This document is a Bid Schedule for the Nome Creek Road Repair project, which is a federal contract opportunity being solicited by the Department of the Interior's Bureau of Land Management.

The Bid Schedule outlines the Base Bid and five Additive Items for the road repair work. The Base Bid includes repairing the Ophir Line Road, correcting grades, repairing portions of the roadbed, cleaning ditches, replacing culverts, and placing new road surface materials. The Additive Items cover additional repairs to the Mount Prindle Line Road, Mount Prindle Campground Road, Ophir Campground Road, Nome Creek Bridge gabions, and the Nome Creek Administrative Runway. The award will be made based on available funding, with the Base Bid being awarded first, followed by the Additive Items as funds allow.

The related federal contract opportunity, Solicitation Number 140L0624R0040, is for the GAOA Nome Creek Road Repair project, to be performed for the Department of the Interior's Bureau of Land Management.

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Nome Creek Road Repair – Bid Schedule (Base Bid plus Additives 01 – 05)

1 | P a g e

BASE PRICE

Pay Item No.

Description Unit Price Amount

01 BASE BID:

Repair the Ophir Line Road (Intersection of US Creek Road and Ophir Alignment Station 5+00 to Ophir Alignment Start of Connection Station 645+14) including correcting grades, repairing short portions of weakened roadbed, cleaning/reshaping ditches, replacing/repairing culverts, and placing roadway surface materials. Work includes establishing borrow site with supporting access roads, temporary bridge, and pit reclamation. Major drainage and culvert work occurs at Dickie’s Hole and Moose Creek Crossing. Work includes replacing informational signage along the route.

Lump Sum

BASE PRICE TOTAL $__________________

ADDITIVE ITEM 01-05 PRICES

Pay Item No.

Description Unit Price Amount

02 ADDITIVE ITEM 01:

Repair the Mount Prindle Line Road (Intersection of US Creek Road and Mount Prindle Alignment Station 4+99.27 to Prindle Alignment Start of Connection 214+49) including correcting grades, repairing embankments, cleaning/re-shaping ditches, replacing/repairing culverts, and placing roadway surface materials. Work includes replacing informational signage along the route.

Lump Sum $_________________

03 ADDITIVE ITEM 02:

Repair the Mount Prindle Campground Road (Loop beginning and ending at Prindle Alignment Start of Connection Station 214+49) including correcting grades, reshaping ditches, replacing/repairing culverts, and placing roadway surface materials. Work includes

Nome Creek Road Repair – Bid Schedule (Base Bid plus Additives 01 – 05)

2 | P a g e replacing informational signage throughout the campground. Additional work includes repairs at the well head to replace the hand pump and protect it against spring flooding.

Lump Sum

04 ADDITIVE ITEM 03:

Repair the Ophir Campground Road (Double loop beginning and ending at Ophir Alignment Station of Connection 642+60 and single loop beginning and ending at Ophir Alignment Start of Connection Station 645+14) including correcting grades, reshaping ditches, replacing/repairing culverts, and placing roadway surface materials. Work includes replacing informational signage throughout the campground.

ADDITIVE ITEM 04:

Repair the Nome Creek Bridge gabions including protection of failing gabion baskets by installing protective rock in locations adjacent to Nome Creek Bridge.

ADDITIVE ITEM 05:

Repair the Nome Creek Administrative Runway (access road to administrative area and runway at approximately 578+00 on Ophir Alignment) including grading and drainage improvements to reduce springtime runway flooding.

GRAND TOTAL (BASE PRICE PLUS ADDITIVE PRICES)

Note: Award will be made as funds are available at time of award. The Base Bid will be awarded first and Additives will be awarded as funds allow.