B.08.02 Att 15 Price Schedule.docx
DOCX document 36 KB Posted
- Solicitation number
- W912GB24R0052
- Issued by
-
Department of the Army European Command
About this file
This document is a Price Schedule for a federal contract opportunity related to the design and construction of new classroom and kitchen facilities at two primary schools in the Shiselweni Region of Eswatini.
The Price Schedule lists the base and option line items, including new classroom facilities at Kamzila Fea Primary School and Makhonza Primary School, as well as options for new kitchen facilities, demolition of existing kitchens, and demolition of an existing classroom at Makhonza. The period of performance, liquidated damages, and instructions for awarding options are also provided. The total price for all base and option items is listed at the end of the schedule.
The related federal contract opportunity is Solicitation W912GB24R0052 for design and construction services to renovate the two primary school facilities in Eswatini. The solicitation includes details on the project location, general scope of work, and instructions for submitting proposals. Companies must be registered in the System for Award Management (SAM) to be eligible for award.
View the file
Other files
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PRICE SCHEDULE
SWZ KAMZILA FEA PRIMARY SCHOOL
SWZ MAKHONZA PRIMARY SCHOOL
SHISELWENI REGION, ESWATINI
15-April-2024
PRICE SCHEDULE
IMPROVE WATER SUPPLY FOR TSAGHKABER & ARVASHOGH COMMUNITIES
TSAGHKABER & ARVASHOGH, ARMENIA
29-NOV-22
Offerors shall provide pricing for all base and option items.
The following items include providing all labor, materials, equipment, and services necessary to complete the design and construction of the work identified in the attached Plans, Specifications, Statement of Work (SOW), Request for Proposal and Base Contract. It also includes preparation of all documents, submittals, and schedules; inspections; and compliance with all technical, quality control, administrative, and safety requirements. All work shall be performed in accordance with these documents. Refer to Specification Section 01 22 00 Price and Payment Procedures for additional description of the work associated with each of the items.
Period of Performance: Refer to clause COMMENCEMENT PROSECUTION AND EXECUTION OF WORK (52.211-10) in the Request for Proposal for the period of performance for all base and option items.
Liquidated Damages: Refer to clause LIQUIDATED DAMAGES-CONSTRUCTION (52.211-12) in the for Proposal for the liquidated damages for all base and option items.
Option Items: The Government reserves the right to award the options up to 90 calendar days from contact award. There will be no period of performance extension if the options are awarded. See Section 01 22 00 for additional information regarding the award of options.
| Item No. |
| Title |
| Quantity |
| Unit |
| Unit Price |
| Amount |
BASE ITEMS
| 0001 |
| Kamzila Fea – New (4) Classroom Facility |
| 1 |
| Job |
| $ |
| $ |
| 0002 |
| Makhonza – New (6) Classroom Facility |
| 1 |
| Job |
| $ |
| $ |
| Total of Base Items 0001 – 0002 |
| $ |
OPTION ITEMS
| 0003 |
| Option 1, Kamzila Fea – New Kitchen Facility |
| 1 |
| Job |
| $ |
| $ |
| 0004 |
| Option 2, Kamzila Fea – Demolish Existing Kitchen Facility |
| 1 |
| Job |
| $ |
| $ |
| 0005 |
| Option 3, Makhonza – New Kitchen Facility |
| 1 |
| Job |
| $ |
| $ |
| 0006 |
| Option 4, Makhonza – Demolish Existing Kitchen Facility |
| 1 |
| Job |
| $ |
| $ |
| 0007 |
| Option 5, Makhonza – Demolish Existing Classroom (classroom #3) Facility |
| 1 |
| Job |
| $ |
| $ |
| Total of Option Item 0003 – 0007 |
| $ |
| Total of all Base and Option Items |
| $ |
EXTENSIONS: All extensions of the unit prices shown will be subject to verification by the Government. In case of variation between the unit price and the extension, the unit price will be considered to be the offer.
-- END OF PROPOSAL SCHEDULE --