This document contains a draft test plan and schedule for a rotary screen press for applying foil to currency. The test plan outlines the schedule for the first two weeks of Factory Integration Testing (FIT) and Best and Final Testing (BAT). The schedule includes daily start and wrap up meetings, demonstrations of production runs with different formats and applications, inspections, job changes, maintenance modes, and error recovery. The related federal contract opportunity is solicitation number 2031ZA23R00005 for a Hot Foil Machine to apply advanced counterfeit deterrent features to future currency designs. The solicitation was issued by the Department of the Treasury Bureau of Engraving and Printing for the design, fabrication, assembly, integration, delivery, installation, set-up, testing and training of a machine to apply foil to currency.
View the file
Other files for this federal contract opportunity
Show all 19
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FIT Schedule
| Rotary Screen Press FIT Schedule - Week 1 | |||||
| Day | Available if Required | 1 | 2 | 3 | 4 |
| AM | FIT Kick-off Meeting | Daily Start Meeting | Daily Start Meeting | Daily Start Meeting | |
| Production Run |
50-subject Format Side 1 (Face) Patch application without UV curing
- Inspection System Demonstration
- Sheet and Foil Registration Demonstration Production Run 50-subject Format Side 1 (Face) Patch application with UV curing
- Sheet and Foil Registration Demonstration Job Change without Format Change Inspection System setup Demo
Visual Inspection
| Control Station & Safety Demo | Feeder Fault Test & Counter Verification | ||
| Inspection Only Mode Demo | |||
| PM |
Data Collection Demo Production Mode
Daily Wrap-up Meeting Daily Wrap-up Meeting Daily Wrap-up Meeting Daily Wrap-up Meeting
| Rotary Screen Press FIT Schedule - Week 2 | |||||
| Day | 5 | 6 | 7 | 8 | 9 |
| AM | Daily Start Meeting | Daily Start Meeting | Daily Start Meeting | Daily Start Meeting | Daily Start Meeting |
| Production Run |
50-subject Format Side 2 (Back) Stripe application with UV curing
Sheet and Foil Registration Demonstration Job Change with format change- 50 subject to 32 Subject
Sheet and Foil Registration Demonstration
| Demonstrate all available "Options" from SOW | ||
| Maintenance Mode Demo | Jam & Error Recovery Demo | Complete all outstanding demonstrations |
Production Mode
| PM | |
| Production Run |
32-subject Format Side 1 (Face)
| Stripe application without UV curing | E-Stop Demo | FIT Wrap Up Meeting | ||
| Daily Wrap-up Meeting | Daily Wrap-up Meeting | Daily Wrap-up Meeting | Daily Wrap-up Meeting |
BAT Schedule
| Rotary Screen Press BAT Schedule - Week 1 | |||||
| Day | Available if Required | 1 | 2 | 3 | 4 |
| AM | BAT Kick-off Meeting | Daily Start Meeting | Daily Start Meeting | Daily Start Meeting | |
| Production Run |
50-subject Format Side 1 (Face) Patch application without UV curing
- Sheet and Foil Registration Demonstration Production Run 50-subject Format Side 1 (Face) Patch application with UV curing
- Sheet and Foil Registration Demonstration Job Change without Format Change Inspection System setup Demo
Visual Inspection
| Control Station & Safety Demo | Feeder Fault Test & Counter Verification | ||
| Inspection Only Mode Demo | |||
| PM |
Data Collection Demo Production Mode
Daily Wrap-up Meeting Daily Wrap-up Meeting Daily Wrap-up Meeting Daily Wrap-up Meeting
| Rotary Screen Press BAT Schedule - Week 2 | |||||
| Day | 5 | 6 | 7 | 8 | 9 |
| AM | Daily Start Meeting | Daily Start Meeting | Daily Start Meeting | Daily Start Meeting | Daily Start Meeting |
| Production Run |
50-subject Format Side 2 (Back) Stripe application with UV curing
Sheet and Foil Registration Demonstration Job Change with format change- 50 subject to 32 Subject
Sheet and Foil Registration Demonstration
| Demonstrate all available "Options" from SOW | ||
| Maintenance Mode Demo | Jam & Error Recovery Demo | Complete all outstanding demonstrations |
Production Mode
| PM | |
| Production Run |
32-subject Format Side 1 (Face)
| Stripe application without UV curing | E-Stop Demo | BAT Wrap Up Meeting | ||
| Daily Wrap-up Meeting | Daily Wrap-up Meeting | Daily Wrap-up Meeting | Daily Wrap-up Meeting |