This document is an Emergency Purchase Statement from the State of Illinois Chief Procurement Office. It details an emergency procurement by the Illinois Department of Human Services (DHS) to purchase coal from Knight Hawk LLC to fuel the power plants at the Choate and Murray Centers. The emergency purchase was necessary after the current contract vendor filed for bankruptcy, leaving the facilities with critically low coal supplies. Knight Hawk LLC was the only supplier with immediate availability in the area. The purchase is for a 90-day supply of coal, to be delivered in approximately 25-ton truckloads. DHS is preparing a competitive solicitation to secure a new long-term contract for coal before the emergency supply is exhausted.

The final cost of the emergency coal purchase is $415,440, with an estimated start date of December 30, 2020 and an estimated end date of March 31, 2021. The purchase was funded through state appropriated funds. DHS was unable to utilize an existing state contract, as the previous vendor had filed for bankruptcy and could no longer supply the coal.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Please wait...

If this message is not eventually replaced by the proper contents of the document, your PDF viewer may not be able to display this type of document.

You can upgrade to the latest version of Adobe Reader for Windows®, Mac, or Linux® by visiting http://www.adobe.com/go/reader_download.

For more assistance with Adobe Reader visit http://www.adobe.com/go/acrreader.

Windows is either a registered trademark or a trademark of Microsoft Corporation in the United States and/or other countries. Mac is a trademark of Apple Inc., registered in the United States and other countries. Linux is the registered trademark of Linus Torvalds in the U.S. and other countries.

Page of

EMERGENCY PURCHASE STATEMENT

State of Illinois Chief Procurement Office Emergency Purchase Statement Version 20.1 .\CPO Letterhead\CPO Letterhead.png

EMERGENCY PURCHASE STATEMENT

Statement Page of State of Illinois Chief Procurement Office Emergency Purchase Statement Version 20.1 .\CPO Letterhead\CPO Letterhead.png Emergency Purchase Details Emergency Category (select the appropriate option from the drop-down menu below):

Reason for selection of this particular vendor:

Description of supplies or services to be provided:

Is there an existing State contract available for the required supplies or services?

If Yes is checked above, explain why the existing contract does not meet the need:

Actual or Estimated*:

*Actual end date and cost will be reported later.

Select the type of funding to be used:

Signatures I am making this statement and providing it to the CPO Office, the Auditor General, and the Procurement Policy Board in compliance with the Illinois Procurement Code and within 10 days after award of the contract.

I have authorized the emergency procurement in accordance with the requirements of the Illinois Procurement Code (30 ILCS 500) and the applicable administrative rule. I know and understand the contents of this statement and all statements herein are true and correct to the best of my knowledge.

EMERGENCY PURCHASE EXTENSION

Extension Page of State of Illinois Chief Procurement Office Emergency Purchase Statement Version 20.1 .\CPO Letterhead\CPO Letterhead.png Extension Justification Actual or Estimated*:

Actual or Estimated*:

Select the type of funding to be used:

Describe the scope of the original emergency (supply, service, etc.):

Describe the scope of the extension (supply, service, etc.). Show justification for extending the original emergency contract, and explain why the extension need cannot be met through a competitive process:

Was authorization to proceed verbally given?

Term of emergency procurement shall not exceed 90 days. Contract may be extended beyond 90 days if CPO determines additional time is necessary; however, prior to execution of extension, CPO must hold a public hearing and provide written determination *Actual end date and cost will be reported later.

Signatures I am requesting an extension of the requested emergency contract. I know and understand the contents of this statement and all statements herein are true and correct to the best of my knowledge.

EMERGENCY PURCHASE FINAL COST AND TERM

Final Cost and Term Page of State of Illinois Chief Procurement Office Emergency Purchase Statement Version 20.1 .\CPO Letterhead\CPO Letterhead.png Final Costs and Term I am reporting the final costs and term for the referenced emergency contract to the CPO and the Auditor General.

11.0.0.20130303.1.892433.887364

PageCount:
CurrentPage:
VendorZip: 62238
VendorState: IL
VendorCity: Cutler
VendorAddress: 7290 County Line Rd
Vendor: Knight Hawk LLC
AgencyZip: 62906
AgencyState: IL
AgencyCity: Anna
AgencyAddress: 1000 N. Main St
AgencyDivision: DHS
AgencyUniversity: Choate Center
CurrentMasterPage:
MasterPageCount:
ReferenceNo: 21-444DHS-DEVDI-R-84282
DropDownListQuickPurchase: To prevent or minimize serious disruption in critical State services that affect health, safety, or collection of substantial State revenues
CheckBox1ProtectingHealth: 0
CheckBox2DiscountedPrice: 0
CheckBox3RareItems: 0
CheckBox4Entertainment: 0
CheckBox5AvoidLapsing: 0
ExplanationForSelectingVendor: The current contract vendor has filed bankruptcy with little notice. We were unable to purchase any remaining coal from that vendor due to the court order. The facility relies on coal to fuel their power plant and Knight Hawk is the only supplier with immediate availability in the area.
ExplanationSuppliesServices: 90 day supply coal purchased by approximately 25 ton truckloads. Coal is critical for Choate and Murray to provide heat and electricity to our facilities. Both centers are at critically low levels due to the contract holder's bankruptcy. A competitive solicitation is being prepared to secure a new contract for coal and will hopefully be completed before our current supply is exhausted.
CheckBoxYes: 0
CheckBoxYes: 1
CheckBoxNo: 1
CheckBoxNo: 0
ExplanationDoesNotMeetNeed:
TextFieldExpectedStartDate: 12/30/2020
TextFieldExpectedEndDate: 03/31/2021
TextFieldAmountExpenditure: $415,400
ActualOrEstimated1: Estimated *
CheckboxFederalFunds: 0
CheckboxFederalFunds: 0
CheckboxStateAppFunds: 1
CheckboxStateAppFunds: 0
CheckBoxStateGrantFunds: 0
CheckBoxStateGrantFunds: 0
CheckBoxOther: 0
IfOtherExplainTextField:
AuthorizedSignature:
TitleField: Agency Procurement Officer
TitleField: Agency Procurement Officer
PrintedNameField: Jean Sandstrom
AuthorizedDateField: 2021-01-12
Start:
End:
AmountOfOriginal:
ActualOrEstimated2: Estimated *
ExpectedExtensionStartDate:
ExpectedExtensionEnd:
AmtExtensionExpenditure:
ActualOrEstimated3:
CheckBoxOther22: 0
IfOtherExplainTextField22:
TextField1:
TextField2:
CheckBoxNA: 0
WhoAuthorizedWork: Jean Sandstrom
TextField3: B-19648 & B-26250
FinalTotalCost: 415,440.00
FinalTotalTerm: 90 Days
PrintedName: Jean Sandstrom
Date: 2021-11-23