Page 11 of 34 test pits at depths suitable for the project improvements. Include geotechnical investigation in areas where borrow material will be used. The Geotechnical work must be performed under the supervision of a professional geotechnical engineer registered with the jurisdiction having authority, and the report must be signed by the Geotechnical Engineer. In the absence of Host Nation codes, perform the geotechnical investigation and report per UFC 3-220-01, Geotechnical Engineering and IBC.

Coordinate testing locations with the KO to avoid impact to existing utilities and facility operations. Utility locates, permits, pavement removal and vegetation clearing is the Contractor’s responsibility. Repair disturbed areas with a concrete patch in paved areas, and compacted soil in non-paved areas. The repaired area must be flush with the adjacent surface. Following restoration, stake and flag each of the hole locations with boring identification numbers. In paved areas, use white paint on the paved surface to mark hole locations. Provide a map indicating the borehole and test pit locations.

2.5.1 REPORT

Include, as a minimum, the following information:

a. Description of field work completed and equipment used; names, signatures and stamps of licensed professionals involved; name of drilling company.

b. A description of site subsurface conditions, regional geology, and seismic conditions at the site.

c. Site map of borehole and test pit locations.

d. High resolution color digital photographs of each borehole and test pit location.

e. Test pit logs with classification of all subsurface materials. The logs must distinguish fill materials from native materials, include all in‐situ test results, and include groundwater depth information, if groundwater is encountered. Distinguish between bedrock and rock boulders.

f. Reports of all the field and laboratory testing.

g. Recommendations for allowable bearing capacity, expected settlement, type of foundation, minimum footing and grade beam dimensions, lateral earth pressure parameters, and minimum depth of foundation for footing and grade beams.

h. Recommendations for preparation, placement, and compaction of onsite soils, borrow material, soil replacement, soil amendment/treatment, structural fill, topsoil, and trench backfill. Include dewatering and temporary retaining structure needs.

i. Soil Resistivity.

j. Frost Depth.

k. Deep foundation information.

l. Recommendations for pavement design and construction.

m. Recommendations for the storm systems involving infiltration.

n. Calculations to support conclusions and recommendations.

2.5.2 DESIGN DRAWINGS AND SPECIFICATIONS

On the design drawings and/or specifications, include geotechnical information that affect the design of the project, including but is not limited to, boring locations, boring logs, groundwater and frost depths, and any details that convey requirements for site preparation.

2.6 SITE SURVEY

Conduct and provide a topographic survey from a licensed surveyor that includes all existing site information needed to design and construct the project. Survey must be conducted prior to the first design submittal. Include x, y, and z coordinates to the nearest 0.005 meters, dimensions, material, and basic characteristics of all features within the project site limits, as well as all features outside of the project site limits that will affect the design and construction of the project. Research record drawings to obtain utility and pavement information that is not visible from the surface. Provide notes

24-Jul-23 Page 12 of 34 indicating the sources and any limitations or assumptions of the data. Provide a copy of the survey in CAD, in addition to the paper/electronic requirements of the Design Analysis. Locate and show on the topographic survey the following information:

a. Property boundary, public right of way, and easements. Include the address numbers, street names, and easement records.

b. Survey monuments. Include description.

c. Spot elevations covering the entire survey limits showing high points, low points, grade changes, and at sufficient intervals to represent the general character of the terrain.

d. Contours in intervals of 0.25 meters.

e. Buildings and other miscellaneous structures. Provide finish floor elevation.

f. Pavements. Include pavement type, thicknesses, joint patterns, and pavement markings. Include top of curb and gutter elevations.

g. Surface Drainage Features.

h. Utility lines and structures. Include rim elevations and invert elevations for utility structures; identification of lines as underground or aboveground;

pipe sizes and materials.

i. Fences. Include height, material, direction of outrigger, gate locations and types.

j. Signs. Include sign text.

k. Railroads.

l. Trees/Woods: In wooded areas that trees are to be protected, locate outside drip line of wooded area, include general density and type of trees. For wooded areas with proposed tree removal, identify trees per Host Nation permitting requirements. Where selective clearing will be proposed, locate trees over 150 millimeter diameter at chest height, and include tree species, diameter at chest height, and dripline diameter.

m. Geotechnical boring locations.

n. Locate environmentally sensitive areas (determined and marked by others).

o. North arrow and scale of drawing.

p. Legend depicting the symbols and abbreviations used on the drawing.

q. Horizontal and vertical coordinate systems, date of survey, licensed surveyor name and license number.

Site information provided to the Contractor by the Government is not to be considered accurate Site Survey information. Utility field locates and as-built research are the responsibility of the Contractor.

Upon completion of construction, update the original survey with an As-built survey of the site as constructed, including underground utility locations and depths. Submit the As-built survey to the KO for approval.

Reference UFC 3-201-01, Civil Engineering, Section 2-2.2-SURVEYING for survey requirements. Use the Universal Transverse Mercator (UTM) coordinate system . The vertical coordinate system must be based on sea level.

2.7 SITE LAYOUT

Locate and design the proposed improvements as indicated on the attached Conceptual Site Plan and as outlined in SECTION 1.1 - PROJECT DESCRIPTION. Amend the site layout as determined by the site-specific constraints, the owner’s preferences, accessibility, future expansion, and opportunities that are identified and evaluated as part of the Contractor’s scope of work.

Site Layout must meet the requirements of Installation Design Guide(s).

The Contractor is responsible for all aspects of the project whether they are shown on the conceptual plan or not.

https://en.wikipedia.org/wiki/Universal_Transverse_Mercator_coordinate_system https://en.wikipedia.org/wiki/Universal_Transverse_Mercator_coordinate_system

24-Jul-23 Page 13 of 34

2.8 DEMOLITION

Remove existing pavement, vegetation, and any other features to construct the proposed improvements. Remove trees with driplines within the footprint of the proposed improvements. Provide straight, neat sawcuts at limits of pavement removal. All contaminated soils discovered require special testing and disposal per Host Nation requirements.

2.8.1 CONSTRUCTION LIMITS

Do not disturb the project site beyond necessary for installation of proposed construction. Do not disturb any areas past the site’s property line. Show demolition work and limits of disturbance in the drawings. Stake-out the limits of disturbance on-site with temporary fencing before beginning construction.

2.8.2 ITEMS TO REMAIN IN PLACE WITHIN CONSTRUCTION LIMITS

Take necessary precautions to avoid damage to existing items to remain in place, to be reused, or to remain the property of the Government. Repair or replace damaged items as required by the KO. Construct and maintain shoring, bracing, and supports as required. Ensure that structural elements are not overloaded. Provide new supports and reinforcement for existing construction weakened by demolition, deconstruction, or removal work. Repairs, reinforcement, or structural replacement require approval by the KO prior to performing said work.

2.8.3 TREES

Protect trees which might be damaged during construction, with a 1.8 meter high fence around the dripline of the tree(s), which is assumed to be the extent of the tree’s roots. Trees are defined as larger than 150mm diameter at 1.3 meters above existing grade. Mitigate for tree removal per Host Nation requirements.

2.8.4 UTILITIES

Any existing utilities encountered that are impacted by this project must be protected, or relocated if protection is not feasible. Remove existing and abandoned utilities under or within 3.0 m of the foundation of any proposed facility or building foundation. Reroute existing utilities to remain in accordance with SOW Section 2.10-UTILITIES. Abandoned utilities must be removed up to the utility main (or next utility main junction) and capped. Manholes or underground structures to be abandoned must be removed to a minimum depth of 50 centimeters below finish grade. Fill abandoned manhole or structure per Section 2.9-EARTHWORK requirements.

2.8.5 DUST, DEBRIS, AND EROSION CONTROL

Prevent the spread of dust, debris, and erosion from the project site. Install erosion control measures before beginning construction. Sweep pavements as often as necessary to control the spread of debris. Do not use water if it results in hazardous or objectionable conditions such as, but not limited to, ice, flooding, erosion, or pollution. Remove snow, dust, dirt, and debris from work areas daily.

Remove and transport the debris in a manner that prevents spillage on streets or adjacent areas. Apply local regulations regarding hauling and disposal.

2.8.6 ADDITIONAL REQUIREMENTS

Reference RFP Section 00 74 01-SPECIAL CONDITIONS, and 01 30 00-GENERAL REQUIREMENTS for additional demolition, protection, and permitting requirements.

2.9 EARTHWORK

Perform all earth work necessary for the installation of the proposed improvements.

2.9.1 PLANS AND SPECIFICATIONS

Define earthwork requirements in the plans and specifications. Include requirements for satisfactory material, borrow material, structural fill, topsoil, 24-Jul-23 Page 14 of 34 utility trenches, replacement and improvement of on-site soils, soil compaction (for subgrades of structures, paving, and landscaped areas), compaction for utility trenches, maximum lift depths, density testing frequency, maximum temporary and permanent slopes, and engineered support systems. The earthwork requirements must not conflict with the recommendations in the Contractor-provided Geotechnical Report.

2.9.2 UNEXPLODED ORDNANCE (UXO) CLEARANCE

Perform a survey and inspection of the work areas in accordance with Host Nation standards, laws, and requirements. If UXO are discovered on site, stop work in the area and immediately notify the KO. UXO will be treated as an unforeseen site condition. Refer to RFP Section 01 30 01-GENERAL CONDITIONS.

2.9.3 CONTAMINATED SOIL

Inspect and test all soil according to Host Nation requirements. If hazardous materials are discovered, cease excavation, secure the area, and notify the KO for further guidance.

2.9.4 CULTURAL RESOURCES

Cultural resources, such as archaeological remains, may be uncovered during excavation operations. If suspected cultural remains are found, cease excavation, secure the area, and notify the KO for further guidance.

2.9.5 TOPSOIL

Remove and save topsoil (approximately first 20 centimeters of excavation).

Separate out subsoil, brush, litter, weeds, roots, stones larger than 25 mm in diameter, and other materials that would interfere with planting and maintenance operations. When restoring the site to finish grade, place topsoil back in excavated areas that do not include proposed paving or structures.

2.9.6 SATISFACTORY MATERIAL

Excavated material (below topsoil), if satisfactory for reuse per the Contractor’s Geotechnical Engineer, may be used on the project site where fill is required.

Unsatisfactory material, and surplus excavated material not required for fill, must be disposed of offsite, and is the responsibility of the Contractor. Borrow material may be required for construction from sources off site. Borrow materials are to be free of hazardous materials and contaminants. Any soil brought in from off-site sources must be certified clean.

2.9.7 BACKFILL COMPACTION

In the absence of Host Nation requirements and geotechnical recommendations, fill and backfill must be placed in layers of 20 centimeters loose thickness and compacted to a minimum 95% of the maximum dry density as determined by Host Nation test method equivalent to ASTM D-1557 (Modified Proctor test). Provide density tests on all lifts at a frequency of 1 test per 40 square meters for foundations and parking, and 1 test per 30 meters of road and utility trench. Round up to nearest whole number (i.e. a 25 square meter foundation requires one test). The location of all tests must be selected by the Contractor’s geotechnical engineer, and copies of all test results must be furnished to the KO. All structure foundation excavations must be inspected and approved by the Contractor’s Geotechnical Engineer prior to placing concrete. Repair earthwork areas as recommended by the Contractor’s Geotechnical Engineer, and approved by the KO.

2.9.8 ENGINEERED SOIL SUPPORT SYSTEMS

Provide engineered soil support systems (i.e. shoring) as required for the construction of the proposed improvements. The Contractor is responsible for all dewatering necessary for earthwork.

24-Jul-23 Page 15 of 34

2.9.9 SITE GRADING

Provide site grading that directs storm water runoff away from improvements either by drainage systems or by grading as follows:

a. Finished grades of earth/grass/gravel surfaces adjacent to improvements must slope away from all exterior edges with a minimum slope of 5% for the first 2 meters.

b. Finished grades of paved surfaces adjacent to buildings and structures must slope away from all exterior edges with a minimum slope of 2% for the first 2 meters.

c. Finished grades must not create stagnating water or ponding anywhere on the project site, nor create ponding on adjacent properties. Provide storm improvements if ponding is unavoidable.

d. Set building finish floor elevations at a minimum of 30 centimeters above the local 100 year flood level.

Site grading around the building must meet Host Nation accessibility guidelines.

The Contractor must limit proposed landscape slopes to a maximum 4H:1V for grass areas requiring mowing and 2H:1V for non-grass areas, which require non-erodible surface (i.e. rock, shrubs with mulch).

2.10 UTILITIES

This section applies to all project underground utilities located outside the building, including but not limited to, sanitary sewer, water supply, storm drainage, electrical, communications, gas, liquid fuel, and heat. See Section 5.0- ELECTRICAL & COMMUNICATIONS for additional utility requirements.

Proposed utility main alignments must be at least 3.0 meters from facility or building foundations, except for building connections. Provide horizontal and vertical separation between new and existing utilities for rehabilitation, maintenance, repair or replacement. Provide utility line depths, bedding, and backfill as required by applicable requirements and geotechnical recommendations.

Minimum cover over pipes is 0.6 meters; greater than frost penetration; or sufficient to support imposed dead and live loads for the pipe materials used;

whichever is more stringent. Place plastic warning tape along the route of the buried pipe after installation at a height of 0.3 meters above the pipe.

Coordinate all required installation, relocation, improvement and protection of utilities held by third party (e.g. public or private utility). This includes coordination of any work to be performed by the utility owner. Choice of materials and products for utility installation must be coordinated with the utility owner (customer or third party) to ensure proper integration and compliance with existing systems and allow for easy maintenance and repair of the utilities in the future.

Provide utility materials per IBC requirements. Provide corrosion protection for utilities that provides the minimum life expectancy specified in Section 1.0- GENERAL. Any piping or equipment exposed to sunlight must be coated with protective coatings suitable for UV exposure with a minimum expected coating life of 10 years before recoating.

2.10.1 STORM SYSTEM

Provide a gravity storm drainage system to direct runoff away from improvements, eliminate ponding, and prevent erosion. A pump system is not allowed. If using an infiltration or detention system, locate infiltration/detention facilities a minimum of 3 meters away and downhill from structures. Provide an overflow to the infiltration/detention system that will not damage improvements or cause erosion.

Storm structures must be concrete, with traffic rated cast iron or ductile iron frames and covers. In the absence of Host Nation standards, design the storm

24-Jul-23 Page 16 of 34 drainage system per UFC 3-201-01, Civil Engineering Chapter 3-Storm Drainage Systems.

Connect building downspouts to proposed storm systems or top splash blocks that drain away from foundations a minimum of 2 meters. Ensure that proposed new Active vehicle barriers and other installed equipment is efficiently drained.

2.11 PAVEMENT

Provide geometric layout of the proposed roadways to allow the design vehicles to safely access and circulate inside the ECF. Design Speed shall be 40 km/h.

Design vehicle for the approach and the access control zone including turning area for rejected vehicles shall be a WB-12 [WB-40] semitrailer which matches most closely with the maximum dimensions & turning radii allowed as per European Regulations for type approval of motor vehicles.

The entire ECF shall accommodate minimum a two-axle passenger van/ bus with the following characteristics:

- Height: 3330mm

- Width: 3400mm

- Length: 9380mm

- Turning radius: 8475 mm

- Total mass: 18,000 KG

Other Design Vehicle to be accommodated include ambulance, and fire trucks deployed by the local emergency services.

In general, geometric design of the pavements and markings shall follow Host Nation standards. In the absence of Host Nation standards, design pavements per UFC 3-201-01, Civil Engineering.

Travel and ID Check lanes shall be minimum 3.6 m wide. Provide lane widening identified by hatched marking where needed to allow for the design vehicles to travel the roadway without the rear wheels leaving the traveling lane.

Proposed pavement works for the project include:

a. Provide asphalt roadways in compliance with the provisions above.

b. Construct concrete paving block paved walkway of minimum 1.5 m width connecting the new pedestrian gate with the ID-Check area and further with the existing pedestrian circulation system of the Base.

c. Provide a Portland Cement Concrete (PCC) island of minimum 3 meters width and minimum 23 meters length accommodating tandem checks by two guards for each ID-Check Lane. See STRUCTURAL Section of the SOW for further details.

d. Replace existing pavement sections where the trenching occurs for utility installation. Sawcut a minimum 30 centimeters beyond edge of trench.

Structural design of the pavements shall follow Host Nation standards. In the absence of Host Nation standards, design pavements per UFC 3-250-01, Pavement Design for Roads and Parking Areas. Average daily traffic (ADT) is estimated to be below 2500 vehicles/day but needs to be verified by the contractor in coordination with the base.

For asphalt concrete, provide compaction and pavement density tests, as well as thickness and evenness tests, at the frequency listed in Section 2.9 - EARTHWORK.

For PCC, reference SOW Section 4.0 - STRUCTURAL for concrete requirements. Perform subgrade tests for all pavements as described in Section 2.9 - EARTHWORK. The location of all tests must be selected by the Contractor’s Geotechnical Engineer, and copies of all test results must be furnished to the KO.

24-Jul-23 Page 17 of 34

2.12 FENCING AND BARRIERS

Provide new perimeter protection for the Base by cable reinforced security fencing where the removal and realignment of the Base’s perimeter fence is necessary for construction of the new facilities. Install new cable reinforced double swing gates for the entry of the ECF and the entry of the limited use gate and integrate the gates into the new perimeter protection. Include a cable reinforced swing gate for pedestrian access to the ECF.

New fencing shall be minimum 2.10 m high chain link fence and comply with Host Nation security fence requirements as implemented for the existing Base’s perimeter protection. In the absence of Host Nation standards, provide fencing as per UFC 4-022-03, Security Fences + Gates and STRUCTURAL Section 4.0 requirements.

Provide double extension arms with 3 strands of barbed wire for a total 2.44 meter height. Match color of existing fence. Provide a lock for each gate with 2 keys for each lock. Provide grounding every 30 meters of fence, at every fence corner, and at gate posts (2 per gate).

Provide one (1) active vehicle barrier (AVB) and a system of passive vehicle barriers to ensure effective containment of the protected area outside the entry control facility against penetration by explosive-laden vehicles. The barriers do not need to be on the DoD Anti-Ram Vehicle Barrier List or DS Certified Ant-Ram Vehicle Barriers.

The active vehicle barrier shall be K4 (M30) rated and cover the complete width of the inbound and outbound lanes at the end of the response zone. Active Vehicle Barrier Travel Time shall be maximum 2 seconds.

The passive vehicle barrier system, especially where combined with security fencing, shall minimum meet provisions of the system designed for the cable reinforced chain link fence as per UFC 4-022-03 utilizing minimum 2 cables of 3/4 inch diameter each (see Att. # 8).

Provide passive Anti-Ram Bollards as per UFC 4-022-02 to protect sections of the cable reinforced fence that are not hardened and where the perimeter protection crosses walkways.

Vehicle barriers utilized will not need to be tested products listed on the DoD Anti-Ram Vehicle Barrier List.

Block off the existing gate with passive barriers like boulders, bollards, jersey barriers eligible to protect the gate against the applicable moving vehicle threat.

2.13 OUTDOOR FURNISHINGS

For each ID-Check island, install a motorized drop arm, a prefabricated guard booth (optional) and a barrier wall to protect the guards against errant impact.

Design the ID Check area in compliance with section 6.4 of SDDCTEA Pamphlet 55-15.

Each prefabricated guard booth shall be minimum 1.2 m wide and 3 m long with an inside ceiling height of minimum of 2.2 m above finish floor. Each booth shall be provided with natural ventilation and installed windows shall ensure 360-degree field of view. Door(s) shall be sliding doors oriented in the direction of each lane for which a guard occupying the booth has vetting responsibility. Each booth shall include a counter oriented such that a guard is facing inbound (ingress) traffic while seated or standing at the counter.