Attch 1 SON.pdf

PDF 117 KB Posted

Attached to
MacDill AFB Torque Machine Brand Name Or Equal
Solicitation number
FA481420TF166
Issued by

View the file

Other files

File Type Posted
Attch 2 Provisions and Clauses.pdf PDF
Combined Synopsis Soliciation.pdf PDF
Attch 3 52.212-5.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Need

Wheel Torqueing System

Vendor must supply a product that meets the following:

1.0 Solution to Torqueing System

The system must be a standard production model designed for aerospace wheel and tire assemblies.

The Torqueing System must be programed to meet shop requirements for torque values of KC- 135 Main (1850- 2880 in-lbs.) and Nose (970 in-lbs.) wheels.

1.1 Power Supply:

The power supply at building 44 will need to be able to meet the needs of the Torqueing System, 208-240 VAC, 1 PH, 60 HZ.

2.0 Included Parts:

Two each sockets will be needed for torqueing system that fits the main (20mm) and nose wheel (5/8 inch) nuts, ¾ in drive.

3.0 On-Site Service Startup:

The contractor shall uncrate and position Torque Machine. They will also provide equipment power-up and functional checks, bolt machinery to the floor, and troubleshoot any remaining issues. Contractor will be required to remove all package material

4.0Training and Warranty Requirements:

Contractor to provide on-sight maintenance and operators training, unlimited attendees.

Contractor to provide a Warranty for 1 (one) year for parts and labor.

5.0 . Place of Delivery

The product will be delivered to MacDill AFB Hangar 2

6.0 Points of Contacts

MSgt Kornia Simmons Comm: (813) 917-8901

TSgt Tyler Trible Comm: (813) 828-8881

File details come from the government source that posted it. Updated .