This is an Award Information document from the Cobb County-Marietta Water Authority (CCMWA) regarding the James E. Quarles Water Treatment Plant No. 2 Valve and Actuator Replacement project in Georgia. The project encompasses the removal of thirty-four electric actuators from various filtration and backwash rate of flow valves, with subsequent installation of one hundred and twelve new valve and actuator assemblies at the Quarles Plant 2 facility. The work includes removal of pneumatic actuators and associated air piping systems, installation of five actuators on raw water pump control valves at the Quarles Raw Water Pump Station on the Chattahoochee River, and rotation of existing ball valves on specific pump units. The CCMWA Board Meeting convened on November 21, 2022, to award the project contract.
Reynolds Construction of Georgia, LLC, based in Fairburn, Georgia, was selected as the award recipient with a verified low bid price of $4,088,000. No additional information regarding pricing terms, funding sources, contract duration, or renewal options is provided in this award document.
Text of this file
At the November 21, 2022 CCMWA Board Meeting, the Quarles Water Treatment Plant No.2 Valve and Actuator Replacement project was awarded to Reynolds Construction of Georgia, LLC of Fairburn, Georgia for the verified low bid price of $4,088,000.
Other files
| File | Type | Posted |
|---|---|---|
| Quarles Valve Actuator Project | — | |
| Addendum 2 | — |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .