This document contains a specification list and description for a federal contract opportunity for guardrail repairs on the Willamette National Forest in Oregon. The specification list outlines standard specifications and supplemental specifications applicable to the project, including general requirements, mobilization, public traffic, soil erosion and sediment control, removal of structures, structural concrete, reinforcing steel, and permanent traffic control. The related federal contract opportunity is solicitation number 1240BH21R0007 for Holiday Farm Fire BAER Guardrail Repairs to remove damaged guardrail systems, install new guardrail sections and terminals, install bridge transition pieces, and conduct reinforced concrete retrofits and curb construction on existing bridges within the McKenzie River Ranger District. The opportunity is issued by the US Department of Agriculture Forest Service Pacific Northwest Region.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Section Date Title

101-109 2014 General Requirements X X X X X X 151 2014 Mobilization X X X X X X 156 2014 Public Traffic X X X X X X 157 2014 Soil Erosion and Sediment Control X X X X X X 203 2014 Removal of Structures and Obstructions X X X X X X 552 2014 Structural Concrete X X 554 2014 Reinforcing Steel X X 617 2014 Guardrail X X X X X X 633 2014 Permanent Traffic Control X X X

Section Date Title

Preface 10/15/20 Preface X X X X X X

101.01 11/09/16 Meaning of Terms X X X X X X

101.03 11/09/16 Abbreviations X X X X X X

101.04 01/22/20 Definitions X X X X X X

102.00 11/09/16 Bid, Award, and Execution of Contract X X X X X X

103.00 11/09/16 Scope of Work X X X X X X

104.00 11/09/16 Control of Work X X X X X X

104.06 11/09/16 Use of Roads by Contractor X X X X X X

105.05 06/29/20 Use of Material Found in the Work X X X X X X

106.01 07/18/17 Conformity with Contract Requirements X X X X X X

106.02 11/09/16 Visual Inspection X X X X X X

107.05 07/18/17 Legal Relations and Responsibility to the Public X X X X X X

108.00 11/09/16 Prosecution and Progress X X X X X X

109.00 11/09/16 Measurement and Payment X X X X X X

109.01 02/22/19 Measurement of Work X X X X X X

109.02 11/09/16 Measurement Terms and Definitions X X X X X X

155.00 11/09/16 Schedules for Construction Contracts X X X X X X

156.00 02/05/19 Public Traffic X X X X X X

157.04 11/01/16 General X X X X X X

617.04 07/09/20 Post Installation X X X X X X

633.00 11/08/16 Permanent Traffic Control X X X

FP-14 SPECIFICATION LIST

All specifications not included in the specification listing, but included by reference, are applicable. "X" denotes applicable standard and/or supplemental specification. The supplementals shown on the specification list are physically attached.

Supplemental Specifications

Standard Specifications