Award Recomm E.T MacKenzie KavcoLF_ConstructionContract 26094.pdf
PDF 6 MB Posted
- Solicitation number
- NIA1 171 260000000636 1
- Issued by
- Allegan County, Michigan
About this file
This is a contract award recommendation letter from AECOM to the Michigan Department of Environment, Great Lakes, and Energy (EGLE) Remediation and Redevelopment Division regarding the Kavco Landfill AST Decommissioning project in Plainwell, Michigan. The project involves the decommissioning of an aboveground storage tank (AST) at the landfill site. Eight responsive bid packages were received and opened by the Department of Technology, Management, and Budget (DTMB) on June 10, 2026. AECOM conducted contractor interviews and evaluated qualifications for the top bidders. The contract was recommended for award on June 30, 2026, with project completion anticipated within 15 days based on the selected contractor's estimated duration.
AECOM recommended awarding the contract to E.T. MacKenzie Company, LLC (ETM) for $177,240.00, which was the fourth lowest base bid among the eight contractors. The award recommendation was based on best value criteria rather than lowest price alone. TSP Construction, LLC submitted the lowest base bid at $174,211.77; however, ETM was selected due to superior performance evaluation scores (average 109.00 versus TSP's 86.38), a shorter estimated project duration (15 days versus 20 days), and reduced Professional Service Contractor oversight costs. The comparison analysis showed ETM's total project cost to the State, including PSC oversight, was $191,029.50 compared to TSP's $192,327.78. The project is funded 100 percent through the Remediation and Redevelopment (RMF SAR) funding source, with the contract expiring on July 7, 2026.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Justification Award of Construction Contract E.T. MacKenzie 26094.doc | DOC document | |
| Bid Tab 260610 26094.pdf | ||
| Memo 260710 Award E.T. MacKenzie Company, LLC Y26341.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
X
X Funding Source
100% RMF
SAR
7/7/26
A contract be awarded to in the amount of $177,240.00 for the best value bid
To:
Ms. Bridget Walsh Michigan Department of Environment, Great Lakes, and Energy (EGLE) Remediation and Redevelopment (RRD) Constitution Hall, 5th Floor South Lansing MI 48933
CC:
Lynn Gosson, EGLE RRD, Grand Rapids District Office
Recommendation Letter
Subject: Kavco Landfill – AST Decommissioning Contractor Recommendation
761/26094.SAR
RFQ-171-260000000311-2
Dear Ms. Walsh, AECOM
3950 Sparks Drive SE Grand Rapids, MI 49546 aecom.com
Project Name:
Kavco Landfill – Plainwell, Michigan AST Decommissioning
Project Ref.:
60782836
From:
Mike Cox, AECOM
Date:
June 30, 2026
Bids for the Kavco Landfill – AST Decommissioning project were received and opened by the Department of Technology, Management, and Budget (DTMB) on June 10, 2026. AECOM has reviewed the eight (8) responsive bid packages received from the DTMB:
Received Contractor Bid Package Total Base Bid ($ USD) TSP Construction, LLC $174,211.77
Job Site Services, Inc. $188,785.00
Catskill Remedial Contracting Services, Inc. $229,371.00
TJM Services, LLC $287,150.00
AECOM has reviewed the submittals and determined TSP Construction, LLC (TSP) and ET MacKenzie Company, LLC (ETM) to be qualified, responsive bidders. During contractor interviews conducted for TSP and ETM, differing amounts for duration of construction were noted. During the interviews, TSP estimated its duration of construction at 20 days and ETM estimated its duration of construction at 15 days. Based on ETM’s ability to perform the work in a shorter timeframe, five days less PSC oversight would be required to perform the work should ETM be selected.
Based on the reduced amount of PSC oversight required using ETM, the State’s overall cost to complete the work would be less using ETM.
A comparison of Performance Evaluations supplied by DTMB was also completed for both TSP and ETM for evaluations completed in 2024, 2025, and 2026. In summary, TSP’s performance evaluations included significant scope and health and safety deficiencies resulting in TSP not being recommended in two separate evaluations and having an average Performance Score of 86.38 between all provided evaluations. ETM’s supplied performance evaluations included comments noting excellent execution of work and having an average Performance Score of 109.00.
E.T. MacKenzie Company, LLC $177,240.00
Cripps Fontaine Excavating, Inc. $219,000.00
Environmental Remediation Group, LLC $282,000.00
Balkema Construction, Inc. $608,488.00
For further details of estimated costs showing ETM as the overall lowest cost to the State for this project and for Performance Evaluation Ratings and calculations, please refer to the attached document entitled TSP ETM Comparison Table.
AECOM recommends awarding the project to ET MacKenzie Company, LLC for the amount of $177,240.00. A summary of the bids is provided in the table above and the qualification submittals for ET MacKenzie Company, LLC are attached to this letter.
If you have any questions, or require additional information, please contact me at mike.cox@aecom.com or 616-634- 6234.
Yours sincerely, Michael K. Cox Senior Project Manager P: 616-634-6234 E: mike.cox@aecom.com
Attachments:
DTMB Bid Tabulation and Recommendation For Contract Award DTMB Best Value Construction Bidder Evaluations for TSP & ETM Performance Evaluations Supplied by DTMB for TSP and ETM TSP ETM Comparison Table Bidder Supplemental Documentation for TSP and ETM mailto:mike.cox@aecom.com mailto:mike.cox@aecom.com
BEST VALUE
CONSTRUCTION BIDDER EVALUATION
April 2025
File No. 761/26094.SAR Project Name/Phase: Kavco Landfill AST Decommissioning Bidder: ET MacKenzie PSC: AECOM Date: 06/25/2026
EVALUATION CHECKLIST
PART ONE: Responsiveness and Responsibility Yes No Review bid forms and bid submittals prior to interview Are all bid forms and bid submittals in order, complete, and signed? X Have all addenda been acknowledged? X Is the bidder a Michigan firm? X Will 50% or more of the persons employed on the project have been residents of the State of Michigan for not less than one year before the beginning of this project?
X
Does the Contractor acknowledge that all subcontractors are required to obtain a State Project Registration (SPR) from the Department of Labor & Economic Opportunity, Wage & Hour Division?
X
Are DCD contractor performance evaluations (if any) acceptable? (Add comments pg. 5 if No) Are the completed projects of similar size and complexity, and references, acceptable? X Is the project superintendent’s resume and past experience with similar projects acceptable? X Does this contractor have a satisfactory (under 1.0) Experience Modification Rate (EMR)? X Is the contractor a member of the MIOSHA Michigan Voluntary Protection Program (MVPP) through the Michigan Department of Labor and Economic Opportunity (LEO - Michigan Voluntary Protection Program (MVPP))?
X
Is the company or are principal individuals on the Federal System for Award Management (http://www.SAM.gov) exclusion list? Barrett will provide Does this contractor have open MIOSHA violations within the last three (3) years prior to bid opening?
(http://www.osha.gov/pls/imis/establishment.html)
X
Does this work include asbestos abatement? If so, does this contractor and/or any asbestos abatement subcontractors have more than four (4) notices of violation?
X
Interview Within the last five (5) years has your organization been issued a Notice Requiring Assurance of Due Performance, Notice of Intent to Default, or Default – Notice of Termination for Cause, on a State of Michigan project? (If yes, attach a detailed explanation.)
X
Within the last five (5) years has any officer or partner of your organization been an officer or partner of another organization that has been issued a Notice Requiring Assurance of Due Performance, Notice of Intent to Default, or Default – Notice of Termination for Cause, on a State of Michigan project? (If yes, attach a detailed explanation.)
X
Is your proposal mathematically, correct? X
Do you have any concerns with or need clarifications of the bid documents? (If yes, attach a detailed explanation.)
X
Does the bid contain deviations such as substitutions or voluntary alternates? X If there are deviations, have those deviations been reviewed?
Have you included all components for a complete project? X Are you comfortable with your bid and your ability to complete the project within the duration specified? X Do you understand the Soil Erosion and Sedimentation Control requirements (if any) for the project? X Do you understand the Special Working Conditions and Supplemental Conditions (if any) for the project? X Do you understand substantial and final completion and liquidated damages, if any? X Does your proposed project schedule reflect the project duration outlined in the bid documents? X Do you anticipate any difficulties obtaining your performance and payment bonds? X Are you using the bonding capacity of any other entity (i.e., subcontractor)? X Do you understand the Davis-Bacon Act / Prevailing Wage requirements per the bid documents? X PSC and PD discuss and decide post-interview Is this contractor responsive? X Is this contractor responsible? X Question to bidder Do you still wish your bid to remain in consideration? X
April 2025
Comments/Explanations of Negative Responses (may attach other sheets)
Signed:
Date
EVALUATION CHECKLIST
PART TWO: Qualitative Components
E x c el le n t
A c ce p ta b le
N o t
A c ce p ta
Interview How do you plan to provide communications and information for this project?
What is your management plan for this project?
Have you worked successfully with the DTMB Design and Construction Division?
Have you worked successfully with the Client Agency?
Have you worked successfully with the Professional Service Contractor?
How many projects have your successfully completed with your principal subcontractors (if any)?
_____ not worked with before ______ 1-5 _______ 5-10+
What percentage of the project work will be self-performed?
___ 5% or less; ___ 6 to 50%; ___ more than 50%
What other projects do you currently have under contract? (Attach separate sheet) Has any required specialized construction been adequately addressed?
What are your primary concerns regarding the successful completion of this project?
How do you intend to record the project as-built documents?
Is the project superintendent a permanent full-time employee of the contractor?
The following section only applies if these items were specifically requested for review in the bid documents.
Was a bid breakdown submitted? ___Y ___ N If yes, is that bid breakdown satisfactory?
Was a list of subcontractors submitted? ___Y ___ N If so, is that list acceptable?
The following section only applies if a project schedule was requested as part of the post-bidding submittals.
Has a proposed project schedule been submitted? ___Y ____ N Is the proposed project schedule acceptable?
Project-Specific Qualitative Questions What is your estimated duration of work to complete the scope? Answer – 15 days X
(Can also include additional questions specific to the project)
Cox, Mike Stamp
Cox, Mike Typewriter
(AECOM) 06/25/2026
File No. 761/26094.SAR Project Name/Phase: Kavco Landfill AST Decommissioning Bidder: TSP Construction, LLC PSC: AECOM Date: 06/22/2026
EVALUATION CHECKLIST
PART ONE: Responsiveness and Responsibility Yes No Review bid forms and bid submittals prior to interview Are all bid forms and bid submittals in order, complete, and signed? X Have all addenda been acknowledged? X Is the bidder a Michigan firm? X Will 50% or more of the persons employed on the project have been residents of the State of Michigan for not less than one year before the beginning of this project?
X
Does the Contractor acknowledge that all subcontractors are required to obtain a State Project Registration (SPR) from the Department of Labor & Economic Opportunity, Wage & Hour Division?
X
Are DCD contractor performance evaluations (if any) acceptable? (Add comments pg. 5 if No) X Are the completed projects of similar size and complexity, and references, acceptable? Contingent upon provision
X
Is the project superintendent’s resume and past experience with similar projects acceptable? Will Provide
X
Does this contractor have a satisfactory (under 1.0) Experience Modification Rate (EMR)? Will provide X Is the contractor a member of the MIOSHA Michigan Voluntary Protection Program (MVPP) through the Michigan Department of Labor and Economic Opportunity (LEO - Michigan Voluntary Protection Program (MVPP))?
X
Is the company or are principal individuals on the Federal System for Award Management (http://www.SAM.gov) exclusion list?
X
Does this contractor have open MIOSHA violations within the last three (3) years prior to bid opening?
(http://www.osha.gov/pls/imis/establishment.html)
X
Does this work include asbestos abatement? If so, does this contractor and/or any asbestos abatement subcontractors have more than four (4) notices of violation?
X
Interview Within the last five (5) years has your organization been issued a Notice Requiring Assurance of Due Performance, Notice of Intent to Default, or Default – Notice of Termination for Cause, on a State of Michigan project? (If yes, attach a detailed explanation.)
X
Within the last five (5) years has any officer or partner of your organization been an officer or partner of another organization that has been issued a Notice Requiring Assurance of Due Performance, Notice of Intent to Default, or Default – Notice of Termination for Cause, on a State of Michigan project? (If yes, attach a detailed explanation.)
X
Is your proposal mathematically, correct? X
Do you have any concerns with or need clarifications of the bid documents? (If yes, attach a detailed explanation.)
X
Does the bid contain deviations such as substitutions or voluntary alternates? X If there are deviations, have those deviations been reviewed?
Have you included all components for a complete project? X Are you comfortable with your bid and your ability to complete the project within the duration specified? X Do you understand the Soil Erosion and Sedimentation Control requirements (if any) for the project? X Do you understand the Special Working Conditions and Supplemental Conditions (if any) for the project? X Do you understand substantial and final completion and liquidated damages, if any? X Does your proposed project schedule reflect the project duration outlined in the bid documents? X Do you anticipate any difficulties obtaining your performance and payment bonds? X Are you using the bonding capacity of any other entity (i.e., subcontractor)? X Do you understand the Davis-Bacon Act / Prevailing Wage requirements per the bid documents? X PSC and PD discuss and decide post-interview Is this contractor responsive? X Is this contractor responsible? X
Question to bidder Do you still wish your bid to remain in consideration? X
Comments/Explanations of Negative Responses (may attach other sheets)
Signed:
Date
EVALUATION CHECKLIST
PART TWO: Qualitative Components
E x c el le n t
A c ce p ta
N o t
A c ce p ta
Interview How do you plan to provide communications and information for this project?
What is your management plan for this project?
Have you worked successfully with the DTMB Design and Construction Division?
Have you worked successfully with the Client Agency?
Have you worked successfully with the Professional Service Contractor?
How many projects have your successfully completed with your principal subcontractors (if any)?
_____ not worked with before ______ 1-5 _______ 5-10+
What percentage of the project work will be self-performed?
___ 5% or less; ___ 6 to 50%; ___ more than 50%
What other projects do you currently have under contract? (Attach separate sheet) Has any required specialized construction been adequately addressed?
What are your primary concerns regarding the successful completion of this project?
How do you intend to record the project as-built documents?
Is the project superintendent a permanent full-time employee of the contractor?
The following section only applies if these items were specifically requested for review in the bid documents.
Was a bid breakdown submitted? ___Y ___ N If yes, is that bid breakdown satisfactory?
Was a list of subcontractors submitted? ___Y ___ N If so, is that list acceptable?
The following section only applies if a project schedule was requested as part of the post-bidding submittals.
Has a proposed project schedule been submitted? ___Y ____ N Is the proposed project schedule acceptable?
Project-Specific Qualitative Questions What is your estimated duration of work to complete the scope? Answer – 20 days X
(Can also include additional questions specific to the project)
Cox, Mike Stamp
Cox, Mike Typewriter
(AECOM) 06/22/2026
Project File No.: 761/19234.SAR Project Y Number: Y25366
Project Department/Agency: EGLE-RRD Project Name/Location: Snedicor's Cleaners, Howell, MI
Contractor Name: E.T. MacKenzie Company, LLC Date of Evaluation: 2/27/2026
Evaluator Name/Agency/Title: Chris Douglas, Weston Solutions of Michigan, Inc., Project Manager
Rating 1 thru 5 Not Applicable
N/A
Yes or No Yes
No No No No
Comments:
CONSTRUCTION CONTRACTOR PERFORMANCE EVALUATION
This form will form part of an objective evaluation of a Contractor's performance on a State of Michigan construction project. This information may affect the determination of responsiveness and responsibility for future bidding. Evaluations must be made only by personnel familiar with the project and the contractor (PD, OFR, PSC, Agency SPC). Notes, photos, and correspondence must be attached to support "poor" ratings.
Overall excellent execution of the project scope, within the agreed timeline, and under budget.
CONSTRUCTION PROJECT ADMINISTRATION
118TOTAL PERFORMANCE AND EVENTS RATING
Did the Contractor make unwarranted change order requests?
Were any Notices of Defective Work filed?
Were any Default/Termination processes started?
Were there safety or MIOSHA concerns noted in the project records?
CONTRACT COMPLETION
Bonds and insurances were timely and complete
The site was clean, secure, & orderly; materials were properly stored Construction met interim and final progress schedule milestones Construction quality met the requirements of the contract Contractor prevented problems & worked positively to correct issues
RECOMMENDATION
Would you recommend this Contractor for a future similar project?
EVENTS OF CONCERN
The Contractor actively promoted safety and quality construction
Punch List was completed timely
The project was properly staffed with competent, qualified people at all stages
As-built Documents were regularly updated and submitted timely Punch List was reasonable for the project scope
Schedule, subcontractor list, and Schedule of Values were submitted on time and complete Construction Schedule was realistic, accurate, & sufficiently detailed Schedule of Values was realistic, accurate, and sufficiently detailed Submittals, Shop Drawings, & Bulletin Quotes were reviewed before submittal, were timely, accurate, & complete Contractor administered the project in accordance with the contract and accepted contracting practice
CONSTRUCTION
RATING SCALE
1 - Poor 2 - Below Average 3 - Average 4 - Above Average 5 - Excellent
If a rating is not known for an item please select "N/A"
Contractor understood and met the requirements of the project Contractor controlled and coordinated the subs and suppliers
PERFORMANCE RATING
The project administration staff was competent and qualified Construction schedule was pro-actively managed, regularly reviewed and updated
Project File No.: 761/23255.SAR
Project Y Number: Y24404
Project Department/Agency: EGLE/RRD
Project Name/Location: MSI 667/Lansing/Ingham Co.
Contractor Name: E.T. MacKenzie
Date of Evaluation: 2/20/2025
Evaluator Name/Agency/Title: Autumn Henney/EGLE/EQA
Rating
1 thru 5 Not Applicable
N/A
Yes or No Yes
No
No
No
No
Comments:
RATING SCALE
1 - Poor 2 - Below Average 3 - Average 4 - Above Average 5 - Excellent
If a rating is not known for an item please select "N/A"
Contractor understood and met the requirements of the project
Contractor controlled and coordinated the subs and suppliers
PERFORMANCE RATING
The project administration staff was competent and qualified
Construction schedule was pro-actively managed, regularly reviewed and updated
The project was properly staffed with competent, qualified people at all stages
As-built Documents were regularly updated and submitted timely
Punch List was reasonable for the project scope
Schedule, subcontractor list, and Schedule of Values were submitted on time and complete
Construction Schedule was realistic, accurate, & sufficiently detailed
Schedule of Values was realistic, accurate, and sufficiently detailed
Submittals, Shop Drawings, & Bulletin Quotes were reviewed before submittal, were timely, accurate, & complete
Contractor administered the project in accordance with the contract and accepted contracting practice
CONSTRUCTION
RECOMMENDATION
Would you recommend this Contractor for a future similar project?
EVENTS OF CONCERN
The Contractor actively promoted safety and quality construction
Punch List was completed timely
CONSTRUCTION CONTRACTOR PERFORMANCE EVALUATION
This form will form part of an objective evaluation of a Contractor's performance on a State of Michigan construction project. This information may affect the determination of responsiveness and responsibility for future bidding. Evaluations must be made only by personnel familiar with the project and the contractor (PD, OFR, PSC, Agency SPC). Notes, photos, and correspondence must be attached to support "poor" ratings.
CONSTRUCTION PROJECT ADMINISTRATION
117TOTAL PERFORMANCE AND EVENTS RATING
Did the Contractor make unwarranted change order requests?
Were any Notices of Defective Work filed?
Were any Default/Termination processes started?
Were there safety or MIOSHA concerns noted in the project records?
CONTRACT COMPLETION
Bonds and insurances were timely and complete
The site was clean, secure, & orderly; materials were properly stored
Construction met interim and final progress schedule milestones
Construction quality met the requirements of the contract
Contractor prevented problems & worked positively to correct issues
Project File No.: 472/19019.TYC
Project Y Number: Y23065
Project Department/Agency: Dept. of Corrections
Project Name/Location: SAI Faility, Various Buildings Demolition Contractor Name: E.T. MacKenzie Company
Date of Evaluation: 1/24/2024 Evaluator Name/Agency/Title: Todd Cordill, RA, NCARB
Rating 1 thru 5 Not Applicable
Yes or No Yes
No No No Yes
Comments:
RATING SCALE
1 - Poor 2 - Below Average 3 - Average 4 - Above Average 5 - Excellent
If a rating is not known for an item please select "N/A"
Contractor understood and met the requirements of the project Contractor controlled and coordinated the subs and suppliers
PERFORMANCE RATING
The project administration staff was competent and qualified Construction schedule was pro-actively managed, regularly reviewed and updated
The project was properly staffed with competent, qualified people at all stages
As-built Documents were regularly updated and submitted timely Punch List was reasonable for the project scope
Schedule, subcontractor list, and Schedule of Values were submitted on time and complete Construction Schedule was realistic, accurate, & sufficiently detailed Schedule of Values was realistic, accurate, and sufficiently detailed Submittals, Shop Drawings, & Bulletin Quotes were reviewed before submittal, were timely, accurate, & complete Contractor administered the project in accordance with the contract and accepted contracting practice
CONSTRUCTION
RECOMMENDATION
Would you recommend this Contractor for a future similar project?
EVENTS OF CONCERN
The Contractor actively promoted safety and quality construction
Punch List was completed timely
CONSTRUCTION CONTRACTOR PERFORMANCE EVALUATION
This form will form part of an objective evaluation of a Contractor's performance on a State of Michigan construction project. This information may affect the determination of responsiveness and responsibility for future bidding. Evaluations must be made only by personnel familiar with the project and the contractor (PD, OFR, PSC, Agency SPC). Notes, photos, and correspondence must be attached to support "poor" ratings.
CONSTRUCTION PROJECT ADMINISTRATION
92TOTAL PERFORMANCE AND EVENTS RATING
Did the Contractor make unwarranted change order requests?
Were any Notices of Defective Work filed?
Were any Default/Termination processes started?
Were there safety or MIOSHA concerns noted in the project records?
CONTRACT COMPLETION
Bonds and insurances were timely and complete
The site was clean, secure, & orderly; materials were properly stored Construction met interim and final progress schedule milestones
Project File No.: 761/24239.SAR
Project Y Number: Y24416
Project Department/Agency: EGLE RRD
Project Name/Location: 4515 Tireman / 10000599
Contractor Name: TSP Construction LLC
Date of Evaluation: 4/16/2024
Evaluator Name/Agency/Title: Rick McGregor/EGLE RRD/EQA
Rating
1 thru 5 Not Applicable
Yes or No Yes
No
No
No
No
Comments:
RATING SCALE
1 - Poor 2 - Below Average 3 - Average 4 - Above Average 5 - Excellent
If a rating is not known for an item please select "N/A"
Contractor understood and met the requirements of the project
Contractor controlled and coordinated the subs and suppliers
PERFORMANCE RATING
The project administration staff was competent and qualified
Construction schedule was pro-actively managed, regularly reviewed and updated
The project was properly staffed with competent, qualified people at all stages
As-built Documents were regularly updated and submitted timely
Punch List was reasonable for the project scope
Schedule, subcontractor list, and Schedule of Values were submitted on time and complete
Construction Schedule was realistic, accurate, & sufficiently detailed
Schedule of Values was realistic, accurate, and sufficiently detailed
Submittals, Shop Drawings, & Bulletin Quotes were reviewed before submittal, were timely, accurate, & complete
Contractor administered the project in accordance with the contract and accepted contracting practice
CONSTRUCTION
RECOMMENDATION
Would you recommend this Contractor for a future similar project?
EVENTS OF CONCERN
The Contractor actively promoted safety and quality construction
Punch List was completed timely
CONSTRUCTION CONTRACTOR PERFORMANCE EVALUATION
This form will form part of an objective evaluation of a Contractor's performance on a State of Michigan construction project. This information may affect the determination of responsiveness and responsibility for future bidding. Evaluations must be made only by personnel familiar with the project and the contractor (PD, OFR, PSC, Agency SPC). Notes, photos, and correspondence must be attached to support "poor" ratings.
CONSTRUCTION PROJECT ADMINISTRATION
101TOTAL PERFORMANCE AND EVENTS RATING
Did the Contractor make unwarranted change order requests?
Were any Notices of Defective Work filed?
Were any Default/Termination processes started?
Were there safety or MIOSHA concerns noted in the project records?
CONTRACT COMPLETION
Bonds and insurances were timely and complete
The site was clean, secure, & orderly; materials were properly stored
Construction met interim and final progress schedule milestones
Project File No.: 761/06201.RRD
Project Y Number: Y07035
Project Department/Agency: EGLE-RRD
Project Name/Location: Waterford Hills Sanitary Landfill, Waterford MI Contractor Name: TSP Environmental
Date of Evaluation: 2/12/2025 Evaluator Name/Agency/Title: Colleen McLean/EGLE/Senior EQA
Rating 1 thru 5 Not Applicable
N/A N/A N/A N/A N/A
N/A N/A N/A
Yes or No No
No No No No
Comments:
RATING SCALE
1 - Poor 2 - Below Average 3 - Average 4 - Above Average 5 - Excellent
If a rating is not known for an item please select "N/A"
Contractor understood and met the requirements of the project Contractor controlled and coordinated the subs and suppliers
PERFORMANCE RATING
The project administration staff was competent and qualified Construction schedule was pro-actively managed, regularly reviewed and updated
The project was properly staffed with competent, qualified people at all stages
As-built Documents were regularly updated and submitted timely Punch List was reasonable for the project scope
Schedule, subcontractor list, and Schedule of Values were submitted on time and complete Construction Schedule was realistic, accurate, & sufficiently detailed Schedule of Values was realistic, accurate, and sufficiently detailed Submittals, Shop Drawings, & Bulletin Quotes were reviewed before submittal, were timely, accurate, & complete Contractor administered the project in accordance with the contract and accepted contracting practice
CONSTRUCTION
RECOMMENDATION
Would you recommend this Contractor for a future similar project?
EVENTS OF CONCERN
The Contractor actively promoted safety and quality construction
Punch List was completed timely
CONSTRUCTION CONTRACTOR PERFORMANCE EVALUATION
This form will form part of an objective evaluation of a Contractor's performance on a State of Michigan construction project. This information may affect the determination of responsiveness and responsibility for future bidding. Evaluations must be made only by personnel familiar with the project and the contractor (PD, OFR, PSC, Agency SPC). Notes, photos, and correspondence must be attached to support "poor" ratings.
TSP’s contract ended 9/30/24. February 11, 2025, TSP came onto the site without permission and removed the Nitrogen tank from the flare system. TSP did not notify the SPM or ERG they needed the tank back or that they were coming on site to get the nitrogen tank.
There are two locked gates to get onto the property and a locked fenced area around the flare that they bypassed without permission.
CONSTRUCTION PROJECT ADMINISTRATION
68TOTAL PERFORMANCE AND EVENTS RATING
Did the Contractor make unwarranted change order requests?
Were any Notices of Defective Work filed?
Were any Default/Termination processes started?
Were there safety or MIOSHA concerns noted in the project records?
CONTRACT COMPLETION
Bonds and insurances were timely and complete
The site was clean, secure, & orderly; materials were properly stored Construction met interim and final progress schedule milestones
Project File No.: 761/24295.SAR
Project Y Number: Y25269
Project Department/Agency: EGLE
Project Name/Location: Detroit Oil Co
Contractor Name: TSP Construction
Date of Evaluation: 2/20/2026
Evaluator Name/Agency/Title: Dominic Aluia/EGLE RRD/ Senior Project Manager
Rating
1 thru 5 Not Applicable
Yes or No No
Yes
No
No
No
Comments:
CONSTRUCTION CONTRACTOR PERFORMANCE EVALUATION
This form will form part of an objective evaluation of a Contractor's performance on a State of Michigan construction project. This information may affect the determination of responsiveness and responsibility for future bidding. Evaluations must be made only by personnel familiar with the project and the contractor (PD, OFR, PSC, Agency SPC). Notes, photos, and correspondence must be attached to support "poor" ratings.
See Additional Comment Page.
CONSTRUCTION PROJECT ADMINISTRATION
67TOTAL PERFORMANCE AND EVENTS RATING
Did the Contractor make unwarranted change order requests?
Were any Notices of Defective Work filed?
Were any Default/Termination processes started?
Were there safety or MIOSHA concerns noted in the project records?
CONTRACT COMPLETION
Bonds and insurances were timely and complete
The site was clean, secure, & orderly; materials were properly stored
Construction met interim and final progress schedule milestones
Construction quality met the requirements of the contract
Contractor prevented problems & worked positively to correct issues
RECOMMENDATION
Would you recommend this Contractor for a future similar project?
EVENTS OF CONCERN
The Contractor actively promoted safety and quality construction
Punch List was completed timely
The project was properly staffed with competent, qualified people at all stages
As-built Documents were regularly updated and submitted timely
Punch List was reasonable for the project scope
Schedule, subcontractor list, and Schedule of Values were submitted on time and complete
Construction Schedule was realistic, accurate, & sufficiently detailed
Schedule of Values was realistic, accurate, and sufficiently detailed
Submittals, Shop Drawings, & Bulletin Quotes were reviewed before submittal, were timely, accurate, & complete
Contractor administered the project in accordance with the contract and accepted contracting practice
CONSTRUCTION
RATING SCALE
1 - Poor 2 - Below Average 3 - Average 4 - Above Average 5 - Excellent
If a rating is not known for an item please select "N/A"
Contractor understood and met the requirements of the project
Contractor controlled and coordinated the subs and suppliers
PERFORMANCE RATING
Summary of Poor Ratings on DTMB-0495 Contractor Evaluation
TSP did not coordinate pre-remedial activity site survey as detailed within this Bid Specs.
The initial site survey was completed after building deconstruction and earth movement had begun.
EGLE PM & PSC, WSP, had to repeatedly request that TSP follow the bid specifications regarding site security including privacy fence, fence clips and sand bags to secure the fencing. Excavation work began on August 20th, 2025. EGLE PM was onsite and observed
UST excavation activities beginning, but the temporary site fence had not been installed to secure the Site. EGLE PM notified WSP PM and a temporary fence was installed later that day.
TSP did not notify EGLE PM of onsite health and safety incident when a construction worker fainted on the job site on Tuesday August 18th, 2025. EGLE PM instead was informed of this medical incident from EGLE’s professional services contractor, WSP, who noted in a phone call that the TSP employees suddenly left the job site. TSP did not follow their HASP and instead transported their employee directly to an alternative hospital. EGLE PM and
EGLE Health and Safety Coordinator Dana Brandt had to repeatedly request documentation of TSP's response to this incident. They did not provide EGLE with documentation of the incident until September 19th, 2025.
Project File No.: 761/17231.SAR
Project Y Number: Y22375
Project Department/Agency: EGLE-RRD
Project Name/Location: Gudith Road Landfill
Contractor Name: TSP
Date of Evaluation: 8/14/2024
Evaluator Name/Agency/Title: Ben Vens/EGLE-RRD/Detroit District Assistant District Supervisor
Rating
1 thru 5 Not Applicable
N/A
N/A
N/A
N/A
Yes or No Yes
No
No
No
No
Comments:
CONSTRUCTION CONTRACTOR PERFORMANCE EVALUATION
This form will form part of an objective evaluation of a Contractor's performance on a State of Michigan construction project. This information may affect the determination of responsiveness and responsibility for future bidding. Evaluations must be made only by personnel familiar with the project and the contractor (PD, OFR, PSC, Agency SPC). Notes, photos, and correspondence must be attached to support "poor" ratings.
CONSTRUCTION PROJECT ADMINISTRATION
82TOTAL PERFORMANCE AND EVENTS RATING
Did the Contractor make unwarranted change order requests?
Were any Notices of Defective Work filed?
Were any Default/Termination processes started?
Were there safety or MIOSHA concerns noted in the project records?
CONTRACT COMPLETION
Bonds and insurances were timely and complete
The site was clean, secure, & orderly; materials were properly stored
Construction met interim and final progress schedule milestones
Construction quality met the requirements of the contract
Contractor prevented problems & worked positively to correct issues
RECOMMENDATION
Would you recommend this Contractor for a future similar project?
EVENTS OF CONCERN
The Contractor actively promoted safety and quality construction
Punch List was completed timely
The project was properly staffed with competent, qualified people at all stages
As-built Documents were regularly updated and submitted timely
Punch List was reasonable for the project scope
Schedule, subcontractor list, and Schedule of Values were submitted on time and complete
Construction Schedule was realistic, accurate, & sufficiently detailed
Schedule of Values was realistic, accurate, and sufficiently detailed
Submittals, Shop Drawings, & Bulletin Quotes were reviewed before submittal, were timely, accurate, & complete
Contractor administered the project in accordance with the contract and accepted contracting practice
CONSTRUCTION
RATING SCALE
1 - Poor 2 - Below Average 3 - Average 4 - Above Average 5 - Excellent
If a rating is not known for an item please select "N/A"
Contractor understood and met the requirements of the project
Contractor controlled and coordinated the subs and suppliers
PERFORMANCE RATING
Project File No.: 761/17231.SAR
Project Y Number: Y22375
Project Department/Agency: EGLE-RRD
Project Name/Location: Gudith Road Landfill
Contractor Name: TSP
Date of Evaluation: 8/14/2024
Evaluator Name/Agency/Title: Anita Emery-DeVisser / WSP /
Rating
1 thru 5 Not Applicable
N/A
N/A
Yes or No Yes
N/A
No
No
No
Comments:
CONSTRUCTION CONTRACTOR PERFORMANCE EVALUATION
This form will form part of an objective evaluation of a Contractor's performance on a State of Michigan construction project. This information may affect the determination of responsiveness and responsibility for future bidding. Evaluations must be made only by personnel familiar with the project and the contractor (PD, OFR, PSC, Agency SPC). Notes, photos, and correspondence must be attached to support "poor" ratings.
I have completed this evaluation given the information contained in the project file. The WSP project manager that was in place when this scope of work was performed has left the company.
CONSTRUCTION PROJECT ADMINISTRATION
80TOTAL PERFORMANCE AND EVENTS RATING
Did the Contractor make unwarranted change order requests?
Were any Notices of Defective Work filed?
Were any Default/Termination processes started?
Were there safety or MIOSHA concerns noted in the project records?
CONTRACT COMPLETION
Bonds and insurances were timely and complete
The site was clean, secure, & orderly; materials were properly stored
Construction met interim and final progress schedule milestones
Construction quality met the requirements of the contract
Contractor prevented problems & worked positively to correct issues
RECOMMENDATION
Would you recommend this Contractor for a future similar project?
EVENTS OF CONCERN
The Contractor actively promoted safety and quality construction
Punch List was completed timely
The project was properly staffed with competent, qualified people at all stages
As-built Documents were regularly updated and submitted timely
Punch List was reasonable for the project scope
Schedule, subcontractor list, and Schedule of Values were submitted on time and complete
Construction Schedule was realistic, accurate, & sufficiently detailed
Schedule of Values was realistic, accurate, and sufficiently detailed
Submittals, Shop Drawings, & Bulletin Quotes were reviewed before submittal, were timely, accurate, & complete
Contractor administered the project in accordance with the contract and accepted contracting practice
CONSTRUCTION
RATING SCALE
1 - Poor 2 - Below Average 3 - Average 4 - Above Average 5 - Excellent
If a rating is not known for an item please select "N/A"
Contractor understood and met the requirements of the project
Contractor controlled and coordinated the subs and suppliers
PERFORMANCE RATING
Project File No.: 751/24141.JLM
Project Y Number: Y25152
Project Department/Agency: Department of Natural Resources
Project Name/Location: Benton Harbor BAS - Paving and Repairs Contractor Name: TS Contract Management
Date of Evaluation: 7/11/2025 Evaluator Name/Agency/Title: Paul McGahan - DTMB Field Rep.
Rating 1 thru 5 Not Applicable
Yes or No Yes
No No No No
Comments:
CONSTRUCTION CONTRACTOR PERFORMANCE EVALUATION
This form will form part of an objective evaluation of a Contractor's performance on a State of Michigan construction project. This information may affect the determination of responsiveness and responsibility for future bidding. Evaluations must be made only by personnel familiar with the project and the contractor (PD, OFR, PSC, Agency SPC). Notes, photos, and correspondence must be attached to support "poor" ratings.
CONSTRUCTION PROJECT ADMINISTRATION
101TOTAL PERFORMANCE AND EVENTS RATING
Did the Contractor make unwarranted change order requests?
Were any Notices of Defective Work filed?
Were any Default/Termination processes started?
Were there safety or MIOSHA concerns noted in the project records?
CONTRACT COMPLETION
Bonds and insurances were timely and complete
The site was clean, secure, & orderly; materials were properly stored Construction met interim and final progress schedule milestones Construction quality met the requirements of the contract Contractor prevented problems & worked positively to correct issues
RECOMMENDATION
Would you recommend this Contractor for a future similar project?
EVENTS OF CONCERN
The Contractor actively promoted safety and quality construction
Punch List was completed timely
The project was properly staffed with competent, qualified people at all stages
As-built Documents were regularly updated and submitted timely Punch List was reasonable for the project scope
Schedule, subcontractor list, and Schedule of Values were submitted on time and complete Construction Schedule was realistic, accurate, & sufficiently detailed Schedule of Values was realistic, accurate, and sufficiently detailed Submittals, Shop Drawings, & Bulletin Quotes were reviewed before submittal, were timely, accurate, & complete Contractor administered the project in accordance with the contract and accepted contracting practice
CONSTRUCTION
RATING SCALE
1 - Poor 2 - Below Average 3 - Average 4 - Above Average 5 - Excellent
If a rating is not known for an item please select "N/A"
Contractor understood and met the requirements of the project Contractor controlled and coordinated the subs and suppliers
PERFORMANCE RATING
Project File No.: 751/24141.JLM
Project Y Number: Y25152
Project Department/Agency: Department of Natural Resources
Project Name/Location: Benton Harbor BAS - Paving and Repairs Contractor Name: TS Contract Management
Date of Evaluation: 7/11/2025 Evaluator Name/Agency/Title: Josiah Meyers/DTMB-DCD/Project Director
Rating 1 thru 5 Not Applicable
Yes or No Yes
No No No No
Comments:
CONSTRUCTION CONTRACTOR PERFORMANCE EVALUATION
This form will form part of an objective evaluation of a Contractor's performance on a State of Michigan construction project. This information may affect the determination of responsiveness and responsibility for future bidding. Evaluations must be made only by personnel familiar with the project and the contractor (PD, OFR, PSC, Agency SPC). Notes, photos, and correspondence must be attached to support "poor" ratings.
CONSTRUCTION PROJECT ADMINISTRATION
101TOTAL PERFORMANCE AND EVENTS RATING
Did the Contractor make unwarranted change order requests?
Were any Notices of Defective Work filed?
Were any Default/Termination processes started?
Were there safety or MIOSHA concerns noted in the project records?
CONTRACT COMPLETION
Bonds and insurances were timely and complete
The site was clean, secure, & orderly; materials were properly stored Construction met interim and final progress schedule milestones Construction quality met the requirements of the contract Contractor prevented problems & worked positively to correct issues
RECOMMENDATION
Would you recommend this Contractor for a future similar project?
EVENTS OF CONCERN
The Contractor actively promoted safety and quality construction
Punch List was completed timely
The project was properly staffed with competent, qualified people at all stages
As-built Documents were regularly updated and submitted timely Punch List was reasonable for the project scope
Schedule, subcontractor list, and Schedule of Values were submitted on time and complete Construction Schedule was realistic, accurate, & sufficiently detailed Schedule of Values was realistic, accurate, and sufficiently detailed Submittals, Shop Drawings, & Bulletin Quotes were reviewed before submittal, were timely, accurate, & complete Contractor administered the project in accordance with the contract and accepted contracting practice
CONSTRUCTION
RATING SCALE
1 - Poor 2 - Below Average 3 - Average 4 - Above Average 5 - Excellent
If a rating is not known for an item please select "N/A"
Contractor understood and met the requirements of the project Contractor controlled and coordinated the subs and suppliers
PERFORMANCE RATING
Project File No.: 751.23237.CTS
Project Y Number: Y24052
Project Department/Agency: DNR
Project Name/Location: Sleeper SP Sewer/Lift Station Improvements Contractor Name: TSP Environmental
Date of Evaluation: 10/13/2025 Evaluator Name/Agency/Title: Chris Schanbeck, DTMB-DCD, Project Director
Rating 1 thru 5 Not Applicable
Yes or No Yes
No No No No
Comments:
CONSTRUCTION CONTRACTOR PERFORMANCE EVALUATION
This form will form part of an objective evaluation of a Contractor's performance on a State of Michigan construction project. This information may affect the determination of responsiveness and responsibility for future bidding. Evaluations must be made only by personnel familiar with the project and the contractor (PD, OFR, PSC, Agency SPC). Notes, photos, and correspondence must be attached to support "poor" ratings.
Bulk of the lift station install went fine but stumbled to complete some late added controls the DNR asked for.
CONSTRUCTION PROJECT ADMINISTRATION
83TOTAL PERFORMANCE AND EVENTS RATING
Did the Contractor make unwarranted change order requests?
Were any Notices of Defective Work filed?
Were any Default/Termination processes started?
Were there safety or MIOSHA concerns noted in the project records?
CONTRACT COMPLETION
Bonds and insurances were timely and complete
The site was clean, secure, & orderly; materials were properly stored Construction met interim and final progress schedule milestones Construction quality met the requirements of the contract Contractor prevented problems & worked positively to correct issues
RECOMMENDATION
Would you recommend this Contractor for a future similar project?
EVENTS OF CONCERN
The Contractor actively promoted safety and quality construction
Punch List was completed timely
The project was properly staffed with competent, qualified people at all stages
As-built Documents were regularly updated and submitted timely Punch List was reasonable for the project scope
Schedule, subcontractor list, and Schedule of Values were submitted on time and complete Construction Schedule was realistic, accurate, & sufficiently detailed Schedule of Values was realistic, accurate, and sufficiently detailed Submittals, Shop Drawings, & Bulletin Quotes were reviewed before submittal, were timely, accurate, & complete Contractor administered the project in accordance with the contract and accepted contracting practice
CONSTRUCTION
RATING SCALE
1 - Poor 2 - Below Average 3 - Average 4 - Above Average 5 - Excellent
If a rating is not known for an item please select "N/A"
Contractor understood and met the requirements of the project Contractor controlled and coordinated the subs and suppliers
PERFORMANCE RATING
Project File No.: 751.18085.MNB
Project Y Number: Y21262
Project Department/Agency: DNR
Project Name/Location: Milliken State Park- Berm Improvments Contractor Name: TSP Enviromental
Date of Evaluation: 5/5/2026 Evaluator Name/Agency/Title: Chris Bahjet, DTMB-DCD- Project Director
Rating 1 thru 5 Not Applicable
Yes or No Yes
No No No No
Comments:
RATING SCALE
1 - Poor 2 - Below Average 3 - Average 4 - Above Average 5 - Excellent
If a rating is not known for an item please select "N/A"
Contractor understood and met the requirements of the project Contractor controlled and coordinated the subs and suppliers
PERFORMANCE RATING
The project administration staff was competent and qualified Construction schedule was pro-actively managed, regularly reviewed and updated
The project was properly staffed with competent, qualified people at all stages
As-built Documents were regularly updated and submitted timely Punch List was reasonable for the project scope
Schedule, subcontractor list, and Schedule of Values were submitted on time and complete Construction Schedule was realistic, accurate, & sufficiently detailed Schedule of Values was realistic, accurate, and sufficiently detailed Submittals, Shop Drawings, & Bulletin Quotes were reviewed before submittal, were timely, accurate, & complete Contractor administered the project in accordance with the contract and accepted contracting practice
CONSTRUCTION
RECOMMENDATION
Would you recommend this Contractor for a future similar project?
EVENTS OF CONCERN
The Contractor actively promoted safety and quality construction
Punch List was completed timely
CONSTRUCTION CONTRACTOR PERFORMANCE EVALUATION
This form will form part of an objective evaluation of a Contractor's performance on a State of Michigan construction project. This information may affect the determination of responsiveness and responsibility for future bidding. Evaluations must be made only by personnel familiar with the project and the contractor (PD, OFR, PSC, Agency SPC). Notes, photos, and correspondence must be attached to support "poor" ratings.
Construction work went smotth, quotes were fair. The restoration after establishing the path, was an issue. Seeded many many times but it didn’t germinate. They asked for aw after source, there is none nearby but that's responsibility. The soil had mixed fine gravel with it. SmithGroup wrote the specification and advised this: STONES VISIBLE There are a couple reasons that you are seeing stones in the lawn area. First, the topsoil was allowed to be unscreened to save money, which means that stones may be mixed in with the topsoil. Here is the language from the specifications:
"1. Topsoil for landscape work shall be a fertile, friable, sandy loam surface soil without admixture of subsoil. Topsoil does not need to be screened through a mechanical plant but must be free of stones larger than 2 inches in any dimension, stumps, trash, debris, and other materials deleterious to plant growth." In recommending the final payment, I asked SG what are the expectations for spring 2026, they said Chris- I would expect the reseeded areas to germinate in the spring and grass to cover the site by the end of June. We shall see .
CONSTRUCTION PROJECT ADMINISTRATION
88TOTAL PERFORMANCE AND EVENTS RATING
Did the Contractor make unwarranted change order requests?
Were any Notices of Defective Work filed?
Were any Default/Termination processes started?
Were there safety or MIOSHA concerns noted in the project records?
CONTRACT COMPLETION
Bonds and insurances were timely and complete
The site was clean, secure, & orderly; materials were properly stored Construction met interim and final progress schedule milestones
TSP ETM Comparison Table
TSP Construction LLC ET MacKenzie Co. LLC Performance Evaluation Rating Information Year
2024 101/yes, 82/yes 92/yes 2025 68/no, 101/yes, 101/yes, 83/yes 117/yes 2026 67/no, 88/yes 118/yes
Average Performance Score 86.38 109.00
Performance Score Comments
2025 McLean 68 score noted that TSP entered a locked site without authorization after their contract end date and removed a tank. 2026 Aluia 67 score eval noted significant deficiencies in following project scope and also did not notify EGLE of a health and safety incident which occured at the site, requring off-site medical treatment.
2026 Weston 118 score noted excellent execution of scope, within timeline, and under budget
Contractor Estimated Duration of Work Indicated During Interview 20 days 15 days Associated PSC On-site Oversight Estimated Costs 18,116.00 13,789.50 Contractor Base Bid 174,211.78 177,240.00
Total of Contractor Bid and PSC Oversight 192,327.78 191,029.50
Rating / Would Recommend?
bwalquist Typewritten Text See Attached bwalquist Typewritten Text See Attached bwalquist Typewritten Text See Attached bwalquist Typewritten Text See Attached bwalquist
See Attached
Barrett Walquist Digitally signed by Barrett Walquist
DN: C=US,
E=bwalquist@mackenzieco.com, OU=E.T.
MacKenzie Company,…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .