Central Service Area
Statement of Work FAA-C90-370
Air Traffic Control Tower Renovation
Project
Quad City International Airport Federal Aviation Administration
Air Traffic Control Tower
6421 74th Ave.
Milan, IL 61265
Prepared By:
Federal Aviation Administration Chicago District Technical Support Center
AJW-C22D
Elgin, Illinois
01 May, 2021
I
C90‐FAA‐370
Table of Contents
Section 1 Section Title Dated
I‐III Table of Contents 05/01/2021
IV‐V Moline ATCT Location Maps 05/01/2021
VI‐XIII Site Pictures 05/01/2021
Specification Title Dated
Section 01 11 00
Scope of Work / General Requirements
05/01/2021
Section 09 68 00 ESD carpet installation 05/01/2021
Section 09 91 00
Painting
Section 22 40 00
Plumbing Fixtures
Appendix I
Schedule of Submittals.
II
Drawings Title Dated
Project Drawings
C90‐370‐G001 Cover Sheet/ Drawing Index ATCT Renovation Project
Milan. Illinois
C90‐370‐A001 Work Layout Plan ‐ Room 202 And 404
ATCT Renovation Project
C90‐370‐A002 Work Layout Plan ‐ Room 509 and 607
ATCT Renovation Project
C90‐370‐A003 Work Layout Plan – ATCT Cab and TRACON
ATCT Renovation Project
C90‐370‐A004 Floor Plan ‐ Room 604 & 605
ATCT Renovation Project – Option Bid Work
C90‐370‐A005 Floor Plan ‐ Room 604 & 605
ATCT Renovation Project– Option Bid Work
C90‐370‐A006 Locker Detail
ATCT Renovation Project– Option Bid Work
C90‐370‐A007 ACCY./Fixture Schedule
ATCT Renovation Project– Option Bid Work
C90‐370‐E001 Work Layout Plan – Electrical and Mechanical ATCT Renovation Project– Option Bid Work
C90‐370‐E002 Electrical Notes
ATCT Renovation Project– Option Bid Work
III
Drawings Title Dated
Reference Drawings
GL‐E‐34‐A1
First And Second Floor Plans Quad City Airport, Moline, Il
06/18/1980
GL‐E‐34‐A2
Third and Fourth Floor Plans
GL‐E‐34‐E1
First And Second Floor Plans
GL‐E‐34‐E2
Third, Fourth, and Cab Floor Plans
IV
FAA‐C90‐370
Vicinity Map – Quad City International Airport.
V
Location Map – Quad City International Airport.
VI
(Moline) MLI ATCT Site Pictures
ATCT Second Floor Room 206. ATCT Second Floor Room 206.
ATCT Third Floor Room 309 ATCT Third Floor – Room 309
VII
ATCT Fourth Floor – Room 406 ATCT Fourth Floor – Room 406
ATCT Fifth Floor – Room 509. ATCT Fifth Floor – Room 509.
VIII
ATCT Sixth Floor – Room 607.
ATCT Sixth Floor – Room 607.
IX
ATCT Room 605 Kitchen/Break Room (Option Bid Work).
X
ATCT Room 605 Kitchen/Break Room (Option Bid Work).
XI
ATCT Cab ESD Carpet to Be Replaced.
XII
TRACON Operations Room ESD Carpet to Be Replaced.
SECTION 01 11 00 – SUMMARY OF WORK
1.01 SUMMARY OF WORK.
A. The Contractor shall furnish all labor, materials, equipment, etc. to complete the interior renovation of the Quad City International Airport Air Traffic Control Tower (ATCT), Milan, Illinois. This work consists of base bid work and bid option work including, but limited to the following principle items:
Base Bid Work
Room 206, 406, 509, and 607 Restrooms
1. Removal and disposal of all plumbing fixtures, restroom accessories, partitions, etc.
2. Removal and disposal of the existing vinyl base.
3. Removal and disposal of the existing 2’x2’ suspended ceiling (metal grid and lay‐ in ceiling tiles).
4. Installation of install new toilet and sink fixtures as indicated on the drawings and equipment schedule. This work includes all related hardware and miscellaneous plumbing required for a complete installation.
5. Installation of new restroom accessories, partitions, and equipment as indicated on the drawings and equipment schedule.
6. Painting of all wall surfaces.
7. Deep cleaning of all floor tile and grout and application of grout sealer.
8. Installation of new supply, return, transfer and exhaust grilles with new grilles.
9. Installation of a new 2’x2’ suspended ceiling system (metal grid and
01 May, 2021
10. Installation of new 2’x2’, 120v, surface mounted lay‐in LED light fixtures (2700k‐3000k) and 120V LED vanity light fixtures(2000K), including fixtures, housing, and drivers. Work includes all related electrical work for a complete installation.
11. Replacement of all existing duplex receptacles with new GFCI receptacles and cover plates at locations required by the National Fire Protection Association (NFPA) 70 National Electrical code as indicated on the drawings.
12. Replace all existing device plates (receptacle, switch, telephone, LAN, etc.) with device new cover plates.
13. All related finish, plumbing and electrical work for a complete installation, including the relocation of all fire detection devices and HVAC temperature sensors as required.
Room 404 TRACON Operations Room and ATCT cab Renovation
14. Removal and disposal of approximately 100 square feet of 2’x2’
Electrostatic Discharge (ESD) carpet tiles the ATCT cab and approximately 500 square feet of 2’x2’ Electrostatic Discharge (ESD) carpet tiles in the TRACON Operations Room.
15. Floor Preparation of the ATCT cab and TRACON Operations Room concrete floor for the new ESD carpet squares.
16. Furnish and install six (6) new 2”x 24”, 26 gauge copper ground strips ‐ two
(2) in the ATCT cab and four (4) in the TRACON Operations Room for connection to the building ground system by others.
17. Installation of approximately 600 square feet of 2’x 2’ ESD carpet squares
Work includes providing all compatible adhesive and floor leveling material to complete both installations.
18. Moving of all furniture in both rooms as required to facilitate the new carpet installation and returning all moved items to their original locations.
01 May, 2021
Bid Option Work
Response to the solicitation shall include a line item cost for the following work for the Government to accept or reject as part of this project.
Room 605 Kitchen/Breakroom
1. Removal and dispose of the existing lockers, including the locker with the 2‐3” drop tubes between the fourth floor and TRACON Operations Room.
2. Removal and disposal of the existing kitchen counter tops and sink.
3. Demolition of a portion of the drywall and metal stud soffit as shown on the drawings.
4. Remove and dispose of the existing 2’x4’ suspended ceiling system (metal grid and lay‐in tiles).
5. Remove and disposal of approximately 250 square feet of carpet squares.
6. Remove and disposal approximately 75 linear feet of vinyl base cove.
7. Reconstruction of the drywall soffit in order to accommodate the new lockers and constructing a new 3’‐0” pass through opening as indicated on the drawings.
8. Furnish and install twenty five (25) new 12”x18”x72” single tier metal lockers, including new locker curb(s) as required by the manufacturer. Work includes all related assembly and installation of the new lockers for a complete installation.
9. Installation of a high pressure laminate kitchen countertop consisting of three sections with backsplash sections.
10. Installation of new cabinet and cabinet door and drawer faces with new laminate finish to matching the existing style. Work includes the installation of new hardware (handles, hinges, etc.).
01 May, 2021
11. Installation of a new double basin stainless steel sink including installation of a new touchless faucet, new spray attachment, a 120/240v, 1 horsepower garbage disposal, sink drain, and all related plumbing work for a complete installation.
12. Installation of approximately 300 square feet of 2’x 2’ commercial grade, high traffic carpet squares. Work includes providing all compatible adhesive and floor leveling material for a complete both installations.
13. Installation of new 3/8” vinyl cove base.
14. Removal and disposal of the existing 2’x2’ suspended ceiling (metal grid and
15. Installation of new supply, return, transfer and exhaust grilles with new grilles.
16. Installation of new 2’x2’, 120v, lay‐in LED light fixtures (4000k), including fixtures, housing, and drivers. Work includes all related electrical work for a complete installation.
17. Replacement of all existing duplex receptacles with new GFCI receptacles and cover plates at locations required by the National Fire Protection Association (NFPA) 70 National Electrical code as indicated on the drawings.
18. Replace all existing device plates (receptacle, switch, telephone, LAN, etc.) with new device cover plates.
19. All related plumbing and electrical work for a complete installation, including the relocation of all fire detection devices and HVAC temperature sensors.
1.02 QUALITY ASSURANCE.
A. The Contractor shall verify all existing site conditions and room measurements for obtaining quantities of materials required and scope of each work line item.
B. The Contractor shall apply all floor and surface finishes in accordance with the manufacturer’s instructions including cleaning of surfaces.
01 May, 2021
C. The Contractor shall furnish all labor, materials, equipment, transportation, moving and other services necessary to accomplish all elements of the project as described in this statement of work and drawings.
D. Construction and installation shall include all miscellaneous and incidental work necessary for complete and operational equipment, system, or construction whether or not such work is specifically shown or specified.
E. The Contractor shall verify that the products submitted for approval are compatible with the work regarding installation as stated in this statement of work.
F. The Contractor shall have had experience with similar installations of comparable size and complexity as regards to coordinating, installation work, and job supervision. Evidence shall be submitted upon request of the Contracting Officer.
G. The Contractor shall comply with all Local, State, and Federal laws, rules and regulations governing the work including the National Electrical Code, Uniform Building Code, and Fire Life Safety codes. The Contractor is responsible to ensure that copies of specified codes and standards are readily available to their personnel.
H. The Contractor is responsible to ensure that their personnel are familiar with workmanship and installation requirements of specified codes, regulatory requirements, consensus standards, and DOT/FAA referenced directives.
1.03 SUBMITTALS.
A. Schedule of Required Submittals Reference (Appendix I).
1. Reference the attached finish, accessory, and plumbing schedules for submittal requirements and notes.
2. All applicable submittals shall include a statement stating they do not contain any (0%) asbestos containing materials.
3. All applicable submittals for paints, sealants, and adhesives include a statement stating they contain Zero‐VOC materials.
01 May, 2021
4. Submittal and Brand Name Usage. Product brand names referenced in this statement of work, drawings, and Appendix I of this statement of work are "known acceptable sources”. The product submitted for approval shall be identical or equal to the brand name product or known acceptable source in meeting the salient characteristics, but it need not exceed the actual minimum requirements.
5. Submit copies of Material Data Safety Sheets for all adhesives, sealants, grout, etc. used in this project.
1.04 REGULATORY REQUIREMENTS.
A. All work shall be accomplished in accordance with all local, state, and federal codes including but not limited to applicable sections of the Uniform Building Code (UBC), Occupational Safety and Health Association (OSHA), American Disabilities Act (ADA), Environmental Protection Association (EPA), National Electrical Code (NEC), and applicable Life‐Safety codes.
B. OSHA reserves the right to inspect the Contractor's work area without advance notice.
C. When the Contractor observes that contract documents are at variance with the above referenced codes notify the COR immediately.
1.05 GOVERNING DOCUMENTS
A. Drawings referenced on the project drawings that are not included in the Contract Drawing List do not apply to this contract unless otherwise specified.
B. For any conflicts between the statement of work and drawings, the work shown on the drawings shall govern.
C. For any conflicts between the electrical work shown on the drawings and the National Fire Protection Association (NFPA) 70, National Electrical Code (NEC) requirements, the more stringent shall govern.
1.06 WORK HOURS/PHASING.
A. All work shall take place during an 8 hour shift Monday through Thursday between the hours of 7:00 PM and 4:00 PM, weekends and national holidays excluded.
B. ESD carpet replacement in the TRACON Operations may be required to be accomplished outside the hours stated above due to air traffic operations. Coordinate the work time the TRACON Operations Room with COR.
C. ESD carpet replacement in the ATCT Cab shall be accomplished between the hours of
10:00 PM and 6:00 AM, Monday through Thursday, national holidays excluded.
D. The Contractor shall plan to complete the work in each room only after the material for each room has been received.
1.07 DEMOLITION.
A. All materials shall be removed such that it would not affect or damage any existing equipment or structure. All waste material shall be hauled and be placed in a dumpster provided by the Contractor.
1.08 GOVERNMENT‐FURNISHED EQUIPMENT. (Reserved).
1.09 CONTRACTOR‐FURNISHED MATERIAL.
A. The Contractor shall furnish all material under this contract. The Contractor shall
Take into account that certain materials to be furnished by the Contractor may be long‐lead‐time items. Therefore, the successful bidder should determine the availability of all material immediately after contract award, and initiate procurement action on long‐lead‐ time items at the earliest possible date.
B. All contractor furnished materials and equipment shall be provided new.
1.10 SECURITY REQUIREMENTS.
A. The Contractor shall provide the COR with a list of the contractor's personnel as required by the Contracting Officer.
1.11 DISPOSAL/CLEANING REQUIREMENTS.
A. The Contractor shall dispose of all debris on a daily basis after each work shift. The Contractor shall provide containers with covers for storage of debris at the site as required.
B. A complete cleaning of each room after renovation has been competed including the wiping down of all walls and furniture, and vacuuming and/or cleaning of the new carpet floors.
1.12 PROTECTION OF EQUIPMENT.
A. The Contractor shall protect all existing furniture, floors and other finished surfaces during renovation as directed by the COR.
1.13 CUTTING AND PATCHING.
A. General Requirements: The Contractor shall be responsible to complete all related cutting, fitting, and patching work required for a complete installation including:
1. Penetrations of building walls (interior or exterior) for the installation of piping, electrical conduit, and mechanical ducts, as indicated on the drawings. This work includes installing fire‐stop material in accordance with the applicable approved National Fire Protection Agency (NFPA) and Underwriter’s Laboratory™ (UL) wall penetration detail.
2. Make parts properly fit.
3. Uncover portions of the work to provide for installation of ill‐timed work.
4. Remove and replace work not conforming to requirements.
5. Return the site to its original condition.
1.14 IDENTIFICATION OF UTILITIES.
A. FAA utilities: All work associated with the location and identification of buried or above ground communications, electrical, mechanical, or plumbing systems owned by the FAA, shall be performed by FAA personnel.
B. Utility Disruption: In the event that properly identified utility or communication services either overhead or buried, are damaged as a result of the Contractor’s activity, such services shall be immediately repaired and the COR and Contracting Officer immediately notified.
1.15 ACCESS TO WORK AREAS.
A. Access to the work areas shall be as directed by the COR. Security precautions against unauthorized facility entrance shall be maintained. Contractor's vehicles are permitted to park near ATCT build
1.16 CONTRACTOR'S LIABILITY.
A. Damage to the existing facility or equipment shall be reported to the COR without delay. The Contractor shall be responsible for repairing or having repaired all damaged areas to the facility or equipment directly caused by the Contractor’s related work. All repairs shall be accomplished, without delay, at the contractor's expense to the satisfaction of the COR.
B. After notice to proceed and prior to the commencement of construction, the Contractor and the COR shall conduct joint inspections of the existing areas affected by the construction. Damage or defects shall be noted and will be used as the basis for determination of damages caused by the contractor's operations.
1.17 FIRE EXTINGUISHING EQUIPMENT.
A. The contractor shall have an equivalent of 2‐25 lb. class A and B fire extinguishers in the work area through the progress of the job. CO2 type fire extinguishers are acceptable.
1.18 PROJECT MEETINGS.
A. The Contractor and COR shall conduct project meetings throughout the construction period as deemed necessary.
1.19 FACILITY CUT‐OVER & INTERRUPTIONS IN SERVICE.
A. Only on‐site FAA maintenance personnel and the COR are authorized to energize and de‐energize equipment or to operate circuit breakers, switches, or fuses in FAA facilities. The COR has the authority to stop work at any time if work activities interfere with the operation of any FAA facility.
B. FAA personnel will disable the ATCT fire detection system remote monitoring during demolition work in the second and third floor offices as well as the application of all paints and floor finishes.
C. FAA policy requires electrical panels be de‐energized when installing new electrical circuits. The Contractor shall coordinate work inside any electrical panel with the COR for a block of time to have a panel de‐energized in order to accomplish the required work.
1.20 TEMPORARY FACILITIES.
A. Contractor staging. The Government will provide space outside of the ATCT do the Contractor to set temporary containers for the storage of material as required. The Contractor shall be responsible for maintaining the staging area for the duration of the project and removal of any temporary containers once the project has been completed.
The Contractor shall be responsible for the security of all materials stored at the site regardless if the site is accessible by the public.
B. Temporary Electrical Power: 120V/240V electrical power is available from the existing building electrical service at no cost to the Contractor. All points of connection for electrical service and any modifications to the electrical system shall be approved by the
COR.
C. Restroom facilities will be made available by to the Contractor. The Government reserves the right limit use.
D. Temporary Construction Aids: The Contractor shall furnish, install, and maintain all construction aids and equipment to facilitate execution of work including but not limited to barricades, scaffolds, staging, ladders, stairs, ramps, runways, platforms, railings, hoists, cranes, chutes, steel plates, etc.
01 May, 2021
E. Temporary Barricades: The Contractor shall furnish, install, and maintain suitable barricades as required to prevent FAA personnel from entering the construction area and to protect the work and existing facilities from construction operations. All barricades shall be removed when they are no longer needed or at the completion of
F. Removal of Temporary Facilities. The Contractor shall promptly remove all temporary facilities from premises at end of the project.
1.21 WARRANTIES.
A. Upon completion of the job submit copies of all warranties including effective dates and contacts information for warranty claims.
1.22 SITE SURVEYS.
A. To coordinate a survey of the facility, contact Mr. Nicholas Pool, FAA Moline SSC Manager,
(309) 799‐5712 (office) or (309) 314‐3773 (cell).
B. All requests for information from the site surveys or drawing review shall be submitted in writing to the Contracting Officer.
End Section 00 01 00
Section 09 68 00 ‐ ELECTROSTATIC DISCHARGE (ESD) CARPET
PART 1 – GENERAL REQUIREMENTS
1.01 SCOPE OF WORK.
A. This section includes all labor, materials, tools and other equipment, services and supervision required to complete installation of new Electro Static Discharge (ESD) carpeting and ground strips as shown on the drawings and described in this statement of
B. Removal and disposal of the existing ESD carpet squares.
C. Floor preparation of the existing floor for the installation of the new ESD carpet squares.
D. Furnish and install six (6) new 2”x 24”, 26 gauge copper ground strips ‐ two (2) in the ATCT cab and four (4) in the TRACON Operations Room for connection to the building ground system by others.
A. The installer of the ESD carpeting shall be an authorized representative installer of the ESD carpet tile manufacturer.
PART 2 – PRODUCTS
2.01 A. ESD Carpet tiles.
1. Physical Characteristics.
a. Construction: Tufted.
b. Texture Textured loop.
c. Stiches per inch: 10.
d. Fiber: Nylon.
e. Dye: 100% solution dyed.
f. Pile height: .091”
g. Size: 24’x24”
h. Indoor Air Quality: Green Label Plus Certification.
i. Flammability: ASTM E‐648 Flooring Radiant Panel ‐ Class 1.
J. Smoke density: ASTM E‐662 NBS Less than 450.
k. Texture & Appearance Retention Rating: >3.0.
2. Static Control Properties
a. Electrostatic Propensity: ESD STM 97.2 (w/ Conductive Footwear) less than 20V.
AATCC 134‐06 (w/o Conductive Footwear) less than
0.4 kV (400 volts)
b. Electrical Resistance: < 1.0 x 109 ohms.
c. Ground path method: copper ground strips.
e. Grounding Frequency: 1 per 1,000 sq. ft.
B. Known acceptable source: Julie Industries Inc. StaticSmart® Presidential Series Level 3 carpet tiles meet the above requirements.
2.02 Adhesive.
A. Carpet tile adhesive shall be quick release, no VOC adhesive, compatible with the carpet tiles.
B. Known acceptable source: Julie Industries Inc. conductive ESD releasable adhesive meet the above requirements.
2.03 Copper Grounding strips.
A. 2”X 48”, 26 gauge copper.
PART 3 – EXECUTION
A. Floor Preparation:
1. Floor system shall be inspected for integrity, smoothness & levelness.
2. Verify dimensions on contract drawings, including stationary consoles, electronic equipment, and wall locations.
3. Remove old carpet and adhesive from the concrete floor and the floor hatch. Adhesive shall be removed thoroughly by scraping, grinding or solvents, to prepare the floor surfaces to comply with the adhesive and carpet manufacturers’ instructions.
4. Clean floor from oil, waxy films, paint, dust, and deleterious substances that prevent adhesion. Leave floor dry, free of residue from existing curing or cleaning agents. Porous areas must be sealed. Concrete floors should be checked for moisture. Vacuum clean immediately before installation.
B. Installation.
1. All work shall be coordinated with the COR. The work plan shall include how the contractor intends to remove and replace carpet, how the area will be vented to keep fumes building up in the cab.
2. The Contractor shall install the carpet following manufacturer's installation instructions and adhering to industry standards as published in the Commercial Carpet Installation
Standards, CRI 104.
3. Carpet tile shall be installed in accordance with the manufacturer's instructions. The proper amount of adhesive shall be applied to the surfaces and all surfaces shall be prepared according to the requirements of the adhesive and carpet manufacturers’ instructions. Installed carpet shall be smooth, uniform and secure. Cutouts such as around doorjambs, along walls and furniture shall be done in a neat, professional manner. Edges of old carpet shall not appear along these cute edges.
4. Carpet tiles shall fit properly in place next to adjacent tiles especially around the floor hatch. All carpet tiles shall be cut and installed according to the carpet manufacturers’ specifications so that no gaps exist between adjacent tiles after their installation. It shall be the Contractor’s responsibility to assure that the carpet tiles fit properly on the floor without unnecessary binding or buckling.
SECTION 09 91 00 ‐ PAINTING
1.01 SCOPE OF WORK.
A. This section includes all labor, materials, tools and other equipment, services and supervision required to complete painting and related work as indicated on finish schedule drawing. This work includes, but is not limited to the following:
1. Painting of finish coats of painted wall surfaces as stated in the statement of work and drawings.
2. Painting surfaces above, behind or below grilles, gratings, diffusers, louvers lighting fixtures, which are exposed to view through these items per the COR.
3. Incidental painting and touching up as required to produce the proper finish for painted surfaces, including touching up of factory finished items.
4. Touching up of or repairing of abraded, damaged or rusted prime coats applied by others.
B. Surface preparation of substrates as required for acceptance of painting. This includes cleaning, small crack repair, patching, caulking, making good surfaces and areas, pre‐treatment, priming and back‐priming to the extent shown on the drawings.
A. Qualification of Painters: Use only qualified journeyman painters for the mixing and application of paint. Upon request, submit evidence that key personnel have successfully performed surface preparation and application of coating on a minimum of three (3) similar projects within the past three (3) years.
B. Notify the COR in writing of any anticipated problems using the finishes specified.
1.03 REGULATORY REQUIREMENTS.
A. Conform to work place safety regulations and requirements of those authorities having jurisdiction for storage, mixing, application and disposal of all paint and related hazardous materials.
B. Deliver and store all painting materials in sealed, original labeled containers bearing manufacturer’s name, brand name, type of paint or coating and color designation, standard compliance, materials content as well as mixing and/or reducing and application requirements in strict accordance with manufacturer ‘s requirements.
PART 2 ‐ PRODUCTS
2.01 GENERAL PRODUCT REQUIREMENTS
A. Paint submitted for approval shall be water‐based latex paint finish with the finish color for each room to be approved by the COT. All paint finishes shall referenced in the current Master Painters Institute (MPI) "Approved Product List" indicating brand label, product name and product code.
This list will be used to determine compliance with the submittal requirements of this specification.
B. Provide paint finishes that do not contain asbestos, Chromate, Cadmium, Mercury, Silica, or
ACGIH‐BKLT and ACGHI‐DOC confirmed or suspected human carcinogens.
C. VOC Content: All paints used shall be zero VOC type paint.
D. Store paint materials in fireproof cabinets provided by the Contractor that meet or exceed OSHA and NFPA requirements
E. Store materials at site at least 24 hours before using, at a temperature between 7 and 30 degrees C (45 and 85 degrees F).
2.02 MIXING AND TINTING.
A. Unless otherwise specified herein or pre‐approved, all paint shall be ready‐mixed and pre‐tinted.
Re‐mix all paint in containers prior to and during application to ensure break‐up of lumps, complete dispersion of settled pigment, and color and gloss uniformity. Where thinner is used, addition shall not exceed paint manufacturer's recommendations.
PART 3 – EXECUTION
3.01 GENERAL REQUIREMENTS.
A. Observe required safety regulations and manufacturer's warning and instructions for storage, handling and application of painting materials.
1. Take necessary precautions to protect personnel and property from hazards due to falls, injuries, toxic fumes, fire, explosion, or other harm.
2. Deposit soiled cleaning rags and waste materials in metal containers approved for that purpose. Dispose of such items off the site at end of each day’s work.
B. Atmospheric and Surface Conditions.
1. Do not apply coating when air or substrate conditions are:
a. Less than 3 degrees C (5 degrees F) above dew point.
b. Below 10 degrees C (50 degrees F) or over 35 degrees C (95 degrees F), unless specifically pre‐approved by the COTR and the product manufacturer. Under no circumstances are application conditions to exceed manufacturer recommendations.
c. When the relative humidity exceeds 85 percent; or to damp or wet surfaces; unless otherwise permitted by the paint manufacturer’s printed instructions.
d. Maintain interior temperatures until paint dries hard.
3.02 CONDITION AND PREPARATION OF SURFACES.
A. The condition and preparation requirements for all surfaces shall be in accordance with
MPI Painting Manual requirements.
B. All walls previously coated with fabric wall covering shall have all residual fabric covering adhesive removed and surface cleaned in order to accept the new paint.
3.03 PAINT REQUIREMENTS.
A. Paint interior surfaces in accordance with the applicable MPI Painting Manual requirements:
1. Concrete Masonry Units: Low/no VOC semi‐gloss latex paint (2 coats).
2. Interior steel door/stairwell. Low/no VOC enamel alkyd semi‐gloss (1 coat).
3.04 FIELD QUALITY CONTROL.
A. Painted surfaces shall be considered to lack uniformity and soundness in accordance with defects noted in the MPI Painting Manual.
B. Painted surfaces rejected by the inspector shall be made good at the expense of the
Contractor in accordance with MPI Painting Manual requirements.
C. Protection and Clean‐Up.
1. Protect all newly painted exterior surfaces from elements condensation and contamination until paint coatings are completely dry. Erect barriers or screens and post signs to warn of or limit or direct traffic.
2. Remove all spilled, splashed, splattered or over sprayed paint as work progresses, remove waste materials and keep area free from an unnecessary accumulation of tools, equipment, surplus materials and debris.
End Section 09 91 00
SECTION 22 44 00‐ PLUMBING FIXTURES
1.01 GENERAL REQUIREMENTS.
A. Scope of Section. Installation of all lavatory fixtures including water closets, urinals, automatic flush valves electric water coolers and faucets as shown on the drawing schedule(s). This includes all associated piping, traps, pipe fittings, escutcheons, hoses, trim, hardware, blocking, anchoring, caulking, etc. necessary for a complete installation and operation.
B. Related Requirements. Reference the Table of Contents for related sections.
C. Submittals. Reference Appendix I of this statement of work submittal requirements.
D. Where supply or drain pipe has to be offset due to beam or stud interference, provide correct and additional piping necessary to eliminate relocation of water closet at no cost to the government.
A. Manufacturer: Provide products manufactured by a company with a minimum of 10 years successful experience manufacturing similar products.
B. Single Source Requirements: To the greatest extent possible provide products from a single manufacturer, unless noted.
C. Accessibility Requirements: Comply with requirements applicable in the jurisdiction of the project, including but not limited to ADA and ICC/ANSI A117.1 requirements as applicable.
D. Hazardous Materials: Comply with EU Directive “Restrictions of Hazardous Substances (RoHS) requirements.”
1.03 DELIVERY, STORAGE, AND HANDLING.
A Deliver, store and handle materials and products in strict compliance with manufacturer's instructions and recommendations. Protect from damage. Replace any damaged material at no cost to the Government as required by the COTR.
1.04 WARRANTY .
A. Manufacturer’s Warranty For Plumbing Fixtures: Provide a manufacturer’s standard 1 year warranty for materials and workmanship.
PART 2 ‐ PRODUCTS
2.01 MANUFACTURER.
A. Material or equipment containing a weighted average of greater than 0.25 percent lead is prohibited in any potable water system intended for human consumption, and shall be certified in accordance with NSF 61 or NSF 372. Endpoint devices used to dispense water for drinking shall meet the requirements of NSF 61.
B. Plastic pipe, fittings, and solvent cement shall be Low/No VOC and meet NSF 14 and shall be NSF listed for the service intended.
PART 3 ‐ EXECUTION
3.01 INSTALLATION.
A. Inspect areas scheduled to receive plumbing fixtures for correct dimensions, plumb ness of walls, and soundness of surfaces that would affect installation of mounting brackets.
B. Verify spacing of plumbing fixtures to assure compatibility with installation of compartments.
C. Prepare substrates including but not limited to blocking and supports in walls and ceilings at points of attachment using methods recommended by the manufacturer for achieving the best result for the substrates under the project conditions.
D. Do not proceed with installation until substrates have been properly prepared with blocking and supports in walls and ceilings at points of attachment and deviations from the manufacturer's recommended tolerances are corrected.
E. Install products in strict compliance with manufacturer’s written instructions and recommendations, including the following:
1. Verify blocking has been installed properly.
2. Verify location does not interfere with door swings or use of fixtures.
3. Comply with manufacturer’s recommendations for backing and proper support.
4. Use fasteners and anchors suitable for substrate and project conditions.
5. Install units rigid, straight, plumb, and level, in accordance with manufacturer’s installation instructions and approved shop drawings.
6. Conceal evidence of drilling, cutting, and fitting to room finish.
7. Test for proper operation.
8. Openings between fixture, floors, and wall finishes shall be caulked, color to match fixture.
F. Supports and Fastening:
1. Secure all fixtures, equipment and trimmings to partitions, walls and related finish surfaces. Exposed heads of bolts and nuts in finished rooms shall be hexagonal, polished chrome plated brass with rounded tops.
2. Through Bolts: For free standing marble and metal stud
3. Toggle Bolts: For hollow masonry units, finished or unfinished.
4. Expansion Bolts: For brick or concrete or other solid masonry. Shall be 6 mm (1/4 inch) diameter bolts, and to extend at least 76 mm (3 inches) into masonry and be fitted with loose tubing or sleeves extending into masonry. Wood plugs, fiber plugs, lead or other soft metal shields are prohibited.
5. Power Set Fasteners: May be used for concrete walls, shall be 6 mm (1/4 inch) threaded studs, and shall extend at least 32 mm (1 1/4 inches) into wall.
6. Lightly cover and protect fixtures and equipment against dirt, water and chemical or mechanical injury.
7. If an installation is unsatisfactory to the COR, the Contractor shall correct the installation at no cost or additional time to the Government.
8. Adjust automatic flush valves faucets, urinals and toilets for proper operation after installation.
3.02 CLEANING AND PROTECTION.
A. Clean exposed surfaces of compartments, hardware, and fittings using methods acceptable to the manufacturer.
B. Touch‐up, repair or replace damaged products until substantial completion.
End of Section 22 44 00
FA
A ‐C ‐3
M ay , 2
P P
EN
D
IX
S C H
ED
U
LE
O F
SU
B M
IT
TA
LS
G
EN
ER
A L C O N
ST
R U C
TI
O N
Su b m it ta l
N o
D es cr ip ti o n
R ef er en ce S o u rc es P ro d u ct te s m it ta l R e q u ir em e ts
D at e
R ec e iv ed e
A p p ro ve d
C o n tr ac to r P er so n el
In fo rm at io
S u b m it a li st o f n am es a n d a n y o th er s ec u ri ty r el at ed e m p lo ye e in fo rm at io n a s re q u ir ed b y th e
C o n tr ac ti n g O ff ic er
W o rk S ch ed le u b m it C o n tr ac to r’ s sc h e d in cl u d in g al l m aj o r co n st ru ct ac ti vi ti es , i n cl u d in g, b u t n o t lim it e d t o
P ro je ct m o b ili za ti o n
Se q u e n ce o f w o rk
D is ru p ti o n s in s er vi ce i.e w at er , e le ct ri ca l, fi re d et e ct io n et c.
‐C ‐3
M ay , 2
EN
ER
A L C O N
ST
R U C
TI
O N C O N
TI
N U
ED
m it ta l
N o
D es cr ip ti er en ce S o u rc es /P ro d m it ta l R e q u ir em e e
R ec e e
A p p ro
Sa fe ty P la u b m it t h e C o n tr ac to r’ s ge n al sa fe ty p la n in cl u d in g sp ec ia l p re ca u ti o n s to b e ta ke n w o rk in g n ea r
FA
A s tr u ct u re s an eq ip m en t.
C o p ie s o f M at er ia l D at a Sa fe ty
Sh ee ts in cl u d in g V O C in fo rm at r al l p ai n ts , a d h es iv es , s ea la n ts gr o u t, e tc . u se d in t h is p ro je
‐C ‐3
M ay , 2
C H
IT
EC
TU
R
L m it ta l
N es cr ip ti er en ce S o u rc es /P ro d te s
Su b m it ta l R e q u ir em e e
R ec e e
A p p ro
R es tr o o m a
K it ch en
/B re ak R o o m ar ea x2 a co u st ic su sp en d ed c e ili n g (g ri t ile s)
A rm st ro n g P e ak ‐f rm
St ee l G ri am p le o f gr id a n d x2 f o r a p p ro va l
G ri d C o lo r:
W h e
W l a n d D o o r
P ai
B ja m in M o o re A ra h a n d S p a o r eq u iv al en t in te ri o r b at h ro o m p ai u b m it c o lo r sa m p le s
V O C r ef er en ce f o r ap p ro va l.
Fi is h : s em i‐ gl o ss
6.
C ar p et T ile s.
M h h aw k In d u st ry h ig h tr af fi c co m m er ci al lo o p p x2 c ar p et t u b m it s am p le c ar p e t ti le s fo r ap p ro
‐C ‐3
M ay , 2
C H
IT
EC
TU
R A L (C O N
TI
N U m it ta l
N o
D es cr ip ti er en ce S o u rc e/ P ro d te s d
Su b m it ta l R e q u ir em e e
R ec e e
A p p ro
7.
M et al lo ck
Ly n lo ck ab le s in gl e m et lo ck er s W X h ig h , 1 d ee p
S u b m it g en er al p ro d rm at io n
S u b m it c o lo r fo r ap p ro
8.
V yl w al l b as e.
p ee
/8 C o m m er ci vi yl b as e.
u b m it s am p le c ar p e t ti le s
Fo r ap p ro
9.
K it ch en
/B re ak ro ca in e t la m in
C ab in et F in is h . P ro vi ro d u ct c u t sh ee ts f la in at e f in is h a ar d w ar e fo r ap p ro
‐C ‐3
M ay , 2
C H
IT
EC
TU
R A L (C O N
TI
N U m it ta l
N o
D es cr ip ti er en ce S o u rc e/ P ro d te s
Su b m it ta l R e q u ir em e e
R ec e e
A p p ro
R es tr o o m a cc es so ri es
R ef er en ce D ra w in g C ‐3 ‐A re fe re n ce s o u rc es
S u b m it g en er al p ro d ch n ic al in fo rm at io n f o r th o se it e m s lis te d f o r ap p ro
F is h : s at
ES
D C ar er en ce t h e st at e m en t o f w o rk f o r
ES
D c ar p et r e q u ir em e n ts
F o r th e kn o w n a cc ep ta so rc e fo r
ES
D c ar p et a ad es iv e su b m it t ge er al p ro d u ct t e ch n rm at io n , i n cl u d in g co lo rs f o r ap p ro va l.
Fo r al te rn at e
ES
D p ro vi d er s su b m it d o cu m en ta ti th t h e a lt er n at e ca rp a d h es iv e m ee ts o r ex ce ed s th e re q u ir em t h e st at em en t o f w rk n g w it h c o lo rs f o r se le ct io
‐C ‐3
M ay , 2
LU
M B
IN
m it ta l
N o
D es cr ip ti er en ce S o u rc e/ P ro d te s
Su b m it ta l R e q u ir em e e
R ec e e
A p p ro
G ar b ag e D is p o sa l* ad ge r™
/2 H P , 2 z.
gr d in g ch am b er c ap ac y, V
S u b m it g en d u ct t ec h n rm at io n f o r ap p ro
W at er f ilt er s ys te el ic an
M o d el P D F‐
‐S ta ge U n d e r‐ C o u n te r D ri n ki n g
W at er F ilt er S ys te m
S u b m it g en d u ct t ec h n rm at io n f o r ap p ro
W al l M o u n te d T o er en ce D ra w in g C ‐3
A f o r re fe re n ce s o u rc es
S u b m it g en d u ct t ec h n rm at io n f o r ap p ro va l.
S u b m it O M m an u al s in cl u d in g re p la ce m e
‐C ‐3
M ay , 2
M B
IN
m it ta l
N o
D es cr ip ti er en ce S o u rc es /P ro d te s
Su b m it ta l R e q u ir em e e
R ec e e
A p p ro
A u to m at ic F lu sh V er en ce D ra w in g C ‐3
A f o r re fe re n ce s o u rc es
S u b m it g en d u ct t ec h n rm at io n f o r ap p ro va l.
S u b m it O M u al s in cl u d in g re p la ce m en t p ar
Si k er en ce D ra w in g C ‐3 f o r re fe re n ce s o u rc es
S u b m it g en d u ct t ec h n rm at io n f o r ap p ro
F is h : W h
Fa u ce er en ce D ra w in g C ‐3 ‐A re fe re n ce s o u rc es
S u b m it g en d u ct t ec h n rm at io n f o r ap p ro
‐C ‐3
M ay , 2
M B
IN
G C o n ti n u e m it ta l N o
D es cr ip ti er en ce S o u rc es /P ro d e
R ec e e
A p p ro
K it ch en
S k*
Tu sc an y™ T o p M o u n t
St ai n le ss S te e l 4 ‐H o le D o u w l K it ch en
S k u b m it g e n d u ct t ec h n rm at io n f o r ap p ro
K it ch en
S in k Fa u ce t*
Zu rn B ‐X L
S u b m it g e n er al p ro d ch n ic al in fo rm at ap p ro
‐C ‐3
M ay , 2
EL
EC
TR
IC
L m it ta l N o
D es cr ip ti er en ce S o u rc e/ P ro d te s
Su b m it ta l R e q u ir em e e
R ec e e
A p p ro
R es tr o o m a ch en
/B re ak ro o m x4 a n d v an it y
LE
D li gh t f ix tu re s
R ef er en ce d ra w in gs f o r re q u ir em u b m it g en d u ct t ec h n rm at io n c u t sh ee ts f o r la u si n g, b al la st s, a s fo r ap p ro
Fi is h : W h
R es tr o o m a ch en
/B re ak ro o m G
FC
I R ec e p ta cl es , L ig h t
Sw it ch es , W al l p la te s, e tc u b m it g en d u ct t ec h n rm at io n c u t sh ee ts f o r la u si n g, b al la st s, a s fo r ap p ro
‐C ‐3
M ay , 2 s:
In d ic at es O p ti o n B id W o rk
. I n st al l n ew r es tr o o m fi xt u re s in a cc o rd an ce w it h t h e la te st A m er ic an In st itu te o f A rc hi te ct s (A
IA
an d A m er ic an w it h D is ab ili es
A D A re q u ir em en ts t o t h e ex te n t p o ss ib le
. R ef er en ce t h is s ta te m en t o f w o rk f o r ad d it io n al r e q u ir em e n ts
. F ie ld lo ca te t h e la yo u t o f th e n ew a cc es so ri es t o b e in st al le d a lo n g w it h t h e C O R
En d A p p e n d ix I
| 370 Cover |
| 0412 22 44 00 |
| 0412 370 Pics |
| 0412 Appendix I |
| 0412 Section 09 68 00 |
| 0412 Section 09 91 00 |
| 0413 011101 |
| 0413 MAPS |
| 041221 TOC |
File details come from the government source that posted it. Updated .