This is a Performance Work Statement (PWS) for the procurement of a PrograMill 7 Dental Mill System and associated maintenance services for the Defense Health Agency at Eisenhower Army Medical Center, Fort Gordon, Georgia. The contract is a non-personal services agreement requiring the contractor to deliver, install, and maintain one PrograMill 7 milling system capable of dry milling dental materials including resins, wax, and zirconia. The Area Dental Laboratory currently processes approximately 30,000 units annually and supports over 130 Army dental treatment facilities worldwide; five existing dry mills have exceeded their life expectancy by two years, making the new system critical for sustained dental prosthesis fabrication capabilities.

The system must meet specific technical requirements including a 5-axis simultaneous control system with repetition accuracy of ±0.003 mm, a high-frequency synchronous spindle reaching 60,000 rpm with 300 watts continuous power, an automatic tool changer with 16-tool magazine capacity, and seamless integration with existing CAD/CAM equipment. The contractor must provide annual preventative maintenance visits including 5-axis calibration, spindle inspection, tool changer verification, suction filter replacement, and hardware cleaning. For corrective maintenance and repairs, the contractor must provide diagnostic services with tech support available 0630–1500 daily, respond within two hours of contact, and complete on-site visits within two business days. Software and firmware updates must be supplied as released by the original equipment manufacturer. The Period of Performance begins September 30, 2026 through September 29, 2027, with four optional one-year renewal periods extending through September 29, 2031. Work shall be performed at U.S. Army Dental Laboratory, Building 322, Fort Gordon, Georgia, during business hours Monday–Friday, 0630–1500, excluding federal holidays.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DHA PWS Template Under SAT

August 2022 Rev. 1

Department of Defense

Defense Health Agency

Performance Work Statement

PrograMill 7 Dental Mill System and Maintenance Services

24 July 2026

Eisenhower Army Medical Center

Fort Gordon, Georgia

August 2022 Rev. 1

1.0 General Information

1.1 This is a non-personal services contract to provide PrograMill 7 Dental Mill System, along with associated annual maintenance and repair services.

1.1.1 Description of services/introduction: The contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to deliver, install, and maintain PrograMill 7 Dental Mill System as defined in this Performance

Work Statement (PWS).

1.1.2 Background: On 01 August 2022, U.S. Dental Laboratory located at Eisenhower Army Medical

Center, Fort Gordon, Georgia awarded contract W91YTZ22P0073 to Ivoclar Vivadent, Incorporated for

Dental Maintenance Services. The period of performance for the contract is 01 August 2022 through 31

July 2026. The Area Dental Laboratory (ADL) requests the procurement of one (1) PrograMill 7 milling system to sustain critical dental prosthesis fabrication capabilities. The ADL is the only full-service dental laboratory with the ability to fabricate a variety of dental prostheses to support over 130 Army dental treatment facilities worldwide. The majority of these dental restorations are produced utilizing a digital workflow that relies heavily on computerized milling technology. Dry milling, as opposed to wet milling, is the required method for processing wax, resins, and zirconia. These materials are essential to the fabrication of crowns, bridges, dentures, and implant restorations. The ADL currently processes approximately 30,000 units annually utilizing a dry milling process. The ADL currently owns 5 dry mills.

Each of these five systems has exceeded its life expectancy by two (2) years.

1.1.3 Scope: Services include delivery, setup, and ongoing preventative and corrective maintenance of the PrograMill 7 Dental Mill System. The contractor shall accomplish the installation of the base system and its scope of delivery (including the PrograMill Suction Unit, CAM software, PC/Monitor, and all associated accessories). Following installation, the contractor shall provide ongoing maintenance to ensure the machine can accurately dry mill zirconia, polymethylmethacrylates (resins), and wax to fabricate inlays, onlays, crowns, bridges, and complete dentures.

1.1.4 Period of Performance (PoP): The contractor shall provide the PrograMill 7 Dental Mill System along with maintenance services per the Performance Work Statement on 30 September 2026. The Period of Performance has a base period of 30 September 2026 through 29 September 2027, including four optional periods.

Option Period One (1): 30 September 2027 through 29 September 2028

Option Period Two (2): 30 September 2028 through 29 September 2029

Option Period Three (3): 30 September 2029 through 29 September 2030

Option Period Four (4): 30 September 2030 through 29 September 2031

1.2 Administrative specifications

1.2.1 Place of performance: The work shall be performed at U.S. Army Dental Laboratory, Eisenhower

Army Medical Center, 300 E Hospital Rd Bldg., 322, Fort Gordon, Georgia.

1.2.2 Recognized Federal holidays: The contractor is not required to conduct business on Federally recognized holidays and Presidential Executive Orders.

August 2022 Rev. 1

1.2.3 Hours of operation: The contractor is responsible for conducting business Monday through Friday, 0630-1500, except Federal holidays or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings. The contractor must at all times maintain an adequate workforce for the uninterrupted performance of all tasks defined within this PWS when the Government facility is not closed for the above reasons.

1.3 Contractor Identification

1.3.1 Contractor personnel performing services in a contractor capacity in a Government facility are required to possess and wear an identification badge that displays his or her name and the name of their company. Ensure all those with whom the person interacts in any face-to-face dealings while supporting the Government understands that the person is contractor support personnel.

2.0 Specific Tasks

2.1 The PrograMill 7 Dental Mill System is required for the dry milling of various dental materials, including resins, wax, and zirconia.

2.2 System Performance: The PrograMill 7 Dental Mill System must feature a 5-axis simultaneous control system and software with short calculation times. The system must intelligently calculate milling strategies based on specific material properties to ensure highly accurate and efficient milling of external/internal contours and preparation margins.

2.3 The PrograMill 7 Dental Mill System must provide a repetition accuracy of ± 0.003 mm. The spindle must demonstrate a concentricity deviation at the inner cone < 3 μm.

2.4 The system must be a high-frequency synchronous spindle with a speed of up to 60,000 rpm, a peak power (Pmax) of 500 watts, and continuous power of 300 watts.

2.5 The PrograMill 7 Dental Mill System must include an automatic tool changer with a magazine capacity for at least 16 tools, and feature tool length measurement and breakage monitoring.

2.6 The system must be fully compatible with the ADL's currently owned CAD/CAM equipment, ensuring seamless integration into existing digital workflows.

2.7 Integration and Setup: The contractor shall configure the system ensuring full compatibility and seamless integration with the ADL's currently owned Computer-Aided Design/Computer-Aided

Manufacturing (CAD/CAM) equipment.

2.8 Validation: The contractor shall ensure the system meets all operational parameters, including 5-axis simultaneous control along with proper vacuum suction integration.

2.9 Annual Preventative Maintenance (PM): The contractor shall provide annual preventative maintenance visits to ensure the equipment operates at OEM specifications. The preventative maintenance includes calibration of the 5-axis system, inspection of 60,000 rpm high-frequency spindle, verification of the automatic tool changer, replacement of suction unit filters, and cleaning of the internal hardware components.

2.10 Repairs and Corrective Maintenance

August 2022 Rev. 1

2.10.1 Service Calls: The contractor shall provide diagnostic and repair services for system malfunctions, including issues with the milling hardware, pneumatic tool clamping, or the integrated CAM software.

2.10.2 Response Time: The contractor shall provide tech support from 0630-1500, daily, within two (2) hours of initial contact, and if an on-site visit is required, be on-site within two (2) business days.

2.10.3 Repair Reports: Upon completion of any repair, the contractor must provide a detailed service report to the Contracting Officer Representative (COR), outlining the fault, the corrective action taken, and any replacement parts used.

2.11 Software and Hardware Updates

2.11.1 CAM Software Maintenance: The contractor shall provide and install ongoing updates to the

PrograMill CAM software to ensure continued seamless data transfer between the CAD and CAM formats.

2.11.2 Firmware Updates: The contractor shall supply updateable hardware patches for the FPGA-integrated processors and 5-axis control electronics as released by the OEM.

3.0 Salient Characteristics

3.1 The system shall utilize advanced CAM software capable of executing rapid computational processing and calculation cycles. It must feature a high-precision, five-axis simultaneous motion control system to govern all milling operations.

3.2 The system shall employ an intelligent CAM output format that establishes a seamless interface between the CAD and CAM software environments. The software must facilitate the uninterrupted, loss-free transfer of critical manufacturing datasets between CAD and CAM software, including:

• Restoration design classifications (e.g., inlays, onlays, crowns, bridges, dentures).

• Material specifications and dimensional attributes.

• Milling configuration parameters.

3.3 The software shall automatically calculate and execute optimized milling strategies. This calculation must guarantee maximum efficiency and high accuracy during the fabrication of intricate external and internal restoration contours and preparation margins.

3.4 Features

3.4.1 The system shall feature a compact footprint not to exceed 18 x 15 inches. The system shall utilize a five-axis machining configuration consisting of three (3) linear axes and two (2) rotational axes to facilitate complex geometric milling.

3.4.2 The unit shall support high-speed data transmission via a standard external USB interface, external compressed air supply, free disc fixing system (98.5 to 98.8 mm diameter), Ivotion denture holder, and automatic tool changer.

3.4.3 Tooling must utilize a standardized, color-coded ring system. Each distinct color ring shall correspond to a specific designated material class. Color coding allows for intuitive and easy tool management.

August 2022 Rev. 1

3.4.4 Base System: Construction machine bed made of solid cast aluminum body. Sheet steel housing, white high-gloss lacquer finish with working chamber flap and accessories drawer. Five axes – 3 linear

(X/Y/Z) and 2 rotational (A/B). An axis: precision ball screws, rolled version, motors with resolution < 1 μm, ground precision guides made of high-alloyed steel, repetition accuracy ± 0.003 mm, backlash-free

Harmonic-Drive with highest concentricity, rotation angle of 360°, infinite rotary axis. B-axis: precision ball screw with rotary transmission, angle of rotation of ± 35° axis arrangement in the work piece control unit. 5-axis simultaneous control electronics with continuous path progression and dynamic pre-calculation. Hardware-based real-time operating system with standardized instruction set. FPGA-integrated processors. Updateable hardware. Real-time path calculation via dedicated hardware engines in the FPGA. Four-quadrant control of the motors for particularly smooth running. Multiple analogues and digital I/Os for controlling the peripherals. Integrated inverter for synchronous and asynchronous motors, electronic gate detection. Ethernet and USB interface. RGB LED lighting with status display in the working chamber.

3.4.5 Accuracy: 3 μm repetition accuracy. Premium spindle with 4-fold hybrid ceramic ball bearings for highest running accuracy. Solid cast body for the lowest vibrations.

3.4.6 Spindle: High-frequency spindle, synchronous with pneumatic tool clamping sealing air to prevent debris from entering. Automatic cone cleaning. Speed up to 60,000 rpm. Peak power (Pmax) of 500 watts. Nominal power (S6) of 450 watts. Continuous power (S1) of 300 watts. 4-fold hybrid ceramic ball bearing with concentricity deviation at inner cone < 3 μm. Stainless steel collet for tools with 3 mm shank diameter and max. 40 mm total length.

3.4.7 Automation: Tool magazine for 16 tools. Tool length measurement and tool breakage monitoring via precision measuring key. Access via working chamber flap with safety lock.

3.4.8 Processing Modes: Dry processing with air nozzles on the spindle hose connection for external suction unit on the side of the housing. Vacuum sensor for monitoring the suction unit. 24 V switch output for controlling suction units.

3.4.9 Connection Requirements: Compressed air 6 to 8 bar with air purity according to ISO 8573-1:2010.

Hose connection for external air extraction system 45 mm in diameter. Power: 100-240 volts, 50/60 Hz, 640 watts. Extraction filter class M with 2500 l/min extraction capacity at 220 hPA. USB port 2.0 B. Data

10/100/1000 Mbit/s BaseT port (auto-sensing). Ethernet via RJ-45 socket.

3.4.10 Environmental Conditions: Operating temperature between 10 °C and 35 °C. Air moisture Max. 80

% (relative), non-condensing.

3.4.11 Dimensions & Weight: Dimensions (W/D/H) 450 × 545 × 630 mm with closed flap and drawer

450 × 695 × 680 mm with open flap and drawer. Footprint (W/D) 375 × 260 mm. Weight 91 kg.

3.4.12 Delivery Items

The following items are to be included with delivery:

• PrograMill Dry machine

• PrograMill Suction Unit

• Adapter connection to suction unit

• PrograMill/PrograPrint PC

August 2022 Rev. 1

• Monitor widescreen

• PrograMill CAM Set with RFID-Reader

• Control cable

• Keyboard

• Spindle service set

• Power cable

• USB cable

• Key for the emergency release of the working chamber door

• Pneumatic hose

• Administrated tool board (ATB) in the accessory’s container

• Cleaning brush for the material holder

• Crevice nozzle for cleaning the working chamber

• Compressed air regulator

• Calibration set: 1 micrometer, 3 calibration discs for manufacturing test and calibration specimen

• Radius cutter with 2 teeth (P200-R2-40)

• Measuring pin

• 2 tool magazine inserts

• Drill bit (2.8 mm) for tool positions

• Carrying aid for transporting the machine

• Transport lock in the working chamber

• Supplement about removing the carrying aid and transport lock

• 4 spare screws for the tool magazine cover

• Zirconium oxide tools

• Operating manual

4.0 Points of Contact

Charles J. Graham Contracting Officer Representative (COR) 706-787-5714 Charles.J.Graham4.civ@health.mil

Mr. Felix Sosagaston

Supply Technician

Phone: (706) 787-5717

Email Address: felix.sosagaston.civ@health.mil

Mr. Chau V. Tran

Supply Technician

Phone: (706) 787-6302