Attch J-4_ New Construction Schedule.pdf
PDF 111 KB Posted
- Attached to
- Undersea Warfare Combat Systems Product Support
- Solicitation number
- N0002421R5231
About this file
This document provides details on an upcoming Undersea Warfare Combat Systems Product Support Industry Day being held by the Department of the Navy Naval Sea Systems Command. The Industry Day will include a program briefing on the SQQ-89 program and anticipated requirements in solicitation N0002421R5231. Attendees will have the opportunity to participate in one-on-one sessions with the Government. Interested firms must register no later than July 21, 2021 and provide their own secure teleconference line if attending virtually. The Industry Day is scheduled for July 28, 2021 and will include a morning program briefing, mid-day break, and afternoon one-on-one sessions. Firms can submit questions in advance of the event. This notice provides relevant information for firms to consider regarding the SQQ-89 program and upcoming procurement but is not itself a solicitation.
View the file
Other files
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Ship # New Construction YardLAY KEELOWLD Duration (days)
1 PASCAGOULA 10/31/2022 10/1/2026 1,431 1
2 PASCAGOULA 10/1/2021 2/28/2022 150 1
3 BATH 10/1/2021 4/30/2022 211 1
4 PASCAGOULA 10/1/2021 10/30/2022 394 1
5 BATH 10/1/2021 1/31/2023 487 1
6 BATH 10/1/2021 9/1/2023 700 1
7 BATH 10/1/2021 2/1/2024 853 1
8 PASCAGOULA 10/1/2021 7/1/2024 1,004 1
9 BATH 9/22/2024 2/1/2028 1,227 1
10 BATH 5/21/2023 10/1/2026 1,229 1
11 PASCAGOULA 10/19/2025 3/1/2029 1,229 1
12 PASCAGOULA 4/20/2025 9/1/2028 1,230 1
13 BATH 2/18/2024 8/1/2027 1,260 1
14 BATH 8/4/2025 7/1/2029 1,427 1
15 BATH 10/1/2021 9/1/2025 1,431 1
16 PASCAGOULA 1/31/2022 1/1/2026 1,431 1
17 PASCAGOULA 2/12/2024 2/1/2028 1,450 1
18 PASCAGOULA 7/10/2023 7/1/2027 1,452 1
19 PASCAGOULA 12/9/2024 12/1/2028 1,453 1
20 BATH 12/9/2024 12/1/2028 1,453 1
Attachment 4 – New Construction Schedule, 08/07/2020, Page 1 of 1