Attachment I - Statement of Work_Redacted.pdf

PDF 272 KB Posted

Attached to
C1DA--AE Design: Renovate/Expand Sterile Processing Federal contract opportunity
Solicitation number
36C25022R0093
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 10

About this file

This document is a request for Standard Form 330 submissions from architect and engineering firms for design services related to a project to renovate and expand sterile processing at the Louis Stokes Cleveland VA Medical Center. The project scope includes programming, design submissions, construction documents, technical specifications, cost estimates, and construction administration services. Interested small business firms must be verified as service-disabled veteran-owned in the Vendor Information Pages database and registered in the System for Award Management to be eligible for consideration. Submissions are due by 4:00 PM Eastern on August 8, 2022 and will be evaluated based on experience and technical competence, professional qualifications, capacity, past performance, geographic location, and ability to comply with limitations on subcontracting to non-similarly situated firms. The design services contract is for a period of 252 calendar days with a construction budget estimated over $10 million.

View the file

Other files for this federal contract opportunity

Other files attached to C1DA--AE Design: Renovate/Expand Sterile Processing, newest first.
File Type Posted
36C25022R0093 0003.docx DOCX document
36C25022R0093 0002.docx DOCX document
Attachment I - Statement of Work - UPDATED as of 06-06-2022.pdf PDF
36C25022R0093 0001.docx DOCX document
36C25022R0093.docx DOCX document
Attachment II - Evaluation Criteria.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project: Renovate and Expand Sterile Processing Project Number: 541‐22‐102

RENOVATE AND EXPAND STERILE PROCESSING

541‐22‐102

03‐26‐2021

TABLE OF CONTENTS

SECTION TITLE

1.0 SCOPE OF WORK

2.0 GENERAL

3.0 PROPOSED CONSTRUCTION DOCUMENT SCHEDULE

4.0 MINIMUM REQUIREMENTS FOR SCHEMATIC DESIGN (SD) SUBMISSION

5.0 MINIMUM REQUIREMENTS FOR DESIGN DEVELOPMENT (DD) SUBMISSION

6.0 MINIMUM REQUIREMENTS FOR 65% SUBMISSION

7.0 MINIMUM REQUIREMENTS FOR 90% SUBMISSION

8.0 MINIMUM REQUIREMENTS FOR 100% SUBMISSION

9.0 MINIMUM REQUIREMENTS FOR FINAL SUBMISSION

10.0 CONSTRUCTION PERIOD SERVICES

1.0 SCOPE OF WORK

1. The A/E (Architect/Engineer) firm shall provide all Programming, Design Submissions, Site Investigation/ Field Verification Services, Asbestos Testing, Construction Documents, Technical Specifications, Cost Estimates, Reports, System Integrator Services and Construction Administration Services for the project “Renovate and Expand Sterile Processing” located at the Louis Stokes Cleveland VAMC, Cleveland, Ohio.

2. This is a multi‐phased project that will renovate approximately 18,000 square feet of Sterile Processing Services (SPS) and Sterile Processing and Distribution (SPD) space on the First Floor of the Main Medical Center. This project provides complete electrical, technology, mechanical, plumbing, fire protection and architectural upgrades.

3. This project may require the installation of a temporary trailer to serve the sterile supply and distribution function with a direct connection to the SPS area to allow space for a new sterile processing to be constructed while the current space remains operational. Once the new sterile processing space was completed the old space would be renovated for bulk storage and distribution.

4. This project will require the replacement of the existing Air Handling Unit for sterile processing.

5. This project will address any Facility Condition Assessment (FCA) issues that pertain to the project areas based on the most recent FCA report.

6. A/E firm shall develop construction documents for bidding for project award not to exceed the construction budget of for construction bidding in Fiscal Year 2023.

7. A/E firm shall develop a phasing plan for this project. Develop project phases as necessary to minimize disruption to the continued operation of the Medical Center. Phasing plans for all disciplines are to be produced to show all of the work that is being completed in a specific phase on separate plan drawings;

temporary partitions and contractor access doors that will be needed for the phase; temporary and final MEP connections that will need to be made for a fully functioning space at the end of a phase; and life safety travel distances at the end of each phase. The phasing plan shall include the scope and timing sequence of each identifiable phase or major activity. Each phase shall be described in terms of the work involved and the required preceding and follow‐on activities, such as staff relocations, underground utility locating services, and medical equipment procurement.

8. A/E firm shall provide up to 4 Deduct Bid Alternates for a minimum of 10% or greater of the Construction cost.

9. Project Schedule is 252 Calendar days from date of notice to proceed to complete Construction Documents, Technical Specifications and Cost Estimate of Construction. Completion of Construction Administration Services will be dependent upon award of Construction Contract.

10. As a part of this contract, the A/E firm shall field verify all existing conditions.

11. Six submissions are required (SD, DD, 65%, 90%, 100%, and Final) plus a Bid Issue submission which constitutes a complete bid package consisting of drawings, specifications, and detailed cost estimate.

12. Provide brand name product list to the COR for preparation of the VA brand name/ equal memo and/or sole source justification.

13. Provide a submittal log based on final specifications.

14. Provide wayfinding locations and solutions if the project modifies any of the facility entrances.

15. Enhanced Commissioning – The VA will employ a third‐party commissioning agent for this project to meet Federal Mandates requiring whole building commissioning and enhanced commissioning requirements. The commissioning authority will verify performance of building components and systems and to ensure design requirements are met, develop a commissioning plan, inclusion of commissioning requirements in construction documents, verification of installation and performance of commissioned systems (testing and system monitoring), operation & maintenance manuals and training, and a commissioning report. The A/E team shall work with the commissioning agent throughout the design and construction process to assure all sustainable objectives are met.

16. Independent Life‐Safety Review – The VA will employ a third‐party life‐safety reviewer for this project to provide a peer review of the project to ensure that the design meets the requirements of the most current version of the NFPA 101 Life Safety Code. The A/E team shall work with the independent life‐ safety reviewer throughout the design and construction process to assure that the requirements of the NFPA 101 Life Safety Code are being met. A/E shall respond in writing to the independent life‐safety reviewer review comments and incorporate any required changes into the Construction Documents.

17. A/E Firm shall engage a third party to provide Master System Integrator (MSI) Services. The MSI must have extensive experience with integrating building management systems using both open and proprietary communications protocols and using the Tridium Niagara Framework. (Reference List Available for MSI if requested). The MSI is to verify and coordinate with the A/E on the various tasks and duties that need to be clearly spelled out regarding the HVAC Contractor and the MSI. The MSI will coordinate work with the HVAC Contractor during construction, but the HVAC Contractor is to provide all VAV controllers and programming and any other devices required at the Tier 3 & 4 Levels. The MSI will program and provide graphics at Tier 1 & 2 and will coordinate with the HVAC Contractor to utilize the Cleveland VA naming convention for all points. The naming convention document guide is available and is to be adhered to. The MSI will be responsible for all professional services regarding the SBS including but not limited to programming (tagging, trending, mapping etc.), graphic design and implementation, design of any JACE and Network implementation as well as long‐term and short‐term trending recommendations in the specifications. The MSI will also verify the appropriate quantity of JACES’s and licensing required for the project based on the systems being installed and integrated into the SBS, system dashboard, analytics design and implementation which will be purchased by the HVAC contractor and programming by the MSI. The MSI is to verify if the facility has license and available points on existing JACES prior to the construction documents being sent out for bid. If additional JACES and Licenses are required, the HVAC Contractor is to be responsible for purchasing the required items.

The MSI shall provide all personnel, facilities, transportation, supplies and qualified supervision necessary to provide the technical/ professional services.

2.0 GENERAL

1. The A/E firm shall prepare all necessary documents. Minimum submission requirements of each phase are outlined in the Design Submission Instructions (PG‐18‐15) located on the Technical Information Library on the CFM website (http://www.cfm.va.gov/til/aeDesSubReq.asp). Information within this SOW shall take precedence over conflicting information in the Design Submission Instructions document. The A/E firm shall edit and tailor the VA Master Construction Specifications as necessary to reflect the project technical requirements.

2. The VAMC will make available the design criteria, and CAD/ BIM files of the existing space. The VA record drawings are not to be expected accurate in all respects and the A/E firm is to verify all features affecting the project by field investigation.

3. A/E firm discussion with the VA Medical Center personnel concerning requirements will be arranged by and participated in by appropriate Engineering and VISN Contracting personnel. The A/E firm shall participate, when required, with the appropriate Project Chief and VAMC COR and other Services in review of project scope, design review comments, etc.

4. In each submission, the A/E firm shall re‐submit the material specified in the prior submission, revised according to the comments made by the VAMC at the prior review. The A/E is to respond in writing addressing each VA comment.

5. The A/E firm shall pay particular attention to the fact that during the construction document stage, plans are not subject to change at the request of the VA Medical Center staff without the approval of the Chief, Engineering Service and the VISN Contracting Officer.

6. The A/E firm shall develop the project using BIM software.

7. The A/E firm shall follow the VA BIM guide when developing the BIM model

(https://www.cfm.va.gov/til/projREq.asp).

8. Integrated Design: Use a collaborative, integrated planning and design process that initiates and maintains an integrated project team in all stages of a project planning and delivery. Establish performance goals for siting, water, materials, and indoor environmental quality along with other comprehensive design goals and ensure incorporation of these goals throughout the design and lifecycle of the building.

9. Master Construction Specifications are available at the VA website http://www.cfm.va.gov/til/spec.asp in Microsoft Word Format. The A/E firm shall provide as part of their service edited specifications to the VAMC for incorporation into the VA Bid Package.

10. All work shall be coordinated with current and upcoming projects to prevent any duplication of efforts.

The VA will provide information regarding upcoming projects that may require coordination.

11. The floor plans for the Structural, HVAC, Plumbing and Electrical drawings shall be at the same scale as the Architectural drawings to facilitate coordination.

12. The VA has ownership of the rights at the date of Closeout Submittal to all CAD files, and Facility Data developed for the Project. The VA may make use of this data following any deliverables.

13. Design shall comply with applicable sections of the Technical Information Library on the Office of Construction and Facilities Management (CFM) website www.cfm.va.gov. Project is to be designed to comply with the latest codes as outlined in the VHA Program Guide PG‐18‐3, Topic 1 – Codes, Standards, and Executive Orders on the TIL. A/E firm will be responsible for complete functional design and provide bidding documents meeting those requirements.

14. Design must comply with the requirements of the most current version of the Office of Electronic Health Record Modernization – OEHRM Site Infrastructure and End User Device (EUD) requirements guide. Contact VA for most current version.

15. Design must comply with the fire alarm zones and fire alarm node locations established under the “Upgrade Fire Alarm System” project (541‐18‐101).

16. The A/E firm shall carefully review all requirements of the latest edition of the Accreditation Manual for Hospitals, of the Joint Commission of Accreditation of Hospitals, with respect to design and operating requirements and report all conflicting conditions in writing.

17. Applicable chapters of VA Master Construction Specifications will be prepared by the A/E firm, including any necessary adaptations. VA HVAC Design Manual, VA Sustainable Design and Energy Reduction Manual, and, ASHRAE Standards 90.1‐2004 and 90.1‐2007, shall apply to specific design requirements.

Refer to Contracting & Architect/Engineer Information and Technical Information Library on the CFM website www.cfm.va.gov for specific Contract Document requirements.

3.0 PROPOSED CONSTRUCTION DOCUMENT SCHEDULE

A. The first submission is to be a Schematic Design (SD) Submission and shall be submitted within 35 days after contract notice to proceed.

This submission shall include:

1. Construction drawing prints ‐ 5 sets half‐size (15x21)

a. 3 sets are to be delivered to Engineering

b. 2 sets are to be delivered to the User Groups

2. Preliminary cost estimate

3. Drawing files on CD – AutoCAD/BIM and PDF

4. Narratives

5. Calculations

B. There will be a 14‐day VA review period of the Schematic Design Submission by the VAMC.

C. The second submission is to be a Design Development (DD) Submission and shall be submitted 35 days after VA approval and comments on the Design Development submission (84 days after contract notice to proceed).

a. 3 sets are to be delivered to Engineering

b. 2 set are to be delivered to the User Groups

2. Preliminary cost estimate

3. Drawing files on CD – AutoCAD/BIM and PDF

4. Narratives

D. There will be a 14‐day VA review period of the Design Development Submission by the VAMC.

E. The third submission is to be a 65% Construction Document Submission and shall be submitted within

42 days after VA approval and comments on the Design Development submission (140 days after contract notice to proceed).

a. 3 sets are to be delivered to Engineering

b. 2 sets are to be delivered to the User Groups

2. Cost estimate with Deduct Bid Alternates

3. 1 copy of the preliminary specifications on CD – no hard copy required.

4. Drawing files on CD/DVD – AutoCAD/BIM and PDF

5. Narratives

F. There will be a 14‐day VA review period of the 65% Construction Document Submission by the VAMC.

G. The fourth submission is to be a 90% Construction Document Submission and shall be submitted within 35 days after VA approval and comments on the 65% submission (189 days after contract notice to proceed).

a. 4 sets are to be delivered to Engineering

b. 2 sets are to be delivered to the User Groups

2. Updated and refined Cost estimate with Deduct Bid Alternates

3. Revised specifications – 1 hard copy and 1 digital file copied on CD. Send to Engineering.

5. Narratives

H. There will be a 14‐day review of the 90% Construction Document Submission by the VAMC.

I. The fifth submission is to be a 100% Construction Document Submission and shall be submitted within 21 days after VA approval and comments on 90% submission (224 days after contract notice to proceed).

a. 4 sets are to be delivered to Engineering

b. 2 sets are to be delivered to the User Groups

2. Final Cost estimate with Deduct Bid Alternates

3. Final Specifications ‐ 1 hard copy and 1 digital copy on CD. Send to Engineering

J. There will be a 14‐day review of the 100% Construction Document Submission by VAMC.

K. The sixth submission is the Final Construction Document Submission and is to be submitted within 14 days after VA approval and comments on 100% submission (252 calendar days after contract notice to proceed). This issue will be sent for Capital Asset Manager, Contracting, and Legal / Technical Reviews.

1. Construction drawing prints ‐ 6 sets half‐size (15x21)

a. 4 sets are to be delivered to Engineering

b. 2 set are to be delivered to the User Groups

2. Final specifications ‐ 2 hard copies and 1 digital copy on CD. Send to Engineering

3. Final cost estimate with Deduct Bid Alternates

4. Drawing files on CD/DVD – AutoCAD/BIM and PDF

5. Brand name product list

6. Submittal Log

7. Certification Memo

L. If there are any comments from Contracting or Legal/Technical they are to be incorporated by the A/E firm within 7 business days. All drawings and specs will then be re‐issued as Bid Issue with a new date.

The drawings will be issued with quantities as noted below. If there aren’t any Contracting, or Legal / Technical comments, then the Final Issue will be used as‐is for Bidding. The A/E firm will provide the documents listed below for the Bid Issue.

M. The Bid Issue Submission shall include:

1. Construction drawing prints ‐ 6 sets half‐size (15x21), 1 set full size

a. 5 sets are to be delivered to Engineering

b. 2 sets are to be delivered to the User Groups

2. Final specifications ‐ 1 hard copy and 1 digital copy on CD. Send to Engineering

3. Final Cost estimate with Deduct Bid Alternates

4.0 FIRST SUBMISSION – SCHEMATIC DESIGN DOCUMENTS

A. Site Planning

1. If project requires the modification of the existing VA campus site, the preliminary plans should show how existing area will be modified including paving, proposed site enclosure (fencing – screen walls, mechanical screen walls, gates/security requirements), landscaping, exterior lighting, etc.

B. Architectural

1. Submit a layout for all floors, penthouses, and roof areas at a scale of not less than 1/8" = 1'‐

0". These drawings will show all rooms, doors, corridors, electrical closets and equipment rooms, low voltage equipment rooms and IRM closets, mechanical shafts, and all vertical circulation.

2. Show the overall exterior dimensions for determining the total gross area of the buildings.

3. Label each room or space with its name and the required net area of the designed net area.

Names on drawings shall be the same as those used in the Space Plan. The area figures will appear in fractional form, e.g., 400/390. Spaces provided but not called for in the Space Plan (such as mechanical rooms) shall be indicated as: ‐/390. The designed net area shall exclude such circulation space within the room as is permitted by the space planning criteria. Plan shall also note all dimensions to finished wall.

4. When the project includes more than one service or activity, as identified in the Space Summary Sheets of the Master Plan or Space Program, each activity shall be labeled, and its boundaries indicated with a heavy or distinctive line. When a service is fragmented or scattered in various locations, then each piece of it shall be similarly outlined and identified.

5. Submit a separate 1/8" scale plan for each floor to show the building's fire protection features.

The plan shall show, as a minimum, smoke barrier partitions, fire partitions, sprinklered areas, location of fire extinguisher cabinets, exit paths to the outside and the occupancy of each fire section. Submit exit calculations for each floor which justify the number of exits provided.

6. Submit a title sheet with drawing index and department index (Revise as necessary for each review).

7. Provide 2‐3 design options for VA review.

C. Functional

1. Submit a written explanation to justify any substantial variations from the Space Plans or Criteria.

D. Transport Systems

1. Provide a written description of all existing transport systems. Describe impact of existing systems on new transport systems.

E. Structural

1. Provide a written narrative describing basis of design and submit description of proposed structural systems.

2. Submit cost estimates for each system. Include foundation and fireproofing costs in estimates.

The A/E firm shall assess the economics of each structural system with due consideration of the systems cost effective on the entire building assembly.

3. Show column and shear wall locations F. Heating, Ventilating and Air Conditioning

1. Provide block load calculations for HVAC. Describe the building elements (walls, windows, roof, etc.), occupancies and internal loads. Size central equipment (chillers, converters, pumps, etc.).

2. Describe major functional areas such as administrative, patient bedrooms and ambulatory with distinct and different HVAC requirements that may necessitate individual HVAC treatment. Describe for each of the above functional areas proposed HVAC systems that will be included in the economic analysis.

3. Provide a written description of the HVAC and central refrigeration system. Demonstrate the rationale for choosing the candidate systems. Provide documentation of any computerized methodology that will be used for the economic analysis.

4. Provide a brief description of the parameters that will be used in the economic analysis for each of the HVAC and Central refrigeration systems. Reference the source of all data.

5. Provide a written description of energy conserving concepts to be analyzed for feasibility.

Demonstrate rationale for the proposed concepts. Provide a brief description of the parameters that will be used in the feasibility analysis for each of the candidate energy conserving concepts. Reference the source of all data.

6. Provide a brief description of existing HVAC and Central refrigeration systems that will interact with the proposed new systems. Describe the impact of the existing systems on the new systems and the impact that the new systems will have on the existing systems with respect to overall system capacity and ability to handle the new loads, system re‐balancing needs, controls interface, etc.

7. Provide a brief description of the methods to be used in sizing ducts and piping.

8. Provide plans showing the location of any proposed new chillers, cooling towers and any outside piping distribution for water and steam.

9. Show on plans the location and size of all mechanical rooms. Provide a block outline of the equipment in each mechanical room.

10. Provide a brief description of the fire and safety aspects of the HVAC systems. Describe the fire and smoke zones and address in principle the fire and safety control systems. Show smoke partitions clearly delineated on the mechanical drawings.

11. For any alterations of existing buildings, determine whether asbestos abatement is required and provide the preliminary findings on the presence of asbestos.

G. Steam Generation

1. Submit estimated heating and process steam load and the capacity and present minimum and maximum demands of the existing boiler plant and capability of existing steam supply and condensate return distribution systems to handle new loads.

2. Show the location of additional boiler and auxiliaries if required.

H. Plumbing and Sanitary

1. Describe basis for design and submit description of proposed systems.

2. Provide plumbing layout for work required.

I. Electrical

1. Furnish a report describing the systems proposed, including appropriate facts to support the designer's decisions including the basic assumptions and points of interconnections with the existing electrical systems. Submit preliminary square foot load calculations for both normal and emergency. Calculations should be broken down into lighting, receptacles, equipment, and mechanical systems. Provide assessment of the impact of the renovated construction to the existing distribution system. Include current demand loading (H.V. switchgear and primary feeder) and projected load of new construction.

2. Provide a sheet for all symbols.

3. On a plan show any proposed and existing underground electrical circuitry, telephone service, or inter‐building signal system (fire alarm, CCTV, radio and security systems), as required.

4. Submit an elementary one‐line diagram of the proposed electrical system. Include high voltage and low voltage switchgear, transformers and low voltage main and/or distribution panels, branch panels and representative methods of feeding 277/480 volt, 120/208 volt, and emergency panels. Show size of any electrical device which will be reused. Locate all electrical and signal closets on floor plans.

5. Submit a report of the fire alarm items.

6. Submit a sample lighting calculation. Describe the proposed method of short‐circuit calculation. Describe the method by which voltage drop and demand will be calculated.

J. Sustainable Design & Energy Efficiency

1. Submit narrative addressing how the design will meet Federal Mandates for sustainability and energy efficiency for Non‐Recurring Maintenance (NRM) Projects.

L. Cost Estimating

1. The A/E firm shall present a cost estimate, utilizing the BIM software, predicated on the assessment made during the preliminary design phase. A comparison will be shown between the A/E's, and the VA's budget cost estimate.

5.0 SECOND SUBMISSION – DESIGN DEVELOPMENT DOCUMENTS

A. Architectural

1. Submit final 1/8" scale design development plans with all of the revisions from the first submission incorporated into the plans. This includes the fire plans and exit calculations. The 1/16" scale preliminary floor plans should show net program area of each room with the designed net area. Outline and label activities or services as required for first submission.

2. Submit 1/8" scale floor plans for each floor showing all plumbing fixtures, room names, room numbers, door locations and swing, and the net program area over the designed net area (which will not be shown on the working drawings). Outline and label activities and services, as required for the first submission.

3. Show schematic sections, as needed, to define the building concept.

4. Submit elevations at all significant sides of the building in sufficient detail for the VA to judge its appearance. All significant materials, including their colors, must be indicated. This includes rooftop mechanical equipment and any architectural screens.

5. Submit a sample sheet of filled out finished Interior Finish schedule forms. The Medical Center will provide Interior Design input, review, and approval.

B. Transport Systems

1. Provide recommendations for all transport systems involved in the project.

C. Structural

1. Submit preliminary drawings to scale showing tentative sizes of column, beam foundations and slabs.

D. Heating, Ventilating and Air Conditioning

1. Provide complete economic analysis of the HVAC and central refrigeration systems. Provide completed feasibility analysis of the approved energy conserving concepts. Provide full documentation of the computerized methodology and full explanation of all coded and abbreviated terms. Make recommendations for the preferred system.

2. Provide updated calculations for block load for each building, sizing of central equipment, and all air handling units with psychometric charts. Provide calculations for pumps, fans, duct mains, water mains, steam mains and steam converters. Provide catalogue cuts of all central equipment and air handling units.

3. Provide the following for the recommended systems:

a. Plans with complete single line diagrams for ductwork and piping showing sizes of mains. Include flow diagrams for air, water and steam.

b. Schematics of the control systems with an outline of the sequence of operation.

Include main aspects of fire and safety controls.

c. Plans showing all mechanical rooms and chiller rooms with block diagrams of all major equipment. Provide typical samples of plans and sections in 1/4" scale.

E. Steam Generation

1. Describe the basis for design including present and future fuel costs which will be used in subsequent computations. Submit a written description of proposed fuel systems for final economic and energy analysis of best fuel or fuels.

2. Develop probable steam demand for building heat losses and ventilation (including humidification) based on "block building" calculations. Provide estimate of steam lead reduction due to heat recovery devices on HVAC systems. Submit a separate estimate of steam requirements for each of the following process steam loads, to the extent proposed for the new building. Show total connected load and diversity for each.

F. Plumbing and Sanitary

1. Show and identify all plumbing fixtures. Show location of pumps, compressors, tanks, and other major central plumbing equipment.

2. Complete plumbing layout for work required in existing buildings including pipe sizes and plumbing fixture identification.

3. Identify smoke partitions, fire alarm zones and fire sprinkler zones on plumbing drawings.

G. Electrical

1. Show preliminary sizes of major components of the electrical one‐line and riser diagrams, including high voltage and normal and emergency distribution equipment.

2. Provide preliminary updated load calculations.

3. Show tentative locations of primary distribution, switchgear/switchboard, engine‐generator sets, unit substations/ pad mount transformer, manholes, and other major items. Indicate the electrical equipment (panel boards, transformers, etc.) to be installed in the proposed electrical closets based on the preliminary riser. Show fire alarm risers and locate fire alarm devices.

4. On typical floor plan indicate location and type of lighting fixtures to be used in each space.

Show special features such as under floor raceways, power outlets, exit lights, fire alarms and signal system devices, and panel boards. Show typical circuitry of branch circuits including receptacles, lighting and power for one major representative area.

5. Electrical drawings shall show fire alarm zones and smoke partitions.

6. All drawings shall show room designations.

7. Existing or demolition work shall be shown by dashed lines.

H. Sustainable Design & Energy Efficiency

1. Submit a narrative describing how this project will meet the requirements of the VA

Sustainable Design Manual for Non‐Recurring Maintenance (NRM) Projects.

I. Cost Estimating

1. Final DD submission cost estimate shall be developed with the BIM software.

6.0 THIRD SUBMISSION ‐ 65% CONSTRUCTION DOCUMENT SUBMISSION

A. Specifications

1. Submit sample edited and marked up VA Master Specifications of each trade for review.

B. Architectural

1. Submit near complete floor plans and half complete details, schedules and large scale plans.

The architectural working drawings should be 65% complete.

2. Show room titles and numbers, door sizes, types and swings on the 1/8" scale plans.

Dimension corridors, rooms, etc. Indicate and identify fixed and portable equipment and plumbing fixtures.

3. Show room finish symbols and key them to the room finish.

4. Provide door and window schedules.

5. Indicate all fire partitions, smoke partitions, safety and protective elements.

6. Draw special details or elevations, etc., at 1/4" scale to show layout and identification of equipment.

7. Draw reflected ceiling plans of all areas and special rooms, indicating all ceiling mounted equipment, lighting fixtures, air diffusers, registers, sprinkler heads, etc.

8. Draw an asbestos abatement plan showing containment areas, access routes, all piping with and without asbestos contaminated insulation.

9. Draw the phasing plan. Plan shall include necessary notes and description (intent).

C. Heating, Ventilation and Air Conditioning (HVAC)

1. Duct and pipe sizing computations shall be half completed. Submit sizing data for duct systems and for water pipe system mains and principal branches.

2. On drawing, show double line representation of all ducts and single line representation of piping system 6" and smaller. Clearly indicate the sizes of ducts and piping. Locate fire and smoke dampers.

3. Show equipment schedules. Submit equipment selections based on manufacturer's catalogue data. Submit supporting calculations.

4. Show control diagrams. Diagrams shall be complete with legend and description of operations.

5. Major details, elevations, sections and legends on the drawings are to be complete.

6. Flow diagrams for systems shall be half complete on the contract drawings. Include flow quantities on the diagrams. Flow and control diagrams may be combined where feasible.

7. In the calculations, provide a tabular recapitulation indicating the air balance between the supply and exhaust, in the design computations showing the volume air, room names and numbers. Show that individual areas which normally constitute an integrally balanced system, such as laboratory, nursing floor, administration, etc., are in balance. For air conditioning systems added to an existing building, show the air balance with respect to the existing exhaust and supply systems to provide a complete building study.

8. Show room names on HVAC plans so that compliance with criteria can be checked.

D. Structural

1. Submit drawings to scale showing tentative sizes of column, beam foundations and slabs. The structural drawings shall be complete enough to correlate with architectural and mechanical features. Submit computations developed to date.

2. Show typical details so that construction features can be defined.

E. Plumbing

1. Show and identify existing and new fixtures, supply/ waste/vent lines, steam lines, etc.

2. Describe basis of design including basic factors and formulate which will be used in subsequent computations. Submit written description of proposed system or combination of systems.

3. Show and identify fire sprinkler fixtures. Piping shall be complete except for sizing. Show location of connection to existing systems.

4. Show location and section of pumps, valves, flow switches, and etc., as necessary.

5. Show existing and new medical air gases. Identify type, routing, etc. if applicable.

F. Electrical

1. Show locations of existing and new electrical and telephone/communications closets, devices and equipment.

2. Submit one‐line riser diagram of the electrical power distribution system and the auxiliary power system connection along with tentative one‐line riser diagrams of all signal and communication systems.

3. Show locations of major items and equipment (i.e., switch, gear, transformers, panel boards, etc.).

4. All floor plans shall have room titles and area function. Location of majority of lighting fixtures and outlets for power and signal systems shall be shown along with tentative layouts of special systems. This shall include a TV entertainment system.

5. Typical lighting and power calculations.

6. Show locations of fire alarm system devices, tie‐in's/extensions of system and a circuit diagram.

G. Phasing

1. Present proposed phasing plans.

2. Identify items/areas for Deduct Bid Alternates, including estimated cost.

3. Phasing of project shall be developed so as to minimize disruption to Medical Center's operation. Also, coordinate with any present or future projects in the planning stages.

H. Cost Estimating

1. Submit cost estimates for each submission of drawings and specifications utilizing the BIM model.

2. Each submission shall contain certification that the quantities have been checked and found to be correct.

3. All estimates shall be based on the most up‐to‐date working BIM model and shall be current as of the date of submission.

4. On phased projects, the cost associated with each phase shall be kept separate.

5. Costs shall include insurance, taxes, and applicable sub‐contractor's mark‐up.

6. Use wage rates that reflect current wages at the time the estimate is submitted. For union labor, include welfare and pension fund costs in labor units as appropriate.

7. Estimate taxes and insurance on labor, such as: public liability, property damage, workmen's compensation, bodily injury, Federal Insurance Contribution Act, social security, federal and state unemployment compensation as an average cost experience for each trade.

8. Price material at the contractor's buying level. Sales taxes are not applicable. Compute insurance and taxes on labor.

9. Because overhead and profit will vary with the trade, size of project, and competition, estimates should reflect an appropriate percentage of each of these items after the labor and material costs have been totaled for each item.

10. Escalation as of time of award shall be shown as a line item.

11. Show costs for the applicable major numerical headings, if available.

12. Show sub‐items of major numerical headings, if available.

13. Show sub‐contractor's overhead and profit.

14. Show total estimated cost.

15. Provide Data Sheets.

16. Show premium for work being performed by a SDVOB.

17. Provide up to 4 Deduct Bid Alternates totaling a minimum of 10% or greater of the construction cost.

I. Asbestos and Hazardous Materials Abatement

1. Execute necessary material and/or air sampling, in project areas, by a Certified Industrial Hygienist (CIH).

2. Samples shall be tested by an accredited laboratory.

3. Submit a detailed report. Report shall include but not be limited to the following: Sampling strategy, location of samples taken, lab results, comments and recommendations.

4. Prepare and submit drawings and specifications indicating areas requiring asbestos abatement, plumbing lines, and/or equipment with asbestos, estimate quantity and areas with asbestos, containment areas and access routes.

5. Reports from previous asbestos investigation, sampling and study will be made available to A/E firm or CIH. These reports may be used only as guidelines and should not be used to determine the extent of asbestos on project or to develop abatement plans from.

J. Sustainable Design & Energy Efficiency

1. Submit a narrative describing how this project will meet the requirements of the VA

Sustainable Design Manual for Non‐Recurring Maintenance (NRM) Projects.

K. Comments

1. Incorporate all comments shown on the Design Development review and provide a written response for each item.

7.0 FOURTH SUBMISSION ‐ 90% CONSTRUCTION DOCUMENT SUBMISSION

A. General

1. Contract drawings and all related documents shall be nearing completion.

2. One set of drawings are to be sent directly to VA provided life safety reviewer. A/E firm will modify drawings as required for full compliance with review.

B. Calculations

1. Assemble complete computations and engineering data including basis of design, systems narratives, equipment selections, pipe and duct sizing. Recapitulations, from which the basic heat load calculations served, sound attenuation for high pressure systems and computations and like data for this submission. Provide a separate volume for each discipline with an index and numbered pages, bound with removable metal fastenings.

C. Specifications

1. When the drawings and specifications are nearing completion, the A/E firm shall furnish the

VA with a brief description of work for inclusion in the invitation for Bids.

2. Submit original, photocopies of VA Master Specification sections to marked‐up suit the project requirements and, also, copies of any sections originated by the A/E firm. Editing and marked‐ up of Master Specifications shall easily identify modifications, deletions, and insertions.

Specifications shall be typed after the review.

D. Architectural

1. Submit completed plans, elevations, details and schedules.

E. Heating, Ventilation and Air Conditioning (HVAC)

1. The drawings and calculations shall be complete.

2. Duct sizing and pipe sizing computations shall be complete with system layout and tabulated data.

3. Show complete equipment schedules.

4. Show complete control diagrams.

5. Details, elevations, sections and legends on the drawings are to be completed. Show a section of each critical point in corridors indicating the location and space allocation intended for all ducts, piping, and larger conduits regardless of trade.

F. Structural

1. Include all structural plans, elevations, sections, details, schedules, and general notes necessary to complete the drawings.

G. Plumbing and Sanitary

1. Submit complete drawings.

2. All piping shall be drawn and all pipes sized.

3. Submit legend, notes, details, plan views and sized riser diagrams, equipment, etc.

H. Electrical

1. Submit complete electrical plans.

2. On drawings, show outlets circuited, all motor outlets, complete riser diagrams, switchboards, panels, and feeders. Show panel and switchboard schedules for all equipment with sizes of mains and branches determined.

3. On detail drawings, show symbols, lighting fixture details and construction details.

4. Electrical floor plans shall be complete with panel location and major components located.

5. Show coordination with all new and relocated VA equipment.

I. Phasing

1. Phasing drawings for new and demo for each discipline are to be complete and coordinated.

J. Cost Estimating

1. Follow the same general instructions as first working drawings submitted.

2. Furnish additional details to the estimator, as design progresses, to show sub‐headings under each major numerical heading.

3. Show unit quantity, unit measure, unit cost, and total cost of labor and material for sub‐ heading.

4. Show a subtotal of labor and material for each sub‐heading.

5. Show taxes and insurance on labor.

6. Show sub‐total of the total cost.

7. Show applicable sub‐contractor's mark‐up as a percentage of cost.

8. Show total cost of each sub‐heading.

9. Show total estimated cost of each major heading.

10. Show summary of major headings.

11. Provide Data Sheets.

12. Show premium for work being performed by a SDVOB.

13. Provide up to 4 Deduct Bid Alternates totaling a minimum of 10% or greater of the construction cost.

K. Asbestos and Hazardous Materials Abatement

1. Drawings shall be complete and show containment areas, suggested location(s) of decontamination facilities, negative pressure (HEPA) units, building/site access routes, all piping/equipment requiring stripping of asbestos contaminate insulation, rounded‐off quantities, etc.

2. Specifications shall be completed.

3. Show phasing as it relates to rest of the project.

L. Sustainable Design and Energy Efficiency

1. Submit a narrative describing how this project will meet the requirements of the VA

Sustainable Design Manual for Non‐Recurring Maintenance (NRM) Projects.

M. Comments

1. Incorporate all comments shown on the 65% design review and provide written response to each item.

8.0 FIFTH SUBMISSION ‐ 100% CONSTRUCTION DOCUMENT SUBMISSION

1. Contract drawings and all related documents shall be completed, fully coordinated, and ready for reproduction for bidding and construction purposes at this review.

2. The A/E firm shall deliver the original working drawings to the Contracting Officer for signature after review and approval of the review material. The working drawings shall bear the seal of the Registered Architect, Professional Engineers, and the principle CIH for the project.

3. The A/E firm shall make any changes to the working drawings or specifications identified as necessary during the 90% CD review.

B. Calculations

1. Assemble complete computations and engineering data including basis of design, systems narratives, equipment selections, pipe and duct sizing. Recapitulations, from which the basic heat load calculations served, sound attenuation for high pressure systems and computations and like data for this submission. Provide a separate volume for each discipline with an index and numbered pages, bound with removable metal fastenings.

C. Specifications

1. When the drawings and specifications are nearing completion, the A/E firm shall furnish the

VA with a brief description of work for inclusion in the Invitation for Bids.

2. Submit final specifications. Verify that all brand names are brought to the attention of the

COR for inclusion in Brand Name or Equal memo or Sole Source justification.

3. Verify that Spec Writer notes and double hash marks // // have been removed.

4. Verify that all referenced spec sections are either included or removed as a reference.

5. Verify that the number of pages in the TOC matches the actual number of pages used.

D. Architectural

1. Submit completed plan, elevations, details and schedules.

E. Heating, Ventilation and Air Conditioning (HVAC)

1. The drawings and calculations shall be complete.

2. Duct sizing and pipe sizing computations shall be complete with system layout and tabulated data.

3. Show complete equipment schedules.

4. Show complete control diagrams.

5. Details, elevations, sections and legends on the drawings are to be completed. Show a section of each critical point in corridors indicating the location and space allocation intended for all ducts, piping, and larger conduits regardless of trade.

F. Structural

1. Include all structural plans, elevations, sections, details, schedules, and general notes necessary to complete the drawings.

G. Plumbing and Sanitary

1. Submit complete drawings.

2. All piping shall be drawn and all pipes sized.

3. Submit legend, notes, details, plan views and sized riser diagrams, equipment, etc.

H. Electrical

1. Submit complete electrical plans.

2. On drawings, show outlets circuited all motor outlets, complete riser diagrams, switchboards, panels, and feeders. Show panel and switchboard schedules for all equipment with sizes of mains and branches determined.

3. On detail drawings, show symbols, lighting fixture details and construction details.

4. Electrical floor plans shall be complete with panel location and major components located.

I. Phasing

1. Phasing plans are to be complete showing demolition, new, and life safety complete for each phase and each trade.

J. Cost Estimating

1. Follow the same general instructions as previous submission.

2. Furnish additional details to the estimator, as design progresses, to show sub‐headings under each major numerical heading.

3. Show unit quantity, unit measure, unit cost, and total cost of labor and material for sub‐ heading.

4. Show a subtotal of labor and material for each sub‐heading.

5. Show taxes and insurance on labor.

6. Show sub‐total of the total cost.

7. Show applicable sub‐contractor's mark‐up as a percentage of cost.

8. Show total cost of each sub‐heading.

9. Show total estimated cost of each major heading.

10. Show summary of major headings.

11. Provide Data Sheets.

12. Show premium for work being performed by a SDVOB.

13. Provide up to 4 Deduct Bid Alternates totaling a minimum of 10% or greater of the construction cost.

K. Asbestos Abatement

1. Drawings shall be complete and show containment areas, suggested location(s) of decontamination facilities, negative pressure (HEPA) units, building/site access routes, all piping/equipment requiring stripping of asbestos contaminate insulation, rounded‐off quantities, etc.

2. Specifications shall be completed.

3. Show phasing as it relates to rest of the project.

L. Certification Memo

1. A/E to submit a certification memo to the VA indicating that their design is independent of future projects and includes all equipment required for the project to be activated and fully functional as required by the OCAMES Updated Construction Guidance and Expectations Memo dated September 12, 2016.

M. Comments

1. Incorporate all comments shown on the 90% design review and provide written response to each item.

9.0 FINAL ISSUE CONSTRUCTION DOCUMENTS SUBMISSION

1. Complete any corrections noted from the 100% CD submission.

2. Provide complete and coordinated drawings and specifications including comments from Life

Safety Plans Examiner.

3. The A/E firm shall provide a final written certification on the drawings form a Certified

Industrial Hygienist as to the mitigation of asbestos for the project.

4. A/E firm interior designer shall submit final 3‐ring binder of finish samples labeled with manufacturer’s data and referenced to finish schedule. Coordinate with VA Interior Designer on submission requirements.

5. When requested, the A/E firm shall upload drawings and specifications to a document printing service for use by Bidders as directed by the Contracting Officer. The Contracting Officer will provide the legal portion (front end section) of the specification.

6. Submit a final cost estimate of construction costs for the project; estimate shall clarify changes or modifications of previous estimates based on projected construction award date.

Final estimate shall identify pricing for each of the major design components of the project.

Estimate shall also identify up to 4 Deduct Bid Alternates totaling a minimum of 10% or greater of the construction cost.

10.0 CONSTRUCTION PERIOD SERVICES

A. Contract Procurement

1. Attend one contractor's Pre‐Bid site visit and respond in writing with recommendations to any questioned items. If necessary, develop amendments or assist with project procurement.

B. Submittal Review

1. The A/E firm shall review all construction materials and equipment and change orders proposed by the contractor for use in construction of this project. All submittals and change order proposals will be reviewed for compliance with the specifications and reasonable costs and returned to Engineering Service within 7 calendar days after receipt.

2. The A/E firm shall review and respond to all RFI’s within 5 business days.

3. Commissioning of the mechanical, electrical, plumbing, fire protection, lighting, and other building systems shall be implemented to verify the intent of the design by inspecting and testing the systems as outlined in the VA Whole Building Commissioning Process Manual and per applicable ANSI/ASHRAE Standards.

C. Site Visits (In addition to site visits listed in Item ‘A’ above)

1. Attend 1 pre‐construction meeting, after award of construction contract.

2. Attend 8 above ceiling and below ceiling 4‐hour site inspections held at the 25%, 50%, 75%, and final inspection of project.

3. Spot checking of contractor’s progress based on eight (8) 4‐hour site visits when requested by the COR. These meetings may also be used to answer technical questions and/or develop minor changes due to site conditions, etc.

4. The A/E firm shall attend 2 construction meeting per month by phone (assume 1 hour) for the duration of construction.

5. The A/E firm shall visit the site at the request of the Contracting Officer to answer technical questions and/or provide clarification to documents due to errors or omissions at no cost to the government. These meetings will not count for meetings noted above.

D. Asbestos Abatement

1. Provide detailed asbestos air sampling report after asbestos abatement has taken place.

E. As Built Drawings

1. The A/E firm shall modify design drawings based on marked drawings supplied by the contractor and are to be verified by the A/E firm in field. As‐Builts to include all addenda and Bulletins issued by the VA and the A/E firm during construction. The changes shall be incorporated into the final BIM Model with the revision documented on the title block as appropriate. These changes shall be bubbled and dated. The A/E firm is to reformat the drawings based on the VA layering system before final submission. A reproducible hardcopy and the electronic model of the “As‐Builts” are to be submitted to the COR on DVD. Any approved shop drawings with major differences from contract drawings, supplemental agreements processed change orders, etc., shall be incorporated.

‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐END OF DOCUMENT‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐