B-1 CPT SOW.pdf

PDF 686 KB Posted

Attached to
B-1 Cabin Pressure Tester
Solicitation number
FA812626Q0033
Issued by

About this file

This is a Statement of Work (SOW) for the procurement of two (2) Diesel-Powered Cabin Pressure Testers (CPTs) designed and certified for use on B-1 aircraft, prepared by the 76 Aircraft Maintenance Group (AMXG) at Tinker Air Force Base on October 9, 2025. The procurement is intended to replace existing obsolete and unreliable equipment (models MT006, MT007, MT021) that have high downtime and low Mean Time Between Repair (MTBR) rates, directly impacting B-1 fleet aircraft availability and increasing maintenance costs.

The contractor must deliver two units of part number 99421-100 (Diesel-Powered Cabin Pressure Tester) manufactured with new or unused components. Each CPT must accurately pressurize the B-1 aircraft cabin and precisely measure cabin leakage rates per applicable B-1 Technical Orders. Units must be fully compatible with existing B-1 pressure systems and test ports, with the contractor responsible for providing necessary adapters. Portability specifications require dimensions not exceeding 4 feet by 3 feet by 2 feet and weight not exceeding 150 pounds; however, Appendix A specifies overall dimensions of 81 inches (height) by 127 inches (length) by 64 inches (width) with a dry weight of 6,140 pounds, indicating a stationary or towed system with lockable wheels. The contractor must report the documented Mean Time Between Failures (MTBF) hours and deliver comprehensive support documentation including two paper copies and digital versions (in Adobe or Microsoft format) of user manuals, parts breakdowns, maintenance literature, system check procedures, and calibration certificates via DoD Safe or disc. Acceptance criteria require crate packaging, zero physical damage (minor cosmetic blemishes acceptable at the discretion of the accepting party), successful installation and configuration per vendor instructions, and all applicable safety standards and certifications compliance. No installation or training is required. The contractor must comply with OSHA requirements, submit a Safety and Health Plan, and ensure all personnel follow Tinker AFB safety protocols and emergency procedures.

View the file

Other files

File Type Posted
Solicitation - FA812626Q0033.pdf PDF
CSS_B-1 CPT.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

For

B-1 Cabin Pressure Tester

PREPARED BY: Creighton M. Gore

76 AMXG/MXDEO

10/9/2025

PREAMBLE

Commander’s Safety Intent

The safety of everyone on Tinker AFB is our top priority. All Individuals must accept personal responsibility for safety and seek opportunities for improving the safety of our work environment. Everyone working on Tinker AFB is challenged to find, fix (if able) and report all hazards and near-misses. It is our shared duty to take every reasonable step and precaution to prevent accidents and preserve the health/safety of each Contractor and Government employee.

1. SCOPE

This Statement of Work (SOW) defines the requirements for the procurement of two (2) Diesel-

Powered Cabin Pressure Testers (CPTs), specifically designed and certified for use on B-1 aircraft. These CPTs are intended to replace existing, obsolete, and unreliable equipment.

2. BACKGROUND

The 76 Aircraft Maintenance Group (AMXG) requires reliable CPTs to measure pressure leaks in B-1 aircraft cabins. Cabin pressure testing is crucial for B-1 aircraft maintainability and safety.

The existing CPTs (MT006, MT007, MT021) are aging and unreliable, posing a significant risk to the maintenance capabilities of the B-1 fleet. The high downtime and low Mean Time

Between Repair (MTBR) of existing units directly impacts aircraft availability and increases maintenance costs.

3. REQUIREMENTS AND ITEM DESCRIPTIONS

3.1. Item Description

The required items for the Diesel-Powered Cabin Pressure Testers are defined in the following table:

Part Number Description Quantity

99421-100 Diesel-Powered Cabin Pressure Tester 2

Table 1 - System Requirements

3.1.1 Support Documentation – Support documentation shall be included with items listed above. Supporting documentation shall include but is not limited to user manuals, parts breakdowns, maintenance literature, system check procedures, and applicable calibration certificates. Paper copies of calibration data shall be co-located in the system kit that includes items calibrated. Two paper copies and a digital version of manuals, parts break down and maintenance literature shall be included with first delivery. Digital manuals should be in Adobe or Microsoft format, capable of editing/notes. All digital content can be delivered via DoD Safe

(https://safe.apps.mil/) or disc.

3.2. Installation

No installation is required.

3.3. New and Unused Parts

The contractor shall manufacture the CPTs with new or unused components.

3.4. Training

No training is required.

3.5. Acceptance

System acceptance is dependent on the following criteria being met and verified:

Asset Condition:

Criteria:

Items crate packed for shipment.

• No physical damage to any system components (hardware, software media, documentation) as verified by visual inspection upon delivery.

• Verification Method: Visual inspection of all delivered items against the packing list.

• Acceptance Threshold: Zero damaged components. Minor cosmetic blemishes that do not affect functionality may be accepted at the discretion of [Accepting Party Name/Role].

System Setup:

Criteria: Successful installation and configuration of all system components according to the vendor's installation instructions and configuration guides. All software components are correctly installed.

3.5.1. Capabilities

Capabilities shall include, but not be limited to:

3.5.1.1 Testing

CPTs must accurately pressurize the B-1 aircraft cabin and precisely measure the cabin leakage rate as outlined in applicable B-1 Technical Orders.

3.5.1.2 Compatibility

The CPTs must be fully compatible with the B-1 aircraft's current pressure system, including existing test ports and fittings. The contractor will be responsible for providing any necessary adapters to connect to the existing B-1 cabin pressure test ports.

3.5.1.3 Safety

The CPTs must meet all applicable safety standards and certifications.

3.5.1.4 Portability

The CPT should be easily moveable in the limited spaces around a B-1. CPTs should not exceed

4ft x 3ft x 2ft. and should not exceed 150 lbs. If on wheels, the wheels must be lockable.

3.5.1.5 Reliability

This is the most important capability. The selected CPT MUST perform reliable leak test to prevent rework. The new CPT is intended to reduce current re-work from an average of 32 hours per job and eliminate down time.

Contractor will report the documented Mean Time Between Failures (MTBF) hours of the proposed system.

4. GENERAL REQUIREMENTS

Commander’s Safety Intent: The safety of everyone on Tinker AFB is our top priority. All

Individuals must accept personal responsibility for safety and seek opportunities for improving the safety of our work environment. Everyone working on Tinker AFB is challenged to find, fix

(if able) and report all hazards and near misses. It is our shared duty to take every reasonable step and precaution to prevent accidents and preserve the health/safety of each contractor and government employee.

4.11. Speak up for safety: Safety surety is an integral part of our overall goal of establishing a world class safety and health program. Our “Speak Out for Safety” initiative ensures a partnership with contractors and government employees to further enhance safety to ensure we are looking out for all our partners and empowers all employees to actively participate in each other’s safety. A safe workplace is everyone's business. As part of the contract team, military, civilian and contractor personnel are empowered to Speak Out for Safety (S.O.S.) when they observe an unsafe act. Events that present imminent danger to personnel or catastrophic damage to property we empower our employees to intercede to ensure continued safe operations.

4.12. Communicating Hazards of Workplace (CHOW): Contractor’s onsite representative communicates all hazards being introduced to the worksite by the Contractor. This is accomplished prior to commencement of work and refreshed daily during performance, IAW

Contractor’s Site Safety Plan.

4.13. Safety and Health Plan: The Contractor shall be responsible for compliance with the

OSHA Public Law 91-596. The Contractor shall submit a Safety and Health Plan (SHP) and corresponding site safety checklist to the CO and the COR (see Appendix C).

4.14. Emergency Procedures: The Contractor personnel shall follow the direction of the

Government personnel regarding emergency procedures, such as fire, tornado, active shooter, bomb threats, or other emergencies. It is the responsibility of the Contractor to provide guidance and to establish procedures for its employees to respond to an emergency. It is the Contractor’s responsibility to account for their employees following an emergency evacuation. The Contractor personnel shall participate with the Government personnel in all fire and tornado drills at no additional cost to the Government.

Appendix A – Weight and Dimensions

Overall Dimensions Height: 81 inches

Length: 127 inches

Width: 64 inches

Weight: (Dry) 6140 pounds

Appendix B – Specifications

File details come from the government source that posted it. Updated .