About this file

This is a Renewal Notice of Award issued by the State of Illinois Chief Procurement Office for General Services for the Toll Highway Authority (THA). The document concerns the renewal of a construction contract for the Elgin O'Hare Western Access (I-490) Roadway Construction project at Touhy Avenue, Mile Post 5.75. The original contract was advertised on August 18, 2022, under BidBuy# 22-557THA-ENGCO-B-28116, with bids received on September 30, 2022. The contract was awarded to F.H. Paschen, S.N. Nielsen & Assoc., LLC on November 17, 2022, via Tollway Board resolution 22579. All contract field work has been completed, though the project experienced delays due to unforeseen conditions and utility complications. Contract closeout is proceeding slowly due to subcontractor reluctance to finalize quantities, necessitating an extension to ensure final payment can be made before expiration. The contract is set to expire on November 1, 2026, and the THA is exercising the second one-year renewal option prescribed in the original contract, extending the term to November 1, 2027.

The original contract award amount was $9,910,401.09 with no additional funds required for the renewal period. The Total Renewal Amount is $0.00, indicating no new funding allocation is needed for the one-year extension. The contract includes Veterans Business Program (VBP) participation of 5.25 percent as a Veteran-Owned Small Business (VOSB) and Business Enterprise Program (BEP) participation of 33.96 percent with Disadvantaged Business Enterprise (DBE) subcontractors as identified in the utilization plan. The renewal is approved in accordance with the terms of the existing contract.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Renewal Notice of Award

State of Illinois Chief Procurement Office for General Services Renewal Notice of Award v.25.2 Page 1 of 1

Agency and Vendor Information

Description I-21-4746 Elgin O’Hare Western Access (I-490) Roadway Construction At Touhy Avenue Mile Post 5.75

Renewal Bid Number 27-557THA-ENGCO-B-54608 Agency THA - Toll Highway Authority

Vendor F.H. Paschen, S.N. Nielsen & Assoc., LLC

Line Item Description

RENEWAL NOTICE THIS IS NOT A SOLICITATION

This construction contract was advertised on 8/18/22, BidBuy# 22-557THA-ENGCO-B-28116. Bids were received on 9/30/22. The contract was awarded by the Tollway Board to F.H. Paschen, S.N.

Nielsen & Assoc., LLC on 11/17/22 via board resolution 22579 in the amount of $ 9,910,401.09. The contract is set to expire on 11/1/26. All contract field work has been completed. Contract was delayed due to unforeseen conditions and utility delays. Contract closeout is ongoing but is proceeding slowly due to subcontractor reluctance to agree to final quantities. Without an extension it is unlikely that final payment can be made before the contract expires. The Tollway would like to utilize the second one-year renewal option prescribed in the contract. No additional funds are required.

Total Renewal Amount $0.00 Original Solicitation Bid Number 23-557THA-ENGCO-B-31559

Renewal Begin Date Renewal End Date Value

Nov 1, 2026 Nov 1, 2027

Farm Leases and Concessions

Value to the State (Estimated Financial Return to the State for this renewal) N/A

Value to the Vendor (Estimated Gross Revenue to the Vendor for this renewal) N/A

Business Enterprise Program/Veterans Business Program

% of VBP Per Utilization Plan 5.25$VOSB % of BEP Per Utilization Plan 33.96%DBE

BEP subcontractor Name List the names of ALL BEP subcontractors identified on the Utilization

Plan

The Percentage of the contract's amount awarded to certified BEP vendor(s) identified in the utilization plan

SPO Written Determination for Contract Award Decision

Renewal - The contract is a renewal in accordance with the terms of the existing contract.

SPO Signature Date

Renewal Notice of Award State of Illinois Chief Procurement Office for General Services Renewal Notice of Award v.25.2 Page of Agency and Vendor Information Renewal Begin Date Renewal End Date Value Farm Leases and Concessions Business Enterprise Program/Veterans Business Program % of VBP Per Utilization Plan % of BEP Per Utilization Plan BEP subcontractor Name List the names of ALL BEP subcontractors identified on the Utilization Plan The Percentage of the contract's amount awarded to certified BEP vendor(s) identified in the utilization plan When Add row is clicked add a new row SPO Written Determination for Contract Award Decision Renewal - The contract is a renewal in accordance with the terms of the existing contract.

6.5.0.20211215.13

CurrentPage:
PageCount:
TextField1: I-21-4746 Elgin O’Hare Western Access (I-490) Roadway Construction At Touhy Avenue Mile Post 5.75
TextField2: 27-557THA-ENGCO-B-54608
DropDownList1: THA - Toll Highway Authority
TextField3: F.H. Paschen, S.N. Nielsen & Assoc., LLC
TextField4: RENEWAL NOTICE THIS IS NOT A SOLICITATION

This construction contract was advertised on 8/18/22, BidBuy# 22-557THA-ENGCO-B-28116. Bids were received on 9/30/22. The contract was awarded by the Tollway Board to F.H. Paschen, S.N. Nielsen & Assoc., LLC on 11/17/22 via board resolution 22579 in the amount of $ 9,910,401.09. The contract is set to expire on 11/1/26. All contract field work has been completed. Contract was delayed due to unforeseen conditions and utility delays. Contract closeout is ongoing but is proceeding slowly due to subcontractor reluctance to agree to final quantities. Without an extension it is unlikely that final payment can be made before the contract expires. The Tollway would like to utilize the second one-year renewal option prescribed in the contract. No additional funds are required.

TextField5: $0.00
TextField6: 23-557THA-ENGCO-B-31559
DateField1: 2026-11-01
DateField2: 2027-11-01
TextField7:
TextField8: N/A
TextField9: N/A
TextField10: 5.25$VOSB
TextField11: 33.96%DBE