Attch 1 - Final SLICK ROCK CULVERTS Specs Third Site.pdf

PDF 2 MB Posted

Attached to
SLICK ROCK CULVERT REPLACEMENT Federal contract opportunity
Solicitation number
140L0621R0001
Issued by
Department of the Interior Bureau of Land Management National Office

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

U.S. BUREAU OF LAND MANAGEMENT

SLICK ROCK CULVERT BRIDGE

U.S. BLM – GILA DISTRICT

SAFFORD FIELD OFFICE

711 S. 14th AVENUE

SAFFORD, AZ 85546

Project Specifications

U.S. DEPARTMENT OF THE INTERIOR

BUREAU OF LAND MANAGEMENT

October 6, 2020

TABLE OF CONTENTS

SLICK ROCK CULVERT BRIDGE/HAEKEL ROAD CULVERTS

SPECIFICATIONS

DIVISION SECTION TITLE

DIVISION 01 – GENERAL REQUIREMENTS

011000 SUMMARY

013100 PROJECT MANAGEMENT AND COORDINATION

013200 CONSTRUCTION PROGRESS DOCUMENTATION

013300 SUBMITTAL PROCEDURES

014000 QUALITY REQUIREMENTS

017300 EXECUTION

017419 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

017700 CLOSEOUT PROCEDURES

DIVISION 02 – EXISTING CONDITIONS

024119 SELECTIVE DEMOLITION

DIVISION 03 – CONCRETE

032000 CONCRETE REINFORCING

033000 CAST-IN-PLACE CONCRETE

DIVISION 31 – EARTHWORK

311000 SITE CLEARING

312000 EARTH MOVING

312510 TEMPORARY EROSION CONTROL

313700 RIPRAP, BOULDERS, SOIL RIPRAP AND BEDDING

DIVISION 32 – EXTERIOR IMPROVEMENTS

321126 CRUSHED AGGREGATE BASE COURSE

321216 ASPHALT PAVING

SECTION 602 – CULVERTS AND DRAINS

SECTION 707 – METAL PIPE

SECTION 634 – PERMANENT PAVEMENT MARKINGS

SECTION 635 – TEMPORARY TRAFFIC CONTROL

TABLE OF CONTENTS 000000 - 1

VICINITY MAP

LOCATION MAP

SECTION 011000 - SUMMARY

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary

Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Project information.

B. Project Summary – The project consists of the replacement of culvert pipes at (3) locations on

Haekel Road in Safford, AZ

First site: Slick Rock culvert bridge. Replacement of existing (5) pipes with (5) new 57” x 38” galvanized steel pipe-arch culverts. Existing culverts are approximately 50.5’ long. Culverts are gauge 12 steel. Culvert corrugations are 2-2/3” x ½” Roadway is 20’ wide. Bottom of wash to top of road is approximately 5’. Rip-Rap will be placed around culvert pipes on both ends and

4’ apron in front and grouted to prevent erosion. Cover for culverts will be a minimum of 12”.

4” asphalt road depth and flush with existing road width will be paved over the minimum 8” aggregate base. Lat/Long: 32.72518, -109.53176. Detour road will need to be placed around pipes to allow for traffic to flow around project site. Location of detour road will be determined with contractor and government officials. Cast in place cut-off walls. 4 feet deep on upstream side. 6 feet deep on downstream side. 6” base aggregate placed and compacted under cut off walls.

Second Site: (2) 24” Round x 40’ length pipes need replaced with (2) new 49” x 33” x 40’ galvanized steel pipe-arch culverts. Roadway is 20’ wide. Bottom of wash to top of road is approximately 4’. Rip-Rap will be placed around culvert pipes on both ends and 4’ apron in front and grouted to prevent erosion. Cover for culverts will be a minimum of 12”. 4” asphalt road depth and flush with existing road width will be paved over the minimum 8” aggregate base. Lat/Long: 32.53759, -109.45473. Detour road will need to be placed around pipes to allow for traffic to flow around project site. Location of detour road will be determined with contractor and government officials.

Third Site: Replacement of existing (1) pipe 30” x 24” with new 30” x 24” galvanized steel pipe-arch culvert. Existing culvert is approximately 40’ long. Culverts are gauge 12 steel.

Culvert corrugations are 2-2/3” x ½”. Roadway is 20’ wide. Bottom of wash to top of road is approximately 4’. Rip-Rap will be placed around culvert pipes on both ends and 4’ apron in front and grouted to prevent erosion. Cover for culverts will be a minimum of 12”. 4” asphalt road depth and flush with existing road width will be paved over the minimum 8” aggregate base. Lat/Long for third site single pipe is 32.5210, -109.4402 .

Detour road will need to be placed around pipes to allow for traffic to flow around project site.

Location of detour road will be determined with contractor and government officials.

Road at all three sites will need to be demolished and paved 5 ft. past culverts on each side to prevent joints above the pipes. Traffic plan needed to direct traffic during project duration.

Engaging a testing agency will be contractor’s responsibility. Compaction testing is required of base aggregate. Test results need to be submitted to government. Sites are approximately 15 miles apart. All permits required to complete project are contractor’s responsibility. All Three

(3) sites will need to be surveyed to ensure proper placement of pipes and proper flow for potential water. Dirt will need to be extended to cover top of pipes and flush with road.

Construction water will be available for construction use on project from well on Haekel Road.

Contractor is responsible for temporary minimum 7500 watt generator to power well.

Contractor is responsible for bringing temporary storage tank, and fill tower during project duration. Contractor is responsible for all water transportation. Construction well location: Lat:

32.705521, Long: -109.500344. Temporary construction fencing is required around construction well site during duration of project and needs to be taken down after completion of project.

Fencing is contractor’s responsibility.

Crack Seal joints of asphalt and existing chip seal. Permanent pavement markings matching existing lines are required.

Any damage to detour roads during construction phase will need to be addressed and repaired by contractor.

BLM borrow pit dirt to be used for detour road only. Suitable base course will need to be brought in for base of asphalt.

Dirt is available for use on project at borrow pit. Lat/Long 32.783679 -109.600303 BLM dirt to be used for detour road if needed.

Furnish and install all pipes and leak resistant connecting pieces to join pipes together.

Contractor to submit submittal schedule and all required submittals to include, but not limited to material data, traffic control plan, safety plan, and quality control plan.

Cast in place cut off walls only to be placed at slick rock culvert bridge location.

All 3 sites get grouted rip rap around pipes, to wash banks, and 4 foot apron in front. End of apron place grouted rip rap 2’ down.

1.3 PROJECT INFORMATION

1. Project Location: Haekel Road and Slick Rock culvert bridge approximately 30 miles southeast of Safford, Arizona in Graham County.

2. Period of Performance: Activity on this project may not begin prior to April 15, 2021 nor extend beyond 90 days.

B. Government: Bureau of Land Management.

1. Government's Representative: Cody Tetrick, COR, BLM Engineer Technician; 1 N.

Central Avenue, Suite 800, Phoenix, Arizona, 85004. Office: (602) 417-9519; Cell: (480)

272-0157; Email: ctetrick@blm.gov.

1.4 WORK COVERED BY CONTRACT DOCUMENTS

mailto:gjaggers@blm.gov

A. The Work of Project is defined by the Contract Documents and consists of the following:

1. Create gravel detour road. Coordinate location of detour road with BLM field office personnel.

2. Removal of existing corrugated steel pipe culverts and roadway surfacing.

3. Replace existing pipes with new galvanized steel pipe-arch culverts mentioned in summary to include all gaskets and joining materials to ensure no leaking and pipes are connected properly.

4. Cast-in-place Cut-Off walls with rebar reinforcing for set of 5 pipes (Slick Rock culvert bridge)

5. Build road above pipes and repave road to flow with existing road on both ends.

6. Third party compaction testing on base aggregate.

7. Grouted rip-rap placed around pipes.

1.5 ACCESS TO SITE

A. General: Contractor shall have limited use of Project site for construction operations as indicated on Drawings by the Contract limits and as indicated by requirements of this Section.

B. Use of Site: Limit use of Project site to areas within the Contract limits indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.

C. Project location: Slick Rock Culvert Bridge on Haekel Road. 32.72518, -109.53176 (5 pipes)

Second Site: Culvert pipes on Haekel Road. 32.53759 -109.45473 (2 pipes)

Third Site: Culvert Pipe on Haekel Road. 32.5210, -109.4402 (1 pipe)

Construction Well Site: 32.705521 -109.500344

Borrow Pit: 32.783679, -109.600303

1.6 WORK RESTRICTIONS

A. Work Restrictions, General: Comply with restrictions on construction operations.

1. Comply with limitations on use of public streets and with other requirements of authorities having jurisdiction.

B. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after providing temporary utility services according to requirements indicated:

1. Notify Government not less than 3 calendar days in advance of proposed utility interruptions.

2. Obtain Government's written permission before proceeding with utility interruptions.

C. Restricted Substances: Use of tobacco products and other controlled substances within the existing buildings and on the Project site is not permitted.

1.7 SPECIFICATION AND DRAWING CONVENTIONS

A. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations.

These conventions are as follows:

1. Imperative mood and streamlined language are generally used in the Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.

2. Specification requirements are to be performed by Contractor unless specifically stated otherwise.

B. Division 01 General Requirements: Requirements of Sections in Division 01 apply to the Work of all Sections in the Specifications.

C. Drawing Coordination: Requirements for materials and products identified on Drawings are described in detail in the Specifications. One or more of the following are used on Drawings to identify materials and products:

1. Terminology: Materials and products are identified by the typical generic terms used in the individual Specifications Sections.

2. Abbreviations: Materials and products are identified by abbreviations as scheduled on

Drawings.

3. Keynoting: Materials and products are identified by reference keynotes referencing

Specification Section numbers found in this Project Manual.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 01

PROJECT MANAGEMENT AND

COORDINATION 013100 - 1

SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION

1.2

SUMMARY

A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:

1. General coordination procedures.

2. Coordination drawings.

3. RFIs.

4. Digital project management procedures.

5. Project meetings.

B. Each contractor shall participate in coordination requirements. Certain areas of responsibility are assigned to a specific contractor.

C. Related Requirements:

1. Section 013200 "Construction Progress Documentation" for preparing and submitting

Contractor's construction schedule.

2. Section 017300 "Execution" for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.

3. Section 017700 "Closeout Procedures" for coordinating closeout of the Contract.

1.3

DEFINITIONS

A. RFI: Request for Information. Request from Government or Contractor seeking information required by, or clarifications of, the Contract Documents.

1.4

INFORMATIONAL SUBMITTALS

A. Subcontract List: Prepare a written summary identifying individuals or firms proposed for each portion of the Work, including those who are to furnish products or equipment fabricated to a special design. Include the following information in tabular form:

1. Name, address, telephone number, and email address of entity performing subcontract or supplying products.

2. Number and title of related Specification Section(s) covered by subcontract.

3. Drawing number and detail references, as appropriate, covered by subcontract.

COORDINATION 013100 - 2

B. Key Personnel Names: Within 14 calendar days of starting construction operations, submit a list of key personnel assignments, including superintendent and other personnel in attendance at Project site. Identify individuals and their duties and responsibilities; list addresses and cellular telephone numbers and e-mail addresses. Provide names, addresses, and telephone numbers of individuals assigned as alternates in the absence of individuals assigned to Project.

1.5 GENERAL COORDINATION PROCEDURES

A. Coordination: Coordinate construction operations included in different Sections of the

Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations included in different Sections that depend on each other for proper installation, connection, and operation.

1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.

2. Coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair.

3. Make adequate provisions to accommodate items scheduled for later installation.

B. Coordination: Each contractor shall coordinate its construction operations with those of other contractors and entities to ensure efficient and orderly installation of each part of the Work. Each contractor shall coordinate its own operations with operations included in different Sections that depend on each other for proper installation, connection, and operation.

1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.

2. Coordinate installation of different components with other contractors to ensure maximum performance and accessibility for required maintenance, service, and repair.

3. Make adequate provisions to accommodate items scheduled for later installation.

C. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.

1. Prepare similar memoranda for Government and separate contractors if coordination of their Work is required.

D. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and scheduled activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:

1. Preparation of Contractor's construction schedule.

2. Preparation of the schedule of values.

3. Installation and removal of temporary facilities and controls.

4. Delivery and processing of submittals.

5. Progress meetings.

6. Pre-installation conferences.

7. Project closeout activities.

COORDINATION 013100 - 3

1.6 COORDINATION DRAWINGS

A. Coordination Drawings, General: Prepare coordination drawings according to requirements in individual Sections, and additionally where installation is not completely indicated on Shop

Drawings, where limited space availability necessitates coordination, or if coordination is required to facilitate integration of products and materials fabricated or installed by more than one entity.

1. Content: Project-specific information, drawn accurately to a scale large enough to indicate and resolve conflicts. Do not base coordination drawings on standard printed data. Include the following information, as applicable:

a. Use applicable Drawings as a basis for preparation of coordination drawings.

Prepare sections, elevations, and details as needed to describe relationship of various systems and components.

b. Coordinate the addition of trade-specific information to coordination drawings in a sequence that best provides for coordination of the information and resolution of conflicts between installed components before submitting for review.

c. Indicate functional and spatial relationships of components of civil, structural, mechanical, and electrical systems.

d. Indicate space requirements for routine maintenance and for anticipated replacement of components during the life of the installation.

e. Indicate required installation sequences.

f. Indicate dimensions shown on Drawings. Specifically note dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements.

Provide alternative sketches to Government indicating proposed resolution of such conflicts. Minor dimension changes and difficult installations will not be considered changes to the Contract.

B. Coordination Drawing Organization: Organize coordination drawings as follows:

1. Structural Penetrations: Indicate penetrations and openings required for all disciplines.

2. Slab Edge and Embedded Items: Indicate slab edge locations and sizes and locations of embedded items for metal fabrications, sleeves, anchor bolts, bearing plates, angles, curbs, and similar items.

3. Electrical Work: Show the following:

a. Runs of vertical and horizontal conduit 1-1/4 inches in diameter and larger.

4. Review: Government will review coordination drawings to confirm that in general the

Work is being coordinated, but not for the details of the coordination, which are

Contractor's responsibility. If Government determines that coordination drawings are not being prepared in sufficient scope or detail, or are otherwise deficient, Government will inform Contractor, who shall make suitable modifications and resubmit.

5. Coordination Drawing Prints: Prepare coordination drawing prints according to requirements in Section 013300 "Submittal Procedures."

C. Coordination Digital Data Files: Prepare coordination digital data files according to the following requirements:

COORDINATION 013100 - 4

1. File Preparation Format: Same digital data software program, version, and operating system as original Drawings.

2. File Preparation Format: DWG, Version 2016 AutoCad, operating in Microsoft Windows operating system.

3. File Submittal Format: Submit or post coordination drawing files using PDF Format.

4. Government will furnish Contractor one set of digital data files of Drawings for use in preparing coordination digital data files.

a. Government makes no representations as to the accuracy or completeness of digital data files as they relate to Drawings.

1.7 REQUEST FOR INFORMATION (RFI)

A. General: Immediately on discovery of the need for additional information, clarification, or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI in the form specified.

1. Government will return without response those RFIs submitted to Government by other entities controlled by Contractor.

2. Coordinate and submit RFIs in a prompt manner so as to avoid delays in Contractor's work or work of subcontractors.

B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:

1. Project name.

2. Project number.

3. Date.

4. Name of Contractor.

5. Name of Government.

6. RFI number, numbered sequentially.

7. RFI subject.

8. Specification Section number and title and related paragraphs, as appropriate.

9. Drawing number and detail references, as appropriate.

10. Field dimensions and conditions, as appropriate.

11. Contractor's suggested resolution. If Contractor's suggested resolution impacts the Contract

Time or the Contract Sum, Contractor shall state impact in the RFI.

12. Contractor's signature.

13. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop

Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.

a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.

C. RFI Forms: Form bound in Project Manual

1. Attachments shall be electronic files in PDF format.

COORDINATION 013100 - 5

D. Government’s Action: Government will review each RFI, determine action required, and respond.

Allow 7 calendar days for Government's response for each RFI. RFIs received by Government after 1:00 p.m. will be considered as received the following calendar day.

1. d

a. Requests for approval of submittals.

b. Requests for approval of substitutions.

c. Requests for approval of Contractor's means and methods.

d. Requests for coordination information already indicated in the Contract Documents.

e. Requests for adjustments in the Contract Time or the Contract Sum.

f. Requests for interpretation of Government's actions on submittals.

g. Incomplete RFIs or inaccurately prepared RFIs.

2. Government's action may include a request for additional information, in which case

Government's time for response will date from time of receipt by Government of additional information.

3. Government's action on RFIs that may result in a change to the Contract Time or the

Contract Sum may be eligible for Contractor to submit Change Proposal according to

Section 012600 "Contract Modification Procedures."

a. If Contractor believes the RFI response warrants change in the Contract Time or the

Contract Sum, notify Government in writing within 10 calendar days of receipt of the RFI response.

E. RFI Log: Prepare, maintain, and submit a tabular log of RFIs organized by the RFI number.

Submit log weekly

2. Name and address of Contractor.

3. Name and address of Government.

4. RFI number including RFIs that were returned without action or withdrawn.

5. RFI description.

6. Date the RFI was submitted.

7. Date Government's response was received.

8. Identification of related Minor Change in the Work, Construction Change Directive, and

Proposal Request, as appropriate.

9. Identification of related Field Order, Work Change Directive, and Proposal Request, as appropriate.

F. On receipt of Government's action, update the RFI log and immediately distribute the RFI response to affected parties. Review response and notify Government within 7 calendar days if

Contractor disagrees with response.

1.8 DIGITAL PROJECT MANAGEMENT PROCEDURES

A. Use of Government's Digital Data Files: Digital data files of Government's CAD drawings will be provided by Government for Contractor's use during construction.

COORDINATION 013100 - 6

1. Digital data files may be used by Contractor in preparing coordination drawings, Shop

Drawings, and Project Record Drawings.

2. Government makes no representations as to the accuracy or completeness of digital data files as they relate to Contract Drawings.

3. Digital Drawing Software Program: Contract Drawings are available in AutoCAD 2016.

4. The following digital data files will be furnished for each appropriate discipline:

a. DWG.

5. At completion of Project, provide digital archive in format that is readable by common desktop software applications in format acceptable to Government. Provide data in locked format to prevent further changes.

B. Web-Based Project Software

1. At completion of Project, provide digital archive in format that is readable by common desktop software applications in format acceptable to Government. Provide data in locked format to prevent further changes.

C. PDF Document Preparation: Where PDFs are required to be submitted to Government, prepare as follows:

1. Assemble complete submittal package into a single indexed file incorporating submittal requirements of a single Specification Section and transmittal form with links enabling navigation to each item.

2. Name file with submittal number or other unique identifier, including revision identifier.

3. Certifications: Where digitally submitted certificates and certifications are required, provide a digital signature with digital certificate on where indicated.

1.9 PROJECT MEETINGS

A. General: Schedule and conduct meetings and conferences at Project site unless otherwise indicated.

1. Attendees: Inform participants and others involved, and individuals whose presence is required, of date and time of each meeting. Notify Government and Government of scheduled meeting dates and times a minimum of 10 calendar days prior to meeting.

2. Agenda: Prepare the meeting agenda. Distribute the agenda to all invited attendees.

3. Minutes: Entity responsible for conducting meeting will record significant discussions and agreements achieved. Distribute the meeting minutes to everyone concerned, including

Government and Government, within 3 calendar days of the meeting.

B. Preconstruction Conference: Schedule and conduct a preconstruction conference before starting construction, at a time convenient to Government and Government, but no later than 15 calendar days after execution of the Agreement.

1. Attendees: Authorized representatives of Government, Government, and their consultants;

Contractor and its superintendent; major subcontractors; suppliers; and other concerned parties shall attend the conference. Participants at the conference shall be familiar with

Project and authorized to conclude matters relating to the Work.

2. Agenda: Discuss items of significance that could affect progress, including the following:

COORDINATION 013100 - 7

a. Responsibilities and personnel assignments.

b. Tentative construction schedule.

c. Phasing.

d. Critical work sequencing and long lead items.

e. Designation of key personnel and their duties.

f. Lines of communications.

g. Use of web-based Project software.

h. Procedures for processing field decisions and Change Orders.

i. Procedures for RFIs.

j. Procedures for testing and inspecting.

k. Procedures for processing Applications for Payment.

l. Distribution of the Contract Documents.

m. Submittal procedures.

n. Sustainable design requirements.

o. Preparation of Record Documents.

p. Use of the premises and existing buildings.

q. Work restrictions.

r. Working hours.

s. Government's occupancy requirements.

t. Responsibility for temporary facilities and controls.

u. Procedures for moisture and mold control.

v. Procedures for disruptions and shutdowns.

w. Construction waste management and recycling.

x. Parking availability.

y. Office, work, and storage areas.

z. Equipment deliveries and priorities.

aa. First aid.

bb. Security.

cc. Progress cleaning.

3. Minutes: Entity responsible for conducting meeting will record and distribute meeting minutes.

C. Pre-installation Conferences: Conduct a pre-installation conference at Project site before each construction activity when required by other sections and when required for coordination with other construction.

1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by the installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend the meeting. Advise

Government and Government of scheduled meeting dates.

2. Agenda: Review progress of other construction activities and preparations for the particular activity under consideration, including requirements for the following:

a. Contract Documents.

b. Options.

c. Related RFIs.

d. Related Change Orders.

e. Purchases.

f. Deliveries.

g. Submittals.

COORDINATION 013100 - 8

h. Sustainable design requirements.

i. Review of mockups.

j. Possible conflicts.

k. Compatibility requirements.

l. Time schedules.

m. Weather limitations.

n. Manufacturer's written instructions.

o. Warranty requirements.

p. Compatibility of materials.

q. Acceptability of substrates.

r. Temporary facilities and controls.

s. Space and access limitations.

t. Regulations of authorities having jurisdiction.

u. Testing and inspecting requirements.

v. Installation procedures.

w. Coordination with other work.

x. Required performance results.

y. Protection of adjacent work.

z. Protection of construction and personnel.

3. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.

4. Reporting: Distribute minutes of the meeting to each party present and to other parties requiring information.

5. Do not proceed with installation if the conference cannot be successfully concluded.

Initiate whatever actions are necessary to resolve impediments to performance of the Work and reconvene the conference at earliest feasible date.

D. Project Closeout Conference: Schedule and conduct a project closeout conference, at a time convenient to Government and Government, but no later than 15 calendar days prior to the scheduled date of Substantial Completion.

1. Conduct the conference to review requirements and responsibilities related to Project closeout.

2. Attendees: Authorized representatives of Government, Government, and their consultants;

Contractor and its superintendent; major subcontractors; suppliers; and other concerned parties shall attend the meeting. Participants at the meeting shall be familiar with Project and authorized to conclude matters relating to the Work.

3. Agenda: Discuss items of significance that could affect or delay Project closeout, including the following:

a. Preparation of Record Documents.

b. Procedures required prior to inspection for Substantial Completion and for final inspection for acceptance.

c. Procedures for completing and archiving web-based Project software site data files.

d. Submittal of written warranties.

e. Requirements for completing sustainable design documentation.

f. Requirements for preparing operations and maintenance data.

g. Requirements for delivery of material samples, attic stock, and spare parts.

h. Requirements for demonstration and training.

i. Preparation of Contractor's punch list.

COORDINATION 013100 - 9

j. Procedures for processing Applications for Payment at Substantial Completion and for final payment.

k. Submittal procedures.

l. Coordination of separate contracts.

m. Government's partial occupancy requirements.

n. Installation of Government's furniture, fixtures, and equipment.

o. Responsibility for removing temporary facilities and controls.

4. Minutes: Entity conducting meeting will record and distribute meeting minutes.

E. Progress Meetings: Conduct progress meetings at biweekly intervals.

1. Coordinate dates of meetings with preparation of payment requests.

2. Attendees: In addition to representatives of Government and Government, each contractor, subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings. All participants at the meeting shall be familiar with Project and authorized to conclude matters relating to the Work.

3. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. Include topics for discussion as appropriate to status of Project.

a. Contractor's Construction Schedule: Review progress since the last meeting.

Determine whether each activity is on time, ahead of schedule, or behind schedule, in relation to Contractor's construction schedule. Determine how construction behind schedule will be expedited; secure commitments from parties involved to do

so. Discuss whether schedule revisions are required to ensure that current and subsequent activities will be completed within the Contract Time.

1) Review schedule for next period.

b. Review present and future needs of each entity present, including the following:

1) Interface requirements.

2) Sequence of operations.

3) Status of submittals.

4) Deliveries.

5) Access.

6) Site use.

7) Temporary facilities and controls.

8) Progress cleaning.

9) Quality and work standards.

10) Status of correction of deficient items.

11) Field observations.

12) Status of RFIs.

13) Status of Proposal Requests.

14) Pending changes.

15) Status of Change Orders.

16) Pending claims and disputes.

17) Documentation of information for payment requests.

COORDINATION 013100 - 10

4. Minutes: Entity responsible for conducting the meeting will record and distribute the meeting minutes to each party present and to parties requiring information.

a. Schedule Updating: Revise Contractor's construction schedule after each progress meeting where revisions to the schedule have been made or recognized. Issue revised schedule concurrently with the report of each meeting.

END OF SECTION 013100

CONSTRUCTION PROGRESS

DOCUMENTATION 013200 - 1

SECTION 013200 - CONSTRUCTION PROGRESS DOCUMENTATION

A. Section includes administrative and procedural requirements for documenting the progress of construction during performance of the Work, including the following:

1. Startup construction schedule.

2. Contractor's Construction Schedule.

3. Construction schedule updating reports.

4. Daily construction reports.

5. Material location reports.

6. Site condition reports.

7. Unusual event reports.

1.3 DEFINITIONS

A. Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling the construction Project. Activities included in a construction schedule consume time and resources.

1. Critical Activity: An activity on the critical path that must start and finish on the planned early start and finish times.

2. Predecessor Activity: An activity that precedes another activity in the network.

3. Successor Activity: An activity that follows another activity in the network.

B. Cost Loading: The allocation of the schedule of values for completing an activity as scheduled.

The sum of costs for all activities must equal the total Contract Sum.

C. CPM: Critical path method, which is a method of planning and scheduling a construction project where activities are arranged based on activity relationships. Network calculations determine when activities can be performed and the critical path of Project.

D. Critical Path: The longest connected chain of interdependent activities through the network schedule that establishes the minimum overall Project duration and contains no float.

E. Event: The starting or ending point of an activity.

F. Float: The measure of leeway in starting and completing an activity.

DOCUMENTATION 013200 - 2

1. Float time is not for the exclusive use or benefit of either Government or Contractor, but is a jointly owned, expiring Project resource available to both parties as needed to meet schedule milestones and Contract completion date.

2. Free float is the amount of time an activity can be delayed without adversely affecting the early start of the successor activity.

3. Total float is the measure of leeway in starting or completing an activity without adversely affecting the planned Project completion date.

G. Resource Loading: The allocation of manpower and equipment necessary for completing an activity as scheduled.

1.4 INFORMATIONAL SUBMITTALS

A. Format for Submittals: Submit required submittals in the following format:

1. Working electronic copy of schedule file, where indicated.

2. PDF file.

3. 3 paper copies, of sufficient size to display entire period or schedule, as required.

B. Startup construction schedule.

1. Submittal of cost-loaded, startup construction schedule will not constitute approval of schedule of values for cost-loaded activities.

C. Startup Network Diagram: Of size required to display entire network for entire construction period. Show logic ties for activities.

D. Contractor's Construction Schedule: Initial schedule, of size required to display entire schedule for entire construction period.

1. Submit a working digital copy of schedule, using software indicated, and labeled to comply with requirements for submittals.

E. CPM Reports: Concurrent with CPM schedule, submit each of the following reports. Format for each activity in reports shall contain activity number, activity description, cost and resource loading, original duration, remaining duration, early start date, early finish date, late start date, late finish date, and total float in calendar days.

1. Activity Report: List of activities sorted by activity number and then early start date, or actual start date if known.

2. Logic Report: List of preceding and succeeding activities for each activity, sorted in ascending order by activity number and then by early start date, or actual start date if known.

3. Total Float Report: List of activities sorted in ascending order of total float.

4. Earnings Report: Compilation of Contractor's total earnings from commencement of the

Work until most recent Application for Payment.

F. Construction Schedule Updating Reports: Submit with Applications for Payment.

G. Daily Construction Reports: Submit at weekly intervals.

DOCUMENTATION 013200 - 3

H. Material Location Reports: Submit at weekly intervals.

I. Site Condition Reports: Submit at time of discovery of differing conditions.

J. Unusual Event Reports: Submit at time of unusual event.

K. Qualification Data: For scheduling consultant.

1.5 QUALITY ASSURANCE

A. Scheduling Consultant Qualifications: An experienced specialist in CPM scheduling and reporting, with capability of producing CPM reports and diagrams within 24 hours of

Government's request.

B. Prescheduling Conference: Conduct conference at Project site to comply with requirements in

Section 013100 "Project Management and Coordination." Review methods and procedures related to the preliminary construction schedule and Contractor's Construction Schedule, including, but not limited to, the following:

1. Review software limitations and content and format for reports.

2. Verify availability of qualified personnel needed to develop and update schedule.

3. Discuss constraints, including work stages.

4. Review delivery dates for Government-furnished products.

5. Review schedule for work of Government's separate contracts.

6. Review submittal requirements and procedures.

7. Review time required for review of submittals and resubmittals.

8. Review requirements for tests and inspections by independent testing and inspecting agencies.

9. Review time required for Project closeout and Government startup procedures.

10. Review and finalize list of construction activities to be included in schedule.

11. Review procedures for updating schedule.

1.6 COORDINATION

A. Coordinate Contractor's Construction Schedule with the schedule of values, list of subcontracts, submittal schedule, progress reports, payment requests, and other required schedules and reports.

1. Secure time commitments for performing critical elements of the Work from entities involved.

2. Coordinate each construction activity in the network with other activities and schedule them in proper sequence.

1.7 CONTRACTOR'S CONSTRUCTION SCHEDULE, GENERAL

A. Computer Scheduling Software: Prepare schedules using current version of a program that has been developed specifically to manage construction schedules.

DOCUMENTATION 013200 - 4

1. Use Microsoft Project, Scheduling component of Project website software specified in

Section 013100 "Project Management and Coordination," for current Windows operating system.

B. Scheduling Consultant: Engage a consultant to provide planning, evaluation, and reporting using

CPM scheduling.

1. In-House Option: Government may waive requirement to retain a consultant if Contractor employs skilled personnel with experience in CPM scheduling and reporting techniques.

Submit qualifications.

2. Meetings: Scheduling consultant shall attend all meetings related to Project progress, alleged delays, and time impact.

C. Time Frame: Extend schedule from date established for the Notice to Proceed to date of final completion.

1. Contract completion date shall not be changed by submission of a schedule that shows an early completion date, unless specifically authorized by Change Order.

END OF SECTION 013200

BLM HAEKEL ROAD

DECEMBER 2019

SUBMITTAL PROCEDURES 013300 - 1

SECTION 013300 - SUBMITTAL PROCEDURES

A. Section Includes:

1. Submittal schedule requirements.

2. Administrative and procedural requirements for submittals.

B. Related Requirements:

1. Section 013100 "Project Management and Coordination" for submitting coordination drawings and subcontract list and for requirements for web-based Project software.

2. Section 013200 "Construction Progress Documentation" for submitting schedules and reports, including Contractor's construction schedule.

3. Section 014000 "Quality Requirements" for submitting test and inspection reports, and schedule of tests and inspections.

4. Section 017700 "Closeout Procedures" for submitting closeout submittals and maintenance material submittals.

5. Section 017839 "Project Record Documents" for submitting record Drawings, record

Specifications, and record Product Data.

A. Action Submittals: Written and graphic information and physical samples that require

Government’s responsive action. Action submittals are those submittals indicated in individual

Specification Sections as "action submittals."

B. Informational Submittals: Written and graphic information and physical samples that do not require Government’s responsive action. Submittals may be rejected for not complying with requirements. Informational submittals are those submittals indicated in individual Specification

Sections as "informational submittals."

1.4 SUBMITTAL SCHEDULE

A. Submittal Schedule: Submit, as an action submittal, a list of submittals, arranged in chronological order by dates required by construction schedule. Include time required for review, ordering, manufacturing, fabrication, and delivery when establishing dates. Include additional time required

SUBMITTAL PROCEDURES 013300 - 2

for making corrections or revisions to submittals noted by Government and additional time for handling and reviewing submittals required by those corrections.

1. Coordinate submittal schedule with list of subcontracts, the schedule of values, and

Contractor's construction schedule.

2. Initial Submittal: Submit concurrently with startup construction schedule. Include submittals required during the first 60 calendar days of construction. List those submittals required to maintain orderly progress of the Work and those required early because of long lead time for manufacture or fabrication.

3. Final Submittal: Submit concurrently with the first complete submittal of Contractor's construction schedule.

a. Submit revised submittal schedule to reflect changes in current status and timing for submittals.

4. Format: Arrange the following information in a tabular format:

a. Scheduled date for first submittal.

b. Specification Section number and title.

c. Submittal Category: Action; informational.

d. Name of subcontractor.

e. Description of the Work covered.

f. Scheduled date for Government’s final release or approval.

g. Scheduled dates for purchasing.

h. Scheduled date of fabrication.

i. Scheduled dates for installation.

j. Activity or event number.

1.5 SUBMITTAL FORMATS

A. Submittal Information: Include the following information in each submittal:

2. Date.

3. Name of Government.

4. Name of Contractor.

5. Name of firm or entity that prepared submittal.

6. Names of subcontractor, manufacturer, and supplier.

7. Unique submittal number, including revision identifier. Include Specification Section number with sequential alphanumeric identifier; and alphanumeric suffix for resubmittals.

8. Category and type of submittal.

9. Submittal purpose and description.

10. Number and title of Specification Section, with paragraph number and generic name for each of multiple items.

11. Drawing number and detail references, as appropriate.

12. Indication of full or partial submittal.

13. Location(s) where product is to be installed, as appropriate.

14. Other necessary identification.

15. Remarks.

16. Signature of transmitter.

B. Options: Identify options requiring selection by Government.

C. Deviations and Additional Information: On each submittal, clearly indicate deviations from requirements in the Contract Documents, including minor variations and limitations; include

SUBMITTAL PROCEDURES 013300 - 3

relevant additional information and revisions, other than those requested by Government on previous submittals. Indicate by highlighting on each submittal or noting on attached separate sheet.

D. PDF Submittals: Prepare submittals as PDF package, incorporating complete information into each PDF file. Name PDF file with submittal number.

E. Submittals for Web-Based Project Software: Prepare submittals as PDF files, or other format indicated by Project software website.

1.6 SUBMITTAL PROCEDURES

A. Prepare and submit submittals required by individual Specification Sections. Types of submittals are indicated in individual Specification Sections.

1. Email: Prepare submittals as PDF package, and transmit to Government. By sending via email. Include PDF transmittal form. Include information in email subject line as requested by Government.

a. Government will return annotated file. Annotate and retain one copy of file as a digital Project Record Document file.

2. Web-Based Project Software: Prepare submittals in PDF form, and upload to web-based

Project software website. Enter required data in web-based software site to fully identify submittal.

3. Paper: Prepare submittals in paper form, and deliver to Government.

B. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.

1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.

2. Submit all submittal items required for each Specification Section concurrently unless partial submittals for portions of the Work are indicated on approved submittal schedule.

3. Submit action submittals and informational submittals required by the same Specification

Section as separate packages under separate transmittals.

4. Coordinate transmittal of submittals for related parts of the Work specified in different

Sections so processing will not be delayed because of need to review submittals concurrently for coordination.

a. Government reserve the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.

C. Processing Time: Allow time for submittal review, including time for resubmittals, as follows.

Time for review shall commence on Government’s receipt of submittal. No extension of the

Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including resubmittals.

1. Initial Review: Allow 14 calendar days for initial review of each submittal. Allow additional time if coordination with subsequent submittals is required. Government will advise Contractor when a submittal being processed must be delayed for coordination.

2. Intermediate Review: If intermediate submittal is necessary, process it in same manner as initial submittal.

3. Resubmittal Review: Allow 14 calendar days for review of each resubmittal.

SUBMITTAL PROCEDURES 013300 - 4

4. Sequential Review: Where sequential review of submittals by Government’s consultants, Government, or other parties is indicated, allow 21 calendar days for initial review of each submittal.

D. Resubmittals: Make resubmittals in same form and number of copies as initial submittal.

1. Note date and content of previous submittal.

2. Note date and content of revision in label or title block and clearly indicate extent of revision.

3. Resubmit submittals until they are marked with approval notation from Government’s action stamp.

E. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators, installers, authorities having jurisdiction, and others as necessary for performance of construction activities. Show distribution on transmittal forms.

F. Use for Construction: Retain complete copies of submittals on Project site. Use only final action submittals that are marked with approval notation from Government’s action stamp.

1.7 SUBMITTAL REQUIREMENTS

A. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.

1. If information must be specially prepared for submittal because standard published data are unsuitable for use, submit as Shop Drawings, not as Product Data.

2. Mark each copy of each submittal to show which products and options are applicable.

3. Include the following information, as applicable:

a. Manufacturer's catalog cuts.

b. Manufacturer's product specifications.

c. Standard color charts.

d. Statement of compliance with specified referenced standards.

e. Testing by recognized testing agency.

f. Application of testing agency labels and seals.

g. Notation of coordination requirements.

h. Availability and delivery time information.

4. For equipment, include the following in addition to the above, as applicable:

a. Wiring diagrams that show factory-installed wiring.

b. Printed performance curves.

c. Operational range diagrams.

d. Clearances required to other construction, if not indicated on accompanying Shop

Drawings.

5. Submit Product Data before Shop Drawings, and before or concurrent with Samples.

B. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base

Shop Drawings on reproductions of the Contract Documents or standard printed data.

1. Preparation: Fully illustrate requirements in the Contract Documents. Include the following information, as applicable:

a. Identification of products.

b. Schedules.

c. Compliance with specified standards.

SUBMITTAL PROCEDURES 013300 - 5

d. Notation of coordination requirements.

e. Notation of dimensions established by field measurement.

f. Relationship and attachment to adjoining construction clearly indicated.

g. Seal and signature of professional government if specified.

2. Paper Sheet Size: Except for templates, patterns, and similar full-size Drawings, submit

Shop Drawings on sheets at least 8-1/2 by 11 inches, but no larger than 11 by 17 inches.

a. Two opaque (bond) copies of each submittal. Government will return one copy.

b. Three opaque copies of each submittal. Government will retain two copies;

remainder will be returned.

C. Samples: Submit Samples for review of kind, color, pattern, and texture for a check of these characteristics with other materials.

1. Transmit Samples that contain multiple, related…