This file contains three Virginia Department of Transportation (VDOT) forms related to Disadvantaged Business Enterprise (DBE) requirements: Form C-48 (Subcontractor/Supplier Solicitation and Utilization Form), Form C-49 (DBE Good Faith Efforts Documentation), and Forms C-111/C-112 (Minimum DBE Requirements and Certification of Binding Agreement with DBE Firms). The forms are part of Attachment O for contract 25-05-3237TP and must be completed by bidders to document their efforts to meet DBE participation goals.
The forms require detailed documentation including: lists of DBE firms solicited and utilized, telephone logs of DBE contacts, documentation of advertisements seeking DBE participation, descriptions of work made available to DBEs, evidence of assistance provided to DBEs in obtaining bonding and insurance, and certification of binding agreements between contractors and DBE firms. Form C-111 specifically requires contractors to calculate and document the percentage of DBE participation achieved, with suppliers counted at 60% credit and manufacturers/haulers at 100% credit. All forms must be signed by the bidder certifying the accuracy of the information provided.
View the file
Other files
Show all 31
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
25-05-3237TP ATTACHMENT O
ATTACHMENT O
SUBCONTRACTOR/SUPPLIER SOLICITATION AND UTILIZATION FORM
DBE GOOD FAITH EFFORTS DOCUMENTATION
MINIMUM DBE REQUIREMENTS
CERTIFICATION OF BINDING AGREEMENT WITH DBE FIRMS
Form C-48 Rev. 2-23-11
COMMONWEALTH OF VIRGINIA
DEPARTMENT OF TRANSPORTATION
SUBCONTRACTOR/SUPPLIER SOLICITATION AND UTILIZATION FORM
(ALL BIDDERS)
PROJECT NO. CONTRACT I.D. NO.
FHWA NO. DATE SUBMITTED
All bidders, including DBEs bidding as Prime Contractors, shall complete and submit the following information as requested in this form within ten (10) business days after the opening of bids.
The bidder certifies this form accurately represents its solicitation and utilization or non-utilization, as indicated, of the firms listed below for performance of work on this contract. The bidder also certifies he/she has had direct contact with the named firms regarding participation on this project.
BIDDER SIGNATURE
TITLE
SUBCONTRACTOR/SUPPLIER SOLICITATION AND UTILIZATION (ALL)
VENDOR
NUMBER NAME OF SUBCONTRACTOR/SUPPLIER
TELEPHONE
NUMBER
DBE OR
NON-DBE
UTILIZED
(Y/N)
NOTE: ATTACH ADDITIONAL PAGES, IF NECESSARY.
BIDDER MUST SIGN EACH ADDITIONAL SHEET TO CERTIFY ITS CONTENT AND COMPLETION OF FORM.
Form C-49 2-24-14
Sheet 1 of 10
COMM0NWEALTH OF VIRGINIA
CONTRACT I.D. NUMBER________________________________
PROJECT NUMBER_____________________________________
FHWA NUMBER________________________________________
DISTRICT______________________________________________
DATE BID SUBMITTED___________________________________
BIDDER’S NAME________________________________________
SIGNATURE____________________________________________
TITLE_________________________________________________
VENDOR NUMBER______________________________________
DBE GOAL FROM BID PROPOSAL____________________________
--DO NOT DETACH--
THIS INFORMATION MUST BE SUBMITTED
WITHIN 2 DAYS AFTER BID OPENING IF YOUR
BID DOES NOT MEET THE PROJECT DBE
REQUIREMENTS, OR
WHEN REQUESTED BY VDOT
Sheet 2 of 10
COMM0NWEALTH OF VIRGINIA
CONTRACT I.D. NO.________________________________DATE SUBMITTED______________
IF THE DBE GOAL ESTABLISHED FOR THIS CONTRACT HAS NOT BEEN MET OR VDOT
REQUESTS THE SUBMITTAL THEREOF, THE BIDDER IS REQUIRED TO SUBMIT GOOD
FAITH EFFORTS AS OUTLINED IN THIS DOCUMENT.
THE BIDDER ACKNOWLEDGES AND CERTIFIES THAT THIS FORM ACCURATELY
REPRESENTS THE INFORMATION CONTAINED HEREIN.
BIDDER SIGNATURE ____
TITLE________________________________________________________________________________________
NAMES OF CERTIFIED DBEs AND THE DATES ON WHICH THEY WERE SOLICITED TO BID
ON THIS PROJECT
INCLUDE THE ITEMS OF WORK OFFERED AND THE DATES AND METHODS USED FOR
FOLLOWING UP INITIAL SOLICITATIONS TO DETERMINE WHETHER OR NOT DBEs WERE
INTERESTED.
NAMES AND VENDOR
NUMBERS OF DBEs
SOLICITED
DATE OF INITIAL
SOLICITATION
ITEM(S) OF WORK
FOLLOW-UP METHODS
AND DATES
NOTE: ATTACH ADDITIONAL PAGES IF NECESSARY
ATTACH COPIES OF SOLICITATIONS, TELEPHONE RECORDS, FAX CONFIRMATIONS,
ELECTRONIC INFORMATION, ETC.
Sheet 3 of 10
CONTRACT I.D. NO._________________DATE SUBMITTED___________________________
FAITH EFFORTS AS OUTLINED IN THIS DOCUMENT.
BIDDER_____________________________________SIGNATURE______________________________________
TELEPHONE LOG
DBE(s) CALLED
TELEPHONE
NUMBER
DATE
CALLED
TIME
CALLED
CONTACT PERSON OR
VOICE MAIL STATUS
Sheet 4 of 10
ITEM(S) OF WORK THAT THE BIDDER MADE AVAILABLE TO DBE FIRMS
IDENTIFY THOSE ITEM(S) OF WORK THAT THE BIDDER MADE AVAILABLE TO DBE
FIRMS OR THOSE ITEM(S) THE BIDDER IDENTIFIED AND DETERMINED TO SUBDIVIDE
INTO ECONOMICALLY FEASIBLE UNITS TO FACILITATE DBE PARTICIPATION. FOR
EACH ITEM LISTED, SHOW THE DOLLAR VALUE AND PERCENTAGE OF THE TOTAL
CONTRACT AMOUNT. IT IS THE BIDDER’S RESPONSIBILITY TO DEMONSTRATE THAT
SUFFICIENT WORK TO MEET THE GOAL WAS MADE AVAILABLE TO DBE FIRMS.
MADE AVAILABLE
BIDDER
NORMALLY
PERFORMS ITEM(S)
(Y/N)
ITEM(S) BROKEN
DOWN TO
FACILITATE
PARTICIPATION
(Y/N)
AMOUNT IN
DOLLARS
PERCENTAGE
OF
CONTRACT
NOTE: INFORMATION REQUIRED FOR THIS SECTION CONTINUED ON SHEET 5
ATTACH ADDITIONAL PAGES IF NECESSARY
Sheet 5 of 10
COMM0NWEALTH OF VIRGINIA
ADDITIONAL INFORMATION REGARDING ITEM(S) OF WORK THAT THE
BIDDER MADE AVAILABLE TO DBE FIRMS (Continued From Sheet 4)
ITEM(S) OF WORK MADE AVAILABLE, NAMES OF SELECTED FIRMS AND DBE STATUS,
DBEs THAT PROVIDED QUOTES, PRICE QUOTE FOR EACH FIRM, AND THE PRICE
DIFFERENCE FOR EACH DBE IF THE SELECTED FIRM IS NOT A DBE.
MADE
AVAILABLE(CONT.)
NAME OF
SELECTED
FIRM AND
VENDOR
NUMBER
DBE OR
NON-DBE
NAME OF
REJECTED
FIRM(S)
QUOTE IN
PRICE
DIFFERENCE IN
NOTE: ATTACH ADDITIONAL PAGES IF NECESSARY.
IF THE FIRM SELECTED FOR THE ITEM IS NOT A DBE, PROVIDE THE REASON(S) FOR
THE SELECTION ON A SEPARATE PAGE AND ATTACH.
PROVIDE NAMES, ADDRESSES, AND TELEPHONE NUMBERS FOR THE FIRMS LISTED
ABOVE.
Sheet 6 of 10
ADVERTISEMENTS OR PROOFS OF PUBLICATION.
NAMES AND DATES OF EACH PUBLICATION IN WHCH A REQUEST FOR DBE
PARTICIPATION FOR THE PROJECT WAS PLACED BY THE BIDDER. ATTACH COPIES OF
PUBLISHED ADVERTISEMENTS OR PROOFS OF PUBLICATION.
PUBLICATIONS DATES OF ADVERTISEMENT
COMM0NWEALTH OF VIRGINIA
NAMES OF AGENCIES CONTACTED TO PROVIDE ASSISTANCE
NAMES OF AGENCIES (SEE SPECIAL PROVISION FOR 107.15) AND THE DATES THESE
AGENCIES WERE CONTACTED TO PROVIDE ASSISTANCE IN CONTACTING,
RECRUITING, AND USING DBE FIRMS. IF THE AGENCIES WERE CONTACTED IN
WRITING, ATTACH COPIES OF SUPPORTING DOCUMENTS.
NAME OF AGENCY
METHOD AND DATE OF
CONTACT
RESULTS
Sheet 8 of 10
TECHNICAL ASSISTANCE AND INFORMATION PROVIDED TO DBEs
EFFORTS MADE TO PROVIDE INTERESTED DBEs WITH ADEQUATE INFORMATION
ABOUT THE PLANS, SPECIFICATIONS, AND REQUIREMENTS OF THE BID DOCUMENTS
TO ASSIST THE DBEs IN RESPONDING TO A SOLICITATION.
IDENTIFY THE DBEs ASSISTED, THE INFORMATION PROVIDED, AND THE DATE OF
CONTACT. ATTACH COPIES OF SUPPORTING DOCUMENTS.
DBEs ASSISTED INFORMATION PROVIDED DATE OF CONTACT
Sheet 9 of 10
EFFORTS MADE TO ASSIST DBEs OBTAIN BONDING, LINES OF CREDIT, INSURANCE, ETC.
EFFORTS MADE TO PROVIDE INTERESTED DBEs IN OBTAINING BONDING, LINES OF
CREDIT, INSURANCE, NECESSARY EQUIPMENT, SUPPLIES, MATERIALS, OR RELATED
ASSISTANCE OR SERVICES, EXCLUDING SUPPLIES AND EQUIPMENT THE
SUBCONTRACTOR PURCHASES OR LEASES FROM THE PRIME CONTRACTOR OR ITS
AFFILIATES.
IDENTIFY THE DBEs ASSISTED, THE ASSISTANCE OFFERED, AND THE DATES OF
SERVICES OFFERED AND PROVIDED. ATTACH COPIES OF SUPPORTING DOCUMENTS.
DBEs ASSISTED ASSISTANCE OFFERED DATES SERVICES OFFERED
AND/OR PROVIDED
Sheet 10 of 10
ADDITIONAL DATA TO SUPPORT DEMONSTRATION OF GOOD FAITH EFFORTS
ADDITIONAL DATA TO SUPPORT DEMONSTRATION OF GOOD FAITH EFFORTS
NOTE: ATTACH ADDITIONAL PAGES, IF NECESSARY
Form C-111 Rev. 2-15-11
MINIMUM DBE REQUIREMENTS
PROJECT NO.
FHWA NO.
* * * INSTRUCTIONS * * *
THIS FORM CAN BE USED BY THE CONTRACTOR TO SUBMIT THE NAMES OF DBE FIRMS TO BE UTILIZED ON THE PROJECT. THE CONTRACTOR SHALL INDICATE THE DESCRIPTION OF THE CATEGORY (S, M, SP or H) AND THE TYPE OF WORK THAT EACH DBE WILL PERFORM AND THE ALLOWABLE CREDIT PER ITEM(S). ADDITIONAL SHEETS TO SHOW THE ALLOWABLE CREDIT PER ITEM MAY BE ATTACHED IF NECESSARY. PLEASE NOTE: THE AMOUNT OF ALLOWABLE CREDIT FOR A DBE SUPPLIER IS 60% OF THE TOTAL COST OF THE MATERIALS OR SUPPLIES OBTAINED AND 100% FOR A DBE MANUFACTURER OF THE MATERIALS AND SUPPLIES OBTAINED.
A CONTRACTOR MAY COUNT 100% OF THE FEES PAID TO A DBE HAULER FOR THE DELIVERY OF MATERIALS AND SUPPLIES TO THE
PROJECT SITE, BUT NOT FOR THE COST OF THE MATERIALS AND SUPPLIES THEMSELVES.
DBE REQUIREMENT %
PERCENT ATTAINED BY BIDDER %
NAMES(S) AND CERTIFICATION NO.
OF DBE(S) TO BE USED
USED AS
SUBCONTR. (S)
MFG. (M)
SUPPLIER (SP)
HAULER (H)
TYPE OF WORK AND ITEM
NO(S)
$ AMOUNT OF
ALLOWABLE
CREDIT PER ITEM
TOTAL $
TOTAL CONTRACT VALUE $ x REQUIRED DBE % = $
I/WE CERTIFY THAT THE PROPOSED DBE(S) SUBMITTED WILL BE USED ON THIS CONTRACT AS STATED HEREON AND ASSURE THAT DURING THE LIFE OF THE CONTRACT. I/WE WILL MEET OR EXCEED THE PARTICIPATION ESTABLISHED HEREON BY THE
DEPARTMENT.
BY
BIDDER SIGNATURE
BY
TITLE DATE
Form C-112 Rev. 3-1-11
CERTIFICATION OF BINDING AGREEMENT
WITH
DISADVANTAGED BUSINESS ENTERPRISE FIRMS
Project No.:
Federal Project No.:
This form is to be submitted in accordance with the Department’s Special Provision for Section 107.15.
It is hereby certified by the below signed Contractors that there exists a written quote, acceptable to the parties involved preliminary to a binding subcontract agreement stating the details concerning the work to be performed and the price which will be paid for the aforementioned work. This document is not intended to, nor should it be construed to, contain the entire text of the agreement between the contracting parties. This document does not take the place of, nor may it be substituted for, an official subcontracting agreement in those situations that may require such an agreement. A copy of the fully executed subcontract agreement shall be submitted to the Engineer within fourteen (14) business days after contract execution.
It is further certified that the aforementioned mutually acceptable quote and fully executed subcontract agreement represent the entire agreement between the parties involved and that no conversations, verbal agreements, or other forms of non-written representations shall serve to add to, delete, or modify the terms as stated.
The prime Contractor further represents that the aforementioned mutually acceptable quote and fully executed subcontract agreement shall remain on file for a period of not less than one year following completion of the prime's contract with the Department or for such longer period as provisions of governing Federal or State law or regulations may require. For purposes of this form, the term Prime Contractor shall refer to any Contractor utilizing a DBE subcontractor, regardless of tier, in which they are claiming DBE credit toward the contract goal.
Contractors further jointly and severally represent that said binding agreement is for the performance of a "commercially useful function" as that term is employed in 49 C.F.R. Part 26.55 (c), (d).
TO BE SIGNED BY THE SUBCONTRACTOR TO THE PRIME CONTRACTOR, AND ANY LOWER TIER
SUBCONTRACTORS HAVING A CONTRACT WITH THE BELOW NAMED DBE FIRM
Prime Contractor
By:
Signature Title
Date:
First Tier Subcontractor if Applicable
Form C-112 Rev. 3-1-11
Second Tier
Third Tier
DBE Contractor
| Attach O |
| 3237TP - Attachment O - VDOT Forms |
| From C-48 |
| Form C-49 |
| THIS INFORMATION MUST BE SUBMITTED |
| Form C-111 |
| C-111 - MINIMUM DBE REQUIREMENTS |
Form C-112
| CONTRACT ID NUMBER: |
| PROJECT NUMBER: |
| FHWA NUMBER: |
| DISTRICT: |
| DATE BID SUBMITTED: |
| BIDDERS NAME: |
| TITLE: |
| VENDOR NUMBER: |
| DBE GOAL FROM BID PROPOSAL: |
| CONTRACT ID NO: |
| DATE SUBMITTED: |
| TITLE_2: |
| NAMES AND VENDOR NUMBERS OF DBEs SOLICITEDRow1: |
| DATE OF INITIAL SOLICITATIONRow1: |
| ITEMS OF WORKRow1: |
| FOLLOWUP METHODS AND DATESRow1: |
| CONTRACT ID NO_2: |
| DATE SUBMITTED_2: |
| BIDDER_2: |
| TITLE_3: |
| DBEs CALLEDRow1: |
| TELEPHONE NUMBERRow1: |
| DATE CALLEDRow1: |
| TIME CALLEDRow1: |
| CONTACT PERSON OR VOICE MAIL STATUSRow1: |
| CONTRACT ID NO_3: |
| DATE SUBMITTED_3: |
| BIDDER_3: |
| TITLE_4: |
| ITEMS OF WORK MADE AVAILABLERow1: |
| BIDDER NORMALLY PERFORMS ITEMS YNRow1: |
| ITEMS BROKEN DOWN TO FACILITATE PARTICIPATION YNRow1: |
| AMOUNT IN DOLLARSRow1: |
| PERCENTAGE OF CONTRACTRow1: |
| CONTRACT ID NO_4: |
| DATE SUBMITTED_4: |
| BIDDER_4: |
| TITLE_5: |
| ITEMS OF WORK MADE AVAILABLECONTRow1: |
| NAME OF SELECTED FIRM AND VENDOR NUMBERRow1: |
| DBE OR NONDBERow1: |
| NAME OF REJECTED FIRMSRow1: |
| QUOTE IN DOLLARSRow1: |
| PRICE DIFFERENCE IN DOLLARSRow1: |
| CONTRACT ID NO_5: |
| DATE SUBMITTED_5: |
| BIDDER_5: |
| PUBLICATIONSRow1: |
| DATES OF ADVERTISEMENTRow1: |
| Text4: |
| CONTRACT ID NO_6: |
| DATE SUBMITTED_6: |
| BIDDER_6: |
| NAME OF AGENCYRow1: |
| METHOD AND DATE OF CONTACTRow1: |
| RESULTSRow1: |
| Text6: |
| CONTRACT ID NO_7: |
| DATE SUBMITTED_7: |
| BIDDER_7: |
| DBEs ASSISTEDRow1: |
| INFORMATION PROVIDEDRow1: |
| DATE OF CONTACTRow1: |
| Text8: |
| CONTRACT ID NO_8: |
| DBE GOOD FAITH EFFORTS DOCUMENTATION: |
| BIDDER_8: |
| TITLE_6: |
| DBEs ASSISTEDRow1_2: |
| ANDOR PROVIDED: |
| CONTRACT ID NO_9: |
| DATE SUBMITTED_8: |
| BIDDER_9: |
| ADDITIONAL DATA TO SUPPORT DEMONSTRATION OF GOOD FAITH EFFORTSRow1: |
| Text11: |
| PROJECT NO: |
| FHWA NO: |
| undefined: |
| undefined_2: |
| OF DBES TO BE USED 1: |
| OF DBES TO BE USED 2: |
| OF DBES TO BE USED 3: |
| OF DBES TO BE USED 4: |
| OF DBES TO BE USED 5: |
| OF DBES TO BE USED 6: |
| HAULER H 1: |
| HAULER H 2: |
| HAULER H 3: |
| HAULER H 4: |
| HAULER H 5: |
| HAULER H 6: |
| NOS 1: |
| NOS 2: |
| NOS 3: |
| NOS 4: |
| NOS 5: |
| NOS 6: |
| CREDIT PER ITEM 1: |
| CREDIT PER ITEM 2: |
| CREDIT PER ITEM 3: |
| CREDIT PER ITEM 4: |
| CREDIT PER ITEM 5: |
| CREDIT PER ITEM 6: |
| undefined_3: |
| Text1: |
| REQUIRED DBE: |
| Text2: |
| undefined_4: |
| BIDDER: |
| Text3: |
| Prime Contractor: |
| Title: |
| Date: |
| Applicable: |
| Title_2: |
| Date_2: |
| Applicable_2: |
| Title_3: |
| Date_3: |
| Applicable_3: |
| Title_4: |
| Date_4: |
| DBE Contractor: |
| Title_5: |
| Date_5: |
File details come from the government source that posted it. Updated .