B.08.02 Att 7_01 22 00 Pay Terms Bid Schedule.docx

DOCX document 50 KB Posted

Attached to
IEU-23-0003 Tsirguliina School Renovation Federal contract opportunity
Solicitation number
IEU-23-0003
Issued by
Department of the Army European Command

About this file

This document includes a price schedule and payment terms for a federal design-build contract opportunity. The contract is for renovations to the Tsirguliina School in Tsirguliina, Estonia including replacement of roofs and basement waterproofing on three buildings. The contract contains base items and optional items, all paid as lump sums. The estimated value is between $1 million to $5 million USD. The period of performance is 455 calendar days from notice to proceed with liquidated damages of $583 per day for delays. Interested offerors must be registered in the US government's System for Award Management to be eligible for award.

View the file

Other files for this federal contract opportunity

Other files attached to IEU-23-0003 Tsirguliina School Renovation, newest first.
File Type Posted
B.08.02 Att 11 Commitment Letters.docx DOCX document
B.08.02 Att 8_BLA Template.docx DOCX document
A.02.17_Att 4_Structural Calculation guidline.pdf PDF
A.02.17_Att 2_Conceptual Site Plan.pdf PDF
A.02.17_Att 3_Roof Areas.pdf PDF
A.03.16 Att 5_Specs Binder IAF-23-0003 Tsirguliina.pdf PDF
A.02.17 SOW Tsirguliina School Renovation.pdf PDF
A.02.17_Att 1_Proj Location Map.pdf PDF
B.07.01 Att 6_Site Visit Registration Spreadsheet.xlsx XLSX spreadsheet
B.08.02 Att 10_PPQ.pdf PDF
B.08.02 Att 8_BLA Template.docx DOCX document
B.08.02 Att 9_BLG Template.docx DOCX document
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

POP and LD Clauses

SECTION 01 22 00

PRICE AND PAYMENT PROCEDURES

16 September 2022

PART 1 GENERAL

PAYMENT TYPES

SINGLE JOB PAYMENT ITEMS

Payment items for the work of this contract for which contract lump sum payments will be made are listed in the PRICE SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular job or unit price payment item, are included in the listed job item most closely associated with the work involved.

The job price and payment made for each item listed constitutes full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.

If there is any work required of this contract that is not associated with a base bid item description or bid option description, then the costs for that work shall be included proportionally spread across the base bid items.

SCHEDULE OF ITEMS: BASE ITEMS

Base Bid Item 0001: Design and Construction of School Building Roof Replacement

Unit of Measure: Job.

Payment will be made for costs associated with the design and construction of the roof replacement on the School Building for the Tsirguliina School Renovation, Tsirguliina, Estonia as indicated in the SECTION 01 10 10 Statement of Work, and shown on the concept plan Statement of Work attachments, with the exception of option item listed below. This work shall include all applicable demolition and removals work to support the work elements contained in this item.

Base Item 0002: Design and Construction of School Building Basement Waterproofing and Insulation and Site Stormwater Drainage Improvements

Unit of Measure: Job.

Payment will be made for costs associated with the design and construction of the basement waterproofing and insulation and site stormwater drainage improvements on the gym building for the Tsirguliina School Renovation, Tsirguliina, Estonia as indicated in the SECTION 01 10 10 Statement of Work, and shown on the concept plan Statement of Work attachments, with the exception of option item listed below. This work shall include all applicable demolition and removals work to support the work elements contained in this item.

SCHEDULE OF ITEMS: OPTION ITEMS

Option Item 0003: Design and Construction of Gym Building Roof Replacement

Unit of Measure: Job.

Payment will be made for costs associated with the design and construction of the roof replacement on the Gym building for the Tsirguliina School Renovation, Tsirguliina, Estonia as indicated in the SECTION 01 10 10 Statement of Work, and shown on the concept plan Statement of Work attachments. This work shall include the roof on the gym building and the adjacent hallways connecting to the School and Kindergarten buildings. This work shall include all applicable demolition and removals work to support the work elements contained in this item.

Option Item 0004: Design and Construction of Gym Building Basement Waterproofing and Insulation and Site Stormwater Drainage Improvements

Unit of Measure: Job.

Payment will be made for costs associated with the design and construction of the basement waterproofing and insulation and site stormwater drainage improvements on the Gym building for the Tsirguliina School Renovation, Tsirguliina, Estonia as indicated in the SECTION 01 10 10 Statement of Work, and shown on the concept plan Statement of Work attachments. This work shall include the roof on the gym building and the adjacent hallways connecting to the School and Kindergarten buildings. This work shall include all applicable demolition and removals work to support the work elements contained in this item.

Option Item 0005: Design and Construction of Kindergarten Building Roof Replacement

Unit of Measure: Job.

Payment will be made for costs associated with the design and construction of the roof replacement on the Kindergarten building for the Tsirguliina School Renovation, Tsirguliina, Estonia as indicated in the SECTION 01 10 10 Statement of Work, and shown on the concept plan Statement of Work attachments. This work shall include all applicable demolition and removals work to support the work elements contained in this item.

Option Item 0006: Design and Construction of Kindergarten Building Basement Waterproofing and Insulation and Site Stormwater Drainage Improvements

Unit of Measure: Job.

Payment will be made for costs associated with the design and construction of the basement waterproofing and insulation and site stormwater drainage improvements on the Kindergarten building for the Tsirguliina School Renovation, Tsirguliina, Estonia as indicated in the SECTION 01 10 10 Statement of Work, and shown on the concept plan Statement of Work attachments. This work shall include all applicable demolition and removals work to support the work elements contained in this item.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

-- End of Section --

SECTION 01 22 00 Page 1 Offerors shall provide pricing for all base and option items.

The following items include providing all labor, materials, equipment, and services necessary to complete the design and construction of the work identified in the attached Plans, Specifications, Scope of Work (SOW), Solicitation/Request for Proposal. It also includes preparation of all documents, submittals, and schedules; inspections; and compliance with all technical, quality control, administrative, and safety requirements. All work shall be performed in accordance with these documents. Refer to Specification Section 01 22 00 Price and Payment Procedures for additional description of the work associated with each of the items.

Period of Performance: Refer to clause COMMENCEMENT PROSECUTION AND EXECUTION OF WORK (52.211-10) in the Solicitation/Request for Proposal for the period of performance for all base and option items.

Liquidated Damages: Refer to clause LIQUIDATED DAMAGES-CONSTRUCTION (52.211-12) in the Solicitation/Request for Proposal for the liquidated damages for all base and option items.

Option Items: The Government reserves the right to award the options up to 90 calendar days after contract award.

Item No.
Description
Qty
Unit
Unit Price
Amount

BASE ITEMS

0001
School Building Roof Replacement
1
Job
$
$
0002
School Building Basement Waterproofing and Insulation and Site Stormwater Drainage Improvements
1
Job
$
$
Total of Base Items 0001-0002
$

OPTION ITEMS

0003
Gym Building Roof Replacement
1
Job
$
$
0004
Gym Building Basement Waterproofing and Insulation and Site Stormwater Drainage Improvements
1
Job
$
$
0005
Kindergarten Building Roof Replacement
1
Job
$
$
0006
Kindergarten Building Basement Waterproofing and Insulation and Site Stormwater Drainage Improvements
1
Job
$
$
Total of Option Items 0003-0006
$
Total of all Base and Option Items
$

EXTENSIONS: All extensions of the unit prices shown will be subject to verification by the Government. In case of variation between the unit price and the extension, the unit price will be considered to be the offer.

ATTACHMENT 1

PRICE SCHEDULE

Tsirguliina School Renovation, Tsirguliina, Estonia

16 September 2022

-- END OF PROPOSAL SCHEDULE --

V5.0 Mar 2020

Tsirguliina School Renovation, Tsirguliina, Estonia

16 September 2021

COMMENCEMENT PROSECUTION AND EXECUTION OF WORK (52.211-10)

The Contractor shall be required to (a) commence work under this contract within 7 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use no later than 455 calendar days after the contractor receives the Notice to Proceed. Any options, if awarded, shall be completed concurrently with all other work.

The time stated for completion shall include final cleanup of the premises. The Government intends to issue a single Notice to Proceed for all work.

LIQUIDATED DAMAGES-CONSTRUCTION (52.211-12)

If the Contractor fails to complete the work associated with this contract within the time specified in under 52.211-10, the Contractor shall pay liquidated damages to the Government in the amount of $583 for each calendar day of delay until the work is completed or accepted.

23 March 2020

File details come from the government source that posted it. Updated .