Attachment II Vendor Price Sheet.xlsx

XLSX spreadsheet 16 KB Posted

Attached to
SRRF -FB 682 DRYDOCK & REPAIR
Solicitation number
6933A225Q000012
Issued by

About this file

This is a vendor pricing template (Attachment II) for federal solicitation 6933A225Q000012 seeking drydock and repair services for SRRF-FB 682 barge through the Department of Transportation Maritime Administration.

The pricing sheet outlines seven major work categories: delivery/towing services including tug service and fuel surcharges; drydocking operations with 30-day duration including blocking, docking/undocking, safety equipment setup, and 20 lay days; exterior hull cleaning and inspection covering 8,289 square feet including high-pressure washing and CFR inspection reporting; surface preparation involving SP6 blasting of 8,289 square feet with grit usage and disposal; optional steel work for removing pad eyes and handrail supports; exterior coating work covering underwater hull (5,787 sf), above water hull (1,426 sf), and main deck (3,520 sf) with multiple coat applications; and cathodic protection involving removal of 56 zinc anodes and installation of 56 new aluminum anodes. Additional work includes fendering removal and reinstallation with blast and coating, plus supplemental labor (200 hours) and materials ($30,000). The work must be performed at a contractor's shipyard within the San Francisco Bay area including Sacramento and Stockton due to the vessel not being deep-seaworthy. A mandatory site visit is scheduled for August 12, 2025 at the Suisun Bay Reserve Fleet in Benicia, California.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

VENDOR PRICE
FB-682 DDX 2025
CLINDESCRIPTIONQTYU/MHRSUNIT
PRICETOTALCOMMENTS
1.1Delivery/Towing1job
Furnish Tug Service RT SBRF-Shipyard, subktr$2way0
Maneuver to/from DD1job0
incl pilotage and other services as req'd0ls0
Fuel surcharge (est cap at 25% of tow rate)1ls0
1.2Drydocking (incl LayDays)1job
build blocks, dock, undock1ea30
haul day (120'x$10/ft = $1200)1day0
Set up/rmv stair tower1job6
Set up/rmv fire protection1job6
R&R temp OSHA-req'd fall protection main deck1ls8est for weighted base stanchions
Lay days (120'x$10/ft = $1200)20day0
all tug assist on/off dock by Yard2ls12incl in towing
fleet vessel for 100% coverage1ls8
DD report - Mark up blocking and anode locations1lot2

1.3 Exterior Hull Cleaning & Inspection 8289 sf

secure all openings to prevent ingress of water1ls2
HP wash (3Kpsi) entire bage8289sf0.003
CFR- Inspect report1ls1
Wash & cleanup drydock area1ls8
handling, store, & disposal of hazmat (if any)0lot0
misc consumables adjustment20hrs0
1.4Surface Preparation8289sf
Secure hatches, vent protection, manhole covers1ls4
R/R shrouding for blast and coating1ls15
SP68289sf0.04
Manlift 2 ea.16hrs1
Grit usage (.002 tons/sqft)17ton4
Blow down and clean up1job8
Inspection & report1ls2
submit CFR with findings/recommendations1ls1
Grit Disposal24ton0
misc consumables adjustment100hrs0
1.5Steel Work Optional
A.Remove small pad eyes from deck8ea0.5
BRemove hand rail stantion supports34ea0.5

misc consumables adjustment 20 hrs 0

1.6Exterior Coating
UWH (K-WL)5787sf0
2 full coats AC11574sf0.008
2 full coats AF11574sf0.008
Above Water Hull (WL-DE) aka Freeboard1426
2 full coats AC2852sf0.008
1 full coat urethane (black)1426sf0.008
paint in hull #, draft marks with 2 full cts high gloss modified acrylic (white)1ls10
Main Deck3520
2 full spray coats AC0sf0.008
1 full coat urethane to perimeters0sf0.008
1 full roll coat 5150LWT0sf0.012
misc consumables adjustment100hrs0
1.7Cathodic Protection
Remove 56 zn anodes and scrap56ea0.7
install 56 new aluminum anodes56ea0.35
misc consumables adjustmenthrs0
1.8R/R Fendering
ARemove SS bolts240ea0.07
BProvide written CFR within 24 hrs for bolts240ea0.015
CRemove fendering1job50
DBlast and Coat SP 6
Ereinstall fendering1job75
manlifts 4 ea.4hrs12
ea
misc consumables adjustment40hrs0
2Other Supplemental Labor & Materials
2.1provide 200 man hours of supplemental repair on yard-wide basis200hrs1
2.2Supplemental Material (30k)1ls0$ 30,000.00

GRAND TOTAL