This document is an Attachment 12 - Contractor Past Experience Information Sheet related to a federal contract opportunity for the design-build renovation of the Phillip Mtywaku Secondary School in Eastern Cape, South Africa.
The key details are: The contract opportunity, solicitation number W912GB24R0048, is for the design and construction of a new five-classroom building, renovation of the existing kitchen and library, and provision of site infrastructure at the Phillip Mtywaku Secondary School. The planned contract type is a Design-Build, Firm Fixed Price construction contract with an estimated value between $1,000,000 and $5,000,000 USD and a 450-day performance period. The USACE Europe District is the procuring agency. The attachment provides a template for contractors to detail their past performance experience, including project details, cost, completion status, and role (prime, subcontractor, joint venture, key subcontractor). Contractors must demonstrate relevant experience to be considered for this opportunity.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT 12 (amended 13 FEB2023) W912GB24R0048_ IAF-24-0001 Phillip Mtywaku Secondary School Eastern Cape, South Africa
CONTRACTOR PAST EXPERIENCE INFORMATION SHEET
PROJECT NO IAF-24-0001 Phillip Mtywaku Secondary School Eastern Cape, South Africa, Page 1
Project Name, Contract number, and Location:
Past Performance:
1. The day, month, and year work was completed: _______________
2. Is this project more than 90% complete? ____ Yes ____ No If “No” explain current percentage of completion, if yes and between 75-99% complete please explain how the percentage was calculated and what work remains.
3. The final cost of this project €_________________________
4. Do not provide a listing of existing or previous contracts, but rather provide detailed information of work for this project:
o Design- Build or Design-Bid-Build o Scope of the project, to include purpose/use of facility.
o Size of the project, differentiate square footage of new construction versus renovation if project includes both.
o Type and percentage of work that was self-performed.
o Whether the project involved new construction, renovation, or both. Clearly delineate square meters for construction and renovation.
o Whether the project was completed for the United States DoD.
(Continue typing if required to provide more information)
ATTACHMENT 2 – CONTRACTOR PAST EXPERIENCE INFORMATION SHEET
PROJECT NO. IAF-24-0001 Phillip Mtywaku Secondary School Eastern Cape, South Africa Page 2
Offeror: A contractor and/or company submitting a proposal for this solicitation.
Prime Contractor: A contractor that performed at least 15% of the work, and managed all other work for the project.
Sub Contractor: A contractor that performed part of the project work, but did not manage the entire project.
Joint Venture: More than one contractor with a legal binding agreement to work together.
Key Subcontractor: A contractor that has signed a letter of commitment to perform work for the duration of the contract for the Offeror, and the Offeror may take credit for the Key Subcontractor’s past performance if it was meaningful to this procurement. Ensure you the letter of commitment is signed by both the Offeror and the Key Subcontractor.
5. Mark one of these selections:
Work was completed as the ____ Prime ____ Subcontractor ___ Joint Venture __ Key Subcontractor
a. No additional information is required for work performed as the Prime other than what is on Page 1 of this form.
b. If work was as a Joint Venture, explain the relationship of the company, which company performed the work, and how the work performed and the relationship provides an added benefit for experience.
c. If work was performed as a Key Subcontractor, explain how the work performed as a Key Subcontractor provides an added benefit for experience:
d. If work was as a Subcontractor, explain how the work performed as a Subcontractor is a benefit for experience such as, responsible for the work performed and managed the portion of work performed including submittals: