The file's text, extracted by GovTribe without its formatting.
Sheet1
| | VENDOR PRICE | | | | |
| | FB-682 DDX 2025 | | | | |
| CLIN | DESCRIPTION | QTY | U/M | HRS | UNIT |
| PRICE | TOTAL | COMMENTS | | | | |
| 1.1 | Delivery/Towing | 1 | job | |
| Furnish Tug Service RT SBRF-Shipyard, subktr$ | 2 | way | 0 |
| Maneuver to/from DD | 1 | job | 0 |
| incl pilotage and other services as req'd | 0 | ls | 0 |
| Fuel surcharge (est cap at 25% of tow rate) | 1 | ls | 0 |
| 1.2 | Drydocking (incl LayDays) | 1 | job | | |
| build blocks, dock, undock | 1 | ea | 30 | |
| haul day (120'x$10/ft = $1200) | 1 | day | 0 | |
| Set up/rmv stair tower | 1 | job | 6 | |
| Set up/rmv fire protection | 1 | job | 6 | |
| R&R temp OSHA-req'd fall protection main deck | 1 | ls | 8 | est for weighted base stanchions |
| Lay days (120'x$10/ft = $1200) | 20 | day | 0 | |
| all tug assist on/off dock by Yard | 2 | ls | 12 | incl in towing |
| fleet vessel for 100% coverage | 1 | ls | 8 | |
| DD report - Mark up blocking and anode locations | 1 | lot | 2 | |
1.3 Exterior Hull Cleaning & Inspection 8289 sf
| secure all openings to prevent ingress of water | 1 | ls | 2 |
| HP wash (3Kpsi) entire bage | 8289 | sf | 0.003 |
| CFR- Inspect report | 1 | ls | 1 |
| Wash & cleanup drydock area | 1 | ls | 8 |
| handling, store, & disposal of hazmat (if any) | 0 | lot | 0 |
| misc consumables adjustment | 20 | hrs | 0 |
| 1.4 | Surface Preparation | 8289 | sf | |
| Secure hatches, vent protection, manhole covers | 1 | ls | 4 |
| R/R shrouding for blast and coating | 1 | ls | 15 |
| SP6 | 8289 | sf | 0.04 |
| Manlift 2 ea. | 16 | hrs | 1 |
| Grit usage (.002 tons/sqft) | 17 | ton | 4 |
| Blow down and clean up | 1 | job | 8 |
| Inspection & report | 1 | ls | 2 |
| submit CFR with findings/recommendations | 1 | ls | 1 |
| Grit Disposal | 24 | ton | 0 |
| misc consumables adjustment | 100 | hrs | 0 |
| 1.5 | Steel Work Optional | | | |
| A. | Remove small pad eyes from deck | 8 | ea | 0.5 |
| B | Remove hand rail stantion supports | 34 | ea | 0.5 |
misc consumables adjustment 20 hrs 0
| 1.6 | Exterior Coating | | | |
| UWH (K-WL) | 5787 | sf | 0 |
| 2 full coats AC | 11574 | sf | 0.008 |
| 2 full coats AF | 11574 | sf | 0.008 |
| Above Water Hull (WL-DE) aka Freeboard | 1426 | | |
| 2 full coats AC | 2852 | sf | 0.008 |
| 1 full coat urethane (black) | 1426 | sf | 0.008 |
| paint in hull #, draft marks with 2 full cts high gloss modified acrylic (white) | 1 | ls | 10 |
| Main Deck | 3520 | | |
| 2 full spray coats AC | 0 | sf | 0.008 |
| 1 full coat urethane to perimeters | 0 | sf | 0.008 |
| 1 full roll coat 5150LWT | 0 | sf | 0.012 |
| misc consumables adjustment | 100 | hrs | 0 |
| 1.7 | Cathodic Protection | | | |
| Remove 56 zn anodes and scrap | 56 | ea | 0.7 |
| install 56 new aluminum anodes | 56 | ea | 0.35 |
| misc consumables adjustment | | hrs | 0 |
| 1.8 | R/R Fendering | | | |
| A | Remove SS bolts | 240 | ea | 0.07 |
| B | Provide written CFR within 24 hrs for bolts | 240 | ea | 0.015 |
| C | Remove fendering | 1 | job | 50 |
| D | Blast and Coat SP 6 | | | |
| E | reinstall fendering | 1 | job | 75 |
| manlifts 4 ea. | 4 | hrs | 12 |
| | | ea | |
| misc consumables adjustment | 40 | hrs | 0 |
| 2 | Other Supplemental Labor & Materials | | | | |
| 2.1 | provide 200 man hours of supplemental repair on yard-wide basis | 200 | hrs | 1 | |
| 2.2 | Supplemental Material (30k) | 1 | ls | 0 | $ 30,000.00 |
GRAND TOTAL