Attachment I SOW.pdf
PDF 892 KB Posted
- Attached to
- USCG Academy Salt Shed
- Solicitation number
- 70Z08426QDL950035
About this file
Request for Quotation Summary
This is a Request for Quotation (RFQ) issued by the U.S. Coast Guard Academy for the demolition of an existing salt shed and replacement with a metal Quonset-type structure at 15 Mohegan Avenue, New London, Connecticut 06320. The project number is 7376438, and the Project Manager is CWO4 Anthony Graziano with LCDR Patrick Page serving as Public Works Officer.
Scope and Requirements:
The contractor must provide all equipment, labor, materials, supervision, and transportation to demolish the existing salt shed and construct a replacement metal building. The new structure shall be a pre-engineered metal S-model Quonset style building with straight walls and curved roof, designed for loads including dead load, snow load, and wind pressures up to 100 mph. Approximate dimensions are 20 feet long by 24 feet high and no more than 16 feet wide. The contractor shall build a concrete form masonry unit (CFMU) foundation using 2'X2'X6' bin blocks (approximately 3,600 lbs. each) with 3,000 psi compressive strength. Roof and wall systems shall use minimum 22-gauge sheet steel with AZ50 aluminum-zinc alloy or galvanized coating. The metal building shall include a minimum five-year manufacturer warranty and fluoropolymer finish or better.
Site and Operational Requirements:
Work hours are 0730 to 1600 Monday through Friday, excluding federal holidays. Contractors must conduct a mandatory site visit, verify all dimensions and square footage, and advise the COR/PM of discrepancies before proposal submission. Contractor personnel require Real ID for facility access. The contractor is responsible for all material storage protection, utility connections/disconnections, waste disposal, parking coordination, and any damages to government property. Water at household pressure and 120V 15A electricity are available at no cost; all other utilities are the contractor's responsibility. Dumpster placement will be designated by the COR/PM. All work must comply with OSHA/EPA regulations and include proper personal protective equipment. Contractors must submit Connecticut licenses, crane certifications (if applicable), shop drawings for CFMU reinforcing details, color samples, and detailed metal building manufacturer specifications and installation tolerances.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFQ 70Z08426QDL950035 Amendment 1.pdf | ||
| RFQ 70Z08426QDL950035.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF HOMELAND SECURITY
UNITED STATES COAST GUARD
COAST GUARD ACADEMY
NEW LONDON, CONNECTICUT 06320
REQUEST FOR QUOTATION OF GROUNDS SHOP SALT SHED REPLACEMENT
PROJECT NUMBER: 7376438
Coast Guard Academy Signature Date CWO4 Anthony Graziano
PROJECT MANAGER
LCDR Patrick Page
PUBLIC WORKS OFFICER
TABLE OF CONTENTS
SECTION TITLE PAGE
DIVISION 01 - GENERAL REQUIREMENTS 1
01 10 00 – GENERAL PARAGRAPHS 1
01 33 00 – SUBMITTALS PROCEDURES 3
01 35 29 – HEALTH AND SAFETY PROCEDURES 4
01 40 00 – QUALITY REQUIREMENTS 5
01 54 19 – TEMPORARY CRANES 6
01 74 19 – WASTE MANAGEMENT AND DISPOSAL 7
DIVISION 02 – EXISTING CONDITIONS 8
02 41 19 – SELECTIVE SITE PREPARATION 8
DIVISION 04 – MASONRY 9
04 28 13 – CONCRETE FORM MASONRY UNITS 9
DIVISION 13 – SPECIAL CONSTRUCTION 10
13 34 19 – METAL BUILDING SYSTEMS 10
DRAWINGS ATTACHED
DIVISION 01 – GENERAL REQUIREMENTS
01 10 00 – GENERAL PARAGRAPHS
PART 1 GENERAL
1.01 REQUEST FOR INFORMATION: Request quotations and proposals from any
Contractor interested, who has the capability of completing the task specified and also serves the New London Connecticut area.
1.02 SCOPE OF WORK: The Contractor shall provide a proposal including all equipment, labor, materials, supervision, and transportation necessary to demolish an existing Salt Shed and replace it with a metal Quonset type structure.
1.03 LOCATION: Project site is behind Johnson Hall at the U.S. Coast Guard Academy, 15 Mohegan Avenue, New London, CT 06320.
1.04 CONTRACT OFFICER'S REPRESENTATIVE: “Contracting Officer’s Representative” (COR) or Project Manager (PM) is appointed by the Contract Officer (KO) to ensure that all the technical requirements are met by the Contractor. Only the KO can make contract changes if he or she approves. The COR or PM cannot make those changes.
1.05 CONTRACTOR REQUIREMENTS:
A. SITE VISIT: Interested Contractors are expected to visit the project site to conduct a survey of the site conditions to be encountered which may affect the cost of the project performance involved. Failure to familiarize with the existing conditions shall not relieve the awarded Contractor from the responsibility of the full completion of the project. Interested Contractors are encouraged to contact the name and number listed on the announcement to schedule a site visit. The Contractor shall verify all dimensions, square footages and advise the COR or PM of any discrepancies found prior to submitting proposals.
B. SECURITY: Contractor personnel will be required to have a Real ID to enter the facility.
C. WORKDAY: The workday is between the hours of 0730 and 1600 local time Monday through Friday excluding all Federal holidays. All work hours will be scheduled around planned Government operations.
D. TIME FRAME: The Contractor shall proceed with work on the negotiated start date determined between the Contractor and COR or PM.
1.06 PROJECT MANAGEMENT:
A. SANITARY FACILITIES: Toilet facilities are available for Contractor use near the job site. The Contractor shall ensure the facilities remain clean after their use.
B. PARKING: See COR or PM for parking arrangements at the Academy during the project performance. Overnight parking is not authorized.
C. MATERIAL STORAGE: Storage of material shall be as directed by the COR or
Project Manager. The Contractor shall protect all materials stockpiled against damage and other risks of loss. The Coast Guard (Government) assumes no responsibility for material or equipment left in the storage area.
D. SMOKING: Smokers are limited to four smoking areas on campus. Awarded Contractor will be provided with Appendix A for smoking locations.
E. UTILITIES: Water at household pressures and electricity at 120V 15A are only available at no cost to the Contractor. Any other utilities that the Academy doesn’t provide shall be the responsibility of the Contractor. Utility connections and disconnections shall be the responsibility of the Contractor.
F. CONTRACTOR DAMAGE: The Contractor shall make any repairs to any damages they caused or made to Government property at no cost to the Government during the duration of the project.
1.07 DRAWINGS: Campus drawing with the project location marked and Technical Exhibit 1 (TE-1) will be provided.
PART 2 PRODUCTS
(Not Used)
PART 3 EXECUTION
(Not Used)
END OF SECTION 01 10 00
SECTION 01 33 00 – SUBMITTALS PROCEDURES
PART 1 GENERAL
1.01 GENERAL: This Section provides procedures and requirements for Contractor proposals.
A. FORWARDING: The Contractor shall forward all submittals to the COR or Project Manager by e-mail and/or hard copy.
B. REVIEWING: The COR or Project Manager will review all submittals for compliance with the best value to the Government.
C. APPROVAL: The Project Manager will reply with approval or disapproval of proposals as per the KO.
1.02 SPECIFIC SUBMITTALS:
A. LICENSING: Submit a copy of State of any Connecticut Contractor’s licenses.
B. CRANE CERTIFICATIONS: Awarded Contractor shall submit crane certifications to the U.S. Coast Guard Safety Officer. This may be done through the COR or PM.
C. CMU:
1) SHOP DRAWINGS: Show fabrication, installation, bending and placement details for unit masonry reinforcing bars.
2) SAMPLES FOR INITIAL SELECTION: Any color samples if available D. STEEL BUILDING: Provide Manufacturer details of metal building that comes close to Government building concept in the Technical Exhibit.
1) SHOP DRAWINGS AND PRODUCT DATA: Indicate assembly dimensions, locations of structural members, connections, attachments, and loads, wall and roof system dimensions, panel layout, general construction details, anchorages and method of anchorage, method or installation; framing anchor bolt settings and placement, sizes, and locations from datum, setting requirements.
2) SAMPLES: Submit color and texture samples of metal coatings finishes.
PART 2 PRODUCTS
(Not Used)
PART 3 EXECUTION
END OF SECTION 01 33 00
SECTION 01 35 29 – HEALTH AND SAFETY PROCEDURES
PART 1 GENERAL
1.01 SUMARY: This Section applies to the necessary requirements the Contractor will need to factor in to comply with the health and safety requirements. No submittals required.
1.02 OSHA/EPA REGULATIONS: During the performance of all work under this contract, the Contractor shall strictly adhere to Environmental Protection Agency (EPA) and OSHA Safety and Health Standards, PART 2 PRODUCTS
(Not Used)
PART 3 EXECUTION
3.01 PERSONAL PROTECTIVE EQUIPMENT (PPE): Contract Employees shall wear properly fitted PPE in accordance with the safety measures dictated by the type of work they are performing.
END OF SECTION 01 35 29
SECTION 01 40 00 – QUALITY REQUIREMENTS
PART 1 GENERAL
1.01 SUMMARY: This Section includes administrative and procedural requirements for quality assurance (QA) and quality control (QC) to the awarded Contractor.
1.02 QUALITY ASSURANCE (QA):
A. BUILDING MANUFACTURER: Manufacturer who has the experience in steel buildings are manufactured in the USA by American workers, ensuring quality.
B. ERECTOR: Company specializing in performing projects for installing metal Quonset style buildings and approved by Manufacturer.
C. PERSONNEL: Contractor personnel should be trained and experienced in building structures required for this project, like concept requirements.
D. CFMU INSTALLER: CFMU installer who has been experienced, licensed or trained in the installation of products whose work has resulted successful in service performance.
E. CFMU MANUFACTURER: An experienced Manufacturer of CFMU units described for this project with a record of successful in-service performance, and sufficient production capacity to produce required units without delay to the project schedule.
1.03 QUALITY CONTROL:
A. CONTRACTOR RESPONSIBILITIES: The Contractor shall perform quality control to verify their work in the project complies with Manufacturer specified requirements.
B. INSPECTION: The Contractor will have to pass an inspection by the COR or PM to determine that all the proposal technical requirements of the Salt Shed have been met.
Punch List items must be corrected before the COR or PM notifies the KO of project completion.
PART 2 PRODUCTS
(Not Used)
PART 3 EXECUTION
END OF SECTION 01 40 00
SECTION 01 54 19 – TEMPORARY CRANES
PART 1 GENERAL
1.01 SUMMARY: This Section includes safe rigging and handling of loads that are lifted with temporary cranes if they are used by the awarded Contractor.
1.02 LIFTING CREW:
A. RIGGING SUPERVISOR: Rigging Supervisor shall be competent, trained and have the authority to supervise all lifting operations and stop any lifting if it is dangerous.
B. CRANE OPERATOR: The Crane Operator shall be responsible for correct operation of the crane in accordance with the crane Manufacturer, be aware of the wind and climactic effects, safe operation of lifting loads and unsafe situations.
C. SIGNALER: The signaler shall be responsible for relaying the signal from the Riggers to the Crane Operator and movement of the crane and load.
D. RIGGERS: Riggers shall be responsible for attaching and detaching the load to and from the crane load lifting attachment, using the correct lifting accessories and equipment in accordance with the operation plan. Riggers shall also be familiar with all hand signals.
E. EQUIPMENT: All rigging and handling equipment is in good working order and equipment test certifications are up to date. The Contractor shall not repair any crane or equipment on the Academy grounds. Any equipment that malfunctions shall be removed from the Government premises and repaired elsewhere.
PART 2 PRODUCTS
(Not Used)
PART 3 EXECUTION
3.01 NOTIFICATION: The Contractor shall notify the Project Manager before bringing heavy equipment onto campus grounds.
END OF SECTION 01 54 19
SECTION 01 74 19 – WASTE MANAGEMENT AND DISPOSAL
PART 1 GENERAL
1.01 SUMMARY: This Section includes requirements for the disposing of non-hazardous project waste by the awarded Contractor.
1.02 DUMPSTER: See COR or PM for placement location. Note that dumpster placement location may need to be located far from the jobsite because of limited area behind Johnson Hall and access needed for the changing out of other dumpsters located nearby.
PART 2 PRODUCTS
(Not Used)
PART 3 EXECUTION
3.01 DISPOSAL OF WASTE: The Contractor shall legally dispose and remove all project waste from demolishing existing salt shed, scrap materials from the new building and clean up the work area after the end of each workday.
END OF SECTION 01 74 19
DIVISION 02 – EXISTING CONDITIONS
SECTION 02 41 19 – SELECTIVE SITE PREPARATION
PART 1 GENERAL
1.01 SUMMARY: This Section applies to all work required for the preparation and removal of the entire Salt Shed structure by the awarded Contractor, and hazardous materials and spills.
PART 2 PRODUCTS
(Not Used)
PART 3 EXECUTION
3.01 VEGITATION OVERGROWTH: Remove all vegetation growth on existing Salt Shed.
3.02 EXISTING SALT SHED: Remove the entire existing Salt Shed structure and dispose of all materials properly off the Coast Guard Academy premises. Metal guard rails are to remain.
END OF SECTION 02 41 19
DIVISION 4 MASONRY
SECTION 04 28 13 – CONCRETE FORM MASONRY UNITS
PART 1 GENERAL
1.01 SUMMARY: This Section includes requirements for assemblies consisting of concrete form masonry units and any cementous mixtures used by the awarded Contractor.
PART 2 PRODUCTS
2.01 CONCRETE FORM MASONRY UNITS: GENERAL: Provide concrete formed, unbroken 2 ’X 2’ X 6’, approximately 3,600 lbs. bin blocks (aka various other names) consisting of lifting lug, compressive strength of 3,000 psi and normal weight class with standard interlocking joints. Provide any useful special shapes that may be available.
2.02 MORTAR MATERIALS AND MIXES:
A. GROUT: ASTM C1107/C1107M; premixed, non-metallic, non-shrink aggregate cement, water reducing and plasticizing agents; capable of developing minimum compressive strength of 2,400 psi in 48 hours and 7,000 psi in 28 days if required.
B. CONCRETE FILL MATERIALS: Compressive Strength of 28 Days 3,000 psi, 8” inches to 11’ inches of Slump: in accordance with ASTM C 143.
2.03 BUTYL SEALANT: ASTM C 1311, single component, solvent release butyl rubber sealant; polyisobutylene plasticized, heavy bodied for expansion joints.
PART 3 EXECUTION
3.01 EXISTING WORK: Build in block items adjoining existing. Fill in solidly with masonry around existing items like the retaining wall.
3.02 CONCRETE BLOCK PLACEMENT:
A. PLACEMENT: Install bin blocks in line with one another ensuring full interlocking between units in accordance with the concept plan.
B. CUTTING CFMU: Cut with motor-driven saws to provide clean, unchipped edges.
3.03 CONSTRUCTION TOLERANCES: For conspicuous horizontal and vertical lines, such as external corners, exposed sills, reveals, and expansion and control joints, do not vary from level and/or plumb by more than 1/4 inch in 20 feet, nor 1/2 inch maximum.
END OF SECTION 04 28 13
DIVISION 13 SPECIAL CONSTRUCTION
SECTION 13 34 19 – METAL BUILDING SYSTEMS
PART 1 GENERAL
1.01 SUMMARY: This Section includes specifications for pre-engineered metal S-model type
Quonset style, straight wall and curved roof building system to be provided by the awarded Contractor.
1.02 DESIGN REQUIREMENTS:
A. LOADS: Design members to withstand dead load, applicable snow load, and loads due to pressure and suction of the wind up to 100 MPH.
B. MOVEMENT: Building only permits minimal component movement without buckling, failure of joint seals, undue stress on fasteners or other detrimental effects.
C. FABRICATIONS: Fabricated wall and roof systems free of distortion or defects detrimental to appearance or performance.
D. SIZE: Select building that has a close overall size of approximately 20’-0” long X
24’-0” high and no more than 16’-0” wide.
1.03 WARRANTY: Minimum five-year Manufacturer warranty for pre-engineered building systems and components including finish.
PART 2 PRODUCTS
2.01 ROOF AND WALL SYSTEM COMPONENTS AND FABRICATIONS:
A. SHEET STEEL: ASTM A792/A792M; AZ50 aluminum-zinc alloy or galvanized coating. Roofing and siding shall be a minimum 22-gauge metal thickness, ribbed and/or standing seam profile lapped edges with factory sealant, field seamed with sufficient coverage.
B. JOINT SEAL GASKETS: Manufacturer's standard type.
C. STRUCTURAL FASTENERS: To maintain load requirements and weather tight installation provide a minimum of galvanized bolts, nuts, and washers.
D. FLASHINGS, CLOSURE PIECES, AND CAPS: Same material and finish.
2.02 FACTORY AND FIELD FINISHING FOR INTERIOR AND EXTERIOR: Precoated steel of fluoropolymer finish or better, color as selected from Manufacturer's standard range.
PART 3 EXECUTION
3.01 WALL AND ROOFING SYSTEMS ERECTION: Fasten system to structural supports, aligned level and plumb. Install sealants and gaskets to prevent weather penetration.
3.02 INSTALLATION TOLERANCES: As per Manufacturer.
END OF SECTION 13 34 19
U.S. COAST GUARD ACADEMY
SALT SHED REPLACEMENT OF WOOD FRAME WITH METAL
Andrew Hoffman Rectangle
EAST ELEVATION SOUTH ELEVATION
ABT 20'-0"
ABT 24'-0"
ABT 16'-0"
RETAINING WALL
CONCEPT MAY STACK
TWO MAFIA BLOCKS
HIGH
EXISTING
RETAINING
WALL
TECHNICAL EXHIBIT
Andrew Hoffman Line
Andrew Hoffman Line
Andrew Hoffman Rectangle
Andrew Hoffman Line
Andrew Hoffman Line
Andrew Hoffman Line
Andrew Hoffman Line
Andrew Hoffman Line
Andrew Hoffman Line
Andrew Hoffman Line
Andrew Hoffman Line
Andrew Hoffman Polygon
Andrew Hoffman Line
Andrew Hoffman Polygon
Andrew Hoffman Rectangle
Andrew Hoffman Rectangle
Andrew Hoffman Rectangle
Andrew Hoffman Rectangle
Andrew Hoffman Rectangle
Andrew Hoffman Line
Andrew Hoffman Line
Andrew Hoffman Line
Andrew Hoffman Line
Andrew Hoffman Line
Andrew Hoffman Line
Andrew Hoffman Line
Andrew Hoffman Line
Andrew Hoffman Line
Andrew Hoffman Line
Andrew Hoffman Line
Andrew Hoffman Line
Andrew Hoffman Line
Andrew Hoffman Line
Andrew Hoffman Line
Andrew Hoffman Line
Andrew Hoffman Line
Andrew Hoffman Line
Andrew Hoffman Line
Andrew Hoffman Rectangle
Andrew Hoffman Polygon
Andrew Hoffman Polygon
Andrew Hoffman Line
Andrew Hoffman Line
Andrew Hoffman Line
Andrew Hoffman Line
Andrew Hoffman Line
Andrew Hoffman Line
Andrew Hoffman Line
Andrew Hoffman Line
Andrew Hoffman Line
Andrew Hoffman Line
Andrew Hoffman Line
Andrew Hoffman Line
Andrew Hoffman Line
Andrew Hoffman Line
Andrew Hoffman Line
Andrew Hoffman Line
Andrew Hoffman Line
Andrew Hoffman Line
Andrew Hoffman Line
Andrew Hoffman Line
Andrew Hoffman Line
Line
NORTH ELEVATIONWEST ELEVATION
TOP OF EXISTING RETAINING WALL
PROVIDE
BACK WALL
GRADE
EXISTING SIDE RETAINING WALL
Andrew Hoffman Rectangle
Andrew Hoffman Polygon
Andrew Hoffman Polygon
Andrew Hoffman Polygon
Andrew Hoffman Polygon
Andrew Hoffman Rectangle
Andrew Hoffman Polygon
Andrew Hoffman Polygon
Andrew Hoffman Polygon
Andrew Hoffman Polygon
Andrew Hoffman Rectangle
Andrew Hoffman Rectangle
Andrew Hoffman Rectangle
Polygonal Line
MOUNTING SECTIONS
NOTE: SECTIONS AND MOUNTING VARY FROM
MANUFACTURER TO MANUFACTURER.
CORRUGATED WALL
CONCRETE FASTENER
CONCRETE FASTENER
STRUCTURE FASTENER
TYPICAL CONCRETE WALL OR BIN BLOCK.
DRIP EDGE LIP
ANGLE
ANGLE
PLAN
Andrew Hoffman Polygon
Andrew Hoffman Polygon
Andrew Hoffman Polygon
Andrew Hoffman Polygon
Andrew Hoffman Oval
Andrew Hoffman Polygonal Line
Andrew Hoffman Polygonal Line
Andrew Hoffman Line
Andrew Hoffman Polygonal Line
Andrew Hoffman Polygonal Line
Andrew Hoffman Line
Andrew Hoffman Rectangle
Andrew Hoffman Line
Andrew Hoffman Polygon
Andrew Hoffman Polygonal Line
Andrew Hoffman Line
Andrew Hoffman Polygonal Line
Andrew Hoffman Line
Andrew Hoffman Line
Andrew Hoffman Line
Andrew Hoffman Line
Andrew Hoffman Line
Andrew Hoffman Line
Andrew Hoffman Line
Andrew Hoffman Line
Andrew Hoffman Line
Andrew Hoffman Line
Andrew Hoffman Line
Andrew Hoffman Polygonal Line
Andrew Hoffman Line
Andrew Hoffman Polygonal Line
Andrew Hoffman Line
Andrew Hoffman Line
Andrew Hoffman Polygonal Line
Andrew Hoffman Line
Andrew Hoffman Line
Andrew Hoffman Line
Andrew Hoffman Line
Andrew Hoffman Line
Andrew Hoffman Line
Andrew Hoffman Polygonal Line
EXISTING SHED
| TABLE OF CONTENTS |
| DIVISION 01 – GENERAL REQUIREMENTS |
| 01 10 00 – GENERAL PARAGRAPHS |
| SECTION 01 33 00 – SUBMITTALS PROCEDURES |
| SECTION 01 40 00 – QUALITY REQUIREMENTS |
| SECTION 01 54 19 – TEMPORARY CRANES |
| SECTION 01 74 19 – WASTE MANAGEMENT AND DISPOSAL |
| SECTION 02 41 19 – SELECTIVE SITE PREPARATION |
| DIVISION 4 MASONRY |
| SECTION 04 28 13 – CONCRETE FORM MASONRY UNITS |
| 1.01 SUMMARY: This Section includes requirements for assemblies consisting of concrete form masonry units and any cementous mixtures used by the awarded Contrator. |
| PART 2 PRODUCTS |
| A. GROUT: ASTM C1107/C1107M; premixed, non-metallic, non-shrink aggregate cement, water reducing and plasticizing agents; capable of developing minimum compressive strength of 2,400 psi in 48 hours and 7,000 psi in 28 days if required. |
| PART 3 EXECUTION |
| 3.02 CONCRETE BLOCK PLACEMENT: |
| A. PLACEMENT: Install bin blocks in line with one another ensuring full interlocking between units in accordance with the concept plan. |
| B. CUTTING CFMU: Cut with motor-driven saws to provide clean, unchipped edges. |
| 3.03 CONSTRUCTION TOLERANCES: For conspicuous horizontal and vertical lines, such as external corners, exposed sills, reveals, and expansion and control joints, do not vary from level and/or plumb by more than 1/4 inch in 20 feet, nor 1/2 inch maximum. |
| END OF SECTION 04 28 13 |
| DIVISION 13 SPECIAL CONSTRUCTION |
| SECTION 13 34 19 – METAL BUILDING SYSTEMS |
| 1.01 SUMMARY: This Section includes specifications for pre-engineered metal S-model type Quonset style, straight wall and curved roof building system to be provided by the awarded Contractor. |
| 1.02 DESIGN REQUIREMENTS: |
| A. LOADS: Design members to withstand dead load, applicable snow load, and loads due to pressure and suction of the wind up to 100 MPH. |
| B. MOVEMENT: Building is permitted of minimal component movement without buckling, failure of joint seals, undue stress on fasteners or other detrimental effects. |
| C. FABRICATIONS: Fabricated wall and roof systems free of distortion or defects detrimental to appearance or performance. |
| D. SIZE: Select building that has a close overall size of approximately 20’-0” long X 24’-0” high and no more than 16’-0” wide. |
| 1.03 WARRANTY: Minimum five-year Manufacturer warranty for pre-engineered building systems and components including finish. |
| PART 2 PRODUCTS |
| PART 3 EXECUTION |
| 3.01 WALL AND ROOFING SYSTEMS ERECTION: Fasten system to structural supports, aligned level and plumb. Install sealants and gaskets to prevent weather penetration. |
| TE.1.Metal.Salt.Shed.Mashup.pdf |