Attachment L - Richmond Schedule.pdf

PDF 174 KB Posted

Attached to
Richmond Partial Seismic Rehabilitation
Solicitation number
148319
Issued by
Multnomah County, Oregon

About this file

This is a project schedule document for the Richmond Partial Seismic Rehabilitation construction project in Oregon. The schedule outlines a comprehensive timeline beginning with Richmond permitting activities from November 5, 2026, through January 27, 2027, followed by construction procurement activities spanning November 13, 2026, through March 3, 2027. Key procurement milestones include an RFP issuance period from November 13 through December 30, 2026, with a mandatory bid walk scheduled for December 1, 2026, and an addendum deadline of December 15, 2026. Sealed proposals are due on December 29, 2026, followed by a 14-day bid review period from December 30, 2026, through January 18, 2027. Interviews, if necessary, are scheduled for January 18-22, 2027, with a notice of intent to award on January 26, 2027, and board deadline on February 9, 2027. Board approval is anticipated on March 2, 2027, with the notice to proceed issued on March 3, 2027.

Construction is divided into two phases with a combined duration of 419 days extending from May 19, 2027, through December 25, 2028. Phase 1 construction runs from May 19, 2027, through December 23, 2027 (157 days), including mobilization in June 2027, nine weeks of active construction from June 14 through August 13, 2027, and demobilization through August 23, 2027, with substantial completion on that date and final completion on September 30, 2027. Phase 2 construction follows from May 16, 2028, through December 25, 2028 (160 days), with an identical structure of mobilization, nine weeks of construction, and demobilization activities, with substantial completion on August 22, 2028, and final completion on October 2, 2028. Each phase includes a three-month closeout period after final completion.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ID Task

Mode

Task Name Duration Start Finish

1 Richmond Permitting 3 mons Thu 11/5/26 Wed 1/27/27

2 Construction Procurement 79 days Fri 11/13/26 Wed 3/3/27

3 RFP Issued 6.8 wks Fri 11/13/26 Wed 12/30/26

4 Bid Walk 1 day Tue 12/1/26 Tue 12/1/26

5 Addendum deadline 1 day Tue 12/15/26 Tue 12/15/26

6 RFP due 1 day Tue 12/29/26 Tue 12/29/26

7 Bid Review 14 days Wed 12/30/26 Mon 1/18/27

8 Interviews (if necessary) 5 days Mon 1/18/27 Fri 1/22/27

9 Notice of intent to award 1 day Tue 1/26/27 Tue 1/26/27

10 Board Deadline 1 day Tue 2/9/27 Tue 2/9/27

11 Pre Contract Meeting- date tbd5 days Mon 2/22/27 Fri 2/26/27

12 Board Approval 1 day Tue 3/2/27 Tue 3/2/27

13 Notice to Proceed Issued 1 day Wed 3/3/27 Wed 3/3/27

14 Construction 419 days Wed 5/19/27 Mon 12/25/28

15 Construction Phase 1 157 days Wed 5/19/27 Thu 12/23/27

16 Ph 1 pre-construction meeting1 day Wed 5/19/27 Wed 5/19/27

17 mobilization 1 day Sat 6/12/27 Sat 6/12/27

18 construction 9 wks Mon 6/14/27 Fri 8/13/27

19 demobilization 6 days Mon 8/16/27 Mon 8/23/27

20 Ph 1 Substantial Completion1 day Mon 8/23/27 Mon 8/23/27

21 Ph 1 Final Completion 1 day Thu 9/30/27 Thu 9/30/27

22 Ph 1 Closeout 3 mons Fri 10/1/27 Thu 12/23/27

23 Construction Phase 2 160 days Tue 5/16/28 Mon 12/25/28

24 Ph 2 pre-construction meeting1 day Tue 5/16/28 Tue 5/16/28

25 mobilization 1 day Sat 6/10/28 Sat 6/10/28

26 construction 9 wks Mon 6/12/28 Fri 8/11/28

27 demobilization 6 days Mon 8/14/28 Mon 8/21/28

28 Ph 2 Substantial Completion1 day Tue 8/22/28 Tue 8/22/28

29 Ph 2 Final Completion 1 day Mon 10/2/28 Mon 10/2/28

30 Closeout 3 mons Tue 10/3/28 Mon 12/25/28

2629 1 4 7 10131619222528 1 4 7 1013161922252831 3 6 9 12151821242730 2 5 8 111417202326 1 4 7 1013161922252831 3 6 9 12151821242730 3 6 9 12151821242730 2 5 8 11141720232629 2 5 8 11141720232629 1 4 7 1013161922252831 3 6 9 12151821242730 3 6 9 12151821242730 2 5 8 11141720232629 2 5 8 11141720232629 1 4 7 1013161922252831 3 6 9 121518212427 1 4 7 1013161922252831 3 6 9 12151821242730 3 6 9 12151821242730 2 5 8 11141720232629 2 5 8 11141720232629 1 4 7 1013161922252831 3 6 9 12151821242730 3 6 9 12151821242730 2 5 8 11141720232629 2 5 8 11141720232629

November 2026 December 2026 January 2027 February 2027 March 2027 April 2027 May 2027 June 2027 July 2027 August 2027 September 2027 October 2027 November 2027 December 2027 January 2028 February 2028 March 2028 April 2028 May 2028 June 2028 July 2028 August 2028 September 2028 October 2028 November 2028 December 2028

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Project: Richmond Seismic & Ro

Date: Tue 10/27/26

Attachment L

File details come from the government source that posted it. Updated .