Attachment I -Performance Work Statement.pdf
PDF 96 KB Posted
- Attached to
- Dynamic Combat Shooting Range
- Solicitation number
- H9224022Q2042
- Issued by
-
United States Special Operations Command
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment II - Pricing.xlsx | XLSX spreadsheet | |
| H9224022Q2042_Dynamic Combat Range_SAM.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Performance Work Statement (PWS)
Naval Special Warfare Command
Dynamic Combat Shooting Range Rental
1. BACKGROUND
1.1 Naval Special Warfare (NSW) personnel requires access to dynamic live fire combat shooting ranges for required training. The ability to utilize locally provided commercial ranges will provide operators with the necessary skills to fulfill WARCOM’s training requirements while saving cost by eliminating unnecessary long-distance travel.
2. OBJECTIVES
2.1 The objective of this procurement is to utilize three (3) live-fire ranges to support dynamic combat shooting and long-range precision shooting for NSW students.
3. SCOPE
3.1 The Contractor shall provide the personnel, management, materials, equipment and training areas (not otherwise provided by the Government) necessary to support the requirements in this Performance
Work Statement (PWS).
4. REQUIREMENTS
4.1 The contractor shall provide use of three (3) local live-fire ranges capable of hosting up to forty (40) personnel for three (3) days, at 7 hours per day, from 0900 to 1600. Range characteristics must meet minimum requirements as set forth below:
4.1.1 Range 1 Characteristics:
4.1.1.1 Length: minimum of 100 yards
4.1.1.2 At least 20 shooting positions
4.1.1.3 Capable of withstanding a maximum of 9 mm caliber Glock-19 pistol rounds
4.1.1.4 Range shall contain 7 lanes of 6 plate steel racks for a total of 42 steel plates.
4.1.1.5 Capable of withstanding a maximum of 5.56 mm caliber M4 rifle rounds
4.1.1.6 Must have one adjustable steel moving target with interchangeable plates.
4.1.1.7 Must have 36 steel plate racks.
4.1.1.8 Overhead coverage not required but preferred; overhead coverage defined by either indoor range or outdoor with any covering that will shield from rain
4.1.1.9 Range training and instruction required.
4.1.2 Range 2 Characteristics:
4.1.2.1 Length: minimum of 100 yards
4.1.2.2 At least 20 shooting positions
4.1.2.3 Capable of withstanding maximum of 5.56 mm caliber M4 rifle rounds
4.1.2.4 Multi-purpose range that allows for dynamic shoots: barricades and multi-story structures with shooting holes that allow for shooting in various positions.
4.1.2.5 Must have moving targets capable of both steel and paper targets.
4.1.2.6 Must have at a minimum, 20 steel targets.
4.1.2.7 Range training and instruction required.
4.1.3 Range 3 Characteristics:
4.1.3.1 Length: minimum of 1200 yards
4.1.3.2 At least ten shooting positions
4.1.3.3 Capable of withstanding 7.62 mm and .300 Win Mag sniper rounds
4.1.3.4 Must have ability for ten steel plates/ ten paper targets at various distances.
4.1.3.5 Range training and instruction not required.
4.1.4 Contractor shall provide a Government approved armory for storage of weapons as described herein and at the conclusion of each training day (Monday, Tuesday, Wednesday, and
Thursday).
5. DELIVERABLES
Deliverable Number PWS Ref. Delivery Date
N/A
6. CONTRACTOR MANPOWER REPORTING
6.1 The contractor shall report all contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract for the Naval Special Warfare Command via a secure data collection site. The contractor is required to completely fill in all required data fields using the following web address: http://www.ecmra.mil/. Reporting inputs will be for the labor executed during the period of performance during each Government fiscal year (FY), which runs
October 1 through September 30. While inputs may be reported any time during the FY, all data shall be reported no later than October 31 of each calendar year, beginning with 2013. Contractors may direct questions to the help desk at help desk at: http://www.ecmra.mil .
7. CONTRACTOR TRAVEL
7.1 Contractor travel is not required nor authorized.
8. SECURITY
8.1 No one other than NSW personnel & staff or Contractor staff will be present on the private ranges identified for use by NSW personnel. The Contractor shall not invite anyone else to view the training
(friends, acquaintances, press, etc.); no observation or recording devices by either the Contractor or non-Contractor personnel are authorized. The Contractor shall intervene if anyone is found violating this security requirement. Contractor shall intervene and prevent unauthorized individuals (“looky loos”) from lingering around training sites to the best of their ability.
8.2 All Contractor personnel are required to be citizens of the United States.
8.3 Controlled Unclassified Information
8.3.1 Unclassified information related to this acquisition is considered Controlled Unclassified
Information (CUI). The contractor shall not release to anyone outside the Contractor’s organization any unclassified information, regardless of medium (e.g., film, tape, document, contractor’s external website, any social media, newspaper, magazine, journal, corporate annual report, etc.), pertaining to any part of this contract or any program related to this contract, unless the Contracting Officer has given prior written approval.
Furthermore, any release of information which associates USSOCOM, NSW, Special
Operation Forces (SOF), or any other component command with an acquisition program, contractor, or this contract is prohibited unless specifically authorized by USSOCOM.
9. GOVERNMENT FURNISHED PROPERTY/EQUIPMENT/INFORMATION (GFP/GFE/GFI)
9.1 The Government will bring all training weapons, ammo, and gear necessary for training.
10. SAFETY
10.1 Safety in all training events shall be paramount. The contractor shall comply with and maintain appropriate safety instructions and qualification standards in accordance with references located in paragraph 13 of this PWS.
10.2 RSO or Controller Responsibility
10.2.1 The assigned RSO will ensure that a range assessment is performed for all non-DoD live fire ranges IAW COMNAVSPECWARCOMINST 3591.1D prior to first-time use.
Assessments will be conducted in accordance with enclosure (3) of the above referenced instruction.
10.2.2 The supported Team will provide an RSO and ROIC per evolution on site who will conduct live fire monitoring to ensure the quality and safety of the exercise.
http://www.ecmra.mil/ http://www.ecmra.mil/ http://www.ecmra.mil/ http://www.ecmra.mil/
10.2.3 The exercise controller shall provide the contractor with applicable safety doctrine as appropriate. Additionally, the exercise controller will have the authority to stop any training being performed when he or she determines that the safety of the students, contractor employees or other personnel are at risk.
10.3 Contractor Responsibility
10.3.1 Nothing in the Performance Work Statement (PWS), nor any government action or failure to act in performance of the contract shall relieve the contractor of its responsibility for the safety of the contractor's personnel and property, the government's personnel and property, and the general public.
10.3.2 Furthermore, nothing in this PWS shall relieve the contractor of its responsibility for complying with applicable Federal, State, and Local laws, ordinances, codes and regulations (including those requiring applicable licenses and permits) in connection with the performance of this contract.
10.3.3 The Contractor facility live fire ranges shall be assessed by a qualified NSW Range Safety
Officer prior to first-time use. The contractor is responsible for compliance with all applicable NSW and DoD live-fire range standards.
10.3.4 The Contractor shall have the authority to stop any training being performed when he or she determines that the safety of the students, contractor employees, or other personnel are at risk.
10.4 Risk Controls
10.4.1 This training is categorized as High Risk in accordance with
COMNAVSPECWARCOMINST 1500.1. As such, an Operational Risk Assessment and the implementation of risk controls are required for this training event.
10.4.2 Troop will insure a certified SOC-M medic is on station at each training event and there is a designated vehicle identified to support CASEVAC.
10.5 Mishaps
10.5.1 The Government process must be in place that will ensure any mishaps are reported, investigated and recorded. This information will be input into the Web Enabled Safety
System (WESS) by the Government.
10.5.2 Safety and training related problems or mishaps involving or observed by the contractor shall be addressed immediately to the designated RSO or ROIC. A formal written report shall be prepared and submitted to the Safety Officer within 2 working days of the incident.
11. QUALITY CONTROL
11.1 The contractor shall implement and maintain a Quality Control Plan (QCP) to ensure work performed conforms to the scope of work and meets the requirements under this PWS. The QCP shall, at a minimum provide a method for performing inspections; identifying, correcting and preventing problems/defective service; addressing customer complaints, and improving the quality of services over the life of the contract.
12. QUALITY ASSURANCE
12.1 The Government reserves the right to perform inspections and surveillance to evaluate the
Contractor’s compliance to the contract terms and performance of the requirements in the PWS. The
Government will make every effort to ensure that the surveillance methods used are conducted in an objective, fair, and consistent manner.
12.2 Contract Discrepancy Report (CDR). In the event of unsatisfactory contractor performance, the CO will issue a CDR that will explain the circumstances and findings concerning the incomplete or unsatisfactory service. The contractor shall acknowledge receipt of the CDR and respond in writing as to how he/she shall correct the unacceptable performance and avoid a recurrence. The Government will review the contractor's corrective action response to determine acceptability and will use any completed CDR as part of an overall evaluation of Contractor performance when determining present or future contractual actions.
13. APPLICABLE DOCUMENTS
Document Web link (if applicable)
NAVSPECWARCOMINST 3591.1D Range Safety
Procedures
Available upon request
OMNAVSPECWARCOMINST 1500.1 High Risk Available upon request
Training Safety Program
14. PLACE OF PERFORMANCE
14.1 Training shall be conducted at a Contractor provided facility within the local trade area defined as the
60-mile radius from JEB Little Creek, VA.
15. PERIOD OF PERFORMANCE
15.1 The range access for training shall be AUG 30 – SEP 1 2022.