Attachment L - Richmond Schedule.pdf
PDF 174 KB Posted
- Attached to
- Richmond Partial Seismic Rehabilitation
- Solicitation number
- 148319
- Issued by
- Multnomah County, Oregon
About this file
This is a project schedule document for the Richmond Partial Seismic Rehabilitation construction project in Oregon. The schedule outlines a comprehensive timeline beginning with Richmond permitting activities from November 5, 2026, through January 27, 2027, followed by construction procurement activities spanning November 13, 2026, through March 3, 2027. Key procurement milestones include an RFP issuance period from November 13 through December 30, 2026, with a mandatory bid walk scheduled for December 1, 2026, and an addendum deadline of December 15, 2026. Sealed proposals are due on December 29, 2026, followed by a 14-day bid review period from December 30, 2026, through January 18, 2027. Interviews, if necessary, are scheduled for January 18-22, 2027, with a notice of intent to award on January 26, 2027, and board deadline on February 9, 2027. Board approval is anticipated on March 2, 2027, with the notice to proceed issued on March 3, 2027.
Construction is divided into two phases with a combined duration of 419 days extending from May 19, 2027, through December 25, 2028. Phase 1 construction runs from May 19, 2027, through December 23, 2027 (157 days), including mobilization in June 2027, nine weeks of active construction from June 14 through August 13, 2027, and demobilization through August 23, 2027, with substantial completion on that date and final completion on September 30, 2027. Phase 2 construction follows from May 16, 2028, through December 25, 2028 (160 days), with an identical structure of mobilization, nine weeks of construction, and demobilization activities, with substantial completion on August 22, 2028, and final completion on October 2, 2028. Each phase includes a three-month closeout period after final completion.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ID Task
Mode
Task Name Duration Start Finish
1 Richmond Permitting 3 mons Thu 11/5/26 Wed 1/27/27
2 Construction Procurement 79 days Fri 11/13/26 Wed 3/3/27
3 RFP Issued 6.8 wks Fri 11/13/26 Wed 12/30/26
4 Bid Walk 1 day Tue 12/1/26 Tue 12/1/26
5 Addendum deadline 1 day Tue 12/15/26 Tue 12/15/26
6 RFP due 1 day Tue 12/29/26 Tue 12/29/26
7 Bid Review 14 days Wed 12/30/26 Mon 1/18/27
8 Interviews (if necessary) 5 days Mon 1/18/27 Fri 1/22/27
9 Notice of intent to award 1 day Tue 1/26/27 Tue 1/26/27
10 Board Deadline 1 day Tue 2/9/27 Tue 2/9/27
11 Pre Contract Meeting- date tbd5 days Mon 2/22/27 Fri 2/26/27
12 Board Approval 1 day Tue 3/2/27 Tue 3/2/27
13 Notice to Proceed Issued 1 day Wed 3/3/27 Wed 3/3/27
14 Construction 419 days Wed 5/19/27 Mon 12/25/28
15 Construction Phase 1 157 days Wed 5/19/27 Thu 12/23/27
16 Ph 1 pre-construction meeting1 day Wed 5/19/27 Wed 5/19/27
17 mobilization 1 day Sat 6/12/27 Sat 6/12/27
18 construction 9 wks Mon 6/14/27 Fri 8/13/27
19 demobilization 6 days Mon 8/16/27 Mon 8/23/27
20 Ph 1 Substantial Completion1 day Mon 8/23/27 Mon 8/23/27
21 Ph 1 Final Completion 1 day Thu 9/30/27 Thu 9/30/27
22 Ph 1 Closeout 3 mons Fri 10/1/27 Thu 12/23/27
23 Construction Phase 2 160 days Tue 5/16/28 Mon 12/25/28
24 Ph 2 pre-construction meeting1 day Tue 5/16/28 Tue 5/16/28
25 mobilization 1 day Sat 6/10/28 Sat 6/10/28
26 construction 9 wks Mon 6/12/28 Fri 8/11/28
27 demobilization 6 days Mon 8/14/28 Mon 8/21/28
28 Ph 2 Substantial Completion1 day Tue 8/22/28 Tue 8/22/28
29 Ph 2 Final Completion 1 day Mon 10/2/28 Mon 10/2/28
30 Closeout 3 mons Tue 10/3/28 Mon 12/25/28
2629 1 4 7 10131619222528 1 4 7 1013161922252831 3 6 9 12151821242730 2 5 8 111417202326 1 4 7 1013161922252831 3 6 9 12151821242730 3 6 9 12151821242730 2 5 8 11141720232629 2 5 8 11141720232629 1 4 7 1013161922252831 3 6 9 12151821242730 3 6 9 12151821242730 2 5 8 11141720232629 2 5 8 11141720232629 1 4 7 1013161922252831 3 6 9 121518212427 1 4 7 1013161922252831 3 6 9 12151821242730 3 6 9 12151821242730 2 5 8 11141720232629 2 5 8 11141720232629 1 4 7 1013161922252831 3 6 9 12151821242730 3 6 9 12151821242730 2 5 8 11141720232629 2 5 8 11141720232629
November 2026 December 2026 January 2027 February 2027 March 2027 April 2027 May 2027 June 2027 July 2027 August 2027 September 2027 October 2027 November 2027 December 2027 January 2028 February 2028 March 2028 April 2028 May 2028 June 2028 July 2028 August 2028 September 2028 October 2028 November 2028 December 2028
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Project: Richmond Seismic & Ro
Date: Tue 10/27/26
Attachment L