This document contains a federal contract solicitation and related opportunity details. The solicitation is for the design and construction of a new parking apron and aircraft parking shelters at Al Jaber Air Base in Kuwait. Key requirements include construction of a new aircraft parking apron and taxiways, enclosed aircraft parking shelters with twelve spaces total across two hangar buildings, and associated site improvements. The estimated value is between $25-100 million. The NAICS code is 236220 and small business size standard is $39.5 million. The period of performance is 649 calendar days from notice to proceed. The acquisition will be competed full and open with a single award of a firm-fixed-price construction contract determined based on best value. The solicitation number is W912ER22R0004 and was released by the U.S. Army Corps of Engineers Transatlantic Middle East District.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

APPENDIX A

SOLICITATION ATTACHMENTS

ATTACHMENT A
CORPORATE CERTIFICATE/AUTHORITY TO BIND PARTNERSHIP
ATTACHMENT B
PERFORMANCE DISTRIBUTION STATEMENT
ATTACHMENT C
CONSTRUCTION EXPERIENCE FORM
ATTACHMENT D
PAST PERFORMANCE OVERVIEW SHEET
ATTACHMENT E
PROJECT SUMMARY FORM
ATTACHMENT F
PAST PERFORMANCE QUESTIONNAIRE (PPQ-0)
ATTACHMENT G
PROPOSAL SCHEDULE AND COST BREAKDOWN SHEET
ATTACHMENT H
FINANCIAL STANDING QUESTIONER
ATTACHMENT I
CALCULATION OF SELF-PERFORMED WORK

ATTACHMENT A

(Section 00 45 00 Representation and Certification)

CORPORATE CERTIFICATE/AUTHORITY TO BIND PARTNERSHIP

A. CORPORATE CERTIFICATE

If a corporation submits the proposal, the Corporate Certificate at paragraph A below must be submitted. If the proposal is submitted by a partnership, the Authority to Bind Partnership at paragraph B below must be completed and a copy of the partnership agreement included with the proposal.

CORPORATE CERTIFICATE

I, , certify that I am the (Title) of the corporation named as offer/contractor herein, that , who signed this proposal/contract on behalf of the offeror/contractor was then of said corporation; that said proposal/contract was duly signed for and on behalf of said corporation by authority of its governing body and within the scope of its governing body and within the scope of its corporate powers.

________________________________(CORPORATE SEAL)

(SIGNATURE)

B. AUTHORITY TO BIND PARTNERSHIP

This is to certify that the names and signatures of all partners are listed below and that the person signing the proposal had authority to actually bind the partnership pursuant to its partnership agreement. Each of the partners individually has full authority to enter into and execute contractual instruments on behalf of said partnership, with the United States of America except as follows: (State "none" or describe limitations, if any). This authority shall remain in full force and effect until such time as the revocation of authority by any cause whatsoever has been furnished in writing to and acknowledged by the Contracting Officer.

(Names and signatures of all partners)

(End of Certificate)

ATTACHMENT B

PERFORMANCE DISTRIBUTION STATEMENT

1. Although not all subcontractors need to be listed, statement must include all major subcontractors, defined as those performing 20% or more of the total dollar value ($) of the contract.

2. Add more lines, if needed, to list more subcontractors.

3. The total “% of Work” column cannot total more than 100%.

4. REMINDER: All subcontractors completing 20% or more of the work require a letter of intent to be submitted.

5. See example below for details.

Line
Company / Entity
Role
Scope of Work
% of Work
1
ABC Company
Offeror
Management, safety, QC, paving, surveying, masonry, misc.
50%
2
Hamid & Sons, Inc.
Major Sub
MEP
20%
3
Overhead Door Co.
Major Sub
Specialty roll-up doors
15%
Line
Company / Entity
Role
Scope of Work
% of Work

Offeror

ATTACHMENT C

CONSTRUCTION EXPERIENCE FORM - INSTRUCTIONS

1. Use one form for each contract.

2. Forms may expand to more than one page, but remember that this form is only for greater weight considerations.

3. Do not make changes to any of the shaded blocks.

4. Complete all non-shaded blocks in the top summary section.

5. Place an “x” next to all Topics that are applicable to the specific contract (not all topics need to be addressed for each contract).

6. Complete the non-shaded “How experience gained” column to describe your experience with that specific topic and how it will enable successful performance on this project.

7. See example below for details.

Summary Section

#
Contract Name / Title
1
D/B Genesis Operational Facilities
Location (Country/Base or City)
Role
Value ($)
Start / End Dates
Al Jaber Air Base, Kuwait
Prime
$93.7 M
May 2018 – Jul 2020

Contract Description - briefly describe the scope and summarize the salient features of the contract

Constructed a logistics facility utilizing conventional design and construction methods to accommodate the mission of the facility. The facility will include a concrete foundation and a concrete structural envelope/frame with concrete masonry unit exterior stucco, fire suppression systems, all utilities, pavements, communications, site improvements, and associated support facilities to provide a complete and useable facility. Facilities will be designed as permanent construction in accordance with the DoD Unified Facilities Criteria (UFC) 1-200-01, General Building Requirements and UFC 1-200-02, High Performance and Sustainable Building Requirements. This project will comply with DoD antiterrorism/force protection requirements per UFC 4-101-01.

Specific Experience (paragraph letters below align with the solicitation evaluation criteria)

Topic
How experience gained on listed contract will enable successful performance on Super Hornet Procurement B
x
a. Similar scope projects.
The access and parking aprons are similar to the paving requirements of TLC. The total paving of this contract, at least $25M, is similar in magnitude to TLC.
x
b. Permits and approvals
Work was performed on Al Jaber Air Base, giving us considerable experience obtaining base passes and badges. We appoint an in-house Security Coordinator to manage the Site Security Plan and liaise with the Al Jaber authorities and the subcontracted private security firm, XXX company. The XXX company provided security and escorts, and has worked on Al Jaber Air Base for more than 20 years.
x
c. Working on or around operational military or airfield facilities
Project is on an operational airfield
x
d. Work locations access
We obtained approval for the Comms Tower in an innovative method, allowing fabrication to start much sooner than in the typical submit/approve process. In addition, because this contract was in Kuwait , we worked all the permits and approvals.

ATTACHMENT D

PAST PERFORMANCE OVERVIEW SHEET

List work which best illustrates current qualifications relevant to this award. Each project listed on this sheet should have a completed Project Summary Form (Attachment E). Mark Prime, Sub, or Joint Venture (ONLY ONE).

Contract Name/Client, Location of Services
Prime
Sub
JV
Total Contract $ Amount
Offeror's Share of Responsibility for Total Construction Contract

SAMPLE: Ellis Island Seawall Renovation/

X
$10,000,000
$10,000,000

1.

3.

4.

5.

6.

7.

8.

9.

10.

OFFEROR’S NAME
DATE

ATTACHMENT E

PROJECT SUMMARY FORM

PROJECT No: (Circle one): 1 2 3 4 5 6 7 8 9 10

Name of Reference Contact:_________________________________________

E-mail Address:___________________________________________________

Telephone Number:________________________________________________

Project Title: _____________________________________________________

Contract Number:_________________________________________________

Location of Project: _______________________________________________

Contract Amount (U.S. Dollar Amount): $_____________________________

Contract Award Date:_____________________________________________

Contract Completion Date:_________________________________________

Contract Duration (Period of Performance):___________________________

Description of the Project’s Scope and Magnitude:

Details of your company’s role and activities during construction of the project:

(Describe your role in this project. Include whether your firm participated as a prime or a subcontractor. SPECIFICALLY describe your roles and responsibilities in the design portion of the contract, if any. Provide details for any past performance problems encountered and the corrective actions taken.

ATTACHMENT F

PAST PERFORMANCE QUESTIONNAIRE (PPQ)

USACE PAST PERFORMANCE QUESTIONNAIRE (Form PPQ)

CONTRACT INFORMATION (Contractor is to complete Blocks 1-4)

1. Contractor Information
Firm Name:CAGE Code:
Address:UEI Number:

Phone Number:

Email Address:

Point of Contact: Contact Phone Number:

2. Work Performed as: |_| Prime Contractor |_| Sub Contractor |_| Joint Venture |_| Other (Explain) Percent of project work performed:

If subcontractor, who was the prime (Name/Phone #):

3. Contract Information Contract Number:

Delivery/Task Order Number (if applicable):

Contract Type: |_| Firm Fixed Price |_| Cost Reimbursement |_| Other (Please specify):

Contract Title:

Contract Location:

Award Date (mm/dd/yy):

Contract Completion Date (mm/dd/yy):

Actual Completion Date (mm/dd/yy):

Explain Differences:

Original Contract Price (Award Amount):

Final Contract Price (to include all modifications, if applicable):

Explain Differences:

4. Project Description:

Complexity of Work |_| High |_| Med |_| Routine

What project in Factor 1, paragraph b. is this project being used to qualify for? (One project can be used to qualify for more than one factor)

How is this project relevant to project of submission? (Please provide details such as similar equipment, requirements, conditions, etc.)

CLIENT INFORMATION (Client is to complete Blocks 5-8)

5. Client Information Name:

Title:

Phone Number:

Email Address:

6. Describe the client’s role in the project:

7. Date Questionnaire was completed (mm/dd/yy):

8. Client’s Signature:

NOTE: USACE REQUESTS THAT THE CLIENT COMPLETES THIS QUESTIONNAIRE AND SUBMITS DIRECTLY BACK TO THE OFFEROR. THE OFFEROR WILL SUBMIT THE COMPLETED QUESTIONNAIRE TO USACE WITH THEIR PROPOSAL, AND MAY DUPLICATE THIS QUESTIONNAIRE FOR FUTURE SUBMISSION ON USACE SOLICITATIONS. CLIENTS ARE HIGHLY ENCOURAGED TO SUBMIT QUESTIONNAIRES DIRECTLY TO THE OFFEROR. HOWEVER, QUESTIONNAIRES MAY BE SUBMITTED DIRECTLY TO USACE. PLEASE CONTACT THE OFFEROR FOR USACE POC INFORMATION. THE GOVERNMENT RESERVES THE RIGHT TO VERIFY ANY AND ALL INFORMATION ON THIS FORM.

ADJECTIVE RATINGS AND DEFINITIONS TO BE USED TO BEST REFLECT

YOUR EVALUATION OF THE CONTRACTOR’S PERFORMANCE

RATING
DEFINITION
NOTE
(E) Exceptional
Performance meets contractual requirements and exceeds many to the Government/Owner’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with few minor problems for which corrective actions taken by the contractor was highly effective.
An Exceptional rating is appropriate when the Contractor successfully performed multiple significant events that were of benefit to the Government/Owner. A singular benefit, however, could be of such magnitude that it alone constitutes an Exceptional rating. Also, there should have been NO significant weaknesses identified.
(VG) Very Good
Performance meets contractual requirements and exceeds some to the Government’s/Owner’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with some minor problems for which corrective actions taken by the contractor were effective.
A Very Good rating is appropriate when the Contractor successfully performed a significant event that was a benefit to the Government/Owner. There should have been no significant weaknesses identified.
(S) Satisfactory
Performance meets minimum contractual requirements. The contractual performance of the element or sub-element contains some minor problems for which corrective actions taken by the contractor appear or were satisfactory.
A Satisfactory rating is appropriate when there were only minor problems, or major problems that the contractor recovered from without impact to the contract. There should have been NO significant weaknesses identified. Per DOD policy, a fundamental principle of assigning ratings is that contractors will not be assessed a rating lower than Satisfactory solely for not performing beyond the requirements of the contract.
(M) Marginal
Performance does not meet some contractual requirements. The contractual performance of the element or sub-element being assessed reflects a serious problem for which the contractor has not yet identified corrective actions. The contractor's proposed actions appear only marginally effective or were not fully implemented.
A Marginal is appropriate when a significant event occurred that the contractor had trouble overcoming which impacted the Government/Owner.
(U) Unsatisfactory
Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the element or sub-element contains serious problem(s) for which the contractor's corrective actions appear or were ineffective.
An Unsatisfactory rating is appropriate when multiple significant events occurred that the contractor had trouble overcoming and which impacted the Government/Owner. A singular problem, however, could be of such serious magnitude that it alone constitutes an unsatisfactory rating.
(N) Not Applicable
No information or did not apply to your contract
Rating will be neither positive nor negative.

TO BE COMPLETED BY THE CLIENT

PLEASE CIRCLE THE ADJECTIVE RATING WHICH BEST REFLECTS

YOUR EVALUATION OF THE CONTRACTOR’S PERFORMANCE.

1. QUALITY

a) Quality of technical data/report preparation efforts
E VG S M U N
b) Ability to meet quality standards specified for technical performance
E VG S M U N
c) Timeliness/effectiveness of contract problem resolution without extensive customer guidance
E VG S M U N
d) Adequacy/effectiveness of quality control program and adherence to contract quality assurance requirements (without adverse effect on performance)
E VG S M U N

2. SCHEDULE/TIMELINESS OF PERFORMANCE:

a) Compliance with contract delivery/completion schedules including any significant intermediate milestones. (If liquidated damages were assessed or the schedule was not met, please address below)
E VG S M U N
b) Rate the contractor’s use of available resources to accomplish tasks identified in the contract
E VG S M U N

3. CUSTOMER SATISFACTION:

a) To what extent were the end users satisfied with the project?
E VG S M U N
b) Contractor was reasonable and cooperative in dealing with your staff (including the ability to successfully resolve disagreements/disputes; responsiveness to administrative reports, businesslike and communication)
E VG S M U N
c) To what extent was the contractor cooperative, businesslike, and concerned with the interests of the customer?
E VG S M U N
d) Overall customer satisfaction
E VG S M U N

4. MANAGEMENT/ PERSONNEL/LABOR

a) Effectiveness of on-site management, including management of subcontractors, suppliers, materials, and/or labor force?
E VG S M U N
b) Ability to hire, apply, and retain a qualified workforce to this effort
E VG S M U N
c) Government Property Control
E VG S M U N
d) Knowledge/expertise demonstrated by contractor personnel
E VG S M U N
e) Utilization of Small Business concerns
E VG S M U N
f) Ability to simultaneously manage multiple projects with multiple disciplines
E VG S M U N
g) Ability to assimilate and incorporate changes in requirements and/or priority, including planning, execution and response to Government changes
E VG S M U N
h) Effectiveness of overall management (including ability to effectively lead, manage and control the program)
E VG S M U N

5. COST/FINANCIAL MANAGEMENT

a) Ability to meet the terms and conditions within the contractually agreed price(s)?
E VG S M U N
b) Contractor proposed innovative alternative methods/processes that reduced cost, improved maintainability or other factors that benefited the client
E VG S M U N
c) If this is/was a Government cost type contract, please rate the Contractor’s timeliness and accuracy in submitting monthly invoices with appropriate back-up documentation, monthly status reports/budget variance reports, compliance with established budgets and avoidance of significant and/or unexplained variances (under runs or overruns)
E VG S M U N
d) Is the Contractor’s accounting system adequate for management and tracking of costs? If no, please explain in Remarks section.
Yes No
e) If this is/was a Government contract, has/was this contract been partially or completely terminated for default or convenience or are there any pending terminations? Indicate if show cause or cure notices were issued, or any default action in comment section below.
Yes No
f) Have there been any indications that the contractor has had any financial problems? If yes, please explain below.
Yes No

6. SAFETY/SECURITY

a) To what extent was the contractor able to maintain an environment of safety, adhere to its approved safety plan, and respond to safety issues? (Includes: following the users rules, regulations, and requirements regarding housekeeping, safety, correction of noted deficiencies, etc.)
E VG S M U N
b) Contractor complied with all security requirements for the project and personnel security requirements.
E VG S M U N

7. GENERAL

a) Ability to successfully respond to emergency and/or surge situations (including notifying COR, PM or Contracting Officer in a timely manner regarding urgent contractual issues).
E VG S M U N
b) Compliance with contractual terms/provisions (explain if specific issues)
E VG S M U N
c) Would you hire or work with this firm again? (If no, please explain below)
Yes No
d) In summary, provide an overall rating for the work performed by this contractor.
E VG S M U N

Please provide responses to the questions above (if applicable) and/or additional remarks.

Furthermore, please provide a brief narrative addressing specific strengths, weakness, deficiencies, or other comments which may assist our office in evaluating performance risk.

ATTACHMENT G

PROPOSAL SHEDULE AND COST BREAKDOWN SHEET

The Proposal Schedule and Cost Breakdown Sheet have been included separately as attachments in PDF.

ATTACHMENT H

FINANCIAL STANDING QUESTIONER

A primary consideration in the source selection process is to determine an offeror’s qualification, responsibility, and financial standing. Prior to awarding a contract, per Federal Acquisition Regulation (FAR) Part 9, the government must determine, through acceptable evidence, that an offeror has adequate financial resources, or the ability to obtain the financial resources, to perform the contract. The substantive answers in Attachment A are to be completed by the offeror’s financial institution. Offerors should obtain a bank stamp or seal AND signature of the referenced individual on the questionnaire. Failure to provide the requested information may render an offeror’s proposal non-responsible, and removed from competition.

GENERAL INFORMATION (to be completed by the contractor):

Contractor’s Name and address:

Point of Contact:

Telephone:

Email:

Solicitation number:

RESPONDENT INFORMATION (to be completed by an authorized Financial Institution representative):

Full Name and Title:

Name of Financial Institution:

Address:

Telephone/Fax:

Email address:

1. Does the contractor have an active account(s) with your financial institution? If yes, how many?

2. How long have the account(s) been active?

3. What are the account(s) average balance (digits only)?

4. How many returns (insufficient funds) has the contractor had in the last 12 months?

5. Does the contractor currently have outstanding loans? If yes, a) how many; b) what are the balances due on those loans (digits only); and c) is the contractor making payments in accordance with the terms of the loans?

6. In the last 12 months, has the contractor been able to meet its financial obligations on time?

7. Does the contractor have a line of credit? If so, a) what is the credit limit (digits only); and b) how much credit is presently available for use (digits only)?

If you need additional space to respond, please indicate that additional documentation was provided in response your above answers.

Certificate of Authority

I, ______________________ certify that as ______________________ of (insert name) (insert job title)

______________________ I am duly authorized to execute this form.

(insert corporation name)

Signature _______________________________________ Date ___________

(Financial Institution Seal/Stamp)

ATTACHMENT I

CALCULATION OF SELF-PERFORMED WORK

Use the following format to identify and calculate cost of the work to be self-performed.

Various definitions which may be helpful in completing this form can be found on page 2, below.

A. Clearly describe the work to be self-performed:

B. Show Calculation of Self-Performed Work:

B.1
Total bid price:
$
B.2
Subtract contractually-required design costs, if any:
$
B.3
Subtract G&A, home office overhead, prime contractor's markups for profit, bond, DBA insurance, etc.:
$
B.4
Total amount of work to be performed under the contract:
$
B.5
Work to be self-performed (Includes mobilization and utilization of owned or rented plant and equipment to be operated by the prime contractor's own employees; only those materials which will be both purchased and installed by the prime's own forces; labor associated with those aforementioned materials or equipment; only those supplies to directly support work performed by the contractor's own employees; and the contractor's own job overhead costs.):
$
B.6
% Self-performed work = Line B.5/ Line B.4 X 100% = %
%

I certify that the above information is current, accurate and complete to the best of my knowledge and that I have the authority to provide the information requested on this form.

DATE NAME

POSITION, COMPANY

The following are definitions concerning self-performance of work by the Prime Contractor, in accordance with FAR Clause 52.236-1 Performance of Work by the Contractor (APR 1984).

"Self-performance of work", "On the site" and "Total amount of work to be performed under the contract" are defined below.

“Self-performance of work” generally includes mobilization and utilization of owned or rented plant and equipment to be operated by the prime contractor's own (not subcontract) employees; only those materials which will be both purchased and installed by the prime's own (not subcontract) forces; labor associated with those aforementioned materials or equipment; only those supplies to directly support work performed by the contractor's own employees, and the contractor's own job overhead costs.

The following is NOT self-performed work for purposes of the clause: Prime contractor markups for profit, general and administrative overhead, bonds, or other indirect costs on self-performed or subcontracted work; "Owner-operated equipment", rental of plant or equipment for operation by subcontractors; purchase of materials for installation by subcontractors.

"On the site" includes the construction site(s) as well as off-site fabrication plant or other facilities necessary to manufacture assemblies or provide materials to be incorporated into the construction project.

“Total amount of work to be performed under the contract" is comprised of all direct (variable, fixed, one-time and semi-variable) costs to the contractor, including jobsite overhead costs, to construct the project. It generally includes all self-performed work, as defined above, and cost of all supplies, materials and subcontracts. It does not include design costs, home or branch office overhead costs or prime contractor markups for bond, profit, etc.”