Attch 1 - Deep Cleaning PWS Range 3 20July26.pdf

PDF 715 KB Posted

Attached to
5 SFS CATM Range Lead Removal
Solicitation number
FA452826QML04
Issued by

About this file

This is a Performance Work Statement (PWS) for specialized firing range decontamination services dated July 20, 2026. The document establishes requirements for a one-time, highly specialized cleaning and decontamination project at a Firing Range facility targeting Debris Room #120 and Range 3. The contractor must provide all necessary labor, materials, and equipment to complete the work within an estimated two-day project duration.

The scope of work includes four primary phases: Mobilization & Safety, Debris Room #120 cleaning, Range 3 cleaning, and Demobilization. For Mobilization & Safety, the contractor must provide hazardous cleanup-suitable Personal Protective Equipment (PPE) for all onsite personnel, including half-face respirators with HEPA cartridges, and establish a negative air environment using HEPA-filtered air scrubbers running throughout the project. Debris Room #120 work involves cleaning walls (approximately 1,115 sq. ft.), pressure steam cleaning of floors (approximately 1,076 sq. ft.), and detailed HEPA vacuuming of all surfaces within the room (approximately 2,192 sq. ft.). Range 3 decontamination requires pressure steam cleaning of floors (approximately 4,992 sq. ft.) and detailed HEPA vacuuming. Demobilization requires on-site decontamination of all equipment. Waste Compliance requirements mandate use of DoT and RCRA-compliant waste containers, proper labeling and markings identifying collected waste, provision of Safety Data Sheets to the installation Hazardous Waste Program Manager for all chemicals used, and preparation of containers for transport to Building 525.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Firing Range Decontamination PWS

Performance Work Statement

(PWS)

Specialized Firing Range Decontamination Services

Date: 20 July 2026

Table of Contents

Executive Summary

1.0 Description of Services

2.0 Scope of Work

2.1 Mobilization & Safety

2.2 Debris Room #120

2.3 Range 3

2.4 Demobilization

2.5 Waste Compliance…………………………………………………………………………………………………………………………3

3.0 Pictures for reference………………………………………………………………………………………………………………….….4-6

Executive Summary This document establishes the Performance Work Statement (PWS) for a one-time, highly specialized cleaning and decontamination project at the Firing Range facility, specifically targeting Debris Room #2 and Range 3. Additionally, it provides a critical comparison against the existing routine maintenance contract to ensure clarity of scope, preventing operational conflicts while identifying supplemental service overlaps.

1.0 Description of Services

The contractor shall provide all necessary labor, materials, and equipment to perform one-time cleaning and decontamination services for the Firing Range facility, specifically within "Debris Room #120" and "Range 3".

2.0 Scope of Work

The contractor shall perform the following tasks:

2.1 Mobilization & Safety

• Provide and utilize Personal Protective Equipment (PPE) suitable for hazardous cleanup for all on-site personnel.

• Use half-face respirators with HEPA cartridges.

• Establish a negative air environment using air scrubbers with HEPA filters running for the duration of the project (estimated 2 days).

2.2 Debris Room #120

• Clean walls (approx. 1,115 sq. ft.).

• Clean the floor using pressure steam (approx. 1,076 sq. ft.).

• Perform detailed HEPA vacuuming of all surfaces within the room (approx. 2,192 sq. ft.).

2.3 Range 3

• Clean the floor using pressure steam (approx. 4,992 sq. ft.).

• Perform detailed HEPA vacuuming.

2.4 Demobilization

• Perform on-site decontamination of all equipment during the cleanup.

2.5 Waste Compliance

• Provide and utilize waste containers that comply with DoT and RCRA requirements to collect all hazardous waste generated.

• Ensure containers are not leaking or damaged, container material is compatible with waste collected, and maximum container weight is not exceeded.

• Provide and utilize DoT and RCRA compliant waste markings and labels which identify waste collected in containers.

• Provide the installation Hazardous Waste Program Manager Safety Data Sheets for any chemicals used during the cleaning process.

• Prepare containers for transport to Building 525.

3.0 Pictures

Executive Summary
1.0 Description of Services
2.0 Scope of Work
2.1 Mobilization & Safety
2.2 Debris Room #120
2.3 Range 3
2.4 Demobilization
2.5 Waste Compliance