RFP No. 36C26123R0013

PRICE BREAKDOWN

Correct Fuel Lines Martinez and Mare Island

DESCRIPTION MATERIAL LABOR TOTAL

01. General Requirements (Division 01) A. Project Manager $ $ $ B. Superintendent $ $ $ C. General Requirements (Mobilization) $ $ $ D. System Commissioning $ $ $

01. General Requirements Subtotal $ $ $

02. Concrete (Division 03)

A. Cut and refinish street curbs, gutters, & bldg.

floors

02. Concrete Subtotal $ $ $

03. Plumbing (Division 22)

A. Install 1” diameter, schedule 40, steel pipe B20

B. Demolition of existing piping B20 $ $ $ C. Install 1” diameter, schedule 40, steel pipe

B19

D. Demolition of existing piping B19 $ $ $ E. Install 1” diameter, schedule 40, steel pipe

B201

F. Demolition of existing piping B201 $ $ $ G. Valve $ $ $ H. Demolish Valve $ $ $ I. Temporary Mobile Diesel Fuel Tanks $ $ $ J. Replace Day Tank $ $ $ K. Miscellaneous (containment pan, etc.) $ $ $

03. Plumbing subtotal $ $ $

04. Earthwork (Division 31)

A. Excavate existing steel pipes and replace ground

04. Earthwork Subtotal $ $ $ SUB TOTAL (Items 1 – 5) $ $ $ General Conditions $ $ $ Overhead $ $ $ Profit $ $ $ Bonds and Insurance $ $ $ Total $ $ $ SUB TOTAL (Items 6 – 7) $ $ $ General Conditions $ $ $ Overhead $ $ $ Profit $ $ $ Bonds and Insurance $ $ $

TOTAL OFFER $ $ $