This document is a request for information template to be used for soliciting questions from contractors on federal construction projects. It specifies that the government requires any questions submitted to specifically identify the relevant specification or drawing number for clarification. Contractors are instructed to submit their name, city, state, phone number and email contact information along with the project number, specification or drawing references, and detailed questions. The government will respond to compliant questions through a solicitation amendment issued by the contracting officer.

The related federal contract opportunity is solicitation number 12905B23Q0175 for a borehole nuclear magnetic logging instrument with a shock proof case to be provided to the USDA Agricultural Research Service Pacific West Area office in Davis, California. Contractors are directed to use this template to submit any requests for additional information on the specifications.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR INFORMATION (RFI)

Award

PROJECT NUMBER: Please ensure that before submitting questions or requests for clarification that you thoroughly read the solicitation, specifications, drawings and other pertinent documents. When submitting questions on this project the Government requires contractors to specifically identify the specification and/or solicitation section(s) or drawing number(s) in reference to the question or request for clarification submitted. No question or request for clarification will be answered by the Government unless the above requirements are met. Failure to comply may prevent the Government from responding in a timely manner.

PROJECT TITLE:

PROJECT LOCATION:

SEND TO:

Email:

On subject line of email include the following: “ – RFI#___“

RFI #: DATE: SPEC/DWG. REFERENCE(s):

INFORMATION NEEDED:

REPLY:

Reply will be issued by Solicitation Amendment by the Contracting Officer

Offerors are responsible to retrieve and acknowledge all Amendments

ATTACHMENTS:

SUBMITTED BY: City/State:

PHONE NO.:

EMAIL:

Attachment 3 http://www.beta.sam.gov/ Jeffery.Ridenour Highlight

Jeffery.Ridenour Highlight

COR Comments: Attachment 3

PROJECT NUMBER:
Construction IDIQ:
U S Department of Agriculture Agricultural Research Service Pacific West Area 800 Buchanan Street Albany CA 94710:
SUBMITTED BY:
CityState:
PHONE NO:
EMAIL:
RFI:
DATE:
SPECDWG REFERENCEs:
INFORMATION NEEDED:
ATTACHMENTS:
Text1:
Text2: USDA/ARS/PWA–POC
Text3: POC@usda.gov
Text4:
Text5:
Text6: