Attch 5 AF 66 Submittal Register.pdf

PDF 655 KB Posted

Attached to
Repair Child Development Center, B227
Solicitation number
FA441822R0002
Issued by

About this file

This submittal register outlines 281 items required from a contractor to repair a child development center at Joint Base Charleston. The contractor must provide preconstruction submittals within 45 days of the notice to proceed, including an accident prevention plan, activity hazard analyses, and qualifications. Shop drawings, product data, samples, design data, test reports, and manufacturer's instructions are also required at various stages for items like sealants, access panels, backflow preventers, ductwork, and mechanical, electrical, and plumbing systems. Closeout submittals like as-built drawings, warranties, and operation and maintenance manuals are due prior to final inspection. The solicitation number for the project is FA441815D0006/FA441819FA053 to improve building systems and reduce temperatures at the 34,400 square foot facility constructed in 2010 at Air Force Mobility Command.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Repair Child Development Center, Bldg.227 at

Joint Base Charleston – Air Base North Charleston, South Carolina

Charleston County

AF Form 66

November 21, 2019 100% Design Submittal

Project Manager: Greg Jones, P.E.

gregj@adcengineering.com JBC Project No. DKFX 18-1073030 ADC Project No. 19070

11/21/2019

PROJECT NUMBER

DKFX 18-1073030

TO BE COMPLETED BY THE PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

DATE CONTRACTOR

NOTIFIED

APPROVED DISAPPROVED

01 11 00, Para 1.6.2, "Outage Requests"; G

01 11 00, Para 1.6.2, "Road

Closure Requests"; G

01 11 00, Para 1.6, "Work

Clearance"; G

01 14 00, Para 1.2.1.1, "List of Contact Personnel"; G

01 30 00, Para 1.2, "View

Location Map"; G

01 30 00, Para 1.3, "Progress and Completion

Pictures"; G

01 30 00, Para 1.6.2, "Resume for the proposed

Superintendent"; G

01 32 16.00 20, Para 1.2, "Qualifications"; G

01 32 16.00 20, Para 1.3, "Project Schedule"; G

01 32 16.00 20, Para 1.4.1, "Initial Contract Progress

Report (AF IMT 3065)"; G

01 32 16.00 20, Para 1.4.2, "Initial Contract Progress

Schedule (AF IMT 3064)"; G

01 32 16.00 20, Para 1.3.3, "Project Schedule Updates";

G

01 32 16.00 20, Para 1.4.1, "Monthly Contract Progress

Reports (AF IMT 3065)"; G

01 32 16.00 20, Para 1.4.2, "Monthly Contract Progress

Schedules (AF IMT 3064)";

G

01 33 00, Para 1.6, "Submittal Register"; G

PROJECT TITLE

Repair Child Development Center, B.227

SOLICITATION/CONTRACT NO. FA441815D0006 /

FA441819FA053

REMARKS

DATE RECEIVED

IN CONTRACTING

DATE

TO

CIVIL

ENGINEERING

RETURN

SUSPENSE

DATE

FOLLOW UP

SCHEDULE OF MATERIAL SUBMITTALS

S D

-1

O P

E R

A T

IO

N

M

A

IN

T E

N A

N C

E

D A

T A

S D

-0

M A

N U

F A

C T

U R

E R

'S F

IE

L

R

P O

R T

S

REQUIRED

SUBMISSION

DATE

CONTRACTOR

RESUBMITTAL

FINAL

APPROVAL

S D

-0

S A

M P

L E

S

S D

-0

D E

S

IG

N D

A T

A

S D

-0

C E

R T

IF

IC

A T

E S

S D

-0

M A

N U

F A

C T

U R

E

'S

IN

S

T R

U C

T

IO

N S

L

I

N

U

M

B

E

R

ITEM OR DESCRIPTION

OF ITEM, CONTRACT

REFERENCE, TYPE OF

SUBMITTAL

(Ref spec & para no.)

S D

-0

P R

E C

O N

S T

R U

C T

IO

B M

IT

T

A L

S

S D

-0

S H

O P

D R

A W

IN

G

S

S D

-0

P R

O D

U C

T D

A T

A

O T

H E

R S

A S

S P

E C

IF

IE

D

S D

-0

T E

S T

R E

P O

R T

S

S D

-1

C L

O S

E O

U T

S U

B M

IT

T

A L

S

AF Form 66

(a) As soon as possible but in no case later than 45 calendar days after NTP.

(b) Prior to Final Inspection.

(c) Prior to Use.

(d) As Required.

DKFX 18-1073030

TO BE COMPLETED BY THE PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

DATE CONTRACTOR

NOTIFIED

APPROVED DISAPPROVED

PROJECT TITLE

Repair Child Development Center, B.227

SOLICITATION/CONTRACT NO. FA441815D0006 /

FA441819FA053

REMARKS

DATE RECEIVED

IN CONTRACTING

DATE

TO

CIVIL

ENGINEERING

RETURN

SUSPENSE

DATE

FOLLOW UP

SCHEDULE OF MATERIAL SUBMITTALS

S D

-1

O P

E R

A T

IO

N

M

A

IN

T E

N A

N

T A

S D

-0

M A

N U

F A

C T

U R

E R

'S F

IE

P O

R T

S

REQUIRED

SUBMISSION

DATE

CONTRACTOR

RESUBMITTAL

FINAL

APPROVAL

S D

-0

S A

M P

L E

S

S D

-0

D E

S

IG

N D

A T

A

S D

-0

C E

R T

IF

IC

A T

E S

S D

-0

M A

N U

F A

C T

U R

E

T R

U C

T

IO

N S

L

I

M

B

E

R

ITEM OR DESCRIPTION

OF ITEM, CONTRACT

REFERENCE, TYPE OF

SUBMITTAL

(Ref spec & para no.)

S D

-0

P R

E C

O N

S T

R U

C T

B M

IT

T

A L

S

S D

-0

S H

O P

D R

A W

IN

G

S

S D

-0

P R

O D

U C

T D

A T

A

O T

H E

R S

A S

S P

E C

IF

IE

D

S D

-0

T E

S T

R E

P O

R T

S

S D

-1

C L

O S

E O

U T

S U

B M

IT

T

A L

S

01 35 26, Para 1.6, "Accident

Prevention Plan (APP)"; G

01 35 26, Para 1.7, "Activity

Hazard Analysis (AHA)"; G

01 35 26, Para 1.6.1.1, "Critical Lift Plan"; G

01 35 26, Para 1.5.1.3, "Crane Operators"; G

01 35 26, Para 1.11, "Notifications and Reports"

01 35 26, Para 1.11.2, "Accident Reports"; G

01 35 26, Para 1.11.3, "Crane Reports"

01 35 26, Para 1.8.1, "Confined Space Entry

Permit"

01 35 26, Para 1.8.1, "Hot

Work Permit"

01 35 26, Para 1.13, "License Certificates"

01 45 00, Para 1.6, "QC

Plan"; G

01 50 00, Para 1.3, "Construction Site Plan"; G

01 50 00, Para 3.4.1, "Traffic

Control Plan"; G

01 50 00, Para 1.4, "Backflow Preventers"

01 50 00, Para 2.2.5, "Backflow Preventer Tests"

01 50 00, Para 1.4.1, "Backflow Tester"

01 50 00, Para 1.4, "Backflow Preventers"

01 54 00.00 31, Para 1.5.2.1, "Affirmative Procurement

Reporting Form"; G

AF Form 66

(a) As soon as possible but in no case later than 45 calendar days after NTP.

(b) Prior to Final Inspection.

DKFX 18-1073030

TO BE COMPLETED BY THE PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

DATE CONTRACTOR

NOTIFIED

APPROVED DISAPPROVED

PROJECT TITLE

Repair Child Development Center, B.227

SOLICITATION/CONTRACT NO. FA441815D0006 /

FA441819FA053

REMARKS

DATE RECEIVED

IN CONTRACTING

DATE

TO

CIVIL

ENGINEERING

RETURN

SUSPENSE

DATE

FOLLOW UP

SCHEDULE OF MATERIAL SUBMITTALS

S D

-1

O P

E R

A T

IO

N

M

A

IN

T E

N A

N

T A

S D

-0

M A

N U

F A

C T

U R

E R

'S F

IE

P O

R T

S

REQUIRED

SUBMISSION

DATE

CONTRACTOR

RESUBMITTAL

FINAL

APPROVAL

S D

-0

S A

M P

L E

S

S D

-0

D E

S

IG

N D

A T

A

S D

-0

C E

R T

IF

IC

A T

E S

S D

-0

M A

N U

F A

C T

U R

E

T R

U C

T

IO

N S

L

I

M

B

E

R

ITEM OR DESCRIPTION

OF ITEM, CONTRACT

REFERENCE, TYPE OF

SUBMITTAL

(Ref spec & para no.)

S D

-0

P R

E C

O N

S T

R U

C T

B M

IT

T

A L

S

S D

-0

S H

O P

D R

A W

IN

G

S

S D

-0

P R

O D

U C

T D

A T

A

O T

H E

R S

A S

S P

E C

IF

IE

D

S D

-0

T E

S T

R E

P O

R T

S

S D

-1

C L

O S

E O

U T

S U

B M

IT

T

A L

S

01 57 19.00 31, Para 1.7.1, "Preconstruction Survey"; G

01 57 19.00 31, Para 1.8.3, "Regulatory Notifications"; G

01 57 19.00 31, Para 1.5, "Environmental Protection

Plan"; G

01 57 19.00 31, Para 1.6, "Dirt and Dust Control Plan";

G

01 57 19.00 31, Para 3.9.2, "Disposal Requirements"

01 57 19.00 31, Para 1.8.4, "Erosion and Sediment

Control Inspection Reports"

01 57 19.00 31, Para 3.4, "Erosion and Sediment

Control Inspection Reports"

01 57 19.00 31, Para 3.4, "Storm Water Inspection

Reports for General Permit"

01 57 19.00 31, Para 1.8.5, "Solid Waste Disposal

Report"; G

01 57 19.00 31, Para 1.8.2, "Contractor 40 CFR employee training records";

G

01 57 19.00 31, Para 3.4.2, "Storm Water Pollution

Prevention Plan compliance notebook"; G

01 57 19.00 31, Para 1.8, "Waste Determination

Documentation"

01 57 19.00 31, Para 3.7.2, "Waste Determination

Documentation"

AF Form 66

(a) As soon as possible but in no case later than 45 calendar days after NTP.

(b) Prior to Final Inspection.

DKFX 18-1073030

TO BE COMPLETED BY THE PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

DATE CONTRACTOR

NOTIFIED

APPROVED DISAPPROVED

PROJECT TITLE

Repair Child Development Center, B.227

SOLICITATION/CONTRACT NO. FA441815D0006 /

FA441819FA053

REMARKS

DATE RECEIVED

IN CONTRACTING

DATE

TO

CIVIL

ENGINEERING

RETURN

SUSPENSE

DATE

FOLLOW UP

SCHEDULE OF MATERIAL SUBMITTALS

S D

-1

O P

E R

A T

IO

N

M

A

IN

T E

N A

N

T A

S D

-0

M A

N U

F A

C T

U R

E R

'S F

IE

P O

R T

S

REQUIRED

SUBMISSION

DATE

CONTRACTOR

RESUBMITTAL

FINAL

APPROVAL

S D

-0

S A

M P

L E

S

S D

-0

D E

S

IG

N D

A T

A

S D

-0

C E

R T

IF

IC

A T

E S

S D

-0

M A

N U

F A

C T

U R

E

T R

U C

T

IO

N S

L

I

M

B

E

R

ITEM OR DESCRIPTION

OF ITEM, CONTRACT

REFERENCE, TYPE OF

SUBMITTAL

(Ref spec & para no.)

S D

-0

P R

E C

O N

S T

R U

C T

B M

IT

T

A L

S

S D

-0

S H

O P

D R

A W

IN

G

S

S D

-0

P R

O D

U C

T D

A T

A

O T

H E

R S

A S

S P

E C

IF

IE

D

S D

-0

T E

S T

R E

P O

R T

S

S D

-1

C L

O S

E O

U T

S U

B M

IT

T

A L

S

01 57 19.00 31, Para 1.8.1, "Disposal Documentation for

Hazardous and Regulated

Waste"

01 57 19.00 31, Para 1.8.2, "Contractor 40 CFR

Employee Training Records"

01 57 19.00 31, Para 1.7.2, "Solid Waste Disposal

Permit"

01 57 19.00 31, Para 1.8.5, "Solid Waste Disposal

Report"

01 57 19.00 31, Para 3.7.2, "Hazardous Waste/Debris

Management"

01 57 19.00 31, Para 1.8.3, "Regulatory Notifications"

01 57 20.00 31, Para , "Material Safety Data Sheets

(MSDS)"

01 57 20.00 31, Para 1.8, "Green Procurement"

01 57 20.00 31, Para 1.8, "Green Procurement"

01 57 20.00 31, Para 1.3, "Recycling Report"

01 57 20.00 31, Para 1.3, "Recycling Report"

01 74 19.00 31, Para 1.3.3, "Construction Waste

Management Plan"; G

01 78 00, Para 1.5.1, "Warranty Management

Plan"

01 78 00, Para 1.5.4, "Warranty Tags"

01 78 00, Para 1.4, "Spare

Parts Data"

AF Form 66

(a) As soon as possible but in no case later than 45 calendar days after NTP.

(b) Prior to Final Inspection.

DKFX 18-1073030

TO BE COMPLETED BY THE PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

DATE CONTRACTOR

NOTIFIED

APPROVED DISAPPROVED

PROJECT TITLE

Repair Child Development Center, B.227

SOLICITATION/CONTRACT NO. FA441815D0006 /

FA441819FA053

REMARKS

DATE RECEIVED

IN CONTRACTING

DATE

TO

CIVIL

ENGINEERING

RETURN

SUSPENSE

DATE

FOLLOW UP

SCHEDULE OF MATERIAL SUBMITTALS

S D

-1

O P

E R

A T

IO

N

M

A

IN

T E

N A

N

T A

S D

-0

M A

N U

F A

C T

U R

E R

'S F

IE

P O

R T

S

REQUIRED

SUBMISSION

DATE

CONTRACTOR

RESUBMITTAL

FINAL

APPROVAL

S D

-0

S A

M P

L E

S

S D

-0

D E

S

IG

N D

A T

A

S D

-0

C E

R T

IF

IC

A T

E S

S D

-0

M A

N U

F A

C T

U R

E

T R

U C

T

IO

N S

L

I

M

B

E

R

ITEM OR DESCRIPTION

OF ITEM, CONTRACT

REFERENCE, TYPE OF

SUBMITTAL

(Ref spec & para no.)

S D

-0

P R

E C

O N

S T

R U

C T

B M

IT

T

A L

S

S D

-0

S H

O P

D R

A W

IN

G

S

S D

-0

P R

O D

U C

T D

A T

A

O T

H E

R S

A S

S P

E C

IF

IE

D

S D

-0

T E

S T

R E

P O

R T

S

S D

-1

C L

O S

E O

U T

S U

B M

IT

T

A L

S

01 78 00, Para 3.9, "Preventative Maintenance"

01 78 00, Para 3.9, "Condition Monitoring"

01 78 00, Para 3.9, "Inspection"

01 78 00, Para 1.5.1, "Instructions"

01 78 00, Para 3.7, "Operation and Maintenance

Manuals"; G

01 78 00, Para 3.1, "As-Built

Drawings"; G

01 78 00, Para 3.3, "Record

Drawings"; G

01 78 00, Para 3.6, "As-Built

Record of Equipment and

Materials"

01 78 00, Para 3.4, "Final

Approved Shop Drawings"

01 78 00, Para 3.5, "Construction Contract

Specifications"

01 78 00, Para 3.1, "Interim

DD FORM 1354"; G

01 78 00, Para 3.1, "Checklist for DD FORM

1354"; G

02 41 00, Para 1.2.1, "Demolition Plan"; G

02 41 00, Para 1.1, "Existing

Conditions"

02 41 00, Para 1.6, "Notification"; G

02 41 00, Para 3.2.2, "Receipts"

78 05 40 00, Para 2.1, "Studs

05 40 00, Para 2.1, "Recycled Content of Steel

Products"

AF Form 66

(a) As soon as possible but in no case later than 45 calendar days after NTP.

(b) Prior to Final Inspection.

DKFX 18-1073030

TO BE COMPLETED BY THE PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

DATE CONTRACTOR

NOTIFIED

APPROVED DISAPPROVED

PROJECT TITLE

Repair Child Development Center, B.227

SOLICITATION/CONTRACT NO. FA441815D0006 /

FA441819FA053

REMARKS

DATE RECEIVED

IN CONTRACTING

DATE

TO

CIVIL

ENGINEERING

RETURN

SUSPENSE

DATE

FOLLOW UP

SCHEDULE OF MATERIAL SUBMITTALS

S D

-1

O P

E R

A T

IO

N

M

A

IN

T E

N A

N

T A

S D

-0

M A

N U

F A

C T

U R

E R

'S F

IE

P O

R T

S

REQUIRED

SUBMISSION

DATE

CONTRACTOR

RESUBMITTAL

FINAL

APPROVAL

S D

-0

S A

M P

L E

S

S D

-0

D E

S

IG

N D

A T

A

S D

-0

C E

R T

IF

IC

A T

E S

S D

-0

M A

N U

F A

C T

U R

E

T R

U C

T

IO

N S

L

I

M

B

E

R

ITEM OR DESCRIPTION

OF ITEM, CONTRACT

REFERENCE, TYPE OF

SUBMITTAL

(Ref spec & para no.)

S D

-0

P R

E C

O N

S T

R U

C T

B M

IT

T

A L

S

S D

-0

S H

O P

D R

A W

IN

G

S

S D

-0

P R

O D

U C

T D

A T

A

O T

H E

R S

A S

S P

E C

IF

IE

D

S D

-0

T E

S T

R E

P O

R T

S

S D

-1

C L

O S

E O

U T

S U

B M

IT

T

A L

S

05 40 00, Para 1.4, "Load-

Bearing Cold-Formed Metal

Framing"

06 10 00, Para 1.5, "Fire-retardant Treatment"

06 10 00, Para 1.4.2, "Structural-use and OSB

Panels"

06 10 00, Para 2.2, "Oriented

Strand Board"

07 92 00, Para 2.1, "Sealants"; G

07 92 00, Para 2.2, "Primers"; G

07 92 00, Para 2.3, "Bond

Breakers"; G

07 92 00, Para 2.4, "Backstops"; G

08 31 00, Para 1.3, "Access

Panels"; G

08 31 00, Para 1.3, "Access

Panels"; G

08 31 00, Para 1.3.2, "Hardware"; G

08 31 00, Para 2.1.6, "Accessories"; G

08 31 00, Para 2.4, "Finishes"; G

08 31 00, Para 1.3.1, "Fire-rating(s) of Assemblies"; G

09 22 00, Para 2.1, "Metal support systems"; G

09 29 00, Para 1.3, "Certifications"; G

09 29 00, Para 2.2.1, "Gypsum Board"; G

09 29 00, Para 2.2, "Asbestos Free Materials"; G

09 29 00, Para 1.3.1, "Indoor

Air Quality"; G

AF Form 66

(a) As soon as possible but in no case later than 45 calendar days after NTP.

(b) Prior to Final Inspection.

DKFX 18-1073030

TO BE COMPLETED BY THE PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

DATE CONTRACTOR

NOTIFIED

APPROVED DISAPPROVED

PROJECT TITLE

Repair Child Development Center, B.227

SOLICITATION/CONTRACT NO. FA441815D0006 /

FA441819FA053

REMARKS

DATE RECEIVED

IN CONTRACTING

DATE

TO

CIVIL

ENGINEERING

RETURN

SUSPENSE

DATE

FOLLOW UP

SCHEDULE OF MATERIAL SUBMITTALS

S D

-1

O P

E R

A T

IO

N

M

A

IN

T E

N A

N

T A

S D

-0

M A

N U

F A

C T

U R

E R

'S F

IE

P O

R T

S

REQUIRED

SUBMISSION

DATE

CONTRACTOR

RESUBMITTAL

FINAL

APPROVAL

S D

-0

S A

M P

L E

S

S D

-0

D E

S

IG

N D

A T

A

S D

-0

C E

R T

IF

IC

A T

E S

S D

-0

M A

N U

F A

C T

U R

E

T R

U C

T

IO

N S

L

I

M

B

E

R

ITEM OR DESCRIPTION

OF ITEM, CONTRACT

REFERENCE, TYPE OF

SUBMITTAL

(Ref spec & para no.)

S D

-0

P R

E C

O N

S T

R U

C T

B M

IT

T

A L

S

S D

-0

S H

O P

D R

A W

IN

G

S

S D

-0

P R

O D

U C

T D

A T

A

O T

H E

R S

A S

S P

E C

IF

IE

D

S D

-0

T E

S T

R E

P O

R T

S

S D

-1

C L

O S

E O

U T

S U

B M

IT

T

A L

S

09 29 00, Para 2.2.1, "Indoor

Air Quality for Gypsum

Board"; G

09 29 00, Para 2.2.2, "VOC

Content of Joint Compound";

G

09 51 00, Para 2.1, "Approved Detail Drawings";

G

09 51 00, Para 2.1, "Acoustical Ceiling Systems";

G

09 51 00, Para 2.2, "Acoustical Units"; G

09 51 00, Para 2.2.1.1, "Acoustical Ceiling Tiles"; G

09 90 00, Para 3.1, "Piping identification"

106 09 90 00, Para 3.1, "stencil" 5

09 90 00, Para 2.1, "Coating"; G

09 90 00, Para 2.1, "Manufacturer's Technical

Data Sheets"

09 90 00, Para 1.9, "Color";

G

09 90 00, Para 1.3, "Applicator's qualifications"

09 90 00, Para 1.4.1.2, "Qualification Testing"; G

09 90 00, Para 3.6.1, "Application instructions"

09 90 00, Para 3.6.2, "Mixing"

09 90 00, Para 1.7.2, "Manufacturer's Material

Safety Data Sheets"

09 90 00, Para 2.1, "Coatings:"; G

AF Form 66

(a) As soon as possible but in no case later than 45 calendar days after NTP.

(b) Prior to Final Inspection.

DKFX 18-1073030

TO BE COMPLETED BY THE PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

DATE CONTRACTOR

NOTIFIED

APPROVED DISAPPROVED

PROJECT TITLE

Repair Child Development Center, B.227

SOLICITATION/CONTRACT NO. FA441815D0006 /

FA441819FA053

REMARKS

DATE RECEIVED

IN CONTRACTING

DATE

TO

CIVIL

ENGINEERING

RETURN

SUSPENSE

DATE

FOLLOW UP

SCHEDULE OF MATERIAL SUBMITTALS

S D

-1

O P

E R

A T

IO

N

M

A

IN

T E

N A

N

T A

S D

-0

M A

N U

F A

C T

U R

E R

'S F

IE

P O

R T

S

REQUIRED

SUBMISSION

DATE

CONTRACTOR

RESUBMITTAL

FINAL

APPROVAL

S D

-0

S A

M P

L E

S

S D

-0

D E

S

IG

N D

A T

A

S D

-0

C E

R T

IF

IC

A T

E S

S D

-0

M A

N U

F A

C T

U R

E

T R

U C

T

IO

N S

L

I

M

B

E

R

ITEM OR DESCRIPTION

OF ITEM, CONTRACT

REFERENCE, TYPE OF

SUBMITTAL

(Ref spec & para no.)

S D

-0

P R

E C

O N

S T

R U

C T

B M

IT

T

A L

S

S D

-0

S H

O P

D R

A W

IN

G

S

S D

-0

P R

O D

U C

T D

A T

A

O T

H E

R S

A S

S P

E C

IF

IE

D

S D

-0

T E

S T

R E

P O

R T

S

S D

-1

C L

O S

E O

U T

S U

B M

IT

T

A L

S

22 00 00, Para 3.5.1.1, "Backflow Prevention

Assemblies"; G

117 22 00 00, Para 3.5, "Tests

22 00 00, Para 3.5.1.1, "Test of Backflow Prevention

Assemblies"; G

22 00 00, Para 1.3, "Materials and Equipment"

120 22 00 00, Para 2.1.1, "Bolts" 5

22 00 00, Para 3.5.1, "Plumbing System"; G

23 00 00, Para 2.8.1.1, "Metallic Flexible Duct"

23 00 00, Para 2.8.1.2, "Duct

Connectors"

124 23 05 15, Para 1.2, "Material

23 05 15, Para 1.2, "Record

Drawings"

23 05 15, Para 1.2, "Connection Diagrams"

23 05 15, Para 3.1, "Installation Drawings"; G

23 05 15, Para 2.1, "Pipe and Fittings"

23 05 15, Para 2.2, "Piping

Specialties"

130 23 05 15, Para 2.3, "Valves" 5

23 05 15, Para 2.4, "Miscellaneous Materials"

23 05 15, Para 2.5, "Supporting Elements"

23 05 15, Para 2.1, "Pipe and Fittings"

23 05 15, Para 2.2, "Piping

Specialties"

135 23 05 15, Para 2.3, "Valves" 5

23 05 15, Para 3.1, "Hydrostatic Tests"

AF Form 66

(a) As soon as possible but in no case later than 45 calendar days after NTP.

(b) Prior to Final Inspection.

DKFX 18-1073030

TO BE COMPLETED BY THE PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

DATE CONTRACTOR

NOTIFIED

APPROVED DISAPPROVED

PROJECT TITLE

Repair Child Development Center, B.227

SOLICITATION/CONTRACT NO. FA441815D0006 /

FA441819FA053

REMARKS

DATE RECEIVED

IN CONTRACTING

DATE

TO

CIVIL

ENGINEERING

RETURN

SUSPENSE

DATE

FOLLOW UP

SCHEDULE OF MATERIAL SUBMITTALS

S D

-1

O P

E R

A T

IO

N

M

A

IN

T E

N A

N

T A

S D

-0

M A

N U

F A

C T

U R

E R

'S F

IE

P O

R T

S

REQUIRED

SUBMISSION

DATE

CONTRACTOR

RESUBMITTAL

FINAL

APPROVAL

S D

-0

S A

M P

L E

S

S D

-0

D E

S

IG

N D

A T

A

S D

-0

C E

R T

IF

IC

A T

E S

S D

-0

M A

N U

F A

C T

U R

E

T R

U C

T

IO

N S

L

I

M

B

E

R

ITEM OR DESCRIPTION

OF ITEM, CONTRACT

REFERENCE, TYPE OF

SUBMITTAL

(Ref spec & para no.)

S D

-0

P R

E C

O N

S T

R U

C T

B M

IT

T

A L

S

S D

-0

S H

O P

D R

A W

IN

G

S

S D

-0

P R

O D

U C

T D

A T

A

O T

H E

R S

A S

S P

E C

IF

IE

D

S D

-0

T E

S T

R E

P O

R T

S

S D

-1

C L

O S

E O

U T

S U

B M

IT

T

A L

S

23 05 15, Para 3.1, "Air

Tests"

23 05 15, Para 3.1, "Valve-

Operating Tests"

23 05 15, Para 3.1, "Drainage Tests"

23 05 15, Para 3.1, "Pneumatic Tests"

23 05 15, Para 3.1, "Non-

Destructive Electric Tests"

23 05 15, Para 3.1, "System

Operation Tests"

23 05 15, Para 1.4.2, "Record of Satisfactory Field

Operation"

23 05 15, Para 1.4.3, "List of

Qualified Permanent Service

Organizations"

23 05 15, Para 1.2, "Records of Existing Conditions"

23 05 15, Para 3.1, "Surface

Resistance"

23 05 15, Para 3.1, "Shear and Tensile Strengths"

23 05 15, Para 3.1, "Temperature Ratings"

23 05 15, Para 3.1, "Bending

Tests"

23 05 15, Para 3.1, "Flattening Tests"

23 05 15, Para 3.1, "Transverse Guided Weld

Bend Tests"

23 05 15, Para 3.1, "Operation and Maintenance

Manuals"

23 05 48.00 40, Para 1.2, "Installation Drawings"

AF Form 66

(a) As soon as possible but in no case later than 45 calendar days after NTP.

(b) Prior to Final Inspection.

DKFX 18-1073030

TO BE COMPLETED BY THE PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

DATE CONTRACTOR

NOTIFIED

APPROVED DISAPPROVED

PROJECT TITLE

Repair Child Development Center, B.227

SOLICITATION/CONTRACT NO. FA441815D0006 /

FA441819FA053

REMARKS

DATE RECEIVED

IN CONTRACTING

DATE

TO

CIVIL

ENGINEERING

RETURN

SUSPENSE

DATE

FOLLOW UP

SCHEDULE OF MATERIAL SUBMITTALS

S D

-1

O P

E R

A T

IO

N

M

A

IN

T E

N A

N

T A

S D

-0

M A

N U

F A

C T

U R

E R

'S F

IE

P O

R T

S

REQUIRED

SUBMISSION

DATE

CONTRACTOR

RESUBMITTAL

FINAL

APPROVAL

S D

-0

S A

M P

L E

S

S D

-0

D E

S

IG

N D

A T

A

S D

-0

C E

R T

IF

IC

A T

E S

S D

-0

M A

N U

F A

C T

U R

E

T R

U C

T

IO

N S

L

I

M

B

E

R

ITEM OR DESCRIPTION

OF ITEM, CONTRACT

REFERENCE, TYPE OF

SUBMITTAL

(Ref spec & para no.)

S D

-0

P R

E C

O N

S T

R U

C T

B M

IT

T

A L

S

S D

-0

S H

O P

D R

A W

IN

G

S

S D

-0

P R

O D

U C

T D

A T

A

O T

H E

R S

A S

S P

E C

IF

IE

D

S D

-0

T E

S T

R E

P O

R T

S

S D

-1

C L

O S

E O

U T

S U

B M

IT

T

A L

S

23 05 48.00 40, Para 1.2, "Outline Drawings"

23 05 48.00 40, Para 1.2, "Equipment and

Performance Data"

23 05 48.00 40, Para 2.2.6, "Isolators"

23 05 48.00 40, Para 2.4, "Type of Isolator"

23 05 48.00 40, Para 2.4, "Type of Base"

23 05 48.00 40, Para 2.4, "Allowable Deflection"

23 05 48.00 40, Para 2.4, "Measured Deflection"

23 05 93, Para 1.3, "Records of Existing Conditions"; G

23 05 93, Para 1.3.3, "TAB

Schematic Drawings and

Report Forms"; G

23 05 93, Para 1.3, "Equipment and

Performance Data"; G

23 05 93, Para 1.5.1, "Independent TAB Agency and Personnel

Qualifications"; G

23 05 93, Para 3.3.2, "TAB

Pre-Field Engineering

Report"; G

23 07 00, Para 3.2.2.4, "MICA Plates"; G

23 07 00, Para 2.3, "Pipe

Insulation Systems"

23 07 00, Para 3.2, "Pipe

Insulation Systems"

23 07 00, Para 3.3, "Duct

Insulation Systems"

AF Form 66

(a) As soon as possible but in no case later than 45 calendar days after NTP.

(b) Prior to Final Inspection.

DKFX 18-1073030

TO BE COMPLETED BY THE PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

DATE CONTRACTOR

NOTIFIED

APPROVED DISAPPROVED

PROJECT TITLE

Repair Child Development Center, B.227

SOLICITATION/CONTRACT NO. FA441815D0006 /

FA441819FA053

REMARKS

DATE RECEIVED

IN CONTRACTING

DATE

TO

CIVIL

ENGINEERING

RETURN

SUSPENSE

DATE

FOLLOW UP

SCHEDULE OF MATERIAL SUBMITTALS

S D

-1

O P

E R

A T

IO

N

M

A

IN

T E

N A

N

T A

S D

-0

M A

N U

F A

C T

U R

E R

'S F

IE

P O

R T

S

REQUIRED

SUBMISSION

DATE

CONTRACTOR

RESUBMITTAL

FINAL

APPROVAL

S D

-0

S A

M P

L E

S

S D

-0

D E

S

IG

N D

A T

A

S D

-0

C E

R T

IF

IC

A T

E S

S D

-0

M A

N U

F A

C T

U R

E

T R

U C

T

IO

N S

L

I

M

B

E

R

ITEM OR DESCRIPTION

OF ITEM, CONTRACT

REFERENCE, TYPE OF

SUBMITTAL

(Ref spec & para no.)

S D

-0

P R

E C

O N

S T

R U

C T

B M

IT

T

A L

S

S D

-0

S H

O P

D R

A W

IN

G

S

S D

-0

P R

O D

U C

T D

A T

A

O T

H E

R S

A S

S P

E C

IF

IE

D

S D

-0

T E

S T

R E

P O

R T

S

S D

-1

C L

O S

E O

U T

S U

B M

IT

T

A L

S

23 07 00, Para 3.4, "Equipment Insulation

Systems"

23 07 00, Para 2.3, "Pipe

Insulation Systems"; G

23 07 00, Para 3.2, "Pipe

Insulation Systems"; G

23 07 00, Para 3.3, "Duct

Insulation Systems"; G

23 07 00, Para 3.4, "Equipment Insulation

Systems"; G

23 07 00, Para 2.2.1.3, "Thermal Insulation"; G

23 07 00, Para 3.1.1, "Display Samples"; G

23 07 00, Para 2.3, "Pipe

Insulation Systems"; G

23 07 00, Para 3.2, "Pipe

Insulation Systems"; G

23 07 00, Para 3.3, "Duct

Insulation Systems"; G

23 07 00, Para 3.4, "Equipment Insulation

Systems"; G

23 09 23.13 20, Para 1.4.1.1, "Control system drawings title sheet"; G

23 09 23.13 20, Para 1.4.1.2, "List of I/O Points"; G

23 09 23.13 20, Para 1.4.1.3, "Control System

Components List"; G

23 09 23.13 20, Para 1.4.1.4, "Control system schematics";

G

23 09 23.13 20, Para 1.4.1.5, "HVAC Equipment Electrical

Ladder diagrams"; G

AF Form 66

(a) As soon as possible but in no case later than 45 calendar days after NTP.

(b) Prior to Final Inspection.

DKFX 18-1073030

TO BE COMPLETED BY THE PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

DATE CONTRACTOR

NOTIFIED

APPROVED DISAPPROVED

PROJECT TITLE

Repair Child Development Center, B.227

SOLICITATION/CONTRACT NO. FA441815D0006 /

FA441819FA053

REMARKS

DATE RECEIVED

IN CONTRACTING

DATE

TO

CIVIL

ENGINEERING

RETURN

SUSPENSE

DATE

FOLLOW UP

SCHEDULE OF MATERIAL SUBMITTALS

S D

-1

O P

E R

A T

IO

N

M

A

IN

T E

N A

N

T A

S D

-0

M A

N U

F A

C T

U R

E R

'S F

IE

P O

R T

S

REQUIRED

SUBMISSION

DATE

CONTRACTOR

RESUBMITTAL

FINAL

APPROVAL

S D

-0

S A

M P

L E

S

S D

-0

D E

S

IG

N D

A T

A

S D

-0

C E

R T

IF

IC

A T

E S

S D

-0

M A

N U

F A

C T

U R

E

T R

U C

T

IO

N S

L

I

M

B

E

R

ITEM OR DESCRIPTION

OF ITEM, CONTRACT

REFERENCE, TYPE OF

SUBMITTAL

(Ref spec & para no.)

S D

-0

P R

E C

O N

S T

R U

C T

B M

IT

T

A L

S

S D

-0

S H

O P

D R

A W

IN

G

S

S D

-0

P R

O D

U C

T D

A T

A

O T

H E

R S

A S

S P

E C

IF

IE

D

S D

-0

T E

S T

R E

P O

R T

S

S D

-1

C L

O S

E O

U T

S U

B M

IT

T

A L

S

23 09 23.13 20, Para 1.4.1.6, "Component wiring diagrams"; G

23 09 23.13 20, Para 1.4.1.7, "Terminal strip diagrams"; G

23 09 23.13 20, Para 1.4.1.8, "BACnet communication architecture schematic"; G

23 09 23.13 20, Para 2.1.1, "Direct Digital Controllers"; G

23 09 23.13 20, Para

2.1.1.13, "BACnet

Gateways"; G

23 09 23.13 20, Para 2.1.3, "BACnet Protocol Analyzer";

G

23 09 23.13 20, Para 2.1.2, "DDC Software"; G

23 09 23.13 20, Para 2.2, "Sensors and Input

Hardware"; G

23 09 23.13 20, Para 2.2.6, "Air Flow Monitoring Station";

G

23 09 23.13 20, Para 2.3, "Output Hardware"; G

23 09 23.13 20, Para 2.4.2, "Surge and transient protection"; G

23 09 23.13 20, Para 2.6, "Indicators"; G

23 09 23.13 20, Para 2.5.1, "Duct smoke detectors"; G

23 09 23.13 20, Para 2.7, "Variable frequency (motor) drives"; G

AF Form 66

(a) As soon as possible but in no case later than 45 calendar days after NTP.

(b) Prior to Final Inspection.

DKFX 18-1073030

TO BE COMPLETED BY THE PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

DATE CONTRACTOR

NOTIFIED

APPROVED DISAPPROVED

PROJECT TITLE

Repair Child Development Center, B.227

SOLICITATION/CONTRACT NO. FA441815D0006 /

FA441819FA053

REMARKS

DATE RECEIVED

IN CONTRACTING

DATE

TO

CIVIL

ENGINEERING

RETURN

SUSPENSE

DATE

FOLLOW UP

SCHEDULE OF MATERIAL SUBMITTALS

S D

-1

O P

E R

A T

IO

N

M

A

IN

T E

N A

N

T A

S D

-0

M A

N U

F A

C T

U R

E R

'S F

IE

P O

R T

S

REQUIRED

SUBMISSION

DATE

CONTRACTOR

RESUBMITTAL

FINAL

APPROVAL

S D

-0

S A

M P

L E

S

S D

-0

D E

S

IG

N D

A T

A

S D

-0

C E

R T

IF

IC

A T

E S

S D

-0

M A

N U

F A

C T

U R

E

T R

U C

T

IO

N S

L

I

M

B

E

R

ITEM OR DESCRIPTION

OF ITEM, CONTRACT

REFERENCE, TYPE OF

SUBMITTAL

(Ref spec & para no.)

S D

-0

P R

E C

O N

S T

R U

C T

B M

IT

T

A L

S

S D

-0

S H

O P

D R

A W

IN

G

S

S D

-0

P R

O D

U C

T D

A T

A

O T

H E

R S

A S

S P

E C

IF

IE

D

S D

-0

T E

S T

R E

P O

R T

S

S D

-1

C L

O S

E O

U T

S U

B M

IT

T

A L

S

23 09 23.13 20, Para 3.4.2, "Performance Verification

Testing Plan"; G

23 09 23.13 20, Para 3.4.4, "Pre-Performance

Verification Testing

Checklist"; G

23 09 23.13 20, Para 3.4.11, "Performance Verification

Testing Report"; G

23 09 23.13 20, Para 1.6.6, "Contractor's Qualifications";

G

23 09 23.13 20, Para 3.4.1, "Pre-PVT Checklist"; G

23 09 23.13 20, Para 1.4, "BACnet Direct Digital

Control Systems"; G

23 09 23.13 20, Para 3.3, "Controls System Operators

Manuals"; G

23 09 23.13 20, Para 2.7.2, "VFD Service Manuals"; G

23 09 23.13 20, Para 3.5.1, "Training documentation"; G

23 21 23, Para 2.1.2, "System Coordination"; G

23 21 23, Para 2.2.2, "Instructions"; G

23 21 23, Para 2.2.5, "Equipment Data"; G

23 21 23, Para 3.5.2, "Training Period"; G

23 21 23, Para 2.8, "Factory

Tests"

23 21 23, Para 3.3, "Field

Quality Control"

AF Form 66

(a) As soon as possible but in no case later than 45 calendar days after NTP.

(b) Prior to Final Inspection.

DKFX 18-1073030

TO BE COMPLETED BY THE PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

DATE CONTRACTOR

NOTIFIED

APPROVED DISAPPROVED

PROJECT TITLE

Repair Child Development Center, B.227

SOLICITATION/CONTRACT NO. FA441815D0006 /

FA441819FA053

REMARKS

DATE RECEIVED

IN CONTRACTING

DATE

TO

CIVIL

ENGINEERING

RETURN

SUSPENSE

DATE

FOLLOW UP

SCHEDULE OF MATERIAL SUBMITTALS

S D

-1

O P

E R

A T

IO

N

M

A

IN

T E

N A

N

T A

S D

-0

M A

N U

F A

C T

U R

E R

'S F

IE

P O

R T

S

REQUIRED

SUBMISSION

DATE

CONTRACTOR

RESUBMITTAL

FINAL

APPROVAL

S D

-0

S A

M P

L E

S

S D

-0

D E

S

IG

N D

A T

A

S D

-0

C E

R T

IF

IC

A T

E S

S D

-0

M A

N U

F A

C T

U R

E

T R

U C

T

IO

N S

L

I

M

B

E

R

ITEM OR DESCRIPTION

OF ITEM, CONTRACT

REFERENCE, TYPE OF

SUBMITTAL

(Ref spec & para no.)

S D

-0

P R

E C

O N

S T

R U

C T

B M

IT

T

A L

S

S D

-0

S H

O P

D R

A W

IN

G

S

S D

-0

P R

O D

U C

T D

A T

A

O T

H E

R S

A S

S P

E C

IF

IE

D

S D

-0

T E

S T

R E

P O

R T

S

S D

-1

C L

O S

E O

U T

S U

B M

IT

T

A L

S

23 21 23, Para 1.3.1, "Manufacturer's

Representative"

23 21 23, Para 3.5.1, "Operation and Maintenance

Manuals"; G

23 21 23, Para 3.5.2, "Training"; G

23 23 00, Para 2.3, "Refrigerant Piping System";

G

23 23 00, Para 2.3, "Refrigerant Piping System"

23 23 00, Para 1.5.2, "Spare

Parts"

23 23 00, Para 1.3.1, "Qualifications"

23 23 00, Para 3.5, "Refrigerant Piping Tests"

23 23 00, Para 3.1, "Verification of Dimensions"

23 23 00, Para 3.5, "Refrigerant Piping Tests"

23 23 00, Para 2.1, "Service

Organization"

23 23 00, Para 1.5, "Maintenance"; G

23 23 00, Para 3.4, "Operation and Maintenance

Manuals"; G

23 23 00, Para 3.4, "Demonstrations"; G

23 65 00, Para 2.5, "Cooling

Towers"; G

23 65 00, Para 3.1, "Demonstrations"; G

23 65 00, Para 1.5.1, "Verification of Dimensions";

G

AF Form 66

(a) As soon as possible but in no case later than 45 calendar days after NTP.

(b) Prior to Final Inspection.

DKFX 18-1073030

TO BE COMPLETED BY THE PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

DATE CONTRACTOR

NOTIFIED

APPROVED DISAPPROVED

PROJECT TITLE

Repair Child Development Center, B.227

SOLICITATION/CONTRACT NO. FA441815D0006 /

FA441819FA053

REMARKS

DATE RECEIVED

IN CONTRACTING

DATE

TO

CIVIL

ENGINEERING

RETURN

SUSPENSE

DATE

FOLLOW UP

SCHEDULE OF MATERIAL SUBMITTALS

S D

-1

O P

E R

A T

IO

N

M

A

IN

T E

N A

N

T A

S D

-0

M A

N U

F A

C T

U R

E R

'S F

IE

P O

R T

S

REQUIRED

SUBMISSION

DATE

CONTRACTOR

RESUBMITTAL

FINAL

APPROVAL

S D

-0

S A

M P

L E

S

S D

-0

D E

S

IG

N D

A T

A

S D

-0

C E

R T

IF

IC

A T

E S

S D

-0

M A

N U

F A

C T

U R

E

T R

U C

T

IO

N S

L

I

M

B

E

R

ITEM OR DESCRIPTION

OF ITEM, CONTRACT

REFERENCE, TYPE OF

SUBMITTAL

(Ref spec & para no.)

S D

-0

P R

E C

O N

S T

R U

C T

B M

IT

T

A L

S

S D

-0

S H

O P

D R

A W

IN

G

S

S D

-0

P R

O D

U C

T D

A T

A

O T

H E

R S

A S

S P

E C

IF

IE

D

S D

-0

T E

S T

R E

P O

R T

S

S D

-1

C L

O S

E O

U T

S U

B M

IT

T

A L

S

23 65 00, Para 3.2, "Packaged Cooling Tower -

Installation Instructions"; G

23 65 00, Para 3.3.1, "Packaged Cooling Tower -

Field Acceptance Test Plan";

G

23 65 00, Para 3.4, "Packaged Cooling Tower -

Field Acceptance Test

Report"; G

23 65 00, Para 2.1, "Service

Organization"

23 65 00, Para 2.5.1.11, "Cooling Tower"

23 65 00, Para 3.2, "Packaged Cooling Tower -

Installation Instructions"

23 65 00, Para 3.1, "Operation and Maintenance

Manuals"

23 81 00, Para 3.7.1, "Spare

Parts"

23 81 00, Para 3.4, "Posted

Instructions"

23 81 00, Para 2.5.1, "Coil

Corrosion Protection"

23 81 00, Para 3.6, "System

Performance Tests"

23 81 00, Para 3.4, "Training"; G

23 81 00, Para 1.5, "Inventory"

23 81 00, Para 2.1, "Supplied Products"

23 81 00, Para 2.2, "Manufacturer's Standard

Catalog Data"

23 81 00, Para 3.5, "Refrigerant Tests

AF Form 66

(a) As soon as possible but in no case later than 45 calendar days after NTP.

(b) Prior to Final Inspection.

DKFX 18-1073030

TO BE COMPLETED BY THE PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

DATE CONTRACTOR

NOTIFIED

APPROVED DISAPPROVED

PROJECT TITLE

Repair Child Development Center, B.227

SOLICITATION/CONTRACT NO. FA441815D0006 /

FA441819FA053

REMARKS

DATE RECEIVED

IN CONTRACTING

DATE

TO

CIVIL

ENGINEERING

RETURN

SUSPENSE

DATE

FOLLOW UP

SCHEDULE OF MATERIAL SUBMITTALS

S D

-1

O P

E R

A T

IO

N

M

A

IN

T E

N A

N

T A

S D

-0

M A

N U

F A

C T

U R

E R

'S F

IE

P O

R T

S

REQUIRED

SUBMISSION

DATE

CONTRACTOR

RESUBMITTAL

FINAL

APPROVAL

S D

-0

S A

M P

L E

S

S D

-0

D E

S

IG

N D

A T

A

S D

-0

C E

R T

IF

IC

A T

E S

S D

-0

M A

N U

F A

C T

U R

E

T R

U C

T

IO

N S

L

I

M

B

E

R

ITEM OR DESCRIPTION

OF ITEM, CONTRACT

REFERENCE, TYPE OF

SUBMITTAL

(Ref spec & para no.)

S D

-0

P R

E C

O N

S T

R U

C T

B M

IT

T

A L

S

S D

-0

S H

O P

D R

A W

IN

G

S

S D

-0

P R

O D

U C

T D

A T

A

O T

H E

R S

A S

S P

E C

IF

IE

D

S D

-0

T E

S T

R E

P O

R T

S

S D

-1

C L

O S

E O

U T

S U

B M

IT

T

A L

S

23 81 00, Para 3.6, "System

Performance Tests"; G

23 81 00, Para 3.7.2, "Service Organizations"

23 81 00, Para 3.4, "Operation and Maintenance

Manuals"; G

26 20 00, Para 2.1, "Panelboards"; G

26 20 00, Para 2.16, "Wireways"; G

26 20 00, Para 3.1.5.1, "Marking strips"; G

26 20 00, Para 2.10.1, "Circuit breakers"; G

26 20 00, Para 2.9, "Switches"; G

26 20 00, Para 3.5.2, "600-volt wiring test"; G

26 20 00, Para 3.5.3, "Grounding system test"; G

26 51 00, Para 1.5.1, "Luminaire Drawings"; G

26 51 00, Para 1.5.2, "Occupancy/Vacancy Sensor

Coverage Layout"; G

26 51 00, Para 2.2, "Luminaires"; G

26 51 00, Para 2.4, "Light

Sources"; G

262 26 51 00, Para 2.3, "Drivers

26 51 00, Para 1.6.1, "LED

Luminaire Warranty"; G

26 51 00, Para 1.5.4, "Luminaire Design Data"; G

26 51 00, Para 2.5.1, "Exit

Signs"; G

26 51 00, Para 2.5.2, "LED

Emergency Drivers"; G

AF Form 66

(a) As soon as possible but in no case later than 45 calendar days after NTP.

(b) Prior to Final Inspection.

DKFX 18-1073030

TO BE COMPLETED BY THE PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

DATE CONTRACTOR

NOTIFIED

APPROVED DISAPPROVED

PROJECT TITLE

Repair Child Development Center, B.227

SOLICITATION/CONTRACT NO. FA441815D0006 /

FA441819FA053

REMARKS

DATE RECEIVED

IN CONTRACTING

DATE

TO

CIVIL

ENGINEERING

RETURN

SUSPENSE

DATE

FOLLOW UP

SCHEDULE OF MATERIAL SUBMITTALS

S D

-1

O P

E R

A T

IO

N

M

A

IN

T E

N A

N

T A

S D

-0

M A

N U

F A

C T

U R

E R

'S F

IE

P O

R T

S

REQUIRED

SUBMISSION

DATE

CONTRACTOR

RESUBMITTAL

FINAL

APPROVAL

S D

-0

S A

M P

L E

S

S D

-0

D E

S

IG

N D

A T

A

S D

-0

C E

R T

IF

IC

A T

E S

S D

-0

M A

N U

F A

C T

U R

E

T R

U C

T

IO

N S

L

I

M

B

E

R

ITEM OR DESCRIPTION

OF ITEM, CONTRACT

REFERENCE, TYPE OF

SUBMITTAL

(Ref spec & para no.)

S D

-0

P R

E C

O N

S T

R U

C T

B M

IT

T

A L

S

S D

-0

S H

O P

D R

A W

IN

G

S

S D

-0

P R

O D

U C

T D

A T

A

O T

H E

R S

A S

S P

E C

IF

IE

D

S D

-0

T E

S T

R E

P O

R T

S

S D

-1

C L

O S

E O

U T

S U

B M

IT

T

A L

S

26 51 00, Para 1.5.5, "LED

Luminaire - IES LM-79 Test

Report"; G

26 51 00, Para 1.5.6, "LED

Light Source - IES LM-80

Test Report"; G

26 51 00, Para 1.5.7, "LED

Light Source - IES TM-21

Test Report"; G

26 51 00, Para 1.5.8, "Occupancy/Vacancy Sensor

Verification Tests"; G

26 51 00, Para 1.5.11.3, "Energy Efficiency"; G

26 51 00, Para 1.6.1.1, "Luminaire Useful Life

Certificate"; G

26 51 00, Para 1.5.3, "LED

Driver and Dimming Switch

Compatibility Certificate"; G

32 31 13, Para 2.1, "Fence

Assembly"; G

32 31 13, Para 3.2.1.1, "Location of Gate

32 31 13, Para 2.1, "Gate

Assembly"; G

32 31 13, Para 2.2.14, "Gate

Hardware and Accessories";

G

32 31 13, Para Part 3, "Erection/Installation

Drawings"; G

32 31 13, Para 2.1, "Fence

Assembly"; G

32 31 13, Para 2.1, "Gate

Assembly"; G

32 31 13, Para 2.2.14, "Gate

Hardware and Accessories";

G

AF Form 66

(a) As soon as possible but in no case later than 45 calendar days after NTP.

(b) Prior to Final Inspection.

DKFX 18-1073030

TO BE COMPLETED BY THE PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

DATE CONTRACTOR

NOTIFIED

APPROVED DISAPPROVED

PROJECT TITLE

Repair Child Development Center, B.227

SOLICITATION/CONTRACT NO. FA441815D0006 /

FA441819FA053

REMARKS

DATE RECEIVED

IN CONTRACTING

DATE

TO

CIVIL

ENGINEERING

RETURN

SUSPENSE

DATE

FOLLOW UP

SCHEDULE OF MATERIAL SUBMITTALS

S D

-1

O P

E R

A T

IO

N

M

A

IN

T E

N A

N

T A

S D

-0

M A

N U

F A

C T

U R

E R

'S F

IE

P O

R T

S

REQUIRED

SUBMISSION

DATE

CONTRACTOR

RESUBMITTAL

FINAL

APPROVAL

S D

-0

S A

M P

L E

S

S D

-0

D E

S

IG

N D

A T

A

S D

-0

C E

R T

IF

IC

A T

E S

S D

-0

M A

N U

F A

C T

U R

E

T R

U C

T

IO

N S

L

I

M

B

E

R

ITEM OR DESCRIPTION

OF ITEM, CONTRACT

REFERENCE, TYPE OF

SUBMITTAL

(Ref spec & para no.)

S D

-0

P R

E C

O N

S T

R U

C T

B M

IT

T

A L

S

S D

-0

S H

O P

D R

A W

IN

G

S

S D

-0

P R

O D

U C

T D

A T

A

O T

H E

R S

A S

S P

E C

IF

IE

D

S D

-0

T E

S T

R E

P O

R T

S

S D

-1

C L

O S

E O

U T

S U

B M

IT

T

A L

S

32 31 13, Para 2.3.1, "Zinc

Coating"; G

32 31 13, Para 2.1, "PVC

Coating"; G

32 31 13, Para 2.2.1, "Fabric"; G

32 31 13, Para 2.2.9, "Stretcher Bars"; G

32 31 13, Para 2.3.3, "Concrete"; G

32 31 13, Para 1.3.1, "Certificates of Compliance"

32 31 13, Para 2.1, "Fence

Assembly"

32 31 13, Para 2.1, "Gate

Assembly"

32 31 13, Para 2.1, "Hardware Assembly"

32 31 13, Para 2.1, "Accessories"

32 31 13, Para 3.3, "Recycled Material Content"

AF Form 66

(a) As soon as possible but in no case later than 45 calendar days after NTP.

(b) Prior to Final Inspection.

File details come from the government source that posted it. Updated .