Attachment J01c Specifications Vol 1.pdf
PDF 4 MB Posted
- Attached to
- Pine Ridge, Kyle, Wanblee Multiple Duplex Sitework & Foundations Federal contract opportunity
- Solicitation number
- 75H701-24-R-00039
About this file
This document is a Solicitation Notice for a construction project to procure various construction tasks, including site preparation, utility installations, foundation and driveway installation, final connections, and garage building for 12 duplexes in Pine Ridge, Kyle, and Wanblee, South Dakota. The solicitation number is 75H701-24-R-00039 and the contract is being procured by the Department of Health and Human Services Indian Health Service as a Firm Fixed Price contract under FAR Part 36. The anticipated project magnitude is between $5,000,000 and $10,000,000 and the Period of Performance is 730 calendar days. The solicitation will be procured as a Request for Proposal using Lowest Price Technically Acceptable evaluation criteria. A site visit is planned, and small businesses under $45 million average annual revenue are encouraged to participate. Registration in the System for Award Management is mandatory.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| A00001-75H70124R00039 Attachment CHANGES SHOWN.pdf | ||
| A00001-75H70124R00039.pdf | ||
| A00001-75H70124R00039 Attachment CLEAN.pdf | ||
| Attachment J02 Wage Determination.pdf | ||
| Attachment J01a Duplex Employee Housing Site Civil Package.pdf | ||
| J04 Company Specialized Experience Construction Form.docx | DOCX document | |
| Attachment J01d Specifications Vol 2.pdf | ||
| J03 Self Performed Calculation Sheet (Construction).pdf | ||
| J05 Past Performance Questionnaire.docx | DOCX document | |
| B01 RFP 75H701-24-R-00039.pdf | ||
| Attachment J01b Duplex Employee Housing Foundation Install Package.pdf | ||
| Attachment J01e Geotechnical Reports.pdf |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Department of Health and Human Services
Indian Health Service Duplex Building and Site Locations
IHS Great Plains Area, South Dakota
CONSTRUCTION DOCUMENTS
Project Specifications
Volume 1
US DEPARTMENT OF HEALTH AND HUMAN SERVICES
INDIAN HEALTH SERVICE
February 23, 2024
DUPLEX BUILDINGS AND SITE LOCATIONS
CONSTRUCTION DOCUMENTS 0 - 1
Project Specifications - Table of Contents
VOLUME 1
000105 Certifications
DIVISION 01 - GENERAL REQUIREMENTS
011000 Summary
013100 Project Management and Coordination
013200 Construction Progress Documentation
013233 Photographic Documentation
013300 Submittal Procedures
014000 Quality Requirements
015000 Temporary Facilities and Controls
017300 Execution
017329 Cutting and Patching
017419 Construction Waste Management and Disposal
017700 Closeout Procedures
017823 Operation and Maintenance Data
017839 Project Record Documents
017900 Demonstration and Training
019113 General Commissioning Requirements
DIVISION 03 - CONCRETE
030130 Maintenance of Cast-In-Place Concrete
031000 Concrete Forming and Accessories
032000 Concrete Reinforcing
033000 Cast-in-place Concrete
033543 Polished Concrete Finishing
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
061000 Rough Carpentry
061600 Sheathing
061753 Shop Fabricated Wood Trusses
064116 Plastic-Laminate-Clad Architectural Cabinets
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
071113 Bituminous Dampproofing
071416 Cold Fluid-Applied Waterproofing
072100 Thermal Insulation
072715 Nonbituminous Self-Adhering Sheet Air Barriers
074113 Standing Seam Metal Roof Panels
074623 Engineered Wood Siding
076200 Sheet Metal Flashing and Trim
079200 Joint Sealants
DIVISION 08 - OPENINGS
CONSTRUCTION DOCUMENTS 0 - 2
081416 Flush Wood Doors
083113 Access Doors and Frames
087100 Door Hardware
088000 Glazing
DIVISION 09 - FINISHES
092216 Non-Structural Metal Framing
092900 Gypsum Board
093013 Ceramic Tiling
096513 Resilient Base and Accessories
096525 Resilient Tile Flooring – LVT
099113 Exterior Painting
099123 Interior Painting
DIVISION 10 - SPECIALTIES
102800 Toilet, Bath, and Laundry Accessories
104416 Fire Extinguishers
DIVISION 11 - EQUIPMENT
113013 Residential Appliances
DIVISION 12 - FURNISHINGS
122413 Roller Window Shades
123661.16 Solid Surfacing Countertops
DIVISION 13 – SPECIAL CONSTRUCTION
Not Used
VOLUME 2
003132 Geotechnical Data
024119 Selective Demolition
DIVISION 21 – FIRE PROTECTION
211300 Fire Protection Systems
DIVISION 22 - PLUMBING
220500 Plumbing Basic Materials and Methods
220517 Sleeves and Sleeve Seals for Plumbing Piping
220518 Escutcheons for Plumbing Piping
220523.12 Ball Valves for Plumbing Piping
220523.14 Check Valves for Plumbing Piping
220529 Hangers and Supports for Plumbing Piping and Equipment
220548.13 Vibration Controls for Plumbing Piping and Equipment
220553 Identification for Plumbing Piping and Equipment
220719 Plumbing Piping Insulation
221116 Domestic Water Piping
221119 Domestic Water Piping Specialties
221316 Sanitary Waste and Vent Piping
221319 Sanitary Waste Piping Specialties
CONSTRUCTION DOCUMENTS 0 - 3
224100 Residential Plumbing Fixtures
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
230500 HVAC Basic Materials and Methods
230513 Common Motor Requirements for HVAC Equipment
230517 Sleeves and Sleeve Seals for HVAC Piping
230529 Hangers and Supports for HVAC Piping and Equipment
230548.13 Vibration Controls for HVAC
230553 Identification for HVAC Piping and Equipment
230593 Testing, Adjusting, and Balancing for HVAC
230713 Duct Insulation
233113 Metal Ducts
233300 Air Duct Accessories
233346 Flexible Ducts
233713.13 Air Diffusers
233713.23 Registers and Grilles
DIVISION 26 - ELECTRICAL
260519 Low Voltage Electrical Power Conductors and Cables
260523 Control-Voltage Electrical Power Cables
260526 Grounding and Bonding for Electrical Systems
260529 Hangers and Supports for Electrical Systems
260533 Raceways and Boxes for Electrical Systems
260544 Sleeves and Sleeve Seals for Electrical Raceways and Cabling
260553 Identification for Electrical Systems
260923 Lighting Control Devices
262416 Panelboards
262726 Wiring Devices
262813 Fuses
262816 Enclosed Switches and Circuit Breakers
265119 LED Interior Lighting
265213 Emergency and Exit Lighting
265619 LED Exterior Lighting
DIVISION 27 - COMMUNICATIONS
270526 Grounding and Bonding for Communication Systems
270533 Identification for Communication Systems
271513 Communications Copper Horizontal Cabling
DIVISION 28 – SECURITY AND FIRE ALARM & DETECTION
282000 Video Surveillance
283100 Fire Alarm Detection Systems
DIVISION 31 - EARTHWORK
311000 Site Clearing
312000 Earth Moving
312333 Trench Excavation and Backfill
312510 Temporary Erosion Control
DIVISION 32 - EXTERIOR IMPROVEMENTS
321123 Crushed Aggregate Base Course
CONSTRUCTION DOCUMENTS 0 - 4
321216 Asphalt Paving
321313 Concrete Paving
323113 Chain Link Fences and Gates
329113 Soil Preparation
329220 Native Seeding
DIVISION 33 - UTILITIES
331100 Water Distribution Systems
333100 Sanitary Sewer Systems
333213 Packaged Wastewater Pumping Station
333400 Sewer Force Mains
334200 Stormwater Conveyance
APPENDIX A
Geotechnical Engineering Report
END OF TABLE OF CONTENTS
95% CONSTRUCTION DOCUMENTS 105 - 1
I hereby certify that this technical submission was prepared by me or under my direct supervision and responsible charge in accordance with the rules and regulations governing Architects and Engineers practicing in the State of South Dakota. I am a duly registered Professional in the State of South Dakota.
Discipline: Architecture
Name: Trevor Mitchell Frank
Registration No.: 11704
Expiration: 05/31/2025
DUPLEX BUILDING AND SITE LOCATIONS CERTIFICATIONS
CONSTRUCTION DOCUMENTS 011000 - 1
I hereby certify that this technical submission was prepared by me or under my direct supervision and responsible charge in accordance with the rules and regulations governing Architects and Engineers practicing in the State of South Dakota. I am a duly registered Professional in the State of South Dakota.
Discipline: Structural
Name: Steven J Halewski
Registration No.: 15599
Expiration: 01/31/2024
Signature
I hereby certify that this technical submission was prepared by me or under my direct supervision and responsible charge in accordance with the rules and regulations governing Architects and Engineers practicing in the State of South Dakota. I am a duly registered Professional in the State of South Dakota.
Discipline:
Name: James Dale Hayson
Registration No.: 11365
Expiration: 07.31.2024
I hereby certify that this technical submission was prepared by me or under my direct supervision and responsible charge in accordance with the rules and regulations governing Architects and Engineers practicing in the State of South Dakota. I am a duly registered Professional in the State of South Dakota.
Discipline: Mechanical
Name: Nicholas Brula
Registration No.: 9965
Expiration: 10/31/2025
NICHOLAS J.
BRULA
S
O
U
T
H
D
A
K
O
T
A
R
E
G
N
O
L
I C
E N
S
E
D
P
R
O
F
E
S S
I O
N
A
L
N
G
I
N E
R
I hereby certify that this technical submission was prepared by me or under my direct supervision and responsible charge in accordance with the rules and regulations governing Engineers practicing in the State of South Dakota. I am a duly licensed Professional Engineer in the State of South Dakota.
Discipline: Electrical
I hereby certify that this technical submission was prepared by me or under my direct supervision and responsible charge in accordance with the rules and regulations governing Architects and Engineers practicing in the State of South Dakota. I am a duly registered Professional in the State of South Dakota.
Discipline: Fire Protection
Name:
Registration No.:
Expiration:
DUPLEX BUILDING AND SITE LOCATIONS SUMMARY
SECTION 011000
SUMMARY
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Project information.
2. Work covered by Contract Documents.
3. Use of premises.
4. Work restrictions.
5. Specification formats and conventions.
1.2 PROJECT INFORMATION
A. Project Identification: US Department of Health and Human Services, Indian Health Service Employee Housing.
1. Project Location: Various locations, South Dakota.
B. Owner (Government): US Department of Health and Human Services – Indian Health Service, IHS Great Plains Area.
C. Architect: Short Elliott Hendrickson Inc. (SEH).
1. Architect's Representative: Matt Massa, Project Manager.
D. Web-Based Project Software: Project software will be used for purposes of managing communication and documents during the construction stage.
1. See Section 013100 "Project Management and Coordination." for requirements for using web-based Project software.
1.3 WORK COVERED BY CONTRACT DOCUMENTS
A. The Work of Project is defined by the Contract Documents and includes, but is not limited to, the following:
1. The Indian Health Service (HIS) is an agency within the U.S. Department of Health and Human Services that provides comprehensive, culturally appropriate health services to American Indian and Alaskan Native people. The project consists of a number of duplex residences for staff of local health service facilities throughout the IHS Great Plains Area in South Dakota. The 2,375 SF wood frame, two-bedroom duplexes are of two types, one with a basement and the other slab-on-grade, depending on soils conditions. Each unit has an attached garage. The project includes all associated mechanical, electrical, and site development work, as well as other Work indicated in the Contract Documents.
CONSTRUCTION DOCUMENTS 011000 - 2
B. Type of Contract:
1. Project will be constructed under a single prime contract.
1.4 USE OF PREMISES
A. Contractor shall have limited use of premises for construction operations as indicated on Drawings by the Contract limits and in the Section. Government will provide on-site areas for temporary facilities, contractor parking and storage of materials as well as the immediate work area for construction.
B. Schedule and sequence operations necessary to complete the work, including coordination with other crafts relative to the Contractor's requirements. Schedule Work in such manner as to avoid delays in overall construction and permit proper installation of work.
C. Limit use of premises to areas within the Contract limits and as allowed by the Government. Do not disturb portions of Project site beyond areas in which the Work is indicated.
1. Government Occupancy: Allow for Government occupancy and operations at Project site.
Government personnel will be continuously occupying areas adjacent to the work area.
Conduct work in a manner that will minimize needs for disruption of normal Government operations. Provide minimum 72 hours advance notice to Government of activities that will impact normal Government operations. Secure Government’s written approval of activities that will impact normal Government operations to avoid delays in overall construction and permit proper installation or work.
2. Driveways and Entrances: Keep driveways, parking and entrances serving premises clear and available to Government, Government employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
a. Schedule deliveries to minimize use of driveways and entrances.
b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
1.5 WORK RESTRICTIONS
A. On-Site Work Hours: Work shall be generally performed during normal business working hours of 7:30 a.m. to 5:00 p.m., Monday through Friday, except when otherwise indicated.
1. Work Hours outside normal business hours may be allowed as coordinated with the Government.
B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed without prior consent from the Government. Submit requests 48 hours in advance of the work to the Government for approval.
C. No signs or advertisements shall be displayed on the construction site or within the premises unless approved by the Government.
D. Existing Utilities
1. Existing Utilities: Notify Government and utility companies of proposed locations and times for excavation.
CONSTRUCTION DOCUMENTS 011000 - 3
2. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.
3. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.
E. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:
1. Notify Government not less than two business days in advance of proposed utility interruptions.
2. Do not proceed with utility interruptions without Government’s written permission.
F. Smoking is not permitted within any building or within 25 feet of entrances, operable windows, or outdoor air intakes.
1.6 SPECIFICATION FORMATS AND CONVENTIONS
A. Specification Format: The Specifications are organized into Divisions and Sections using the CSI/CSC's "Masterformat" numbering system.
1. Division 01 – General Requirements: Sections in Division 01 govern the execution of the Work of all Sections in the Specifications.
B. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations.
These conventions are as follows:
1. Abbreviated Language: Language used in the Specifications and other Contract Documents is abbreviated. Words and meanings shall be interpreted as appropriate.
Words implied, but not stated, shall be inferred as the sense requires. Singular words shall be interpreted as plural, and plural words shall be interpreted as singular where applicable as the context of the Contract Documents indicates.
2. Imperative mood and streamlined language are generally used in the Specifications.
Requirements expressed in the imperative mood are to be performed by Contractor.
Occasionally, the indicative or subjunctive mood may be used in the Section Text for clarity to describe responsibilities that must be fulfilled indirectly by Contractor or by others when so noted.
a. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.
C. Terminology: All references to “Owner” and “Contracting Officer” shall be replaced with the term “Government” (when referring to the person acting for the Government). All references to “Architect” or “Engineer” shall be replaced with the term “Government” (when referring to the person who is to be contacted regarding the project).
1.7 Buy American Act (BAA)
A. All products incorporated into the Work are required to comply with the Buy American Act (BAA).
For any non-BAA-compliant product that may be specified or shown on the Drawings, the Contractor shall submit an equal BAA-compliant product substitution for approval.
CONSTRUCTION DOCUMENTS 011000 - 4
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 011000
DUPLEX BUILDING AND SITE LOCATIONS PROJECT MANAGEMENT AND COORDINATION
CONSTRUCTION DOCUMENTS 013100 - 1
SECTION 013100
PROJECT MANAGEMENT AND COORDINATION
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
1. Definitions.
2. Informational submittals.
3. Coordination procedures.
4. Coordination drawings.
5. Project meetings.
6. Requests for Interpretation (RFIs).
7. Digital project management procedures.
8. Environmental coordination.
9. Permits.
1.2 DEFINITIONS
A. Request for Interpretation (RFI): Request from Contractor seeking interpretation or clarification of the Contract Documents.
1.3 INFORMATIONAL SUBMITTALS
A. Subcontract List: Prepare a written summary identifying individuals or firms proposed for each portion of the Work, including those who are to furnish products or equipment fabricated to a special design. Include the following information in tabular form:
1. Name, address, telephone number, and email address of entity performing subcontract or supplying products.
2. Number and title of related Specification Section(s) covered by subcontract.
1.4 COORDINATION PROCEDURES
A. Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections that depend on each other for proper installation, connection, and operation.
B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
1. Prepare similar memoranda for Government and separate contractors if coordination of their Work is required.
CONSTRUCTION DOCUMENTS 013100 - 2
C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:
1. Preparation of Contractor's Construction Schedule.
2. Preparation of the Schedule of Values.
3. Installation and removal of temporary facilities and controls.
4. Delivery and processing of submittals.
5. Progress meetings.
6. Preinstallation conferences.
7. Project closeout activities.
8. Startup and adjustment of systems.
1.5 COORDINATION DRAWINGS
A. Coordination Drawings: Prepare Coordination Drawings according to requirements in individual Sections and where installation is not completely indicated on the Shop drawings, where limited space availability necessitates coordination, or if coordination is required for installation of products and materials fabricated by separate entities.
1. Content: Project-specific information, drawn accurately to scale. Do not base Coordination Drawings on reproductions of the Contract Documents or standard printed data. Include the following information, as applicable:
a. Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, and electrical systems.
b. Indicate dimensions shown on the Contract Drawings and make specific note of dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements. Provide alternate sketches to Government for resolution of such conflicts. Minor dimension changes and difficult installations will not be considered changes to the Contract.
c. Indicate space requirements for routine maintenance and for anticipated replacement of components during the life of the installation.
d. Show location and size of access doors required for access to concealed dampers, valves, and other controls.
B. Coordination Digital Data Files: Prepare coordination digital data files according to the following requirements:
1. File Preparation Format: Same digital data software program, version, and operating system as original Drawings.
2. File Submittal Format: Submit or post coordination drawing files using Portable Document Format (PDF) file format.
3. Government will furnish Contractor one set of digital data files of drawings and models, according to Section 1.8, prepared by Government, for use in preparing coordination digital data files.
1.6 PROJECT MEETINGS
A. General: Schedule and conduct meetings and conferences at Project site, unless otherwise indicated.
CONSTRUCTION DOCUMENTS 013100 - 3
1. Attendees: Inform participants and others involved, and individuals whose presence is required, of date and time of each meeting. Notify Government of scheduled meeting dates and times.
2. Agenda: Prepare the meeting agenda. Distribute the agenda to all invited attendees.
3. Minutes: Record significant discussions and agreements. Distribute the meeting minutes to everyone concerned, including Government, within three days of the meeting.
B. Preconstruction Conference: Schedule a preconstruction conference before starting construction, at a time convenient to Government, but no later than 15 days after execution of the Agreement. Hold the conference at Project site or other convenient location. Conduct the meeting to review responsibilities and personnel assignments, review required work, project drawings, specifications, construction schedules, payroll, payments, and administrative provisions of the Contract. Be prepared to summarize and explain procedures planned for the project and present specified preconstruction submittals.
1. Attendees: Authorized representatives of Government, Contractor and its superintendent;
major subcontractors; suppliers; and other concerned parties shall attend the conference.
All participants at the conference shall be familiar with Project and authorized to conclude matters relating to the Work. The mechanical and electrical subcontractor’s attendance will be required.
2. Agenda: Discuss items of significance that could affect progress, including the following:
a. Tentative construction schedule.
b. Critical work sequencing and long-lead items.
c. Designation of key personnel and their duties.
d. Procedures for processing field decisions and Modifications.
e. Procedures for RFIs.
f. Procedures for testing and inspecting.
g. Procedures for processing Applications for Payment.
h. Distribution of the Contract Documents.
i. Submittal procedures.
j. Preparation of Record Documents.
k. Use of the premises.
l. Work restrictions.
m. Government occupancy requirements.
n. Responsibility for temporary facilities and controls.
o. Construction waste management and recycling.
p. Parking availability, office, work, and storage areas.
q. Equipment deliveries and priorities.
r. First aid.
s. Security.
t. Progress cleaning.
u. Working hours.
3. Minutes: Record and distribute meeting minutes.
C. Preinstallation Conferences: Conduct a preinstallation conference at Project site before each construction activity that requires coordination with other construction.
1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by the installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend the meeting. Advise Government of scheduled meeting dates.
2. Agenda: Review progress of other construction activities and preparations for the particular activity under consideration, including requirements for the following:
CONSTRUCTION DOCUMENTS 013100 - 4
a. Contract Documents.
b. Options.
c. Related RFIs and Related Modifications.
d. Purchases, Deliveries, Submittals.
e. Review of mockups.
f. Possible conflicts and/or Compatibility problems.
g. Time schedules and Weather limitations.
h. Manufacturer's written recommendations.
i. Warranty requirements.
j. Acceptability of substrates.
k. Space and access limitations.
l. Regulations of authorities having jurisdiction.
m. Testing and inspecting requirements.
n. Installation procedures.
o. Coordination with other work.
p. Required performance results.
q. Protection of adjacent work.
r. Protection of construction and personnel.
3. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.
4. Reporting: Distribute minutes of the meeting to each party present and to parties who should have been present.
5. Do not proceed with installation if the conference cannot be successfully concluded.
Initiate whatever actions are necessary to resolve impediments to performance of the Work and reconvene the conference at earliest feasible date.
D. Progress Meetings: Conduct progress meetings at weekly intervals. Hold the meetings at the project site. Coordinate dates of meetings with preparation of payment requests. Additional progress meetings may be requested by either the Government or Contractor.
1. Attendees: In addition to representatives of Government, each contractor, subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented. All participants shall be familiar with Project and authorized to conclude matters relating to the Work.
2. Agenda: Review and correct or approve minutes of previous progress meeting. Review items of significance that could affect progress. Include as appropriate:
a. Contractor's Construction Schedule: Review progress since the last meeting.
Determine whether each activity is on time, ahead or behind schedule. Determine how construction behind schedule will be expedited; secure commitments from parties involved to do so. Discuss whether schedule revisions are required to ensure that current and subsequent activities will be completed within the Contract Time.
1) Review schedule for next period.
b. Review present and future needs of each entity present, including the following:
1) Interface requirements.
2) Sequence of operations.
3) Status of submittals.
4) Deliveries.
5) Off-site fabrication.
6) Access.
7) Site utilization.
8) Temporary facilities and controls.
9) Work hours.
10) Hazards and risks.
CONSTRUCTION DOCUMENTS 013100 - 5
11) Progress cleaning.
12) Quality and work standards.
13) Status of correction of deficient items.
14) Field observations.
15) RFIs.
16) Status of proposal requests.
17) Pending changes.
18) Status of Modifications.
19) Pending claims and disputes.
20) Documentation of information for payment requests.
c. Reporting: Record the meeting minutes. Distribute minutes of the meeting to each party present and to parties who should have been present.
d. Schedule Updating: Revise Contractor's Construction Schedule after each progress meeting where revisions to the schedule have been made or recognized. Issue revised schedule concurrently with the report of each meeting.
1.7 REQUESTS FOR INTERPRETATION (RFIs)
A. Procedure: Immediately on discovery of the need for interpretation of the Contract Documents, and if not possible to request interpretation at Project meeting, prepare and submit an RFI in the form specified.
1. RFIs shall originate with Contractor. RFIs submitted directly by entities other than Contractor will be returned with no response.
2. Coordinate and submit RFIs in a prompt manner so as to avoid delays in Contractor's work or work of subcontractors.
B. Content of the RFI: Include a detailed, legible description of item needing interpretation and the following:
1. Project name.
2. Date.
3. Name of Contractor.
4. Name of Contracting Officer.
5. RFI number, numbered sequentially.
6. Specification Section number and title and related paragraphs, as appropriate.
7. Drawing number and detail references, as appropriate.
8. Field dimensions and conditions, as appropriate.
9. Contractor's suggested solution(s). If Contractor's solution(s) impact the Contract Time or the Contract Sum, Contractor shall state impact in the RFI.
10. Contractor's signature.
11. Requested date for response.
12. Attachments: Include drawings, descriptions, measurements, photos, Product Data, Shop
Drawings, and other information necessary to fully describe items needing interpretation.
Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.
C. RFI Forms: Software-generated form with substantially the same content as indicated above, acceptable to Government.
1. Identify each page of attachments with the RFI number and sequential page number.
CONSTRUCTION DOCUMENTS 013100 - 6
D. Government's Action: Government will review each RFI, determine action required, and return it.
Allow fifteen calendar days for Government’s response for each RFI. RFIs received after 1:00 p.m. will be considered as received the following working day.
1. The following RFIs will be returned without action:
a. Requests for approval of submittals.
b. Requests for approval of substitutions.
c. Requests for approval of Contractor’s means and methods.
d. Requests for coordination information already indicated in the Contract Documents.
e. Requests for adjustments in the Contract Time or the Contract Sum.
f. Requests for interpretation of Government’s actions on submittals.
g. Incomplete RFIs or RFIs with numerous errors.
2. Government’s action may include a request for additional information, in which case Government’s time for response will start again.
E. On receipt of Government’s action, update the RFI log and immediately distribute the RFI response to affected parties. Review response and notify Government within seven days if Contractor disagrees with response.
F. RFI Log: Prepare, maintain, and submit a tabular log of RFIs organized by the RFI number.
Submit log monthly. Include the following:
1. Project name.
2. Name and address of Contractor.
3. Name and address of Contracting Officer.
4. RFI number including RFIs that were dropped and not submitted.
5. RFI description.
6. Date the RFI was submitted.
7. Date Government’s response was received.
8. Identification of related bilateral or unilateral modifications, extensions, and changes in scope, as appropriate.
1.8 DIGITAL PROJECT MANAGEMENT PROCEDURES
A. Use of Government's Digital Data Files: Digital data files of Government's CAD drawings will be provided by Government for Contractor's use during construction.
1. Digital data files may be used by Contractor in preparing coordination drawings, Shop Drawings, and Project record Drawings.
2. Government makes no representations as to the accuracy or completeness of digital data files as they relate to Contract Drawings.
3. Digital Drawing Software Program: Drawings are available in AutoCAD Civil 3D 2018.
B. PDF Document Preparation: PDFs are required to be submitted shall be prepared as follows:
1. Assemble complete submittal package into a single indexed file incorporating submittal requirements of a single Specification Section and transmittal form with links enabling navigation to each item.
2. Name file with submittal number or other unique identifier, including revision identifier.
3. Certifications: Where digitally submitted certificates and certifications are required, provide a digital signature with digital certificate on where indicated.
CONSTRUCTION DOCUMENTS 013100 - 7
1.9 ENVIRONMENTAL COORDINATION
A. Contractor’s Environmental Manager: Designate an on-site party responsible for overseeing the Contractor’s conformance to environmental goals for the project and implementing procedures for environmental protection.
1. Qualifications: Minimum 3 years Construction experience on projects of similar size and scope; with environmental procedures similar to those of this project; must be familiar with environmental regulations applicable to construction operations.
2. Responsibilities: Responsibilities shall include:
a. Ensure compliance with applicable Federal, State, and local environmental regulations, including maintaining required documentation.
b. Implement the Waste Management Plan (WMP).
c. Implement the Indoor Air Quality (IAQ) Management Plan.
d. Present an overview of environmental issues and summarize site specific procedures relating to management plans at the Preconstruction conference.
e. Provide training for Contractor personnel in accordance with their position requirements.
f. Monitor and document environmental procedures.
B. Perform project quality control in accordance with specified requirements including:
1. Quality Requirements.
2. Regulatory Requirements.
3. Indoor Air Quality (IAQ) Management.
4. Noise & Acoustics Management.
5. Temporary Storm Water Pollution Management.
6. Construction Waste Management.
7. Compliance with environmental regulations: As specified in Regulatory Requirements.
Submit Contractor 40 CFR employee training records upon request of Government.
C. Provide documentation for environmental procedures as specified herein.
1.10 PERMITS
A. General:
1. Permits and Responsibilities: The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses and permits, and for complying with any Federal, State and municipal laws, codes, and regulations applicable to the performance of the work. Contractor will apply, obtain, and provide payment for permits. The Contractor shall also be responsible for all damages to persons or property that occur as a result of the Contractor’s fault or negligence. The Contractor shall also be responsible for all materials delivered and work performed until completion and acceptance of the work.
2. For the purpose of this contract the Contractor will not be considered an agent of the Government. Therefore the Contractor will comply with the appropriate Federal, State and local laws.
B. Coordination with Agencies with Jurisdiction for Utility Connections: Contact the Agency(ies) with Jurisdiction as needed and sufficiently in advance to avoid delaying the work: Coordinate meetings, reporting requirements, inspections, or any other requirements.
CONSTRUCTION DOCUMENTS 013100 - 8
PART 2 - PRODUCTS (Not Used)
END OF SECTION 013100
DUPLEX BUILDING AND SITE LOCATIONS CONSTRUCTION PROGRESS DOCUMENTATION
CONSTRUCTION DOCUMENTS 013200 - 1
SECTION 013200
CONSTRUCTION PROGRESS DOCUMENTATION
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes administrative and procedural requirements for documenting the progress of construction during performance of the Work, including the following:
1. Contractor's Construction Schedule.
2. Submittals Schedule.
3. Daily construction reports.
4. Field condition reports.
1.2 DEFINITIONS
A. Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling the construction project. Activities included in a construction schedule consume time and resources.
1. Critical activities are activities on the critical path. They must start and finish on the planned early start and finish times.
2. Predecessor Activity: An activity that precedes another activity in the network.
3. Successor Activity: An activity that follows another activity in the network.
B. CPM: Critical path method, which is a method of planning and scheduling a construction project where activities are arranged based on activity relationships. Network calculations determine when activities can be performed and the critical path of Project.
C. Critical Path: The longest connected chain of interdependent activities through the network schedule that establishes the minimum overall Project duration and contains no float.
D. Float: The measure of leeway in starting and completing an activity.
E. Major Area: A story of construction, a separate building, or a similar significant construction element.
1.3 SUBMITTALS
A. Submittals Schedule: Submit electronic (pdf) copy of schedule. Arrange the following information in a tabular format:
1. Scheduled date for first submittal.
2. Specification Section number and title.
3. Submittal category (action or informational).
4. Name of subcontractor.
5. Description of the Work covered.
6. Scheduled date for Government’s final release or approval.
CONSTRUCTION DOCUMENTS 013200 - 2
B. Contractor's Construction Schedule: Submit electronic (pdf) copy of initial schedule, large enough to show entire schedule for entire construction period.
C. CPM Reports: Concurrent with CPM schedule, submit electronic (pdf) copy of each of the following computer-generated reports. Format for each activity in reports shall contain activity number, activity description, cost and resource loading, original duration, remaining duration, early start date, early finish date, late start date, late finish date, and total float in calendar days.
1. Activity Report: List of all activities sorted by activity number and then early start date, or actual start date if known.
2. Logic Report: List of preceding and succeeding activities for all activities, sorted in ascending order by activity number and then early start date, or actual start date if known.
3. Total Float Report: List of all activities sorted in ascending order of total float.
D. Daily Construction Reports: Submit electronic (pdf) copy at weekly intervals.
E. Field Condition Reports: Submit electronic (pdf) copy at time of discovery of differing conditions.
1.4 COORDINATION
A. Coordinate Contractor's Construction Schedule with the list of subcontracts, Submittals Schedule, progress reports, payment requests, and other required schedules and reports.
1. Secure time commitments for performing critical elements of the Work from parties involved.
2. Coordinate each construction activity in the network with other activities and schedule them in proper sequence.
1.5 SUBMITTALS SCHEDULE
A. Preparation: Submit a schedule of submittals, arranged in chronological order by dates required by construction schedule. Include time required for review, resubmittal, ordering, manufacturing, fabrication, and delivery when establishing dates.
1. Coordinate Submittals Schedule with list of subcontracts and Contractor's Construction Schedule.
2. Submit concurrently with the first complete submittal of Contractor's Construction Schedule.
1.6 CONTRACTOR'S CONSTRUCTION SCHEDULE, GENERAL
A. Time Frame: Extend schedule from date established for the Notice to Proceed to date of Final Completion.
1. Contract completion date shall not be changed by submission of a schedule unless specifically authorized by Modification.
B. Activities: Treat each story or separate area as a separate numbered activity for each principal element of the Work. Comply with the following:
CONSTRUCTION DOCUMENTS 013200 - 3
1. Procurement Activities: Include procurement process activities for the following long lead items and major items, requiring a cycle of more than 60 days, as separate activities in schedule.
2. Submittal Review Time: Include review and resubmittal times.
3. Startup and Testing Time: Include required startup and testing times.
4. Substantial Completion: Indicate completion in advance of date established for Substantial
Completion and allow time for Government’s administrative procedures necessary for certification of Substantial Completion.
C. Constraints: Include constraints and work restrictions indicated in the Contract Documents and as follows in schedule, and show how the sequence of the Work is affected.
D. Milestones: Include milestones indicated in the Contract Documents in schedule, including, but not limited to, the Notice to Proceed, Substantial Completion, and Final Completion.
E. Contract Modifications: For each proposed contract modification and concurrent with its submission, prepare a time-impact analysis to demonstrate the effect of the proposed change on the overall project schedule.
F. Contractor's Construction Schedule Updating: At a minimum of monthly intervals, and at any major occurrence impacting schedule, update schedule to reflect actual construction progress and activities. Issue schedule one week before each regularly scheduled progress meeting.
G. Distribution: Distribute copies of approved schedule to Government, separate contractors, testing and inspecting agencies, and other parties identified by Contractor with a need-to-know schedule responsibility.
1.7 CONTRACTOR'S CONSTRUCTION SCHEDULE (CPM SCHEDULE)
A. General: Prepare network diagrams using AON (activity-on-node) format.
B. Preliminary Network Diagram: Submit diagram within 14 days of date established for the Notice of Award. Outline significant construction activities for the first 60 days of construction. Include skeleton diagram for the remainder of the Work.
C. CPM Schedule: Prepare Contractor's Construction Schedule using a computerized time-scaled CPM network analysis diagram for the Work.
1. Develop network diagram in sufficient time to submit CPM schedule so it can be accepted for use no later than 30 days after date established for the Notice to Proceed.
a. Failure to include any work item required for performance of this Contract shall not excuse Contractor from completing all work within applicable completion dates, regardless of Government’s approval of the schedule.
2. Establish procedures for monitoring and updating CPM schedule and for reporting progress. Coordinate procedures with progress meeting and payment request dates.
3. Use "one workday" as the unit of time. Include list of nonworking days and holidays incorporated into the schedule.
D. CPM Schedule Preparation: Prepare a list of all activities required to complete the Work. Using the preliminary network diagram, prepare a skeleton network to identify probable critical paths.
CONSTRUCTION DOCUMENTS 013200 - 4
1. Activities: Indicate the estimated time duration, sequence requirements, and relationship of each activity in relation to other activities. Include estimated time frames for the following activities:
a. Preparation and processing of submittals.
b. Mobilization and demobilization.
c. Purchase and delivery of materials.
d. Fabrication.
e. Utility interruptions.
f. Installation.
g. Inspections and approvals.
h. Testing and any required commissioning.
2. Critical Path Activities: Identify critical path activities, including those for interim completion dates. Scheduled start and completion dates shall be consistent with Contract milestone dates.
3. Processing: Process data to produce output data on a computer-drawn, time-scaled network. Revise data, reorganize activity sequences, and reproduce as often as necessary to produce the CPM schedule within the limitations of the Contract Time.
4. Format: Mark the critical path. Locate the critical path near center of network; locate paths with most float near the edges.
a. Subnetworks on separate sheets are permissible for activities clearly off the critical path.
E. Initial Issue of Schedule: Prepare initial network diagram from a list of straight "early start-total float" sort. Identify critical activities. Prepare tabulated reports showing the following:
1. Contractor or subcontractor and the Work or activity.
2. Description and Principal events of activity.
3. Immediately preceding and succeeding activities.
4. Early and late start and finish dates.
5. Total float or slack time.
F. Schedule Updating: Concurrent with making revisions to schedule, prepare tabulated reports showing the following:
1. Identification of activities that have changed.
2. Changes in early and late start and finish dates.
3. Changes in activity durations in workdays.
4. Changes in the critical path.
5. Changes in total float or slack time.
6. Changes in the Contract Time.
1.8 REPORTS
A. Daily Construction Reports: Prepare a daily construction report recording the following information concerning events at Project site:
1. List of subcontractors at Project site.
2. Equipment at Project site.
3. Material deliveries.
4. High and low temperatures and general weather conditions.
5. Accidents.
CONSTRUCTION DOCUMENTS 013200 - 5
6. Stoppages, delays, shortages, and losses.
7. Meter readings and similar recordings.
8. Orders and requests of authorities having jurisdiction.
9. Services connected and disconnected.
10. Equipment or system tests and startups.
11. Photographs
B. Field Condition Reports: Immediately on discovery of a difference between field conditions and the Contract Documents, prepare and submit a detailed report. Submit with a request for interpretation. Include a detailed description of the differing conditions, together with recommendations for changing the Contract Documents.
PART 2 - PRODUCTS (Not used)
PART 3 - EXECUTION (Not used)
END OF SECTION 013200
DUPLEX BUILDING AND SITE LOCATIONS PHOTOGRAPHIC DOCUMENTATION
CONSTRUCTION DOCUMENTS 013233 - 1
SECTION 013233
PHOTOGRAPHIC DOCUMENTATION
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes administrative and procedural requirements for the following:
1. Preconstruction photographs.
2. Concealed Work photographs.
3. Periodic construction photographs.
4. Final completion construction photographs.
B. Related Requirements:
1. Section 017700 "Closeout Procedures" for submitting photographic documentation as Project Record Documents at Project closeout.
2. Section 024119 "Selective Demolition" for photographic documentation before selective demolition operations commence.
3. Section 311000 "Site Clearing" for photographic documentation before site clearing operations commence.
1.2 INFORMATIONAL SUBMITTALS
A. Key Plan: Submit key plan of Project site and building with notation of vantage points marked for location and direction of each photograph. Indicate elevation or story of construction. Include same information as corresponding photographic documentation.
B. Digital Photographs: Submit image files within three days of taking photographs.
1. Submit photos electronically. Include copy of key plan indicating each photograph's location and direction.
2. Identification: Provide the following information with each image description in file metadata tag:
a. Name of Project.
b. Name and contact information for photographer.
c. Name of Contractor.
d. Date photograph was taken.
e. Description of location, vantage point, and direction.
f. Unique sequential identifier keyed to accompanying key plan.
1.3 FORMATS AND MEDIA
A. Digital Photographs: Provide color images in JPG format, produced by a digital camera with minimum sensor size of 12 megapixels, and at an image resolution of not less than 3200 by 2400 pixels. Use flash in low light levels or backlit conditions.
DUPLEX BUILDING AND SITE LOCATIONS PHOTOGRAPHIC DOCUMENTATION
CONSTRUCTION DOCUMENTS 013233 - 2
B. Digital Images: Submit digital media as originally recorded in the digital camera, without alteration, manipulation, editing, or modifications using image-editing software.
C. Metadata: Record accurate date and time from camera.
D. File Names: Name media files with date and sequential numbering suffix.
1.4 CONSTRUCTION PHOTOGRAPHS
A. Photographer: Engage a qualified photographer to take construction photographs.
B. General: Take photographs with maximum depth of field and in focus.
1. Maintain key plan with each set of construction photographs that identifies each photographic location.
C. Preconstruction Photographs: Before commencement of the Work, take photographs of Project site and surrounding properties, including existing items to remain during construction, from different vantage points, as directed by Government.
1. Flag construction limits before taking construction photographs.
2. Take 20 photographs to show existing conditions adjacent to property before starting the
Work.
3. Take 20 photographs of existing buildings either on or adjoining property to accurately record physical conditions at start of construction.
4. Take additional photographs as required to record settlement or cracking of adjacent structures, pavements, and improvements.
D. Concealed Work Photographs: Before proceeding with installing work that will conceal other work, take photographs sufficient in number, with annotated descriptions, to record nature and location of concealed Work, including, but not limited to, the following:
1. Underground utilities.
2. Underslab services.
3. Piping.
4. Electrical conduit.
5. Waterproofing and weather-resistant barriers.
E. Periodic Construction Photographs: Take 20 photographs weekly. Select vantage points to show status of construction and progress since last photographs were taken.
F. Final Completion Construction Photographs: Take 20 photographs after date of Substantial Completion for submission as Project Record Documents. Government will inform photographer of desired vantage points.
PART 2 - PRODUCTS (Not Used)
END OF SECTION 013233
DUPLEX BUILDING AND SITE LOCATIONS SUBMITTAL PROCEDURES
CONSTRUCTION DOCUMENTS 013300 - 1
SECTION 013300
SUBMITTAL PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, Design Computations, and other submittals.
1.2 RELATED SECTIONS– related sections include submittal requirements for those sections.
A. 013100 “Project Management and Coordination”
B. 013200 "Construction Progress Documentation"
C. 014000 "Quality Requirements"
D. 017700 "Closeout Procedures"
E. 017823 "Operation and Maintenance Data"
F. 017839 "Project Record Documents"
G. 017900 "Demonstration and Training" for submitting video of demonstration of equipment and training of Government personnel.
1.3 DEFINITIONS
A. Action Submittals: Information that requires Government’s responsive action.
B. Informational Submittals: Information that does not require Government’s responsive action.
Submittals may be rejected for not complying with requirements.
1.4 SUBMITTAL PROCEDURES
A. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.
1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.
2. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently.
Government reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.
B. Submittals Schedule: Comply with requirements in Section "Construction Progress Documentation" for list of submittals and time requirements.
CONSTRUCTION DOCUMENTS 013300 - 2
C. Processing Time: Allow enough time for submittal review, including time for resubmittals, as follows. Time for review shall commence on Government's receipt of submittal. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including resubmittals.
1. Initial Review: Allow 14 calendar days for initial review of each submittal. Allow additional time if coordination with subsequent submittals is required. Government will advise Contractor when a submittal being processed must be delayed for coordination.
2. Intermediate Review: If intermediate submittal is necessary, process it in same manner as initial submittal.
3. Resubmittal Review: Allow 14 calendar days for review of each resubmittal.
D. Submittals Labelling:
1. Label each submittal for identification; include name of firm or entity…
This is the start of the file's text. The full file is on GovTribe.