B-54855 RR-26-2068_emergency-purchase-extension-approval~2.pdf
PDF 3 MB Posted
- Attached to
- Notice of Emergency Contract Extension: I-88 and Canadian National Railway Bridge Repair M.P. 121.19
- Solicitation number
- 27-557THA-ENGCO-B-54855
- Issued by
- Dupage County, Illinois
About this file
This is an Emergency Purchase Extension Approval form submitted to the Illinois Chief Procurement Office by the Toll Highway Authority (THA) Engineering Division, located in Downers Grove, Illinois. The extension pertains to an emergency contract with Lorig Construction Company (Des Plaines, Illinois) for emergency repairs to Bridge 821, which carries CN railroad traffic over westbound I-88. The original emergency contract, valued at $3,000,000, was initiated following an unforeseen vehicular impact that damaged a primary structural member of the bridge. The scope of work includes maintenance of traffic, temporary shoring and support measures, repair or replacement of damaged structural steel bridge components, construction of temporary crossovers, and implementation of a counterflow traffic configuration on I-88. The original contract period ran from September 4, 2026, to December 2, 2026, with the requested extension period extending from December 3, 2026, through June 4, 2027. The extension is necessary to complete permanent structural repairs, final design work, procurement and fabrication activities, traffic-control modifications, and restoration of normal traffic operations.
The THA estimates that approximately $600,000 has been expended or committed to date for emergency response activities, with approximately $239,000 paid to date. The extension carries an estimated expenditure of $0, as costs remain subject to completion of the design process, final negotiations, and project reconciliation; however, the Tollway does not currently anticipate exceeding the original $3,000,000 emergency purchase estimate. The THA indicates that final repairs are weather-dependent and may not be completed until Spring 2027. The extension request emphasizes that a separate competitive procurement would delay completion of permanent repairs and prolong the emergency condition, thereby increasing risks to public safety and Tollway and railroad operations. The THA has indicated strong encouragement for DBE/VOSB subcontractor participation.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Please wait...
If this message is not eventually replaced by the proper contents of the document, your PDF viewer may not be able to display this type of document.
You can upgrade to the latest version of Adobe Reader for Windows®, Mac, or Linux® by visiting http://www.adobe.com/go/reader_download.
For more assistance with Adobe Reader visit http://www.adobe.com/go/acrreader.
Windows is either a registered trademark or a trademark of Microsoft Corporation in the United States and/or other countries. Mac is a trademark of Apple Inc., registered in the United States and other countries. Linux is the registered trademark of Linus Torvalds in the U.S. and other countries.
Page of
EMERGENCY PURCHASE EXTENSION APPROVAL
Section 20-30(a) of the Procurement Code provides that a contract for an emergency may be extended beyond 90 calendar days with the approval of the chief procurement officer (CPO). Prior to execution of the extension, the CPO shall receive this completed form justifying the extension. The duration of the extension shall be limited to the scope of the emergency.
State of Illinois Chief Procurement Office for General Services Emergency Purchase Extension Approval v. 25.2
EMERGENCY PURCHASE EXTENSION APPROVAL
State of Illinois Chief Procurement Office for General Services Emergency Purchase Extension Approval v.25.2 Page of Section 20-30(a) of the Procurement Code provides that a contract for an emergency may be extended beyond 90 calendar days with the approval of the chief procurement officer (CPO). Prior to execution of the extension, the CPO shall receive this completed form justifying the extension. The duration of the extension shall be limited to the scope of the emergency.
Extension Justification Actual or Estimated:
Has this emergency contract been extended before? Please detail in the space below:
BidBuy Reference # Amount Start Date End Date
1. Provide detail about the events that led the agency to conduct an emergency procurement:
2. What is the scope of work of the initial emergency contract? Please detail below:
3. Does this extension change the scope of work?
If yes, please detail below:
4. Provide justification for extending the original emergency contract:
5. Does this emergency contract correct or eliminate the emergency condition?
Please detail:
6. Explain why the need cannot be met through a competitive procurement process.
7. Is a competitive procurement in process to replace this emergency contract?
8. What is the effect of a denial of this extension request?
Signatures below cannot be delegated.
APO Signature I am requesting an extension of the requested emergency contract. I believe all statements herein are true and correct to the best of my knowledge.
SPO Signature CPO Signature 11.0.0.20130303.1.892433.887364
| DropDownList1: If yes, please detail |
| DropDownList1: THA - Toll Highway Authority |
| DropDownList1: THA - Toll Highway Authority |
| DropDownList1: THA - Toll Highway Authority |
| DropDownList1: THA - Toll Highway Authority |
| CurrentPage: |
| PageCount: |
| VendorZip: 60018 |
| VendorState: IL |
| VendorCity: Des Plaines |
| VendorAddress: 250 E. Touhy Ave. |
| Vendor: Lorig Construction Company |
| AgencyZip: 60515 |
| AgencyState: IL |
| AgencyCity: Downers Grove |
| AgencyAddress: 2700 Ogden Ave. |
| AgencyDivision: Engineering |
| ReferenceNumber: B-54855 |
| AmountOfOriginal: 3000000.00000000 |
| ActualOrEstimated2: Estimated |
| TextField15: 27-557THA-ENGCO-B-54025 |
| Start: 2026-09-04 |
| End: 2026-12-02 |
| ExpectedExtensionStartDate: 2026-12-03 |
| ExpectedExtensionEnd: 2027-06-04 |
| AmtExtensionExpenditure: 0.00000000 |
| ActualOrEstimated3: Estimated |
| TextField5: To date, the Contractor has utilized a DBE maintenance of traffic and pavement marking vendor. The agency will continue to strongly encourage DBE/VOSB subcontractor participation to the vendor. |
| TextField7: |
| NumericField4: 0 |
| DateField3: |
| DateField4: |
| TextField8: |
| NumericField2: 0 |
| DateField5: |
| DateField6: |
| TextField9: |
| NumericField3: 0 |
| DateField7: |
| DateField8: |
| TextField6: Bridge 821, which carries CN railroad traffic over westbound I-88, sustained an unforeseen vehicular impact that damaged a primary structural member. The damage required immediate evaluation and stabilization of the structure, implementation of traffic control measures on I-88, and temporary shoring to allow railroad operations to safely resume under restrictions. Permanent structural repairs are required to restore the damaged bridge components, including associated maintenance of traffic modifications necessary to complete the work while maintaining I-88 traffic. Due to the unanticipated nature of the incident and the need to immediately stabilize the structure, protect the traveling public, maintain Tollway and railroad operations, and expedite permanent repairs, an emergency procurement was necessary. |
| TextField13: The initial emergency contract includes the work necessary to stabilize Bridge 821 following the accident. The work includes maintenance of traffic, temporary shoring and support measures, and the repair or replacement of damaged structural steel bridge components. The work also includes construction of temporary crossovers and implementation of a counterflow traffic configuration on I-88 to facilitate the structural repairs while maintaining vehicular traffic. Temporary stabilization measures are required to support the structure and allow continued railroad operations until permanent structural repairs are completed. |
| CheckBox7: 0 |
| CheckBox8: 1 |
| TextField1: |
| TextField2: An extension of the original emergency contract is necessary to complete the permanent repairs associated with the unforeseen damage to Bridge 821. Immediate stabilization measures, maintenance of traffic, and structural steel fabrication activities were initiated to protect the traveling public and maintain Tollway and railroad operations. Approximately $600,000 has been expended or committed to date for these emergency response activities. Final repairs and restoration of the roadway are weather-dependent and may not be completed until Spring 2027. |
While the structure has been stabilized and emergency measures have been implemented, the permanent repair work cannot be completed within the original emergency procurement period. Construction of the median crossover is required before permanent repairs can proceed, and the final repair design remains under development. In addition, contractor pricing for the crossover work and permanent bridge repairs has not yet been finalized.
The cost of the permanent structural repairs and associated ancillary work remains uncertain until the design is finalized and contractor pricing is received and negotiated. As a result, the estimated total cost of the repair effort cannot yet be determined with a reasonable degree of certainty.
This request is intended solely to extend the existing emergency contract period through June 4, 2027, to allow sufficient time for completion of the final design, traffic-control modifications, procurement and fabrication activities as necessary, construction of the permanent structural repairs, restoration of normal traffic operations, and resolution of any unforeseen conditions encountered during construction.
Continuation of the existing emergency contract will allow the work to proceed without interruption, maintain continuity of operations, and minimize risks to Tollway users and railroad operations while the permanent repair work is completed and the emergency condition is fully eliminated.
While there is always the potential for costs to change as the design process and negotiations are completed, the Tollway does not currently anticipate exceeding the original emergency purchase estimate of $3,000,000. To date, approximately $600,000 of work has been negotiated and agreed upon under the emergency purchase, and approximately $239,000 has been paid. Based on the current status of the project, no substantial increase beyond the original estimate is anticipated at this time. Any final costs remain subject to completion of the design process, final negotiations, and project reconciliation.
| WhoAuthorizedWork: |
| CheckBox3: 1 |
| CheckBox4: 0 |
| TextField10: Upon completion of the work, the permanent structural repairs will eliminate the emergency condition by restoring the damaged bridge components and removing the need for temporary stabilization measures associated with the incident. |
| TextField12: The emergency condition has not yet been eliminated and the ongoing stabilization, traffic control, and repair activities must continue without interruption. A separate competitive procurement would delay completion of the permanent repairs while temporary measures remain in place, increasing the duration of the emergency condition and the associated risks to Tollway and railroad operations. |
| CheckBox6: 0 |
| CheckBox5: 1 |
| DropDownList2: |
| TextField11: |
| TextField14: Denial of the extension would delay completion of the permanent structural repairs and prolong the emergency condition. Temporary stabilization and traffic control measures would need to remain in place, increasing the potential for impacts to public safety and continued Tollway and railroad operations. |
| TextField3: B-54855 |
| AuthorizedSignature: |
| TitleField: |
| SignatureField2: |
| DateField2: 2026-11-20 |
| CheckBox1: 1 |
| CheckBox2: 0 |
| TextField4: |
| SignatureField1: |
| DateField1: 2026-11-20 |
File details come from the government source that posted it. Updated .