Attachment H2 - Draft Foil Test Plan v2.xlsx

XLSX spreadsheet 21 KB Posted

Attached to
Hot Foil Machine Federal contract opportunity
Solicitation number
2031ZA23R00005
Issued by
Department of the Treasury Bureau of Engraving and Printing

About this file

This document contains a draft test plan and schedule for a rotary screen press for applying foil to currency. The test plan outlines the schedule for the first two weeks of Factory Integration Testing (FIT) and Best and Final Testing (BAT). The schedule includes daily start and wrap up meetings, demonstrations of production runs with different formats and applications, inspections, job changes, maintenance modes, and error recovery. The related federal contract opportunity is solicitation number 2031ZA23R00005 for a Hot Foil Machine to apply advanced counterfeit deterrent features to future currency designs. The solicitation was issued by the Department of the Treasury Bureau of Engraving and Printing for the design, fabrication, assembly, integration, delivery, installation, set-up, testing and training of a machine to apply foil to currency.

View the file

Other files for this federal contract opportunity

Other files attached to Hot Foil Machine, newest first.
File Type Posted
2031ZA23R00005 RFP - Amendment 0003.pdf PDF
2031ZA23R00005 RFP - Amendment 0002.pdf PDF
Attachment G - OEHS Attachments_Updated.pdf PDF
2031ZA23R00005 RFP Amendment 0001.pdf PDF
Attachment F2 - NIST.SP.800-53r5.pdf PDF
Attachment G1 - 75W-08.0-02 EHS Boilerplate Requirements for Construction and Services Contractors.pdf PDF
Attachment I - Social Distancing and Contract Tracing Device (SDCT) Device FAQ and Privacy Act.pdf PDF
Attachment F1 - FIPS-PUB-199-final.pdf PDF
Attachment A - BEP Sensitive Information NDA.pdf PDF
Attachment F3 - BEP Rev 5 MSP Final Signed For Your Reference (2).pdf PDF
Attachment J - Past Performance Questionnaire - BEP.docx DOCX document
Attachment G - OEHS Attachments.docx DOCX document
Attachment F5 - BCONF_Win10_IoT_Flowsys_20210324.xlsx XLSX spreadsheet
Attachment F4 - DOJ Ref Mapping PIVCard Certificates to a Privileged Account Open Version.pdf PDF
Attachment H1 - Hot Draft Test Plan.doc DOC document
2031ZA23R00005 RFP.pdf PDF
Attachment D REV A 50-SUBJECT STACK AND RACK CART with Component Drawings.pdf PDF
Attachment E - 50 Subject Universal CalCheck Target 818x700 REV4_1 roll.pdf PDF
Attachment G2 - 75D-07.0-04 EHS Contractor Requirements.pdf PDF
Show all 19

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FIT Schedule

Rotary Screen Press FIT Schedule - Week 1
DayAvailable if Required1234
AMFIT Kick-off MeetingDaily Start MeetingDaily Start MeetingDaily Start Meeting
Production Run

50-subject Format Side 1 (Face) Patch application without UV curing

- Inspection System Demonstration

- Sheet and Foil Registration Demonstration Production Run 50-subject Format Side 1 (Face) Patch application with UV curing

- Sheet and Foil Registration Demonstration Job Change without Format Change Inspection System setup Demo

Visual Inspection

Control Station & Safety DemoFeeder Fault Test & Counter Verification
Inspection Only Mode Demo
PM

Data Collection Demo Production Mode

Daily Wrap-up Meeting Daily Wrap-up Meeting Daily Wrap-up Meeting Daily Wrap-up Meeting

Rotary Screen Press FIT Schedule - Week 2
Day56789
AMDaily Start MeetingDaily Start MeetingDaily Start MeetingDaily Start MeetingDaily Start Meeting
Production Run

50-subject Format Side 2 (Back) Stripe application with UV curing

Sheet and Foil Registration Demonstration Job Change with format change- 50 subject to 32 Subject

Sheet and Foil Registration Demonstration

Demonstrate all available "Options" from SOW
Maintenance Mode DemoJam & Error Recovery DemoComplete all outstanding demonstrations

Production Mode

PM
Production Run

32-subject Format Side 1 (Face)

Stripe application without UV curingE-Stop DemoFIT Wrap Up Meeting
Daily Wrap-up MeetingDaily Wrap-up MeetingDaily Wrap-up MeetingDaily Wrap-up Meeting

BAT Schedule

Rotary Screen Press BAT Schedule - Week 1
DayAvailable if Required1234
AMBAT Kick-off MeetingDaily Start MeetingDaily Start MeetingDaily Start Meeting
Production Run

50-subject Format Side 1 (Face) Patch application without UV curing

- Sheet and Foil Registration Demonstration Production Run 50-subject Format Side 1 (Face) Patch application with UV curing

- Sheet and Foil Registration Demonstration Job Change without Format Change Inspection System setup Demo

Visual Inspection

Control Station & Safety DemoFeeder Fault Test & Counter Verification
Inspection Only Mode Demo
PM

Data Collection Demo Production Mode

Daily Wrap-up Meeting Daily Wrap-up Meeting Daily Wrap-up Meeting Daily Wrap-up Meeting

Rotary Screen Press BAT Schedule - Week 2
Day56789
AMDaily Start MeetingDaily Start MeetingDaily Start MeetingDaily Start MeetingDaily Start Meeting
Production Run

50-subject Format Side 2 (Back) Stripe application with UV curing

Sheet and Foil Registration Demonstration Job Change with format change- 50 subject to 32 Subject

Sheet and Foil Registration Demonstration

Demonstrate all available "Options" from SOW
Maintenance Mode DemoJam & Error Recovery DemoComplete all outstanding demonstrations

Production Mode

PM
Production Run

32-subject Format Side 1 (Face)

Stripe application without UV curingE-Stop DemoBAT Wrap Up Meeting
Daily Wrap-up MeetingDaily Wrap-up MeetingDaily Wrap-up MeetingDaily Wrap-up Meeting