The key details are:
- The contract will be a design-build, firm fixed price (FFP) construction contract with an estimated value between $500,000 and $1,000,000 USD.
- The planned performance period is between one and two calendar years after contract award, including the complete design and entire construction project.
- The scope of work includes repairing the garage floor and interior trench drains, repairing the vehicle washing area and installing an oil water separator, repairing the garage interior walls and exterior walls, providing new exterior wall waterproofing and insulation, replacing the roof membrane and pavement, providing new railings and fall protection, replacing the vehicle entry door, lighting, heating pipes, and existing railings, and installing domestic water and sanitary service for overhead ambulance washing.
- This is a pre-solicitation announcement, and the formal solicitation is planned to be issued within 30 days. The contract will be competed with full and open competition, without any small business set-asides or socioeconomic preferences.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| B.08.02_Att8_Bank Letter of Assurance (BLA) Template_New.docx | DOCX document | |
| B.08.02 lt22_Att4_Dedication Plaque.pdf | ||
| B.08.02_Att5_Price Schedule Purvciems.docx | DOCX document | |
| B.08.02 lt22_Att1_Location Map.pdf | ||
| B.08.02 lt22_Att2_As-built Site-Utilities Plan.pdf | ||
| B.08.02_Att7_Full Spec Binder.pdf | ||
| B.08.02_Att9_Past Performance Questionair PPQ.docx | DOCX document | |
| B.08.02 lt22_Att3_ConcArchDwgs.pdf | ||
| B.08.02_Att10_Site Visit Attendee Worksheet.xlsx | XLSX spreadsheet | |
| B.08.02 lt22_011010_GaragePurvciems SOW.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION 01 22 00
PRICE AND PAYMENT PROCEDURES
01/21
PART 1 GENERAL
PAYMENT TYPES
The costs for performance of any work required by the contract which is not associated with a specific base or option item description shall be included in the first base item (Base Item 0001).
Single Job Payment Items
Payment items for the work of this contract for which contract lump sum payments will be made are listed in the PRICE SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular job or unit price payment item, are included in the listed job item most closely associated with the work involved.
The job price and payment made for each item listed constitutes full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.
SCHEDULE OF ITEMS: BASE ITEMS
Base Item 0001: Building Renovation and Improvements
Unit of Measure: Job.
Payment will be made for costs associated with the design and construction of new exterior wall waterproofing and protective insulation boards, and exterior drainage, provide new roof membrane and paving for garage roof that serves as first floor entry terrace, provide new railing between first floor entry terrace and non-walkable garage roof, provide new fall protection on top of garage entry and exit driveway’s retaining walls, replace existing railing around garage, repair garage interior walls and interior sides of exterior walls as indicated in the SECTION 01 10 10 and shown on the conceptual layout, with the exceptions of the bid options listed below. This work shall include all applicable demolition and removals work to support the work elements contained in this item.
SCHEDULE OF ITEMS: OPTION ITEMS
Awarding of Options
The Government reserves the right to award any option or combination of options in any order and the exercise of any option will not commit the Government to award any other option(s).
Option 1: Item 0002: Repair garage floor and interior trench drains
Unit of Measure: Job.
Payment will be made for costs associated with the design and construction of repairs to the garage’s floor and interior trench drains to help increase the buildings capacity to deal with water entering the building. This includes water and snow melt from the emergency vehicles as indicated in SECTION 01 10 10 and the conceptual layout, with the exceptions of the bid options listed below.
Option 2: Item 0003: Repair vehicle washing area and provide Oil Water Separator
Payment will be made for costs associated with the design and construction of repairs and improvements to the garage’s vehicle wash station. This includes the installation of an oil water separator and a domestic water and sanitary service for overhead ambulance washing as indicated in SECTION 01 10 10 and the conceptual layout, with the exceptions of the bid options listed below.
Option 3: Item 0004: Replace garage interior lighting
Payment will be made for costs associated with the design and construction of the replacement of the garage’s overhead lighting as indicated in SECTION 01 10 10 and the conceptual layout, with the exceptions of the bid options listed below.
Option 4: Item 0005: Replace main heating pipes
Unit of Measure: Job.
Payment will be made for costs associated with the design and construction of the replacement of the garage’s main heating pipes up to the current new stainless-steel connections installed in the latest renovation as indicated in SECTION 01 10 10 and the conceptual layout, with the exceptions of the bid options listed below.
Option 5: Item 0006: Replace vehicle entry door
Unit of Measure: Job.
Payment will be made for costs associated with the design and construction of the replacement of the garage’s roll up door on the exit side with an insulated door as indicated in SECTION 01 10 10 and the conceptual layout, with the exceptions of the bid options listed below.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
-- End of Section - V7 Aug 2020 SECTION 01 22 00 Page 3