SECTION 01 22 00

PRICE AND PAYMENT PROCEDURES

06/19

PART 1 GENERAL

0. PHASING REQUIREMENTS

0. PAYMENT TYPES

1. SINGLE JOB PAYMENT ITEMS

Payment items for the work of this contract for which contract lump sum payments will be made are listed in the PRICE SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular job or unit price payment item, are included in the listed job item most closely associated with the work involved.

The job price and payment made for each item listed constitutes full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.

If there is any work required of this contract that is not associated with a base bid item description or bid option description, then the costs for that work shall be included in the first base bid item.

0. SCHEDULE OF ITEMS: BASE ITEMS

2. Base Item 0001: Design and Construct three (3) Classrooms including covered terrace walkway.

Unit of Measure: Job.

Payment will be made for costs associated with the construction of a single-story concrete / masonry building with three (3) classrooms, single-sloped metal roof and covered terrace walkway. Construction work includes but is not limited to installing doors, louvered windows, paint, blackboard paint, exterior concrete stairs and ramp.

2. Base Item 0002: Demolition of one (1) makeshift tent classroom.

Unit of Measure: Job.

Payment will be made for costs associated with the demolition of a single-story makeshift temporary classroom building made of wood structure covered with textile.

0. SCHEDULE OF ITEMS: OPTION ITEMS

3. Option 1: Item 0003: Design and Construct one (1) Classroom including covered terrace walkway.

Unit of Measure: Job.

Payment will be made for costs associated with the construction of a single-story concrete / masonry building with one (1) classroom as an addition to the three classrooms described in the Base Items with single-sloped metal roof and covered terrace walkway. Construction work includes but is not limited to installing doors, louvered windows, paint, blackboard paint, exterior concrete stairs and ramp.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used