Attachment J - Schedule of Material Submittals.xlsx
XLSX spreadsheet 34 KB Posted
- Attached to
- Paint Hallways MPF, B246
- Solicitation number
- MXDP23-1007
About this file
This document is a schedule of material submittals for solicitation number MXDP23-1007 to paint hallways at MPF, B246. It requires the contractor to submit 29 items on specific dates, including a proof of OPSEC training 2 weeks prior to base access, a summary of site investigation within 5 days of NTP, a progress schedule and contract progress report weekly, and meeting minutes within 3 days of meetings. Hazardous material and waste plans are due prior to NTP 2, as well as an asbestos abatement plan 10 days before construction. Records of existing conditions, a phase plan, and a construction site plan are due within 45 days of NTP 1. During construction, the contractor must submit daily QC reports weekly and materials testing results within 7 days of tests. Completion documents like an O&M manual, DD Form 1354, and construction warranty management plan are due at final inspection or within 2 weeks thereafter. Paint submittals are due prior to NTP 2. The solicitation was issued by the Department of the Air Force Air Education and Training Command.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Submittals Schedule SCHEDULE OF SUBMITTALS PROJECT # MXDP 23-1007 PROJECT TITLE Painting Hallways MPF, B246 SOLICITATION / CONTRACT NO.
| (To be completed by Project Engineer) | (To be completed by Contract Administrator) | ||||||||||||||
| LINE NUMBER | ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTAL | C = Construction Project D = Design Project | LAUGHLIN DIV 01 SPECIFICATIONS | ENVIRONMENTAL QUALITY CONSTRUCTION SPECIFICATIONS LAFB | STATEMENT OF WORK | NUMBER OF PAPER COPIES REQUIRED. DIGITAL COPIES ARE REQUIRED FOR ALL SUBMITTALS | REQUIRED SUBMISSION DATE | DATE RECEIVED IN CONTRACTING | DATE TO CIVIL ENGINEERING | RETURN SUSPENSE DATE | SUBMITTAL NUMBERS | DATE CONTRACTOR NOTIFIED | CONTRACTOR RESUBMITTAL | FINAL APPROVAL | REMARKS |
APPR
fergusog: Enter date the Contractor was notified of submittal approval
(MM/DD/YY)
DIS
fergusog: Enter date the Contractor was notified of submittal disapproval
(MM/DD/YY)
| NTP 1 - Submitals | ||||||
| 1 | Proof of OPSEC Training | D | 2.4 | 3.1 | 2 Weeks prior to base access | |
| 2 | Summary of site investigation | D | 7.1.1 | 3.0 | NLT 5 Days after NTP 1 | |
| 3 | Progress Schedule Form and Contract Progress Report | C, D | 6.1 | 6.1 | Weekly | |
| 4 | Meeting Minutes | D | 6.2.1 | 5.3 | NLT 3 Days after meeting | |
| 5 | Entry Access List (EAL) | C | 1.8.2 | 2 Weeks prior to base access | ||
| 6 | AF Form 103, Work Clearance Request | C | 2.2 | 3.3.1 | NLT 30 days after NTP 1 | |
| 7 | Contractor Safety Plan | C | 3.2.1 | NLT 30 days after NTP 1 | ||
| 8 | Certificate of Contractor Safety Compliance | 3.2.2 | NLT 7 days after NTP 1 | |||
| 9 | QC Manager Qualifications | C, D | 4.2.3 | NLT 7 days after NTP 1 | ||
| 10 | QC Plan | C, D | 4.2.4 | NLT 30 days after NTP 1 | ||
| 11 | Construction Site Plan | 12.1 | 3.0 | NLT 30 days after NTP 1 | ||
| 12 | Hazardous Material Approval (Safety Data Sheets) | C | 3.2.1 | NLT 30 days after NTP 1 (as required) | ||
| 13 | Hazardous Waste Training Certificate | 3.2.2 | Prior to NTP 2 |
(as required) 14 Hazardous Waste / Material Procedures 3.2.2 Prior to NTP 2 (as required)
| 15 | Asbestos Hazard Abatement Plan | 3.5.2.1 | NLT 10 days prior to construction start |
| 16 | Copy of notification to Department of State Health Services | 3.5.2.1 | NLT 10 days prior to construction start |
| 17 | Worker/Area Protection Plan | 3.5.2.2 | Prior to NTP 2 |
(as required)
| 18 | Phase Plan | C , D | 6.1.2 | 3.0 | NLT 45 Days after NTP 1 | |
| 19 | Records of Existing Conditions | C, D | 1.5, 7.1.1 | 3.0 | NLT 45 Days after NTP 1 | |
| NTP 2 - Construction | ||||||
| 20 | Non-Hazardous Waste Disposal Manifest and/or Waste Shipment Record | C | 5.1 / 6.2 | 2.1 | NLT 30 days from the date of signature of receiving facility | |
| 21 | Hazardous Waste Disposal Manifests | C | 5.2 / 6.2 | 2.1 | As required, prior to removal from Government property | |
| 22 | Hazmat Usage Log | C | 6.1 | 2.1 | End of each month during construction | |
| 23 | QC Daily Inspection Reports | C | 4.2.6 | 5.3 | Weekly | |
| 24 | Materials Testing | C | 7.1.3 | As required, within 7 days of test | ||
| 25 | Operation and Maintenance Data | C | 10.4.12 | NLT 2 weeks after Final Inspection | ||
| 26 | Completion Inspection (QC Manager Punchlist) | C | 13.4 | 5.4 | NLT 3 days after Pre-Final Inspection | |
| 27 | Draft DD Form 1354 | C | 13.3 | Prior to Pre-Final Inspection | ||
| 28 | Final DD Form 1354 | C | 13.3 | At Final Inspection | ||
| 29 | Construction Warranty Management Plan | C | 13.2 | NLT 2 weeks after Final Inspection | ||
| Project Specific Submittals | ||||||
| 30 | Paint Submittals | C | 2.1 | Prior to NTP 2 | ||
| Schedule of Submittals Template, Feb 05 (SAF/AQCP) |
Task Order # FA3099-16-D-0002-0002 SOW Atch 2
&"Times New Roman,Regular"&12Page &P of &N