AV-00070-9J_B3165_ReplaceHVACSOW.pdf

PDF 294 KB Posted

Attached to
HVAC Repair
Solicitation number
W91QV124R9999
Issued by

About this file

This document is a Statement of Work (SOW) for a Design-Build project to replace the HVAC system in Building 3165 at Fort Belvoir, Virginia. The building is the home of the Operational Support Airlift Activity (OSA-A) and is approximately 15,485 gross square feet.

The key objectives are to demolish the existing central station air handling unit (AHU), roof top unit (RTU), and associated equipment, and replace them with a new variable air volume (VAV) HVAC system with electric reheat. The new system will rezone the HVAC to provide local temperature control in command offices and proper heating, cooling, and ventilation in the remaining areas. The contractor will be responsible for architectural, structural, civil, mechanical, plumbing, fire protection, electrical, and other related work to complete the replacement. The performance period is 730 calendar days, with design due within 215 calendar days after partial notice to proceed. The contractor must follow all applicable regulations, codes, and sustainable design requirements.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Directorate of Public Works Engineering Division

Fort Belvoir, VA 22060-5130

STATEMENT OF WORK (DESIGN-BUILD)

Project No.: AV-00070-9J Facility No.: 3165 Project Description: Repair Airfield Ops Building HVAC Project Manager: Christopher Bray Date: 5 Jan 2024

A. DESIGN-BUILD STATEMENT OF WORK:

The contractor shall provide and install all materials, labor, equipment, transportation, and services to design and repair building 3165’s HVAC system, Fort Belvoir, Virginia. Note that the square footage provided in this statement of work are approximate.

General Description:

Building 3165 is located at 6921 Britten Dr, Fort Belvoir, VA 22060. It is the home to the Operational Support Airlift Activity (OSA-A). OSA-A is a multi-component Army activity which oversees the management of the non-executive fixed wing operations at the Davidson Amy Airfield. The building was built in 1976, totaling 15,485 gross square foot. The building features office spaces (total 8,612 SF), conference rooms (total 1,157 SF), server room (497 SF), telecommunications room (292 SF), fitness area (271 SF), loading bay receiving area (465 SF), and secure working area (257 SF). The remainder of the building’s square footage are mechanical rooms, hallways, and storage rooms.

In general, the Building’s HVAC is divided between 1 central station air handling unit (AHU), (1) 20-ton packaged roof top unit (RTU) with electric heating, 11 mini-split units, 1 computer room air conditioning unit, 2-unit heaters, and 4 window units. The current central station AHU and RTU were zoned and ducted for a different layout within spaces. As a result, multiple spaces have large temperature and humidity deltas from the building’s set point. The building also utilizes steam generated from (1) 400 MBH gas fired boiler to provide heating throughout the building. Additionally, the building has experienced water flowing out of the ductwork.

The intent of this project is to demolish the old central station air handling unit and roof top unit along with their respective ancillary equipment, steam piping, ductwork, condensate pumps, controls, and boiler. In its place the intent is to replace the 2 systems with a variable air volume (VAV) system with electric reheat at the terminal units. Additionally, the replacement HVAC system shall rezone the HVAC to provide local temperature control to command offices and provide the remaining areas with proper heating, cooling, and ventilation. Additionally, the replacement system shall not place air handlers or other large equipment on the roof. The HVAC systems serving the server room, computer room, IT offices near the computer room, UPS room, and secure area will not be part of this contract and will remain in place. The spaces internal to the building shall not be reconfigured, change use, or change occupancy.

Summary of Works (see UFC 1-300-7A):

1. Architectural:

1. The contractor shall Validate the existing as-built conditions.

2. The contractor shall Demolish, remove, and dispose of the roof curb and pitch pockets that support the existing Roof Top Unit.

3. The contractor shall Demolish, remove, and dispose, of fence surrounding the existing roof top unit.

4. The contractor shall Demolish, remove, and dispose, of roof curbs and pitch pockets that support the existing condensing units that are to be removed based on the mechanical design.

5. The contractor shall Demolish, remove, and dispose, of abandoned in place roof curb.

6. The contractor shall Provide new roof decking like existing that matches color, material, and texture.

7. The contractor shall Install new roof decking, so it is coplanar with the existing roof decking for the penetrations created in items 2-5.

8. The contractor shall Remove portions of roof decking and structure to prepare for new openings required for proposed work including but not limited to, piping, ductwork, electrical conduit, and refrigerant lines.

9. The contractor shall Not modify the layout or function of the building’s interior spaces.

10. The contractor shall identify, provide, and install the minimum modification to mechanical rooms on the building’s northwest elevation to accommodate fire protection, moisture penetration resilience, placement of mechanical equipment within the bounds set in mechanical scope (10,11), and mechanical room building envelope.

11. The contractor shall Protect existing equipment while construction is taking place.

12. The contractor shall provide and install wall patching where existing components are removed during demolition and the hole created is not re-used per the design plans.

13. The contractor shall Clean existing roof drains and inspect for leaks.

2. Structural:

1. The contractor shall Validate existing as-built conditions.

2. The contractor shall Protect existing equipment while construction is taking place.

3. The contractor shall identify, provide, and install the minimum structural modifications necessary to support the replacement HVAC system. Modifications include but are not limited to, demolition and placement of concrete pads, erecting new concrete masonry unit (CMU) walls and roof repair of mechanical room on northwest elevation.

4. The contractor shall provide all structural analysis needed to support hanging new ductwork and pipe runs.

5. The contractor shall Not modify the layout or function of the building’s interior spaces.

6. The contractor shall identify, provide, and install the minimum modification to mechanical rooms that are only accessible from the building’s exterior to accommodate the placement of mechanical equipment and standoffs from electrical panels.

3. Civil:

1. The contractor shall Validate the existing as-built conditions.

2. The contractor shall Protect existing equipment while construction is taking place.

3. The contractor shall Identify and provide all grading, geotech surveys, topographic surveys, site boring, drainage studies, footings, erosion/sediment control, permitting, and excavation necessary to support the replacement HVAC system.

4. The contractor shall Identify and provide, all documentation, site plans, square footage calculations, erosion control plans, and other permitting documentation necessary to modify mechanical rooms that are only accessible from the building’s exterior.

5. For concrete pads required for exterior mounted Air Handling Units/Condensers, the contractor shall relocate/redistribute any soil excavated for the installation of the pad in the vicinity of B3165.

6. The contractor shall stabilize the relocated/redistributed soil per the Virginia Erosion Control handbook standard.

7. The contractor shall comply with MS4 DEQ and local land disturbing regulations and requirements.

4. Mechanical:

2. The contractor shall Protect existing equipment while construction is taking place.

3. The contractor shall Demolish, remove, and dispose of existing Roof Top Unit and its associated, ductwork, dampers, controls, steam piping, condensate pumps, condensate piping, steam traps, heating coils and other ancillary equipment necessary to support the full replacement of the system.

4. The contractor shall Demolish remove and dispose of exiting boiler that serves the steam system for the building. If, during design development, it is discovered that the boiler serves the hot water distribution throughout the building, provide an adequate natural gas replacement boiler that meets the hot water requirement served by the existing boiler to include associated pumps, valves, and controls as required.

5. If, during design development, it is discovered that the existing steam piping serves the heating in the IT offices, the contractor shall provide a hot water heating coil replacement to meet the heating load in the areas served by the steam coil.

6. The contractor shall Demolish remove and dispose of the existing mini split condensers and their associated indoor units that serve the conference room, commanders offices, fully enclosed office spaces, and open office spaces.

7. The contractor shall Provide and install a new Variable air Volume (VAV) HVAC system with electric reheat rezoned for the existing spaces.

8. The contractor shall validate plenum space/height available for installation of the VAV units above the Acoustic Ceiling tiles prior to ordering equipment, ensuring all new equipment will fit with proper clearances for ductwork, electrical conduit, controls wiring, and preventative maintenance functions.

9. The contractor shall Provide and install localized thermostatic control to, the commander’s office, conference rooms, fully enclosed office spaces, gym, and open office spaces.

10. The contractor shall Provide and install a minimum of 1 indoor Air-Handling Unit (AHU) and 1 outdoor AHU with Direct Exchange (DX) cooling and hot water heating coils that operate independently from one another.

11. The contractor shall Provide and install all pumps necessary to circulate hot water throughout the replacement HVAC system.

12. The contractor shall Provide and install a new location for indoor and outdoor air handling units on the northwest elevation of the building.

13. The contractor shall Place air handlers, and their dx condensing units, within the area enclosed from a line coplanar with the furthest exterior mechanical room wall and a line coplanar to the exterior room walls that are all located on the northwest elevation.

14. The contractor shall Minimize the amount of water piping runs that extend directly over workspace areas.

15. The contractor shall not place equipment beyond the lines that are coplanar with the building walls that are parallel with Britten Dr.

16. The contractor shall Provide and install a minimum of 12, pressure independent, Fan powered, VAV boxes with electric reheat.

17. The contractor shall Provide and install a minimum of 2 natural gas boilers to supply hot water to the AHU’s heating coils configured in a manor such that 1 boiler serves 1 air handler each and operate independently of each other.

18. The contractor shall not remove the existing HVAC that serves the IT rooms, IT offices, Computer room, Uninterruptible power supply (UPS) room, and secure area.

19. The contractor shall not modify the exhaust ventilation serving the restrooms.

20. The contractor shall Re-use the 2 existing mechanical room spaces accessible only from the building’s exterior for new equipment to be installed.

21. The contractor shall provide and install new, appropriately sealed, insulated, ductwork with hangars.

22. The contractor shall provide and install all required expansion tanks for boilers.

23. The contractor shall provide and install volume dampers to enable proper air-balancing of the overall system.

24. The contractor shall provide and install a volume damper at each main-to-branch duct connection routing to a VAV unit.

25. The contractor shall provide and install Direct expansion (DX) equipment specifically designed and manufactured for VAV application.

26. The contractor shall provide and install air handling units, VAV boxes, zone dampers, and zone DDC controls from the same equipment manufacturer per UFC 3-410-01, Section 3- 7.10.

27. The contractor’s design and installation of the new air-handling units providing cooling & heating airflow to the VAV units shall incorporate the following:

a. A Variable frequency drive (VFD) connected to the AHU’s fan configured to modulate the AHU fan rotational speed based on the downstream duct static pressure setpoint.

b. The designer of record shall meet ASHRAE Standard 62.1-2022 requirements and use a minimum of 75 occupants within B3165 for outdoor air calculations.

c. Provide and install AHU(s) with MERV 13 filters.

d. The AHU(s) with DX cooling coils will be connected to an exterior, air-cooled condensing unit.

e. The contractor shall not manifold two, independent refrigeration circuits into a single circuited DX (Evaporator coil). If the condensing unit does have two, independent refrigeration circuits, configure the DX coil to have either two or four distributors. DX coils, equipped with either two or four distributors, can be configured with either intertwined or horizontal-split cutting circuiting. Intertwined circuiting is preferred for this VAV application to facilitate a warmer coil surface at part load, which reduces the risk of frost and still provide a constant leaving air temperature.

f. The contractor shall provide and install each new AHU with an appropriately sized vibration isolation between the unit base and the concrete pad.

g. The contractor shall provide and install each new AHU with a flexible ductwork connector for the unit/fan inlet and unit/fan outlet to reduce noise/vibration transmission.

28. The contractor’s Design and Installation of the new VAV terminal units shall incorporate the following items:

a. Each VAV will be a Pressure-Independent unit to facilitate better airflow control regardless of system pressure fluctuations.

b. Each VAV will be a Fan-Powered unit (Parallel style) to compensate for varying loads during occupied hours.

c. Each VAV Fan will include an Electrically Commutated Motor (ECM) for noise reduction and greater airflow range considerations.

d. Each VAV will include a transformer to convert the primary power supply voltage to the voltage required by the Direct Digital controller.

e. Each VAV will include a differential pressure transducer for connection with the direct digital controller to measure the difference between the high pressure and low-pressure ports of the flow ring. The transducer will be self-adjusting to changes in environment temperature and humidity.

f. Each VAV will include an electric reheat coil sized appropriately for the airflow range and zone served. The electric heating coil (in kW) will have the ability to provide a minimum of 2-stage heating to meet full load and partial heating load flexibility. If required, provide unit with electric heater silicon-controlled rectifier (SCR) to allow for minimum 2-stage heating.

g. Flexible air duct connectors will only be permitted on the downflow side of the VAV unit(s) to facilitate easier connection to the round openings of ceiling diffusers. The length of any duct connector from the VAV unit to the ceiling diffuser shall not exceed five (5) feet in length. Flexible ductwork IS NOT permitted upstream of any VAV terminal unit.

h. If the ductwork from supply-air mains to the individual VAV unit(s) requires a sheet metal reducer fitting, a minimum duct length, equal to 3 duct diameters is required from the reducer fitting to the inlet of the VAV units. This required duct length from reducer to VAV unit inlet is meant to prevent airflow separation prior to entering the VAV flow ring sensors.

i. Each new installed VAV will be suspended in the plenum space above the acoustical ceiling tile with vibration isolation hangers to reduce transmission of vibration and noise produced by the suspended VAV boxes. The hangers can be either a neoprene hanger molded with oil resistant compounds, or a Spring-type isolation hanger sized appropriately for the weight of the suspended unit.

j. Each VAV will utilize a “Foil-Faced” internal insulation to reduce airborne contaminants from entering the occupied space.

29. The Design and Installation of the new Air Handling Units and associated VAV’s will incorporate a Direct Digital Control (DDC) System with the following items:

a. The HVAC control system for this facility will be a “Stand-Alone” system with all required controls equipment being located within the facility or mechanical/electrical rooms. B3165’s HVAC controls will not be connected to any Installation-Wide front end.

b. The new installed DDC system will be hard-wired from sensors, equipment controllers, AHU’s, etc back to a primary Building Control Unit/Cabinet. Wi-Fi DDC equipment WILL NOT be permitted to avoid conflicts with Installation Cybersecurity Standards. Contractor will provide all required wiring/cables for DDC system operation.

c. Provide and install a minimum of two (2) static pressure sensors for AHU fan speed control. One sensor shall be placed a minimum of two-thirds the distance of the longest main supply air duct. The second static pressure sensor will be placed at the AHU fan discharge (This sensor may be factory-installed as part of the AHU package and pre-factory tested).

d. A LONWORKS compatible protocol for control system architecture is preferred based on UFC 3-410-02 requirements. Any deviation from this must first be approved by the DPW Project Engineer via the equipment submittal process.

e. All software required for DDC system installation and operational capability will be included in the project.

f. Provide and install an outdoor air temperature sensor.

g. Each VAV unit will be provided with a terminal unit controller.

h. Each VAV terminal unit will incorporate a multi-point, averaging flow ring measuring the velocity of air at the unit primary air inlet.

i. Provide and install a temperature, humidity, and static pressure sensor(s) in the at the discharge side of the new AHU’s.

j. The new AHU’s will be provided with a DDC unit controller for connection to the overall Building Control Unit/cabinet.

k. Provide any required transformer(s) required for connection to the DDC AHU unit controller.

l. Provide a minimum of 4 humidity room sensors located in different locations throughout the facility wired back to the primary Building Control Units. Another option for the humidity sensors is to install a combination temperature/humidity sensor at the specific locations versus separate sensors.

m. Each newly installed VAV terminal unit will be provided with a wired zone sensor located within the zone served by the VAV. The zone sensor will provide the following features:

i. Temperature sensor allowing the occupant to choose a temperature setpoint that satisfies their personal preference.

ii. COMM module that provides local RJ22 connection port for maintenance diagnostics.

iii. Occupied mode override push buttons.

5. Plumbing:

2. The contractor shall Protect existing equipment while construction is taking place.

3. The contractor shall Demolish existing steam piping, condensate lines, steam traps, necessary, control valves, and other ancillary steam piping that is present in the existing conditions to support full replacement of the RTU, central station air handler.

4. The contractor shall Demolish refrigerant lines for the condensing units to be removed.

5. The contractor shall Provide and install new, thermally insulated, hot water supply and return piping to new boilers, heating coils, and circulator pumps. New Hot water supply and return piping will be marked with pre-printed, color-coded, with lettering indicating service, and showing flow direction. For piping less than NPS of 6”, provide full-band pipe markers, extending 360 degrees around the pipe, fastened by one of the following:

a. Snap-on application of pre-tensioned semi-rigid plastic pipe marker.

b. Adhesive lap joint in pipe marker overlap.

c. Laminated or bonded application of pipe marker to pipe or insulation.

d. Taped to pipe or insulation with color-coded plastic adhesive tape, not less than ¾” wide; full circle at both ends of pipe marker, tape lapped 1-1/2”.

6. The contractor shall Provide and install all check valves, fittings, pipe sealants, control valves, and drains on replacement mechanical system.

7. All new shut-off valves for water or natural gas applications will be “Full-Port” ball valves.

8. All new circuit balancing valves in HVAC Hot water piping (as required for applications ½” –

2” NPS) shall meet the following requirements:

a. Valves will be of a “Y” pattern, equal percentage globe style and perform the functions of precise flow measurement and balancing with positive drip-tight shut-off.

b. Valves will be rated for the operating temperature of the hot water.

c. Valves will provide multi-turn, 360-degree adjustment with micrometer type indicators located on the valve handwheel.

d. Valves will be furnished with precision machined venturi built into the valve body to provide highly accurate flow measurement and balancing. The venturi shall have two, ¼” threaded brass metering ports with check valves and gasketed caps located on the inlet side of the valve. Valves shall be furnished with flow smoothing fins downstream of the valve seat and integral to the forged valve body to make the flow laminar. The valve body, stem, and plug shall be brass. The handwheel shall be high-strength resin.

9. The contractor shall Provide and install new gas lines and their associated valves from the gas meter to the new boilers.

10. For water piping that is exposed to the ambient conditions, The contractor shall provide and install additional stainless steel pipe insulation jacketing to protect from insulation degradation and damage.

11. The contractor shall Provide abd install new refrigerant piping to DX condensers. Provide thermal protection and pipe jackets to protect refrigerant lines from mechanical damage, corrosion, and thermal efficiency loss due to exposure to the ambient conditions of the refrigerant lines.

6. Fire Protection and Alarm:

Local fire determination considered the project intent to be an alteration level 2 per international existing building code (IEBC).

3. The contractor shall Provide and install the minimum fire protection modifications necessary to support the HVAC replacement. Modifications include but are not limited to, rezoning of detection of notification, providing new fire dampers in mechanical equipment, providing fire separation between mechanical spaces where equipment will be places, and providing new fire panels.

4. The contractor shall Provide and install all appropriate fire stopping for penetrations through walls.

7. Electrical/Lighting/Communication/Security:

3. The contractor shall Demolish all electrical switches, controls, relays, circuits, and other ancillary equipment necessary to support the replacement HVAC system.

4. The contractor shall Provide and install all controllers, wiring, conduit, switches, surge protection, and electrical panels needed to support the replacement HVAC system.

5. The contractor shall reuse existing panels where feasible.

8. Utilities Privatization contract coordination and payment: contractor shall provide all required load letters and design documents and pay for (3rd party payment) for electrical service, water and wastewater services, and natural gas service to Dominion Energy (DE), American Water (AW) and Washington Gas (WG), respectively, as applicable.

9. Communication, Security, and System furniture

a. Support work only, these are NEC and user contracts: provide empty conduits and junction boxes with pull wires for communication and security system. Provide electrical circuits (conduits, wirings, junction boxes, circuit breakers, panelboard and connections) for system furniture, as applicable.

10. Environmental requirements:

Per Executive Order 13834, May 2018 as well as DoD Strategic Sustainability Plan, contractors are mandated to recycle at least 60% of construction and demolition(C&D) debris. Diversion, disposal amount and disposal site information must be reported to the Ft Belvoir Directorate of Public Works (DPW) Environmental and Natural Resources Division (ENRD) Attn: Vijay Ivatury vijay.m.ivatury.civ@mail.mil, 703-806-0061, in appropriate format that display the project description, date ticket number, type of material, tonnage and disposal site.

If any work is to be performed that would result in land disturbance, the guidelines outlined in the referenced “Fort Belvoir MS4 Program Bulleting #1” shall be followed for design, submittals, and attaining approval from DPW and possibly VADEQ depending on how much land disturbance is expected. If no work will result in land disturbance, the guidelines outlined in the referenced “Fort Belvoir ESC Technical Bulletin #4” shall be followed to ensure that no illicit discharges occur

If additional asbestos within the building is suspected by the contractor in addition to what has been mailto:vijay.m.ivatury.civ@mail.mil identified by the government, contractor is to have a professional licensed asbestos firm test the building and provide a report to the government on the findings. Provide all certifications and licenses.

If a project has 10,000 sq ft or greater of land disturbance, the project will need to be reviewed and approved by VADEQ. A minimum of 60 days will need to be scheduled for this review

11. Other specific requirements: Interior Hardware:

a. Provide locksets with 7-pin small format interchangeable core with keyway type A. Locksets and latch sets must conform to ANSI A156.2, series 4000, Grade 2 and be UL Listed. Locksets and cores to be of the same manufacturer to maintain complete lockset warranty. Permanent core face must be the same finish as the lockset finish.

b. Interior Doors: Install lever handles and construction cores. Provide Ft Belvoir Lock Smith a core key, permanent cores, 4 door keys and 2 master keys. Warrantee shall be a minimum of 10 years.

c. Exterior Hardware: Provide hardware as required for access and egress. Provide Ft Belvoir Lock Smith with permanent cores, a core key, 4 keys per door, 2 master keys and permanent cores. The master key shall not be the same master as the interior doors. Warrantee shall be a minimum of 10 years.

d. Mechanical Rooms: Ft Belvoir standard for exterior application. Permanent keys and cores shall be stamped with the applicable key mark for identification. Permanent keys will also be stamped “U.S. Gov.-Do Not Duplicate"

e. Telecommunication Rooms: Ft Belvoir Standard for exterior application.

f. Electrical Rooms: Ft Belvoir Standard for exterior application.

Deliver permanent cores, core keys, keys and master keys to:

Aleut Attn: Bruce Best 9460 Jackson Loop, Building 1420 Ft. Belvoir, VA 22060

B. DESIGN REQUIREMENTS:

1. All works shall meet or exceed Army Regulations, Unified Facility Criteria (UFCs), International Building Code (IBC), State and local codes, industry standards and the attached Sustainable Design Elements. Contractor shall comply with all applicable codes for DoD facilities as stated in UFC 1-200-01, General Building Requirements. All UFCs are available online at www.wbdg.org

This project will comply with ABA Accessibility Standards for DoD Facilities at http://access-board.gov/ada-aba/aba-standards-dod.cfm http://www.wbdg.org/ http://access-board.gov/ada-aba/aba-standards-dod.cfm http://access-board.gov/ada-aba/aba-standards-dod.cfm

2. Designers of Record (DOR) Professional Registered members of the Contractor’s Design-Build team that check, approve, sign, date, and certify, prior to submitting the deliverables to the Government, that the D-B design submittals comply with the contract requirements. There should be a designer of record for each area of work that requires submittal approval

a. The DOR's stamp, sign, and date each design drawing and other design deliverables under their responsible discipline at each design submittal stage. The DOR(s) are responsible for maintaining the integrity of the design and for compliance with the contract requirements through construction and documentation of the as-built condition by coordination, review and approval of extensions of design, material, equipment and other construction submittals, review and approval or disapproval of requested deviations to the accepted design or to the contract, coordination with the Government of the above activities, and by performing other typical professional design responsibilities.

b. After the contract award, the D-B contractor is fully responsible for his/her own design and construction, quality, full compliance with the RFP and his/her accepted proposal, and is liable for its faults.

c. The Government will not place itself in an approval position unless there are critical designs such as energy feeds, heating, ventilation and air-conditioning (HVAC), energy budget limitations, utility monitoring and control systems(UMCS) preparation, electronic security systems which the Government wants to share the risk in design with the D-B contractor.

3. CONTRACTOR SUBMITTAL PROCEDURES

The purpose of this regulation is to establish systematic procedures for managing contractor submittals so that contractors and the government may effectively schedule, control and process submittals required by the contract and regulate the timely flow of materials incorporated into the construction

a. D-B contract submittals are classified as follows:

b. Designer of Record Approved (DA) Submittals

c. Conformance Review (CR) Submittals

d. Government Approved (GA) Submittals

e. Designer of Record Approval and Conformance Review (DA/CR) Submittals

f. Designer of Record and Government Approved (DA/GA) Submittals

g. For Information Only (FIO) Submittals

Government review will not duplicate the Designer of Record responsibilities, and accordingly will not include reviews such as checking all design calculations.

4. At minimum, the contractor shall comply with the Whole Building Design Guide (WBDG) Division 1-General Requirements and Unified Facilities Guide Specifications (UFGS) to include but not limited to:

UFGS-01 11 00 Summary of Work

UFGS-01 20 00.00 20 Price and Payment Procedures UFGS-01 30 00 Administrative Requirements UFGS-01 32 01.00 10 Project Schedule UFGS-01 33 00 Submittal Procedures UFGS-01 33 16.00 Design Data (Design after Award) UFGS-01 35 26 Governmental Safety Requirements for APP (Accident Prevention Plan) review checklist (http://www.belvoir.army.mil/safety/construction.asp) UFGS-01 45 00.10 20 Quality Control for Minor Construction Other quality specs UFGS-01 57 19 Temporary Environmental Controls Recycled recovered material UFGS-01 74 19 Construction and Demolition Waste Management UFGS-01 78 00 Closeout Submittals [UFGS-01 91 00.15 Total Building Commissioning] (not typically in sow)

*The above are the minimum UFGS requirements, they are the responsibility of the contractor and the Designer of Record (DOR) to provide edited and relevant specifications for government review. The DOR shall evaluate the UFGS and provide the necessary edited specifications to meet project intent.

*In addition to the specifications listed above, the design and construction must be in accordance with the latest revision/edition of the reference codes and standards. The term “latest revision/edition” is defined as the version adopted as of the project award date.

*For any discrepancies between various Government and non-Government standards and codes listed above, the most stringent shall govern.

5. DESIGN REVIEW SUBMISSION FORMAT

Note: All specifications to be submitted to the government shall be provided in [Master Spec] industry format.

To include at a minimum the applicable submittals from Part 2 of UFGS 01 33 16.00 10 Design After Award

a. The contractor shall submit to the Government two (2) Arch D size (24”x36”), two (2) Arch B size (11”x17”) paper copies and four (4) CDs containing electronic files of 35% design documents to include preliminary design drawings (in PDF file format), outline specifications, preliminary cost estimate, design analysis and alternatives.

b. The contractor shall submit to the Government two (2) Arch D size (24”x36”), two (2)

Arch B size (11”x17”) paper copies and four (4) CDs containing electronic files of 65% design documents to include design drawings (in PDF file format), edited specifications, design analysis & calculations and cost estimates. The contractor shall also provide responses to the Government’s 35% design comments.

c. The contractor shall submit to the Government two (2) Arch D size (24”x36”), two (2)

Arch B size (11”x17”) paper copies of 100% design documents to include construction drawings and specifications, design analysis & calculations and cost estimates. The contractor shall also provide these 100% design documents in electronics format (CD-

ROM). Stamped/Sealed drawings shall be in CAD (AutoCAD) and in PDF. The contractor shall keep one set of the Issue for Construction (IFC) drawings and specification available at the construction site at all times. The contractor shall also provide responses to the Government’s 65% design comments.

d. The Government will review contractor design submissions to verify adherence to contract requirements. Design reviews by the Government are not to be interpreted as resulting in an approval of the Contractor's apparent progress toward meeting contract requirements but are intended to discover any information which can be brought to the Contractor's attention which might prevent costly errors and misdirection. The Contractor shall remain completely responsible for designing, constructing the project in full compliance with the requirements, and be singularly responsible to satisfy the terms of the resulting contract.

e. Specifications/Calculations: calculations shall be titled with each analysis clearly indicating subject/problem being studied, applied references, design analysis. The specifications shall be sufficiently detailed and edited to direct the construction contractor to execute the scope of work, outlined in this scope of work. The specifications and calculations shall be the latest version to completely encompass the scope of work and reflect the design of the project. Calculations shall be provided when any changes to floor layout result in relocation of any mechanical, electrical, plumbing, civil, and/or life safety and fire protection components.

6. REQUIRED SUBMITTALS

a. APP (Accident Prevention Plan)

b. BOD (Basis of Design)

c. Safety Plan

d. Environmental Plan

e. Laydown Area Plan

f. Construction Schedule (includes design/construction review period)

C. CONSTRUCTION REQUIREMENTS:

1. The contractor shall submit to the Government a digging permit request, conduct a pre-construction meeting with the Government and submit to the Government progress schedule and submittal register. The contractor shall not begin work until an approved digging permit is received.

2. The contractor shall coordinate and complete project in a timely manner to reduce disruption of daily activities. The contractor shall strategically place all required barricades in order to direct traffic around work areas to protect project areas.

3. To allow the government project manager sufficient time to inspect and accept all prep work, the contractor shall notify the government project manager, not later than five (5) working days prior to any concealment.

4. The contractor shall conduct a site meeting with the government project manager prior to any procurement and/or site work. The contractor shall also conduct weekly coordination meetings with the Government and user when works start.

5. The contractor shall conduct a schedule update meeting with the government project manager at a minimum once a month.

6. The contractor shall not commence any removal/demo of existing equipment, until all materials required to complete project are on hand and on site. The contractor shall ensure all materials with long lead times are ordered in a timely manner.

7. Any changes alterations and/or adjustments to the statement of work and/or the drawings will be approved by the government project manager prior to proceeding. If such alterations/adjustments require modification of any permits, the contractor shall not begin work on the alterations/changes until the modified permits are received.

8. The contractor shall verify the existing site conditions and the existing site dimensions prior to bid submittal.

9. The project site shall be clean and orderly at all times.

10. The contractor is responsible for identifying all latent conditions and shall contact the government project manager to verify latent conditions prior to continuation of work.

11. The contractor is responsible for all required dust protection; protection of existing areas surrounding the project areas and the matching of existing finishes as applicable.

12. The contractor shall develop and provide to the government project manager a proposed work schedule and notify him/her prior to any site work.

13. If required, the contractor shall be responsible for utility connections up to five feet outside of the building. Utilities to include but not limited to water, sanitary, sprinkler, gas, and electric.

D. OTHER REQUIREMENTS:

1. The performance period for this contract is 730 calendar days. The contractor shall complete the design within 215 calendar days after Partial Notice to Proceed (PNTP) issued. Full Notice to Proceed (FNTP) will be issued 14 calendar days after Issued For Construction (IFC) drawings are accepted.

a. 35% design: 45 calendar days after PNTP; allow 21 calendar days for Government’s comments; allow 7 calendar days for Designer to review and respond to Government’s comments, a meeting is required at the end of this 7 days.

b. 65% design: 30 calendar days after receipt of Contractors comment responses for 35% design; allow 21 calendar days for Government’s comments; allow 7 calendar days for Designer to review and respond to Government’s comments, a meeting is required at the end of this 7 days.

c. 100% design: 21 calendar days after receipt of Contractors comment responses for 65% design; allow 21 calendar days for Government’s comments; allow 7 calendar days for Designer to review and respond to Government’s comments, a meeting is required at the end of this 7 days.

d. Issue for Construction (IFC) Submission / Final Design: [14] calendar days after receipt of the 100% design; allow [7] calendar days for Government to accept this Final Design.

e. Government shall respond to RFI request within 10 to 14 days. Government shall respond to submittal review within 10 to 14 days. Government to sign transmittal/RFI sheet indicating if it is accepted, accepted with notes, or rejected.

2. Phasing Requirements/Restrictions/Temporary Services:

[The contractor will be required to phase-in all related work requirements of the project as the user will continue occupying the building throughout. This will include a three day notice to the user in order to arrange relocation intent.]

[The contractor is required to submit a phasing schedule to the government project manager before construction.]

3. QUALIFICATIONS ACCEPTANCE The contractor shall be responsible to provide qualified personnel that meet project requirements and are acceptable to the Government. Failure to do so may be deemed sufficient reason by the Government to terminate work as provided in the Termination for Default clause of the contract.

4. Preproposal Site Visit: a pre-proposal site visit can be arranged with the project manager. The site visit provides an opportunity to discuss and clarify this Request for Proposal (RFP). Nothing said or represented during the site visit shall be deemed to modify RFP requirements unless followed by a written amendment. The Offeror is requested to submit questions relative to the RFP after the site visit through the RFI process. Any government provided building drawings are provided for reference only, the contractor still has the responsibility to verify all site conditions.

It is the contractor’s responsibility to verify load-bearing and non-loading walls if any demolition of walls are included in the scope of this project. Contractor to provide a signed engineering assessment and drawings stamped by a licensed structural Professional Engineer (PE) to the government for review.

5. Submit Pricing in CSI format with breakdown by materials, labor, and equipment, G&A/OH, profit and bonds, and quantities (do not submit lump sum amounts). Provide subcontractor's pricing breakdown in CSI format with breakdowns also. If the proposal is not in the requested format, it will delay the completion of this requirement. The contractor shall provide a narrative describing how the work will be performed in response to the solicitation. The contractor shall also identify key personnel and provide an organizational chart.

6. CLOSEOUT SUBMITTAL REQUIREMENTS

a. Provide all testing and training required to complete the contract. HVAC TAB work should be done by independent testing company and submit to Government for approval. Training should be provided to building manager, maintenance personnel, and DPW personnel as required.

b. Complete start-up testing of systems and equipment/components as recommended by the manufacturers.

c. Manuals: The contractor shall provide manuals/documentation reflecting constructed building features/systems, including specifications, shop drawings, design calculations, and operation/maintenance requirements.

d. Operation and Maintenance Manual: The contractor shall prepare three (3) detailed Operation and Maintenance Manuals to assure satisfactory operations and to provide maintenance per manufacturer’s recommendations. In addition to operating sequences of start-up and shutdown, all models of operation shall be described, including emergency/safety shut-offs, efficiency or energy conservation adjustments, noise/vibrations adjustments, control calibration procedures, etc.

e. Warranties: The design/build contractor shall provide the COR a current and complete list of all warranted items and equipment responsibilities, specific warranties and guarantees, final certifications, and similar documents at the time of acceptance/substantial completions.

f. As-Built Drawings: the contractor shall provide “As-Builts Drawings”, [specifications] and documents based upon actual site installation, as should be reflected within latest record drawings/documents. The contractor shall submit to the Government four (4) Arch D size (24”x36”), four (4) Arch B size (11”x17”) paper copies and four (4) CDs containing electronic files of project closeout drawings (in PDF file format), specifications, and other applicable documents.

7. AT/OPSEC REQUIREMENTS

a. Clearance of personnel: It is the A/E and/or contractor’s responsibility to obtain security clearances for employees working in a Federal Installation. The government is not responsible for work delays or additional costs associated with the A/E’s and/or contractor’s failure to obtain clearances for their employees.

b. AT Level I training. This standard language is for contractor employees with an area of performance within an Army controlled installation, facility or area:

All contractor employees, to include subcontractor employees, requiring access Army installations, facilities and controlled access areas shall complete AT Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer, if a COR is not assigned, within 30 calendar days after completion of training by all employees and subcontractor personnel. AT level I awareness training is available at the following website: http://jko.jten.mil

c. iWATCH Training: This standard language is for contractor employees with an area of performance within an Army controlled installation, facility or area: The contractor and all associated sub-contractors shall brief all employees on the local iWATCH program (training standards provided by the requiring activity ATO). This local developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed within 30 calendar days of contract award and within YY calendar days of new employees commencing performance with the results reported to the COR NLT XX calendar days after contract award.

For contracts that require a formal OPSEC program: The contractor shall develop an OPSEC Standing Operating Procedure (SOP)/Plan within 90 calendar days of contract award, to be reviewed and approved by the responsible Government OPSEC officer. This plan will include a process to identify critical information, where it is located, who is responsible for it, how to protect it and why it needs to be protected. The contractor shall implement OPSEC measures as ordered by the commander. In addition, the contractor shall have an identified certified Level II OPSEC coordinator per AR 530-1.

d. For contracts that require OPSEC Training:Per AR 530-1 Operations Security, the contractor employees must complete Level I OPSEC Awareness training. New employees must be trained within 30 calendar days of their reporting for duty and annually thereafter. Level I OPSEC training is available at the following website:

http://cdse.edu/catalog/elearning/GS130.html (Duration: 45 minutes).

8. REAL PROPERTY REQUIREMENT

DD FORM 1354 TRANSFER AND ACCEPTANCE OF MILITARY REAL PROPERTY

Contractor shall provide pertinent cost, unit of measurement, and description data regarding construction, repairs and or alterations to Real Property Facilities to update DD Form 1354. For specific information requirements, the contractor shall coordinate with the Project Manager and reference the Unified Facilities Criteria (UFC) Criteria or Transfer and Acceptance of Military Real Property, UFC 1-300-08, 16 April 2004 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-1-300-08. The UFC specifies frequency and how to complete the DD Form 1354. This document should be consulted in executing responsibilities. Frequency of submission is as follows:

a. Draft DD Form 1354 at 30% Design

b. Interim DD Form 1354 and update to Draft at Completion of Design

c. Interim DD Form 1354 and update to Draft at 90 % Construction Completion

d. Red-Zone Inspection: Government shall provide 1354 documentation to the contractor.

Contractor shall submit final 1354 at 100% construction completion. The DD Form 1354 documentation shall be submitted electronically to the Project Manager for review. This data shall be provided prior to submission of final request for payment.

e. Final payment shall not be approved until all necessary data for DD 1354 is received and approved.

9. Real ID ACT Requirements

a. To access the installation of Fort Belvoir requires that driver’s license and state identification cards by compliant with the REAL ID Act. Effective October 11, 2018, individuals with driver’s license or state identification cards from states listed below will need a secondary ID to receive a pass to access Fort Belvoir. If they do not have a secondary form of ID they’ll be denied access or they’ll have to be accompanied by a Trusted Traveler. Attachment B of this document includes acceptable secondary IDs. If they have an ENHANCED driver’s license, a secondary ID is not required.

b. For more information on extensions or to see if your driver’s license or state identification card is compliant with the REAL ID ACT please view this link, https://www.dhs.gov/real-id#. Scroll down to the US Map and click on your state.

c. Listed below are states that will require a secondary ID effective October 11, 2018.

Extensions may occur so please view the link above for updates

Alaska Minnesota Pennsylvania

American Samoa Missouri Puerto Rico

California Montana Rhode Island

Guam New Hampshire U.S. Virgin Island

Illinois New Jersey Virginia

Kentucky Northern Mariana Island Washington State

Maine Oklahoma

Massachusetts Oregon

E. ATTACHMENTS/DRAWINGS/SKETCHES:

Attachment B: REAL ID ACT Secondary Forms of Identification

*** END ***