About this file
This is an Emergency Purchase Extension Approval form submitted by the Illinois Department of Transportation (IDOT), Business Services Division, to the State of Illinois Chief Procurement Office seeking approval to extend an emergency contract with LCPTracker for payroll and prevailing wage software maintenance. The original emergency contract (BidBuy Reference #B-52275) ran from May 1, 2026, through July 29, 2026, at a cost of $77,822.10. IDOT is requesting a 90-day extension (BidBuy Reference #B-53289) from July 30, 2026, through October 29, 2026, with an estimated cost of $79,474.54. The scope of work involves maintaining and updating the LCPTracker Payroll Solution software, which manages prevailing wage laws and rates at the state and federal levels. IDOT has published an Invitation for Bid (Bid #27-494DOT-FINAD-B-52823) for a long-term software solution replacement with a bid opening date of July 30, 2026, and plans to evaluate bids and submit a contract award for approval in August 2026, at which point the emergency contract will be terminated.
The extension is justified by IDOT's need to maintain continuous legal compliance with federal prevailing wage requirements, including the Davis-Bacon Act, which mandates retention of payroll documents for three years post-project completion. LCPTracker performs over 70 automated validation checks on submitted payrolls to prevent wage violations and identify discrepancies, and maintains government security standards including FedRAMP Moderate and SOC compliance. The procurement is under $100,000, therefore no Business Enterprise Program (BEP) participation goal is required. This is the first extension of the emergency contract, which originated after the vendor's previous Sole Source contract expired on January 28, 2026, and IDOT completed a small purchase with emergency conditions through April 30, 2026. The extended emergency contract does not change the scope of work and was approved by the Chief Procurement Office on July 27, 2026. The effect of denying this extension would result in loss of support for a vital component of IDOT's payroll system, particularly the prevailing wage functionality.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
EMERGENCY PURCHASE EXTENSION APPROVAL
State of Illinois Chief Procurement Office for General Services Emergency Purchase Extension Approval v.26.1 Page 1 of 3
Section 20-30(a) of the Procurement Code provides that a contract for an emergency may be extended beyond 90 calendar days with the approval of the chief procurement officer (CPO). Prior to execution of the extension, the CPO shall receive this completed form justifying the extension. The duration of the extension shall be limited to the scope of the emergency.
Zip: 92866State: CACity: OrangeAddress: 117 E. Chapman Ave.
Vendor: LCPTracker
Zip: 62764State: ILCity: SpringfieldAddress: 2300 South Dirksen Parkway
Requesting Agency: DOT - Transportation Division: Business Services
Extension Justification Original BidBuy Reference #: B- 52275
Emergency Extension BidBuy Reference #: B- 53289
Amount of original contract: $ 77,822.1
Actual or Estimated: Actual
Original Emergency Term Start Date:05/01/2026 Original Emergency Term End Date: 07/29/2026
Expected Extension Start Date: 07/30/2026 Expected Extension End Date: 10/29/2026
Amount of extension contract: $ 79,474.54 Actual or Estimated: Estimated
Is there BEP participation on this contract? If no, explain why
This procurement is < $100,000, hence a BEP goal is not required.
Has this emergency contract been extended before? Please detail in the space below:
BidBuy Reference # Amount Start Date End Date
$0.00
$0.00
$0.00
1. Provide detail about the events that led the agency to conduct an emergency procurement:
The Agency entered into a Sole Source contract with LCPTracker that expired on 01/28/2026. Once the contract ended, the Agency completed a small purchase with emergency conditions until 04/30/2026. The initial development of a long-term solicitation took longer than expected, so the Agency had to declare an emergency while the solicitation was taking place.
2. What is the scope of work of the initial emergency contract? Please detail below:
Maintain maintenance on the LCPTracker Payroll Solution software which provides maintenance for prevailing wage laws and rates at the State and Federal Level; until such time as the IFB contract has been executed.
Emergency Purchase Extension Approval v.26.1 Page 2 of 3
Section 20-30(a) of the Procurement Code provides that a contract for an emergency may be extended beyond 90 calendar days with the approval of the chief procurement officer (CPO). Prior to execution of the extension, the CPO shall receive this completed form justifying the extension. The duration of the extension shall be limited to the scope of the emergency.
Zip: 92866State: CACity: OrangeAddress: 117 E. Chapman Ave.
Vendor: LCPTracker
Zip: 62764State: ILCity: SpringfieldAddress: 2300 South Dirksen Parkway
Requesting Agency: DOT - Transportation Division: Business Services
3. Does this extension change the scope of work? Yes No If yes, please detail below:
Original BidBuy Reference #: B- 52275
4. Provide justification for extending the original emergency contract:
LCPTracker needs to be maintained (and kept continuously updated) primarily to ensure strict legal compliance with prevailing wage laws such as the Davis-Bacon Act and to manage government contracts.
Legal Compliance: Federal, Sate, and local agencies are required to submit verified payroll records to ensure employees are paid correctly.
Audit and Dispute Readiness: Federal regulations (including the Davis-Bacon Act) mandate that employers and agencies retain all payroll documents for at least three years after project completion. Centralized maintenance protects businesses from sudden demands for historical records
Automated Error Checking: LCPTracker actively runs over 70 validation checks on submitted payrolls. Maintaining and inputing data properly prevents wage violations and identifies discrepancies before they result in financial penalties.
Data Security: The platform is continuously monitored and maintained to meet high-level government security standards, including FedRAMP Moderate and SOC requirements.
5. Does this emergency contract correct or eliminate the emergency condition?
Yes No Please detail:
The Agency has published an Invitation for Bid for a long-term software solution, and that IDOT is requesting an additional 90 day extension to complete the IFB procurement process.
6. Explain why the need cannot be met through a competitive procurement process.
The original contract was procured via the piggyback method of procurement from 2021 to 2024, before it was procured as a Sole Source from 2024 to 2025. Until the IFB is in place, the maintenance for the Agency’s payroll and prevailing software needs to remain in place
Emergency Purchase Extension Approval v.26.1 Page 3 of 3
Section 20-30(a) of the Procurement Code provides that a contract for an emergency may be extended beyond 90 calendar days with the approval of the chief procurement officer (CPO). Prior to execution of the extension, the CPO shall receive this completed form justifying the extension. The duration of the extension shall be limited to the scope of the emergency.
Zip: 92866State: CACity: OrangeAddress: 117 E. Chapman Ave.
Vendor: LCPTracker
Zip: 62764State: ILCity: SpringfieldAddress: 2300 South Dirksen Parkway
Requesting Agency: DOT - Transportation Division: Business Services
7. Is a competitive procurement in process to replace this emergency contract?
Yes No Status: published
BidBuy Bid # 27-494DOT-FINAD-B-52823 has been published as an Invitation for Bid, with a Bid Opening Date of 07/30/2026. IDOT will work to evaluate bids and submit the contract award for approval during the month of August. Once a long -term contract is in place, the Agency will move to terminate the emergency contract.
8. What is the effect of a denial of this extension request?
The Agency will lose support of a vital part of its Payroll system, most particularly the prevailing wage component.
Original BidBuy Reference #: B- 52275
Signatures below cannot be delegated.
APO Signature I am requesting an extension of the requested emergency contract. I believe all statements herein are true and correct to the best of my knowledge.
APO Signature: Date: Jul 27, 2026
SPO Signature
SPO Signature: Date: Jul 27, 2026
CPO Signature Based on my review, I approve the Agency to proceed in accordance with the emergency contract extension detailed in this document.
Based upon my review, I approve the Agency to proceed with the following changes:
CPO Signature: Date: Jul 27, 2026
Page of
Section 20-30(a) of the Procurement Code provides that a contract for an emergency may be extended beyond 90 calendar days with the approval of the chief procurement officer (CPO). Prior to execution of the extension, the CPO shall receive this completed form justifying the extension. The duration of the extension shall be limited to the scope of the emergency.
State of Illinois Chief Procurement Office for General Services Emergency Purchase Extension Approval v. 26.1
EMERGENCY PURCHASE EXTENSION APPROVAL
State of Illinois Chief Procurement Office for General Services Emergency Purchase Extension Approval v.26.1 Page of Section 20-30(a) of the Procurement Code provides that a contract for an emergency may be extended beyond 90 calendar days with the approval of the chief procurement officer (CPO). Prior to execution of the extension, the CPO shall receive this completed form justifying the extension. The duration of the extension shall be limited to the scope of the emergency.
Extension Justification Actual or Estimated:
Has this emergency contract been extended before? Please detail in the space below:
BidBuy Reference # Amount Start Date End Date
1. Provide detail about the events that led the agency to conduct an emergency procurement:
2. What is the scope of work of the initial emergency contract? Please detail below:
3. Does this extension change the scope of work?
If yes, please detail below:
4. Provide justification for extending the original emergency contract:
5. Does this emergency contract correct or eliminate the emergency condition?
Please detail:
6. Explain why the need cannot be met through a competitive procurement process.
7. Is a competitive procurement in process to replace this emergency contract?
8. What is the effect of a denial of this extension request?
Signatures below cannot be delegated.
APO Signature I am requesting an extension of the requested emergency contract. I believe all statements herein are true and correct to the best of my knowledge.
SPO Signature CPO Signature 11.0.0.20130303.1.892433.887364
| DropDownList1: If no, explain why |
| DropDownList1: DOT - Transportation |
| DropDownList1: DOT - Transportation |
| DropDownList1: DOT - Transportation |
| CurrentPage: |
| PageCount: |
| VendorZip: 92866 |
| VendorState: CA |
| VendorCity: Orange |
| VendorAddress: 117 E. Chapman Ave. |
| Vendor: LCPTracker |
| AgencyZip: 62764 |
| AgencyState: IL |
| AgencyCity: Springfield |
| AgencyAddress: 2300 South Dirksen Parkway |
| AgencyDivision: Business Services |
| ReferenceNumber: 52275 |
| TextField15: 53289 |
| AmountOfOriginal: 77822.10000000 |
| ActualOrEstimated2: Actual |
| Start: 05/01/2026 |
| End: 07/29/2026 |
| ExpectedExtensionStartDate: 07/30/2026 |
| ExpectedExtensionEnd: 10/29/2026 |
| AmtExtensionExpenditure: 79474.54000000 |
| ActualOrEstimated3: Estimated |
| TextField5: This procurement is < $100,000, hence a BEP goal is not required. |
| TextField7: |
| NumericField4: 0 |
| DateField3: |
| DateField4: |
| TextField8: |
| NumericField2: 0 |
| DateField5: |
| DateField6: |
| TextField9: |
| NumericField3: 0 |
| DateField7: |
| DateField8: |
| TextField6: The Agency entered into a Sole Source contract with LCPTracker that expired on 01/28/2026. Once the contract ended, the Agency completed a small purchase with emergency conditions until 04/30/2026. The initial development of a long-term solicitation took longer than expected, so the Agency had to declare an emergency while the solicitation was taking place. |
| TextField13: Maintain maintenance on the LCPTracker Payroll Solution software which provides maintenance for prevailing wage laws and rates at the State and Federal Level; until such time as the IFB contract has been executed. |
| CheckBox7: 0 |
| CheckBox8: 1 |
| TextField1: |
| TextField2: LCPTracker needs to be maintained (and kept continuously updated) primarily to ensure strict legal compliance with prevailing wage laws such as the Davis-Bacon Act and to manage government contracts. |
Legal Compliance: Federal, Sate, and local agencies are required to submit verified payroll records to ensure employees are paid correctly.
Audit and Dispute Readiness: Federal regulations (including the Davis-Bacon Act) mandate that employers and agencies retain all payroll documents for at least three years after project completion. Centralized maintenance protects businesses from sudden demands for historical records
Automated Error Checking: LCPTracker actively runs over 70 validation checks on submitted payrolls. Maintaining and inputing data properly prevents wage violations and identifies discrepancies before they result in financial penalties.
Data Security: The platform is continuously monitored and maintained to meet high-level government security standards, including FedRAMP Moderate and SOC requirements.
| WhoAuthorizedWork: |
| CheckBox3: 0 |
| CheckBox4: 1 |
| TextField10: The Agency has published an Invitation for Bid for a long-term software solution, and that IDOT is requesting an additional 90 day extension to complete the IFB procurement process. |
| TextField12: The original contract was procured via the piggyback method of procurement from 2021 to 2024, before it was procured as a Sole Source from 2024 to 2025. Until the IFB is in place, the maintenance for the Agency’s payroll and prevailing software needs to remain in place |
| CheckBox6: 1 |
| CheckBox5: 0 |
| DropDownList2: published |
| TextField11: BidBuy Bid # 27-494DOT-FINAD-B-52823 has been published as an Invitation for Bid, with a Bid Opening Date of 07/30/2026. IDOT will work to evaluate bids and submit the contract award for approval during the month of August. Once a long -term contract is in place, the Agency will move to terminate the emergency contract. |
| TextField14: The Agency will lose support of a vital part of its Payroll system, most particularly the prevailing wage component. |
| TextField3: 52275 |
| AuthorizedSignature: |
| TitleField: 2026-07-27 |
| SignatureField2: |
| DateField2: 2026-07-27 |
| CheckBox1: 1 |
| CheckBox2: 0 |
| TextField4: |
| SignatureField1: |
| DateField1: 2026-07-27 |